Professional Documents
Culture Documents
CHAPTER 1
INTRODUCTION
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
2
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CHAPTER 1 : INTRODUCTION
1.0 GENERAL
Construction is a key sector of the national economy for countries all around the world, as
traditionally it took up a big portion in nations total employment and its significant contribution to
a nations revenue as a whole. However, until today, construction industries are still facing
numbers of contingent problems that were bounded to beresolved since the past time. The
chronic problems of construction are well known such as Low productivity, poor safety, inferior
working conditions, and insufficient qualityand the phenomenon of the poor performance and
conditions inconstruction had long been witnessed and recorded by academics and practitioners
throughout the world.
Nowadays, increasing foreign competition, the scarcity of skilled labour and the need toimprove
construction quality are the key challenges faced by the construction industry.Responding to those
challenges imposes an urgent demand to raise productivity, qualityand to incorporate new
technologies to the industry. A lack of responsiveness can holdback growth, and to development of
the needed infrastructure for the constructionindustry and other key activities in the country.
With the lean construction paradigm, construction industry had started to be reviewed and
evaluated in the possibilities of implementing these new lean perspectives of production concepts in
the construction processes to optimize the overall construction performance on construction stage
as well as design stage. Performance improvement opportunities in construction can then be
addressed by adopting waste identification/ reduction strategies in the flow processes inparallel with
value adding strategies with the introduction of new management tools andwith proper trainings
and education programs. Unfortunately, these new leanconstruction concepts especially those on
wastes and values most of the times are notwell understood by construction personnel.
Particularly, waste is generally associatedwith waste of materials in the construction processes
while non-value adding activitiessuch as inspection, delays, transportation of materials and others
are not recognised as waste. As the result of that, the productivity of construction industry cannot
be fully optimized due to the narrow interpretation on the concept of wastecurrent adopted. In
this case, substantial education programs need to be arranged for allrelated parties involved in
order to implement the new process improvement strategiessuccessfully throughout the
construction process cycle.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
3
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
It is presumably that construction industries in india are facing the same generic(process-related)
problems/ wastes on construction activities which was also faced bytheir counterparts regardless
those in developed countries or developing countries.However, the main problem is the lack of
clear indicators on quantitative parameters to assess the extent of thoseproblems/ wastes to have
been impacted on the overall performance and productivity oflocal construction industries. To
date, there have not been many well-documentedquantitative studies and records on to process-
related problems/ wastes which arisen onconstruction site. As a result of that, the introduction of
the concepts and framework of new lean construction ideology are seen as an opportunity to
address the existing problems in local construction industry and utilising concepts and framework
of new lean construction ideology can then go further to formulate the extent of impactsof those
problems/ wastes on a more structured and quantitative basis.
Prior to assess the severity of the process-related problems/ wastes which existed in
theconstruction processes for the local construction industries, the differentiate oftraditional and
new production/ construction concepts will have to be drawn prior tofurther investigation and
evaluation on any project performances. New measurementparameters such as waste, value, cycle
time or variability that was not covered undertraditional concepts are to be introduced into this
study as accordance to the leanconstruction ideologies and the subjects in this case; the local
construction personnelwill be subsequently examined with those new parameters to review the
level ofunderstanding and practicability in local construction industry compare to therequirements
and the concepts set forth by lean construction philosophy.
1.2 OBJECTIVES
1. Examine the general perceptions of the local construction industry with the lean construction
principles of practices.
2. Determine the degree of problems arisen from wastes identified in existing scenario and
practices in local construction industry.
3. Identify the source of wastes (classified under lean construction) & Study of the potential
project productivity improvements by reducing and eliminating the wastes as classified under
lean construction.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
4
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
1.3 METHODOLOGY
(d) Conclusion
Based on above analysis a suitable conclusion will be formulated and scope for the future
work will be suggested.
This study is restricted to infrastructure companies dealing with highway projects in india.
Literature review will be carried out till 1st week of February, 2010
Data collection and data analysis will be completed by 4th week of march, 2010
Conclusion will be finalized at the 3rd week of april, 2010.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
5
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CHAPTER 2
LITERATURE
REVIEW
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
6
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
2.0 INTRODUCTION
The chronic problems of construction are well known: low productivity, poor safety, inferior
working conditions, and insufficient quality. (Koskela, 1993) However, most of the time, those
critical problems of construction were left unattended because people of the industry refrained to
believe or accept that there is a solution to those problems. According to Koskela (1992), the
incapability to improve the productivity level of construction projects is mainly perceived by
people in the industry as due to its peculiarities and special features: one-of-a-kind nature of
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
7
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
projects, site production, and temporary multi-organisation. Most people concluded that its
fragmented nature, lack of co-ordination and communication between parties, adversarial
contractual relationships, and lack of customer focus inhibit the industry's performance.
Therefore, the organisation, planning, allocation and control of these resources, processes and
technologies are what finally determine the productivity that can be achieved.
Most of the early efforts involved new technology and process adoption from manufacturing
practices i.e. industrialisation, prefabrication and modularisation (new process adoption) and
computer integrated construction and automated construction (new technology adoption).
However, there have been no signs of major improvements to construction has resulting from both
trends of process dissemination and solutions as quoted by Koskela (2000). The main reasons
behind the failure of achieving any major improvements from both trends are mainly due to certain
key features between manufacturing and construction. A comparison with manufacturing shows the
key features, which distinguishes construction from manufacturing, is the extent of uncertainty
evident throughout the production phase as shown in Table 2.2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
8
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
The core of the new production philosophy is based on the conclusive understanding that all
production systems are constituted of 2 main activities: Conversions and Flows (waiting, moving,
and inspecting). In the new production paradigm, only conversion activities add value to the final
product whereas flow activities do not; value is determined under the value stream of the
customers with the satisfaction of their requirements and cost paid on the final product. Therefore,
the primary objectives for process/ performance/ productivity improvement under the flagship of
new production philosophy should be targeted separately. That can be done through the
improvement of flow activities by primarily focusing on reducing or eliminating them and on the
other hand, conversion activities should be focused on making them more efficient. This has
important implications for the design, control, and improvement of production processes, because
according to Koskela (1992), traditional production management paradigm sees the whole
process simply as a conversion of an input into an output that can be divided into sub-processes,
which are also conversion processes. All activities have been treated as though they were value-
adding conversions without separating from the flow processes.
Based on the understanding of the production process can be consists of both conversion and flow
activities, a generic process improvement plan based on new production philosophy can be derived
from the study of Enton (1994) on lean productivity of construction professions. The first step to
implement process improvement plan is by analysis and separation of conversions and flows
activities. For conversions activities identified, those activities should be channeled into the quality
cycles (Quality control, Quality assurance and Total Quality Management) to increase efficiency of
value added conversions. Whereas, for flow activities, the approach should be consists of way of
flows simplification (through Elimination, simplification and automation) in order to reduce or
eliminate non-value added flow activities.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
9
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
The first core principle which has been used in conjunction with transformation concept stated
that: The transformation process can be decomposed into subprocesses, which also are transformation
process of breaking up the total transformation (production process) into much smaller and more
manageable transformations and eventually can be further breakdown into individual continual
tasks.
The second core principle of the transformation model is a general acceptance of independency
principle that the cost of the total process can be minimized through minimising the cost of each sub-
process. The key issue pertaining to this principle leads to the assumption that every sub-processes
of a total process are independent from each other and therefore cost minimisation can be applied
through focus on cost management in each operation, sub-process or department.
The third core principle formulated currently recommended that It is advantageous to insulate the
production process from the external environment through physical or organisational buffering. This
principle is related to the independence assumption from the second core principle as discussed
above and it reflects that the transformation process that is most important, and it is thus a
requisite to shield it from the erratic conditions in the environment.
FLOW CONCEPT
The flow view of production, firstly proposed by the Gilbreths (1922) in scientific terms, has
provided the basis for JIT and lean production. This view was firstly translated into practice by
Ford (1926). As a result, the flow view is embodied in JIT and lean production and the triumph of
the JIT and lean production has practically proven the power of this conception.
The new production concept of flow was emerged apparently from the erroneous view of
decomposition in the transformation model of production that is the intervals between
transformations, which happen to be non transformations activities. In flow concept, production is
viewed as a flow, where, in addition to transformation, there are waiting, inspection and moving
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
10
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
stages. Production management equates to minimizing the share of non transformation stages of the
production flow, especially by reducing variability. In this context, flow model is looking beyond
transformation model by taking non-transformations activities into consideration as to improve
overall flow efficiency.
The first core principle of this flow concept is the introduction of time as resource in production
and therefore the main focus is in the amount of time consumed by the total transformation and its
parts by aiming for the production improvement at shortening of the total time of production.
The second core principle of the flow concept is that time is consumed by two types of activities in
the overall production flow which are transformation activities and non-transformation activities.
Gilbert (1922) categorised the non transformation activities as transfer, delay and inspection as
showed in Figure 1 and it is obvious that these non-transformation activities are unnecessary and
the less of them is better and best if there are none of them.
This third concept of value generation concept views production as a means for the fulfillment of
customer needs. Production management equates to translating these needs accurately into a
design solution, and then producing products that conform to the specified design. It focus on
control of the transformation and flow, namely control for the sake of the customer and it is important to
highlights that the value generation concept does not focus on any particular aspect of physical
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
11
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
production like transformation and flow model do but rather on its control in securing value
generated for the customer.
The production in construction is of assembly-type, where different material flows are connected
to the end product. In construction, there are 3 types of flows as suggested by Koskela (2000):
material flow (the transportation of components to the site for particular installation), location flow
(e.g. one particular trade goes through the different part of the building or construction site to get
their work done) and assembly flow (e.g. the sequential of works of assembly and installation).
There are at least seven resource flows that unite to generate the construction task as illustrated In
Figure 2. Many of these resource flows are of relatively high variability, and thus the probability of
a missing input is considerable.
Construction productions are subjected to more sources of variability and the insight gained is that
construction consists of assembly tasks involving a high number of input flows. Planning and
controlling production becomes very important and tasks and flows have to be considered in
parallel in production management because: realization of tasks heavily depends on flows, and progress
of flows in turn is dependent on realization of task (Koskela, 2000)
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
12
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Waste in the construction industry has been the subject of several research projects around the
world in recent years. However, Most studies tend to focus on the waste of materials, which is only
one of the resources involved in the construction process. This seems to be related to the fact that
most studies are based on the conversion model, in which material losses are considered to be
synonymous of waste. Formosa, (2002) stated that many people in the industry have considered
waste are directly associated with the debris removed from the site and disposed of in landfills and
they suggested that the main reason for this relatively narrow view of waste is perhaps the fact that
it is relatively easy to see and measure. The main focus for those conventional material waste
studies in construction are seen to be restricted to physical waste or material waste in construction
and/ or the specific impacts due to the physical waste itself.
Formosa, (1999) in their earlier research paper entitled Method for Waste Control in Building
Industry had significantly grouped some researches and studies done by other researchers around
the world on the wastes in construction into 2 main aspects based on the impacts of the
construction waste namely :
1. Impacts on the environmental damage that result from the generation of waste material.
2. Economic aspects of waste in construction industry.
Some conclusions that were drawn from those conventional construction waste studies above such
as:
1. The waste of building materials is occasionally far higher than the nominal figures assumed
by the companies in their cost estimates.
2. There is a very high variability of waste indices from site to site. Furthermore, similar sites
might present different levels of wastes for the same material. This indicates that a
considerable portion of this wastage can be avoided.
3. Some companies do not seem to be concerned about material waste, since they do not
apply relatively simple procedures to avoid waste on site. None of them had a well-defined
material management policy, neither a systematic control of material usage.
4. The lack of knowledge was an important cause of waste. Most building firms did not know
the amount of waste they had.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
13
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
5. Most causes of waste are related to flaws in the management system, and have very little to
do with the lack of qualification and motivation of workers. Also, waste is usually the result
of a combination of factors, rather than originated by an isolated incident.
6. A significant portion of waste is caused by problems, which occur in stages that precede
production, such as inadequate design, lack of planning, flaws in the material supply system,
etc.
The waste & value loss in terms of quality cost has been 10 20% of the project cost. It
has also recorded the causes of these quality problems are 46% design-related, 22%
construction-related and 15% are related to material supply.
The second factor that contributed to waste and value loss as compiled by Koskela is the
factor of constructability. It was found from a constructability report stating that projects
where constructability has been specifically addressed have reported 6 - 10% savings of
construction costs.
Researchers have estimated that 10 12% savings in labour cost could be produced by
materials management systems. some researchers also reported that savings of 10% in
materials costs can be achieved from vendor cooperation in streamlining the material flow.
It has been found that construction work flow consists of a lot of non value-adding activities
where they consume a high percentage of overall working time. All the estimation given
from the researches compiled by Koskela, the average distribution of working time used in
value-adding activities ranging around 30% to 40%. Oglesby and his co-author estimated
around 36% in 1989 while Levy in 1991 claimed that the average share of working time is
31.9 % in the United States.
Another waste factor is lack of safety. safety-related costs are estimated to be 6 percent
of total project costs as reported by Levitt & Samelson.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
14
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
15
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
This means that there are 2 approaches to improving processes for new production philosophy
compared to conventional conversion view. One is to improve the efficiency of both value-adding
and non value-adding work, and the other is to eliminate waste by removing non value-adding
activities. Therefore, waste should be defined as any losses produced by activities that generate
direct or indirect costs but do not add any value to the product from the point of view of the
client.
The primary objectives for this new movement will be looking at value to the client and throughput,
the movement of information or materials to completion. Improvement results from reducing
waste that is the difference between the current situation and perfection, i.e., meeting customer
unique requirements in zero time with nothing in store.
Industry researchers and practitioners have acknowledged that there are many non-value adding
activities during the design and construction process and majority of those wasteful activities
consuming time and effort without adding value for the client. Since the beginning of a construction
project, Construction Managers have to deal with many factors that may negatively affect the
construction process, producing different types of waste (Serpell,1995). Waste includes both the
incidence of material losses and the execution of unnecessary work that generates additional costs
but does not add value to the product (Koskela, 1992). Moreover, some researchers, Alarcon
(1993), Koskela (1992) and Serpell, (1995) stated that waste in construction and
manufacturing include delay times, quality costs, lack of safety, rework, unnecessary transportation
trips, long distances, improper choice of management, methods or equipment and poor
constructability.
Regarding the possibility to control the incidence of waste, Formoso, (1999) commented that
there is an acceptable level of waste, which can only be reduced through a significant change in the
level of technological development. Based on the ratio of prevention investment cost over the cost
of waste itself, they have classified wastes into two general groups:
1. Unavoidable waste (or natural waste), in which the investment necessary to its reduction is higher
than the economy produced, The percentage of unavoidable waste in each process depends on the
company and on the particular site, since it is related to the level of technological development.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
16
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
2. Avoidable waste, when the cost of waste is significantly higher than the cost to prevent it. Waste
can also be classified according to its origin, i.e. the stage that the main root cause is related to.
Although waste is usually identified during the production stage, it can be originated by processes
that precede production, such as materials manufacturing, training of human resources, design,
materials supply, and planning as studied by Alarcon (1994), Womack and Jones, (1996),
Formoso, et al. (1999), Koskela (2000) and many others.
Shingo proposed the following waste classification whereby waste was classified by it nature, which
based on the Ohnos framework of Toyota Production System:
1. Waste due to overproduction;
2. Waste due to wait periods;
3. Waste due to transport;
4. Waste due to system itself;
5. Waste due to stock;
6. Waste due to operation;
7. Waste due to defects;
Based on Shingos seven wastes, Formoso, (1999) went on to propose their main classification of
waste based on the analysis of some project sites they had carried out as shown below. It was
thought that the further classification will help managers to understand the different forms of waste,
why they occur and how to act in order to avoid them.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
17
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
3. Waiting time: related to the idle time caused by lack of synchronisation and levelling of
material flows, and pace of work by different groups or equipments. One example is the idle
time caused by the lack of material or by lack of work place available for a gang.
5. Processing: related to the nature of the processing (conversion) activity, which could only
be avoided by changing the construction technology. For instance, a percentage of mortar is
usually wasted when a ceiling is being plastered.
9. Others: waste of any nature different from the previous ones, such as burglary, vandalism,
inclement weather, accidents, etc.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
18
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Some researchers have proposed some qualitative model by postulating the loss of productivity in
construction using categories of non-productive time. Researchers such as Borcherding in 1986
explained the loss of productivity in large and complex constructions using five categories of non-
productivities time as listed below:
Borcherdings five waste categories of non-productive time are found very much similar to the
categories of wastes of productive time proposed by Serpell (1995) derived from their case as
shown Figure 4 below:
However, they highlighted some limitations to the waste classification of nonproductive time. For
example the waste of time related to slow work is related to the efficiency of processes,
construction equipment and personnel. But it is difficult to measure it because it is first necessary
to know the optimal efficiency that can be achieved, which is not always possible.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
19
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Instead of classifying the waste of productive time, Serpell, (1995) went a step further to
breakdown those wastes factors in relation of work categories. There are 3 types of work
categories as proposed:
1. Productive work (value-adding activities)
2. Contributory work (non value-adding activities but essential for conversion process): Those
contributory work which are classified as waste include transporting, instruction, measuring,
cleaning and others
3. Non-contributory work (non value-adding activities): Those non contributory work which are
classified as waste include waiting, idle time, travelling, resting, physiological needs, and rework.
There are also other categories of waste that have been mentioned in the literature, such as
accidents, working under sub-optimal conditions (Koskela 2000), design and products that do not
meet users needs. (Womack and Jones 1996) The main role of existing classification of waste is
to call the attention of people to most likely problems, since not all waste is obvious: it often
appears in the guise of useful work. (Shingo 1988).
After understanding the classification of waste, it is important to examine the type of possible
causes that lead to the occurrence of waste in construction process. This is very important because
just by knowing the waste itself just would help to monitor them but not reduce or eliminate them
from the process loops. To work out a continuous improvement strategy in reducing and
eliminating those wastes in construction processes, the origin of the waste itself has to be
identified.
A typical waste identification survey underlined a few examples of waste sources according to
different area of functions such as administration, use of resources and information systems. Several
potential sources of waste can be grouped under the particular area of functions and it can be
created to suit the need of particular projects such as the diagnostic survey developed by students
Francisco Lowener, Francisco Lira and Marcelo Beratto as documented by Alarcon (1994) listed
down the following potential sources of waste in their project:
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
20
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A. Administration
1. Unnecessary requirements
2. Excessive control
3. Lack of control
4. Poor planning
5. Bureaucracy
B. Use of resources
1. Surplus
2. Shortage
3. Misuse
4. Poor distribution
5. Poor quality
6. Availability
C. Information systems
1. Unnecessary
2. Defective
3. Late
4. Unclear
Serpell (1995) on the other hand identified several controllable causes of waste. Although his
study was mainly concentrated on wasted time but the classification of the causes to waste is found
rather structured and detailed compared to the previous listed in waste identification survey. They
divided the controllable wastes as identified from their research projects into three different
activities, which associate to flows, conversions, and management activities.
1. Controllable causes associated to flows The principal flow causes were as follow:
a) Resources
Materials: Lack of materials at the work place; materials are not well distributed; inadequate
transportation means
Equipment: Non availability; inefficient utilisation; inadequate equipment for work needs
Labour: personal attitudes of workers; stoppage of work
b) Information
Lack of information;
Poor information quality
Timing of delivery is inadequate
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
21
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
22
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
23
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
5. Quality of work life: A measure of employees affective response to working and living in
organizational systems. Often, the management focus is on insuring that employees are
satisfied, safe and secure and so forth
6. Innovation: This is the creative process of adaptation of product, service, process or
structure in response to internal as well as external pressures, demands and changes, needs and
so forth
7. Profitability: A measure or a set of measures of the relationships between financial resources
and uses for those financial resources. Embarking with the new production philosophies,
Koskela (1992) has proposed some new measures as required for construction, to stimulate
continuous improvement such as:
1. Waste: Number of defects, rework, number of design errors and omissions,
number of change orders, safety costs, excess consumption of materials, etc;
2. Value: Value of the output to the internal customer;
3. Cycle time: Cycle time of main processes and sub processes;
4. Variability: Deviations from the target, such as schedule performance.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
24
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CHAPTER 3
DATA
COLLECTION
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
25
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
The purposes of this research thesis is to see whether the lean construction principles of waste
concepts have been well comprehended, accepted and adopted by the highway personnel especially
in waste recognition, reduction and elimination for the continuous improvement in construction
processes.
A quantitative research approach was adopted for this thesis requiring the development and
dissemination of a questionnaire survey. Due to the population of this research are virtually too
difficult to be quantified as the main targeted respondents would include all personnel who has
direct managerial experiences in construction field, the non-probability sampling methods will be
adopted in this research instead of probability sampling. Purposive sampling for specific groups or
types of respondents will be conducted by using expert sampling technique which involves the
assembling of a sample of managerial personnel with known experience and expertise in managing
construction field processes.
The thesis is conducted through structured questionnaires where those questionnaires were sent
to the particular qualified respondents. The respondents were approached through their
companies and firms namely L&T ECC, IRB infrastructures, BACKBONE enterprises, LASA INDIA,
MSK PROJECTS(I) LTD.etc.
This thesis was postulated around determining the general perceptions and actions of the
construction personnel against wastes in construction and the concept of nonproductive time or
wasted time were then integrated into the research process as the key element of lean
construction philosophy regarding flow concept. In this case, Waste in construction process is
classified into three main categories, which are direct conversion waste, non-contributory time
waste and contributory time waste. 19 waste elements are outlined consists of 9 direct conversion
wastes, 7 non-contributory time wastes and 3 contributory time wastes as shown in Table 3.1
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
26
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
In response to the examine the frequencies causes of wastes and their inter-relation with waste
elements, several waste causes factors were categorised into 5 main groups of cause factors which
are Management & Administration Factors (4 factors), People Factors (6 factors), Execution Factors
(6 factors), Material Factors (6 factors) and Information and Communication Factors (3 factors).
The entire breakdown of the waste cause factors is shown in Table 3.2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
27
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
28
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A randomly selected group of targeted respondents consists of those personnel who have a
commanding role in the highway project and resource management and extensive site experiences
were targeted as respondents for the sample survey. There has been a wide spectrum of personnel
with different position and job title, which had been responded to the survey and for the purpose
of analysis and comparison, the whole sample of respondents have been regrouped into 2 main
categories which are:-
1. Project management orientated group
2. Site operative management orientated group
Project management orientated group will feature those who have relatively more responsibilities
in overall project execution and resource management and not so much on site operative
management by its nature of job scope. Therefore, this group will involve personnel more on
planning, inter-coordinating and directing role in construction process and as for the sample
respondents for this research will include project managers, general managers, project schedulers/
planners, quantity surveyors.
Site operative management orientated group will feature those who have relatively more
responsibilities on the site operative management by its nature of job scope. The group will mainly
involve personnel in solving construction problems on site, more on intra-coordinating with
internal groups and trades, and as for the sample respondents for this research will include site
managers, site engineers, resident engineer and senior quality manager.
The structure of questionnaires is divided into 5 main sections. (Refer sample questionnaire on
Appendix V) The first 2 sections of questionnaires are intended to examine the general perception
and acceptance of Lean Construction philosophy of local construction industries based on the
respondents waste concepts.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
29
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
In this case, the respondents were asked to recognise 19 wastes elements and their personnel
experiences in controlling those waste elements during construction processes. There are 2-
options available for the respondents and there were required to answer whether the wastes
elements as listed is a waste or non-waste and whether they are controlled or not controlled
during the construction processes.
The third and fourth sections are intended to review the extent of waste problems in existing local
industry by ranking them in term of frequencies of occurrences and rate the likelihood of particular
waste sources/ causes in their construction practices where they work. For section 3, Respondents
were able to identify how frequently the waste occurred using 5 categories: (1) Never; (2) Very
Rare; (3) Seldom; (4) Frequent; and (5) Very Frequent and the respondents were provided with five
different scales from 1 (no significant effect variable) to 5 as (high detrimental effect variable);
For section 4, Respondents were asked to determine the likelihood of particular waste sources/
causes using 4 categories: (1) Most unlikely; (2) Unlikely; (3) Likely; (4) Most Likely and the
respondents were provided with five different scales from 1 (no significant likelihood) to 5 as (high
detrimental likelihood)
The fifth section is to examine the relevant sources of wastes as outlined in the fourth section to
have caused the particular construction wastes. The respondents were asked to identify the most
possible causes and other possible causes to the wastes elements in order to create a matrix table
between construction wastes and their sources of wastes.
Score assignment is a process of assigning values for each of the item and this is an important
process of conducting inferential analysis especially for correlation test using Pearson-r where
aggregation of points are required for this research. Score assignment for section 1 and 2, each
positive answer is assigned with 2 points and each negative answer is assigned with 1 point. Based
on the waste categories in Table 3.1, the maximum points for direct conversion wastes that can
be aggregated for each case is (2 X 9) equal to 18 points and the minimum of (1 X 9) equal to 9
points; Maximum points for non-contributory time waste is (2 X 7) or 14 points and minimum of (1
X 7) or 7 points whereas for maximum points for contributory time wastes is (2 X 3) or 6 points
and minimum of (1 X 3) or 3 points.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
30
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Score assignment for section 3 and 4 is based on the multiple-scale format. For section 3, points are
ranged from 1 to 5 and maximum points that can be aggregated for direct conversion wastes is (5
X 9) or 45 points, minimum of (1 X 9) or 9 points; for noncontributory time wastes, maximum that
can be achieved is (5 X 7) or 35 points and minimum of (1 X 7) or 7 points while maximum for
contributory time wastes is (5 X 3) or 15 points and minimum of (1 X 3) or 3 points. For section 4,
points are ranged from 1 to 4 but since correlation are not going to be tested in this section but
rather each item is going to be tested separately with One-way t-test for ranking purposes,
therefore not aggregation of points are required.
After all the primary data have been collected and processed, those data will then be analysed
according to the appropriate analysis methods. Analysis methods in this research are mainly divided
into 2 parts: (1) Descriptive analysis and (2) Inferential statistical analysis. Descriptive statistical
analysis is used to present the background profiles about the respondents and provide further
information for the inferential statistical analysis, besides that, the analysis on the descriptive data
about the waste recognition and waste control events in section 1 & 2 will also be conducted under
the same category. Inferential statistical analysis will be used to test certain research hypothesis,
type of analysis tools to be used include Coefficient Pearson r for correlation testing and one-way
t-test for frequencies ranking.
Inferential statistic analysis will use correlation Pearson-r to conduct testing on 9 hypotheses to see
whether any significant inter-relationship existed between understanding of wastes and actual
control practices of wastes in construction processes based on 3 cases of waste categories. The 9
hypotheses are:
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
31
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
In every case above, the correlation Pearson-r will tell us the magnitude and direction of the
association between two variables. In SPSS, the outcomes of the Pearson-r analysis will provide us
three pieces of information: (1) the correlation coefficient, (2) the significance and (3) the number
of cases (N). The correlation coefficient is a number between +1 and -1. This number tells us about
the magnitude and direction of the association between two variables. The magnitude is the
strength of the correlation. The closer the correlation is to either +1 or -1, the stronger the
correlation. If the correlation is 0 or very close to zero, there is no association between the two
variables. The direction of the correlation tells us how the two variables are related.
One-Way t-test will be carried out basically to get the ranking on the frequencies of occurrence of
the wastes elements in section 3 and the likelihood of recognition certain wastes causes factors as
in section 4. In SPSS, the outcomes of the One-Way t-test analysis will provide us four pieces of
information: (1) the number of cases (N), (2) the mean value, (3) the standard deviation and (4) the
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
32
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
standard error means. The ranking will be done separately in a descending order from the greatest
magnitude of the mean value to the lowest mean value to differentiate the degree of frequencies
and likelihood from the less significant to the most significant as rated by the respondent of the
research.
The last part of the analysis will be involving the development of the Causes and Effects Matrix table
by combining all the inputs by the respondents in section 5 into the whole list of construction
wastes and waste causes table. From there, descriptive statistic analysis will take place in sorting out
the wastes causes factors and put them into 6 wastes factors as discussed previously and represent
the Matrix Table in Bar charts format for easy interpretation of the results.
16
14
12
10
NO'S
0
construct
project project general resident quality highway site
ion
manager planner manager engineer engineer engineer engineer
manager
Series 1 15 10 4 10 10 10 8 14
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
33
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
17 ON BOT BASIS.
DURATION :- 30 MONTHS.
CASE STUDY 2
DURATION :- 30 MONTHS.
PVT. LTD
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
34
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CASE STUDY 3
DURATION :- 12 MONTHS.
CASE STUDY 4
DURATION :- 18 MONTHS.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
35
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CASE STUDY 5
DURATION :- 18 MONTHS.
CASE STUDY 6
DURATION :- 30 MONTHS.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
36
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CASE STUDY 7
DURATION :- 24 MONTHS.
CASE STUDY 8
DURATION :- 36 MONTHS.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
37
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CASE STUDY 9
DURATION :- 30 MONTHS.
CASE STUDY 10
BHADRAK TO BALASORE
DURATION :- 24 MONTHS.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
38
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CHAPTER 4
DATA
ANALYSIS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
39
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
This chapter will present all the results obtained from the data analysis waste concepts and waste
causes factors in construction processes. Descriptive statistic analysis and inferential statistic
analysis will be utilised to present the results. The presentation of analysis of descriptive statistic
analysis will be conducted in the form of bar charts, pie charts and matrix tables to show the
distribution and frequencies of the particular variables. The presentation of analysis of inferential
statistic analysis will be done by using result outputs generated directly from SPSS 16. The
respondents for this research consists of 81 project and site management personnel with a wide
spectrum of positions ranging from project manager, project planner, general manager, construction
manager, resident engineer, quality engineer, highway engineer, site engineer & manager.
The descriptive analysis on the respondents waste perceptions and control actions will mainly
focusing on identifying the numbers of counts on wastes recognised and waste events controlled as
reckon by the respondents for 3 waste categories namely, direct conversion wastes, non
contributory wastes and contributory wastes.
Since the lean construction philosophy considered all those waste elements as tabulated in the
questionnaires as construction wastes which need to be reduced, eliminated or somehow
controlled, the degree of perceptions on wastes for the local construction industries eventually can
be verified by determining the numbers of positive counts on each of those wastes elements.
Besides that, an analysis over a matrix tables by crosstabbing both the waste concepts and waste
control actions will be carried out to study the frequencies of 4 different potential scenarios which
are anticipated to be occurred.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
40
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Under this category, there are 9 wastes elements. Those items are indexed as F, G, H, I, J, K, L, N,
S in the section A, B and C of the questionnaires. For the total of 81 respondents by calculation as
(9 X 81), it sums up a total of 729 overall counts of inputs. For construction waste recognition, all
the inputs are tabulated in Table 4.1 below and a total of 612 positive counts are recorded or
approximately 84% and it is shown a high recognition on the waste concepts for the elements
tested in this category.
This analysis concluded that a high recognition rate on direct conversion wastes by the
respondents. The breakdown of numbers of the waste elements recognised as wastes under this
direct conversion category are shown in Figure 6. The result shows that Item N: (Materials for
rework/ repair works/ defective work) is the most recognized construction wastes with 78 positive
counts while Item F: (Over-allocation/ Unnecessary equipment) is the least recognised construction
wastes with only 57 positive counts under the direct conversion waste category.
90
80
70
60
50
40
30
20
10
0
F G H I J K L N S
NON WASTE 24 15 21 15 12 9 6 3 12
WASTE 57 66 60 66 69 72 75 78 69
RECOGNITION CASES
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
41
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
F G H I J K L N S
1 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 1 1) NON WASTE
3 2 2 2 1 2 2 2 2 2 2) WASTE
4 2 2 2 2 2 2 2 2 2
5 1 1 1 1 2 2 2 2 2
6 2 2 2 2 2 2 2 2 2
7 2 2 2 2 2 2 1 2 2
8 1 1 1 2 1 1 2 1 2
9 1 1 1 2 2 2 2 2 2 LEGEND :-
10 1 1 1 2 1 1 1 2 2
11 2 2 2 2 2 2 2 2 2 F) Over allocation/unnecessary equipments on site
12 2 2 2 1 2 2 2 2 2
13 2 2 2 2 1 2 2 2 1 G) Over allocation/unnecessary materials on site
14 2 2 2 2 2 2 2 2 2
15 2 2 2 1 2 1 2 2 2 H) Over allocation/unnecessary workers on site
16 2 2 2 2 2 2 2 2 2
17 2 2 2 2 2 2 2 2 2 I) Unnecessary procedures & working protocols
18 2 2 2 2 2 2 2 2 2
19 1 2 1 2 2 2 2 2 2 J) Material loss/stolen from site during
20 2 2 2 2 2 2 2 2 2
21 2 2 2 2 1 2 2 2 1
construction periods
22 2 2 1 1 2 2 2 2 2
23 2 2 2 2 2 2 2 2 2 K) Material deterioration/damage during
24 1 2 2 2 2 2 2 2 2 construction periods
25 2 2 2 2 2 2 2 2 1
26 1 1 1 2 2 2 2 2 2 L) Mishandling or error in construction
27 1 2 2 2 2 2 2 2 2 applications/installation
28 2 2 2 2 2 2 2 2 2
29 2 2 2 2 2 2 2 2 1 N) Material for rework/repair works/defective
30 2 2 2 1 2 2 2 2 2
31 2 2 2 2 2 2 2 2 2
works
32 1 1 1 1 2 2 2 2 2
33 2 2 2 2 2 2 2 2 2 S) Accidents on site
34 2 2 2 2 2 2 1 2 2
35 1 1 1 2 1 1 2 1 2
36 1 1 1 2 2 2 2 2 2
37 1 1 1 2 1 1 1 2 2
38 2 2 2 2 2 2 2 2 2
39 2 2 2 1 2 2 2 2 2
40 2 2 2 2 1 2 2 2 1
41 2 2 2 2 2 2 2 2 2
42 2 2 2 1 2 1 2 2 2
43 2 2 2 2 2 2 2 2 2
44 2 2 2 2 2 2 2 2 2
45 2 2 2 2 2 2 2 2 2
46 1 2 1 2 2 2 2 2 2
47 2 2 2 2 2 2 2 2 2
48 2 2 2 2 1 2 2 2 1
49 2 2 1 1 2 2 2 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
42
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
50 2 2 2 2 2 2 2 2 2
51 1 2 2 2 2 2 2 2 2
52 2 2 2 2 2 2 2 2 1
53 1 1 1 2 2 2 2 2 2
54 1 2 2 2 2 2 2 2 2
55 2 2 2 2 2 2 2 2 2
56 2 2 2 2 2 2 2 2 1
57 2 2 2 1 2 2 2 2 2
58 2 2 2 2 2 2 2 2 2
59 1 1 1 1 2 2 2 2 2
60 2 2 2 2 2 2 2 2 2
61 2 2 2 2 2 2 1 2 2
62 1 1 1 2 1 1 2 1 2
63 1 1 1 2 2 2 2 2 2
64 1 1 1 2 1 1 1 2 2
65 2 2 2 2 2 2 2 2 2
66 2 2 2 1 2 2 2 2 2
67 2 2 2 2 1 2 2 2 1
68 2 2 2 2 2 2 2 2 2
69 2 2 2 1 2 1 2 2 2
70 2 2 2 2 2 2 2 2 2
71 2 2 2 2 2 2 2 2 2
72 2 2 2 2 2 2 2 2 2
73 1 2 1 2 2 2 2 2 2
74 2 2 2 2 2 2 2 2 2
75 2 2 2 2 1 2 2 2 1
76 2 2 1 1 2 2 2 2 2
77 2 2 2 2 2 2 2 2 2
78 1 2 2 2 2 2 2 2 2
79 2 2 2 2 2 2 2 2 1
80 1 1 1 2 2 2 2 2 2
81 1 2 2 2 2 2 2 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
43
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
For construction waste events control, the total counts will calculated as (9 X 81) equal to 729Nos.
of inputs as tabulated in Table 4.2. A total of 531 positive counts are recorded appx. 73% and it
shows a slight drop in percentage on the waste control practices for the elements tested compared
to the construction waste recognized previously by the same set of respondents. In other words,
the respondents recognise the direct conversion wastes more than eventually control them.
However, the analysis result still shows that there are high control exercises on direct conversion
wastes as reported by the respondents. The breakdown of numbers of the waste elements
recognised as wastes under this direct conversion waste category are shown in Figure 7. From
chart in Fig. however it shows that Item F: (Overallocation/ Unnecessary equipment on site) have the
highest positive counts (69 Nos) on event controlled while Item S: (Accidents on site) is recorded as
the least event controlled with 39 Nos. of positive counts.
By cross tabbing of both Table 4.1 & 4.2 will result in a matrix table as show in Table 4.3 below.
This matrix table can be used to explain the inter-relationship between the direct conversion waste
concepts of the respondents with their actual control practices on construction processes. As
anticipated, there are 4 potential scenarios as observed, which are Case 1: Waste recognised and
controlled; Case 2: Waste not recognised and not controlled; Case 3: Waste recognised but not
controlled and Case 4: Waste not recognised but controlled.
From the analysis, it is found that Case 1 is the most occurrence scenario with 438 cases (60%)
followed by Case 3: 174 cases (23.86%), Case 4: 93 cases (12.75%) and finally Case 2: 24 cases
(3.3%). However, These results show that over half of the direct conversion construction wastes
have fully been recognised and controlled simultaneously but this analysis result is not very
convincing as there are still very high percentage of cases where wastes were partially recognised
and controlled and not recognised and controlled at all.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
44
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
F G H I J K L N S
1 2 2 2 2 1 1 2 2 1
2 2 2 2 2 1 1 2 2 1 1) NOT CONTROL
3 2 2 2 2 1 2 2 2 1 2) CONTROL
4 2 2 2 2 1 2 2 2 1
5 1 1 1 2 2 2 2 2 2
6 2 2 2 2 2 2 2 2 2
7 2 2 2 1 1 2 1 2 1
8 2 2 2 2 2 2 2 2 2
9 2 2 2 2 2 2 2 2 2 LEGEND :-
10 2 2 2 1 1 1 2 1 1
11 1 1 1 2 2 2 1 2 1 F) Over allocation/unnecessary equipments on site
12 2 2 2 1 2 2 2 1 2
13 2 2 2 1 2 2 1 2 2 G) Over allocation/unnecessary materials on site
14 2 1 1 1 1 1 1 1 1
15 2 2 2 2 2 2 2 1 1
H) Over allocation/unnecessary workers on site
16 2 2 2 2 2 1 2 2 2
17 2 2 2 2 2 2 2 2 2
18 1 1 1 2 2 2 2 2 2 I) Unnecessary procedures & working protocols
19 2 2 2 2 2 2 2 2 1
20 2 2 2 2 1 2 2 2 1 J) Material loss/stolen from site during
21 2 2 2 1 2 2 2 2 2 construction periods
22 2 2 2 2 2 2 2 2 2
23 1 1 1 2 2 2 1 1 1 K) Material deterioration/damage during
24 2 1 1 1 2 2 2 1 1 construction periods
25 2 2 2 1 1 1 2 2 2
26 2 2 2 2 1 1 2 2 1
L) Mishandling or error in construction
27 2 2 2 2 2 2 2 2 2
28 2 2 2 2 1 1 2 2 1 applications/installation
29 2 2 2 2 1 1 2 2 1
30 2 2 2 2 1 2 2 2 1 N) Material for rework/repair works/defective
31 2 2 2 2 1 2 2 2 1 works
32 1 1 1 2 2 2 2 2 2
33 2 2 2 2 2 2 2 2 2 S) Accidents on site
34 2 2 2 1 1 2 1 2 1
35 2 2 2 2 2 2 2 2 2
36 2 2 2 2 2 2 2 2 2
37 2 2 2 1 1 1 2 1 1
38 1 1 1 2 2 2 1 2 1
39 2 2 2 1 2 2 2 1 2
40 2 2 2 1 2 2 1 2 2
41 2 1 1 1 1 1 1 1 1
42 2 2 2 2 2 2 2 1 1
43 2 2 2 2 2 1 2 2 2
44 2 2 2 2 2 2 2 2 2
45 1 1 1 2 2 2 2 2 2
46 2 2 2 2 2 2 2 2 1
47 2 2 2 2 1 2 2 2 1
48 2 2 2 1 2 2 2 2 2
49 2 2 2 2 2 2 2 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
45
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
90
80
70
60
50
NO'S
40
30
20
10
0
F G H I J K L N S
NON CONTROL 12 18 18 24 30 21 18 18 42
CONTROL 69 63 63 57 51 60 63 63 39
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
46
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
F G H I J K L N S
1 Case 1 :- waste & control
2
3 Case 2 :- Nonwaste & non control
4
5
Case 3:- waste & non control
6
Case 4 :- non waste & control
7
8
9
LEGEND :-
10
11 F) Over allocation/unnecessary equipments on site
12
13 G) Over allocation/unnecessary materials on site
14
15 H) Over allocation/unnecessary workers on site
16
I) Unnecessary procedures & working protocols
17
18 J) Material loss/stolen from site during
19 construction periods
20
21 K) Material deterioration/damage during
22 construction periods
23
24 L) Mishandling or error in construction
25 applications/installation
26
27
N) Material for rework/repair works/defective
28
works
29
S) Accidents on site
30
31
32
33
34
35
36
37
38
39
40
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
47
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
TABLE 4.3 :- MATRIX TABLE FOR
78 DIRECT CONVERSION WASTE
79
80
81
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
48
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Under this category, there are only 7 wastes elements indexed as A, B, C, D, E, M and O in the
section A, B and C of the questionnaires. For the total of 81 respondents by calculation as (7 X 81),
it sums up a total of 567 overall counts of inputs.
For construction waste recognition, all the inputs are tabulated in Table 4.4 below and a total of
387 positive counts are recorded or approximately 68% and it is still a high recognition on the
waste concepts for the elements tested in this category but it is relatively lower in percentage
compared to analysis carried out previously on direct conversion waste.
The breakdown of numbers of the waste elements recognised as wastes under this
noncontributory time waste category are shown in Figure 8. It is worthwhile to point out that
most of the respondents do not recognised Item O: (Time for workers resting during construction) as
construction as only 15 out of 81 respondents recognised it as construction waste. On the
opposite side, the most recognised construction waste under this non-contributory time waste
category is Item M: (Time for rework/ repair work/ defective works) which recorded a 75 positive
counts out of the maximum 81.
Same is the case for the controlled events which is tabulated in Table 4.5 & total of 465 counts
have been recorded or appx.82% and it shows an increase in percentage on the waste event
control for the elements tested compared to the construction waste recognised under this
category.
The breakdown of numbers of the waste elements recognised as wastes under this
noncontributory time waste category are shown in Figure 9. It shows that Item E:
(Waiting for the clarification and confirmation by client and consultants) is the least controlled waste
event where more than half of the respondents reported as waste event not being controlled. Item
B: (Waiting for equipment to be delivered on site) on the other hand recorded a perfect waste control
event.
Same as direct conversion waste analysis, the cross tabbing of both Table 4.4 & 4.5 for non-
contributory waste will result in a matrix table as show in Table 4.6. This matrix table can be used
to explain the inter-relationship between the non-contributory waste concepts of the respondents
with their actual control practices on construction processes. Again, 4 potential scenarios cases are
investigated for non-contributory time waste category.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
49
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A B C D E M O
1 1 2 2 2 1 2 1 1)NON WASTE
2 2 2 2 2 2 2 1
3 2 1 1 1 1 2 1 2) WASTE
4 2 1 1 2 2 2 1
5 2 2 2 2 2 2 1
6 2 2 2 2 1 2 2
7 2 2 1 2 2 2 1
8 2 2 2 2 2 1 1
9 2 2 2 2 2 2 1
10 1 1 1 1 2 1 2
11 2 2 2 2 2 2 1
LEGEND :-
12 2 2 2 2 1 2 2
13 1 1 2 2 1 2 1
A) Waiting for others to complete their works
14 2 2 2 2 2 2 1
15 1 2 2 2 2 2 1 before the proceedings works can be carried out
16 2 2 2 2 2 2 2
17 1 1 1 1 2 2 1 B) Waiting for equipments to be delivered on site
18 2 2 2 2 1 2 1
19 2 2 2 2 2 2 1 C) Waiting for materials to be delivered on site
20 2 1 1 2 2 2 1
21 1 1 1 2 2 2 1 D) Waiting for skilled workers to be on site
22 2 2 2 2 1 2 2
23 2 1 1 1 1 2 1 E) Waiting for clarification & confirmation by client
24 2 2 2 2 2 2 1
& consultants
25 2 2 2 2 2 2 1
26 2 2 2 2 1 2 1
27 2 1 2 2 2 2 1
M) Time for rework/repair works/defective works
28 1 2 2 2 1 2 1
29 2 2 2 2 2 2 1 O) Time for workers resting during construction
30 2 1 1 1 1 2 1
31 2 1 1 2 2 2 1
32 2 2 2 2 2 2 1
33 2 2 2 2 1 2 2
34 2 2 1 2 2 2 1
35 2 2 2 2 2 1 1
36 2 2 2 2 2 2 1
37 1 1 1 1 2 1 2
38 2 2 2 2 2 2 1
39 2 2 2 2 1 2 2
40 1 1 2 2 1 2 1
41 2 2 2 2 2 2 1
42 1 2 2 2 2 2 1
43 2 2 2 2 2 2 2
44 1 1 1 1 2 2 1
45 2 2 2 2 1 2 1
46 2 2 2 2 2 2 1
47 2 1 1 2 2 2 1
48 1 1 1 2 2 2 1
49 2 2 2 2 1 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
50
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
50 2 1 1 1 1 2 1
51 2 2 2 2 2 2 1
52 2 2 2 2 2 2 1
53 2 2 2 2 1 2 1
54 2 1 2 2 2 2 1
55 1 2 2 2 1 2 1
56 2 2 2 2 2 2 1
57 2 1 1 1 1 2 1
58 2 1 1 2 2 2 1
59 2 2 2 2 2 2 1
60 2 2 2 2 1 2 2
61 2 2 1 2 2 2 1
62 2 2 2 2 2 1 1
63 2 2 2 2 2 2 1
64 1 1 1 1 2 1 2
65 2 2 2 2 2 2 1
66 2 2 2 2 1 2 2
67 1 1 2 2 1 2 1
68 2 2 2 2 2 2 1
69 1 2 2 2 2 2 1
70 2 2 2 2 2 2 2
71 1 1 1 1 2 2 1
72 2 2 2 2 1 2 1
73 2 2 2 2 2 2 1
74 2 1 1 2 2 2 1
75 1 1 1 2 2 2 1
76 2 2 2 2 1 2 2
77 2 1 1 1 1 2 1
78 2 2 2 2 2 2 1
79 2 2 2 2 2 2 1
80 2 2 2 2 1 2 1
81 2 1 2 2 2 2 1
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
51
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A B C D E M O
1 2 2 2 2 1 2 2
2 2 2 2 2 2 2 2 1) NOT CONTROL
3 2 2 2 2 2 2 2
2) CONTROL
4 2 2 2 2 1 2 2
5 2 2 2 2 2 2 2
6 2 2 2 2 2 2 2
7 2 2 2 2 1 2 2
8 2 2 2 2 2 2 2
9 2 2 2 2 2 2 2
10 2 2 2 2 1 2 1
11 2 2 2 1 2 2 1
12 2 2 2 2 1 1 1 LEGEND :-
13 2 2 1 1 1 2 2
14 1 2 1 1 1 1 1 A) Waiting for others to complete their works
15 2 2 2 2 1 1 2
16 2 2 2 2 2 2 2 before the proceedings works can be carried out
17 2 2 2 2 2 2 2
18 2 2 2 2 2 2 1 B) Waiting for equipments to be delivered on site
19 2 2 2 2 1 2 2
20 2 2 2 2 2 2 2 C) Waiting for materials to be delivered on site
21 2 2 1 1 1 2 2
22 2 2 2 2 1 2 2 D) Waiting for skilled workers to be on site
23 2 2 2 2 2 1 1
24 2 2 2 1 1 2 2 E) Waiting for clarification & confirmation by client
25 2 2 2 2 1 2 1 & consultants
26 2 2 2 2 2 2 2
27 2 2 2 2 1 2 2
M) Time for rework/repair works/defective works
28 2 2 2 2 1 2 2
29 2 2 2 2 2 2 2
30 2 2 2 2 2 2 2
O) Time for workers resting during construction
31 2 2 2 2 1 2 2
32 2 2 2 2 2 2 2
33 2 2 2 2 2 2 2
34 2 2 2 2 1 2 2
35 2 2 2 2 2 2 2
36 2 2 2 2 2 2 2
37 2 2 2 2 1 2 1
38 2 2 2 1 2 2 1
39 2 2 2 2 1 1 1
40 2 2 1 1 1 2 2
41 1 2 1 1 1 1 1
42 2 2 2 2 1 1 2
43 2 2 2 2 2 2 2
44 2 2 2 2 2 2 2
45 2 2 2 2 2 2 1
46 2 2 2 2 1 2 2
47 2 2 2 2 2 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
52
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
48 2 2 1 1 1 2 2
49 2 2 2 2 1 2 2
50 2 2 2 2 2 1 1
51 2 2 2 1 1 2 2
52 2 2 2 2 1 2 1
53 2 2 2 2 2 2 2
54 2 2 2 2 1 2 2
55 2 2 2 2 1 2 2
56 2 2 2 2 2 2 2
57 2 2 2 2 2 2 2
58 2 2 2 2 1 2 2
59 2 2 2 2 2 2 2
60 2 2 2 2 2 2 2
61 2 2 2 2 1 2 2
62 2 2 2 2 2 2 2
63 2 2 2 2 2 2 2
64 2 2 2 2 1 2 1
65 2 2 2 1 2 2 1
66 2 2 2 2 1 1 1
67 2 2 1 1 1 2 2
68 1 2 1 1 1 1 1
69 2 2 2 2 1 1 2
70 2 2 2 2 2 2 2
71 2 2 2 2 2 2 2
72 2 2 2 2 2 2 1
73 2 2 2 2 1 2 2
74 2 2 2 2 2 2 2
75 2 2 1 1 1 2 2
76 2 2 2 2 1 2 2
77 2 2 2 2 2 1 1
78 2 2 2 1 1 2 2
79 2 2 2 2 1 2 1
80 2 2 2 2 2 2 2
81 2 2 2 2 1 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
53
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
90
80
70
60
50
NO'S
40
30
20
10
0
A B C D E M O
NONWASTE 18 27 24 12 27 6 66
WASTE 63 54 57 69 54 75 15
90
80
70
60
50
NO'S
40
30
20
10
0
A B C D E M O
NON CONTROL 3 0 9 15 42 12 21
CONTROL 78 81 72 66 39 69 60
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
54
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A B C D E M
1 Case 1 :- waste & control
2
3 Case 2 :- Nonwaste & non control
4
Case 3:- waste & non control
5
6 Case 4 :- non waste & control
7
8
9
10
11 LEGEND :-
12
13
A) Waiting for others to complete their works
14
before the proceedings works can be carried out
15
B) Waiting for equipments to be delivered on site
16
17 C) Waiting for materials to be delivered on site
18
19 D) Waiting for skilled workers to be on site
20
21 E) Waiting for clarification & confirmation by client
22 & consultants
23
M) Time for rework/repair works/defective works
24
25 O) Time for workers resting during construction
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
55
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
TABLE 4.6 :- MATRIX DIAGRAM FOR
77
NON CONTRIBUTORY WASTE
78
79
80
81
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
56
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Under this category, there are only 3 wastes elements indexed as P, Q & R in the section A, B and
C of the questionnaires. For the total of 81 respondents by calculation as (3 X 81), it sums up a
total of 243 overall counts of inputs. For construction waste recognition, all the inputs are tabulated
in Table 4.7 below and a total of 30 positive counts are recorded or approximately 12% and this a
very low recognition on the waste concepts for the elements tested under this category compared
to analysis carried out previously on direct conversion waste and non-contributory time waste.
The breakdown of numbers of the waste elements recognised as wastes under this contributory
time waste category are shown in Figure 10. It is not surprising to see that all the 3 items
registered under contributory time wastes are recording significant negative counts, which
represent non waste recognition for the contributory time wastes. Very much different with the
first 2 waste recognition analysis, all 3 items are recording high negative counts that above 20
counts where Item P: (Time in supervising and inspecting the construction works) with the greatest
numbers of negative counts (26 Nos.) followed by Item R: (Time for transporting workers, equipment
and materials) 23 Nos. and Item Q: (Time for instructions and communication among different tiers and
trades of workers) 22 Nos.
Same is the case for the controlled events which is tabulated in Table 4.8 & total of 216 counts
have been recorded or appx.89% and it shows an increase in percentage on the waste event
control for the elements tested compared to the construction waste recognised under this
category. The breakdown of numbers of the waste elements recognised as wastes under this
contributory time waste category are shown in Figure 11. It shows that all the 3 items are having
high positive counts for waste event control where all 3 items of contributory time waste are
recording above 20 Nos. of positive counts lead by Item P: (Time in supervising and inspecting the
construction works) with 78 Nos.
Again, by cross tabbing of both Table 4.7 & 4.8 for contributory waste will result in a matrix table
as show in Table 4.9. Therefore, the inter-relationship between the contributory waste concepts
of the respondents with their actual control practices on construction processes can be explained
using this matrix table. 4 potential scenarios cases are to be investigated for contributory time
waste category.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
57
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
P Q R P Q R
1 1 2 2 1 1 1 2
1) NON WASTE
2 1 1 1 2 2 2 2 2) WASTE
3 1 1 1 3 2 2 2
4 1 1 1 4 2 2 2
5 1 1 1 5 2 2 2
6 1 1 1 6 2 2 2 1) NOT CONTROL
7 1 1 1 7 2 2 2 2) CONTROL
8 1 1 1 8 2 2 2
9 1 1 1 9 2 2 2
10 2 1 1 10 1 1 1
11 1 1 2 11 2 2 2
12 1 1 1 12 2 2 2
13 1 1 1 13 2 2 2
14 1 1 1 14 2 2 2 LEGEND :-
15 1 1 1 15 2 2 2
16 1 1 2 16 2 2 2 P) Time in supervising / inspecting the
17 1 2 1 17 2 2 2
18 1 1 1 18 2 1 2 construction works
19 1 1 1 19 2 2 2
20 1 1 1 20 2 2 2 Q) Time for instructions & communication
21 1 1 1 21 2 2 2 among different tiers & trades of workers
22 1 2 1 22 1 2 2
23 1 2 2 23 2 1 2 R) Time for transporting workers, equipments
24 1 1 1 24 2 2 2 & materials
25 1 2 1 25 2 2 2
26 1 1 1 26 1 2 2
27 1 1 1 27 2 2 2
28 1 2 2 28 1 1 2
29 1 1 1 29 2 2 2
30 1 1 1 30 2 2 2
31 1 1 1 31 2 2 2
32 1 1 1 32 2 2 2
33 1 1 1 33 2 2 2
34 1 1 1 34 2 2 2
35 1 1 1 35 2 2 2
36 1 1 1 36 2 2 2
37 2 1 1 37 1 1 1
38 1 1 2 38 2 2 2
39 1 1 1 39 2 2 2
40 1 1 1 40 2 2 2
41 1 1 1 41 2 2 2
42 1 1 1 42 2 2 2
43 1 1 2 43 2 2 2
44 1 2 1 44 2 2 2
45 1 1 1 45 2 1 2
46 1 1 1 46 2 2 2
47 1 1 1 47 2 2 2
48 1 1 1 48 2 2 2
49 1 2 1 49 1 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
58
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
50 1 2 2 50 2 1 2
51 1 1 1 51 2 2 2
52 1 2 1 52 2 2 2
53 1 1 1 53 1 2 2
54 1 1 1 54 2 2 2
55 1 2 2 55 1 1 2
56 1 1 1 56 2 2 2
57 1 1 1 57 2 2 2
58 1 1 1 58 2 2 2
59 1 1 1 59 2 2 2
60 1 1 1 60 2 2 2
61 1 1 1 61 2 2 2
62 1 1 1 62 2 2 2
63 1 1 1 63 2 2 2
64 2 1 1 64 1 1 1
65 1 1 2 65 2 2 2
66 1 1 1 66 2 2 2
67 1 1 1 67 2 2 2
68 1 1 1 68 2 2 2
69 1 1 1 69 2 2 2
70 1 1 2 70 2 2 2
71 1 2 1 71 2 2 2
72 1 1 1 72 2 1 2
73 1 1 1 73 2 2 2
74 1 1 1 74 2 2 2
75 1 1 1 75 2 2 2
76 1 2 1 76 1 2 2
77 1 2 2 77 2 1 2
78 1 1 1 78 2 2 2
79 1 2 1 79 2 2 2
80 1 1 1 80 1 2 2
81 1 1 1 81 2 2 2
INPUTS OF INPUTS OF
CONSTRUCTION CONSTRUCTION
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
59
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
90
80
70
60
50
40
30
20
10
0
P Q R
NON WASTE 78 66 69
WASTE 3 15 12
90
80
70
60
50
NO'S
40
30
20
10
0
P Q R
NON CONTROL 3 15 12
CONTROL 78 66 69
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
60
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
P Q R
1
2 Case 1 :- waste & control
3
4 Case 2 :- Nonwaste & non control
5
6
Case 3:- waste & non control
7
Case 4 :- non waste & control
8
9
10
11
12
13 LEGEND :-
14
15
P) Time in supervising / inspecting the construction
16 works
17
Q) Time for instructions & communication among
18
different tiers & trades of workers
19
20 R) Time for transporting workers, equipments &
21 materials
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
61
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75 TABLE 4.9 :- MATRIX DIAGRAM
76
FOR CONTRIBUTORY TIME WASTE
77
78
79
80
81
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
62
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
This section will discuss about the analysis results from inferential analysis. Statistic tools such as
correlation Pearson-r and One-Way t-test will be utilised to test some hypotheses of the study and
determine the frequency ranking of each particular event or case as rated by the respondents.
These 3 hypotheses are to be tested together using correlation Pearson r, and the results show
that there are not significant correlations among each other (refer Table 4.10) as the two-tail sig.
value (K) is more than 0.05 for 3 cases tested. Hence Hypothesis 1, 2 and 3 is rejected.
HYPOTHESIS 1 TEST
Variables D WASTE 1
D WASTE 2 -.145
K = .314> .05
HYPOTHESIS 2 TEST
Variables D WASTE 1
D WASTE 3 -.040
K = .575>.05
HYPOTHESIS 3 TEST
Variables D WASTE 2
D WASTE 3 - .056
K= .593> .05
Table 4.10 showing Correlation Pearson-r results summaries for hypothesis 1, 2 and 3
(Refer Appendix 1 for Correlation Pearson-r result outputs from SPSS 16.0)
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
63
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Same as direct conversion wastes, there are 3 hypotheses to be tested under this noncontributory
wastes category:
These 3 hypotheses are to be tested together using correlation Pearson r, and the results show
that there are not significant correlations among each other (refer Table 4.11) as the two-tail sig.
value (K) is more than 0.05 for 3 cases tested. Hence Hypothesis 4, 5 and 6 is rejected.
HYPOTHESIS 4 TEST
Variables NON CON 1
NON CON 2 .026
K = .224> .05
HYPOTHESIS 5 TEST
Variables NON CON 1
NON CON 3 -.291
K = .470>.05
HYPOTHESIS 6 TEST
Variables NON CON 2
NON CON 3 .325
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
64
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Same as previous 2 wastes categories, there are 3 hypotheses to be tested under this contributory
wastes category:
These 3 hypotheses are to be tested together using correlation Pearson r, and the results show
that there are significant correlations between the way contributory time wastes have been
perceived (CON1) with the tendency to control those wastes (CON2) as the 2-tail sig. value (K)
signify the correlation is significant at 0.01 level or value K < 0.01 with a negative correlation (r = -
.551) whereas the other 2 cases are tested non-significant with the 2-tail sig. value (K) is more than
0.05. (Refer Table 4.12) Hence Hypothesis 7 is accepted and hypothesis 8 and 9 is rejected.
HYPOTHESIS 7 TEST
Variables CON 1
CON 2 -.555
HYPOTHESIS 8 TEST
Variables CON 1
CON 3 -.223
K = .217>.05
HYPOTHESIS 9 TEST
Variables CON 2
CON 3 .281
Table 4.12 showing Correlation Pearson-r results summaries for hypothesis 7, 8 and 9
(Refer Appendix 1 for Correlation Pearson-r result outputs from SPSS 16.0)
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
65
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
66
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
From the mean ranking results, it shows that time wastes categories regardless of contributory
time or non-contributory time wastes occurred at the top of the list compared to direct
conversion wastes. Therefore, it is recommended that for construction processes improvements, it
is eventually those contributory and noncontributory times waste variables that have to be given
more attentions and in real fact, most of them are related to process flows and sequences and this
can lead to lean constructions tools and methods which are developed mostly to tackle those
wastes resulted from process flow inefficiencies.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
67
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
68
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
As from the mean ranking result shows that Item E2: (Late information and decision making) is highly
regarded as the main contributory sources or causes to the construction wastes with the highest
mean value (3.63) and with a 0.26 from the second rank item D2: (Poorly scheduled delivery of
material to site).
Among the clusters of cause factors observed from Table 6.14, there are 3 categories of waste
sources/ causes factors are widely acknowledged as the key contributory factors to construction
wastes. Those categories included Information and Communication Factors, Management and
Administration Factors and Material Factors as most of the Cause factors captured under these 3
categories are rated with the mean value over 3.
Overall, the likelihood of recognising the items above as the sources/ causes of wastes that will
impact on the productivity of the projects, are still reasonably high as most of the mean value for
the items tested were clustering around the scale 3 value representing likely as a sources/ causes
of wastes. However, there are also some exceptions such as Item C1: (Inappropriate construction
methods) and Item C2: (Outdated equipment) both recorded a slightly low mean values of 2.67 and
2.52 respectively.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
69
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
major cause
70
60
50 not relevant
30 execution factors
people factors
20
management & adminstration
factors
10
0
A B C D E F G H I J K L M N O P Q R
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
70
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
other cause
100
90
80
not relevant
70
information & communication
60 factors
material factors
50
execution factors
40
people factors
30
10
0
A B C D E F G H I J K L M N O P Q R
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
71
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
The matrix table provides a clearer insight into the types of causes factors that directly related
construction wastes, as we shall see that in Figure 12, Management and Administration Factors has
a relatively high counts numbers in causing the construction wastes items ranging from Item A to
Item I and Item Q, Materials Factors dominants over Item J & K and People Factors score higher in
Item M, N and O. By conducting this causes and effects matrix exercise, we can know that each
types of construction wastes has a different roots causes to the problems and it is important to
identify those particular causes to the problems in order to a proper corrective or preventive
actions can be carried to ensure continuous improvement in performance of construction activities.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
72
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CHAPTER 5
CONCLUSION
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
73
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
CHAPTER 5 : CONCLUSION
5.0 INTRODUCTION
This chapter concludes the whole study based on the findings. The tested hypotheses will be
related to the research objectives and further interpreted and conclusion on the achievement of
the research objectives. Some recommendations will also be drawn from the findings and the
limitations during the research.
The discussion on the findings of the research will be carried in 2 separate ways:
1. Relating the research findings to research objectives
2. Rewritten hypotheses and interpret the results
In fact, lean construction philosophy sees these contributory works as not adding any values to the
client even though they are sometimes necessary for the progress of the overall construction
processes. On the bright side, the research results also show a very high percentage on those
contributory works as being controlled during the construction processes signaling that those
contributory time wastes are actually well aware off those activities even though they being not
recognised as construction wastes.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
74
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
Eventually by breaking down the waste categories, it is made clear that the flow time wastes are the
prominent events that occurred in construction processes. Therefore, based on that information, a
better performance improvement strategies can be arranged to target at those flow related wastes
events, as those events are usually invisible or ignored by conventional construction management.
The construction processes can be further streamlined by reducing or eliminating those flow waste
elements by implementing the lean construction principles and practices such as employee
involvements, kanzan, JIT concepts etc at all level of construction processes.
In this research, major sources of wastes are also been identified directly related to the respective
construction wastes from the wastes causes and effects matrix as shown in Appendix 4. From the
aggregated results shows that management and administrative factors are recognised as the
dominant sources of wastes for most of the cases while material factors and people factors are
more dominant for a few wastes types. If compared to the ranking of the likelihood for waste
factors to impact the construction productivity in general, information and communications factors
which are hardly seen as a dominant factor of any construction wastes types at the top of the
ranking list follow tightly by management and administrative factors. On the low side, the executive
factors and people factors scored relatively low in the ranking.
This is a very good exercise to point out the causes and effects relationship between the sources of
waste and waste itself for processes control, reengineering or redesign by targeting directly at the
respective sources of wastes for processes improvement. In most leaner construction organisition,
they usually practise this exercise in a survey called waste identification survey (WIS) through work
sampling practices in order to monitor and improve their flow performance from time to time
during their construction activities.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
75
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
The non-significant over almost all the hypotheses tested in correlation testing shows that there
were not uniformity in the way the construction waste are recognised and controlled even with the
high recognition and control rates. Recognising particular construction wastes or frequencies of
occurrence of construction wastes on site by the construction personnel do not prompt them to
control them and vice versa, recognizing construction wastes are not prompt by the frequencies of
occurrence of those wastes during construction site. The construction wastes are treated very
subjectively from cases to cases and suggested that no proper doctrine or philosophy in supporting
for particular waste recognition and control mechanism.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
76
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
In the importance of continuous process and productivity improvement, having the correct
concepts and understanding and having the right attitudes to mitigate and control the flow and flow
related wastes are very essence. In this case, the worst scenario would be someone actually not
knowing what is the waste and therefore not put in any efforts to control it and letting the wastes
to repeat from time to time. There might be some other reasons for not recognising wastes and
not controlling them. Some would not treat it as a waste as those wastes are recoverable due to
defaults by others and some misunderstanding that wastes are necessary to avoid others bigger
wastes from happening. For example, as cited from the only 1 qualitative inputs from all 81
questionnaires received stated that waiting for clarification and confirmation by client and
consultants is not a waste because he/ she believed that it is important to wait for clarification and
confirmation because lack of this will be more wastage (redo the task). From the results of cross-tab
matrix tables shows a relatively low percentage of that particular scenario and that should be a
good sign for the construction industries.
However, for the scenarios of knowing the wastes but not controlling them hit a rather high
numbers of cases and percentage especially in direct conversion wastes. This is particularly not a
good sign where those wastes are left behind the construction processes and hinder the full
potential of process improvement. The results to this might be abundant. One of the reason would
be the costs to control or improve the wastes might be higher that the cost of the wastes itself.
Besides that, the reasons of not control the wastes even the wastes are identified and recognised
perhaps is due to not sufficient tools and knowledge to control them and some might due to
misunderstanding during execution and not well trained personnel.
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
77
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
REFERENCES
1. Abdul Rashid Abdul Aziz and Abdul Aziz Hussin, (2003) Construction Safety In Malaysia: A
Review Of Industry Performance And Outlook For The Future in journal of Construction
Research, pp.146-148.
2. Alarcn, Luis F. (1993). Modeling waste and performance in construction. In Lean
Construction, Alarcn (Ed.), A.A. Balkema, Rotterdam, The Netherlands, 1997
3. Alarcn, Luis F. (1994). Tools for the identification and reduction of waste in construction
projects. In Lean Construction, Alarcn (Ed.), A.A. Balkema, Rotterdam, The Netherlands,
1997
4. Enton, David (1994). Lean production productivity improvements for construction
professions In Lean Construction, Alarcn (ed.), A.A. Balkema, Rotterdam, The Netherlands,
1997.
5. Formosa, Carlos T et al (2002) Material waste in building industry: main causes and
prevention. In Journel of Construction Engineering and Management, July/ August, pp. 316-318
6. Koskela, Lauri (1993).Lean production in construction. In Lean Construction, Alarcn (ed.),
A.A. Balkema, Rotterdam, The Netherlands, 1997.
7. Koskela, Lauri (1992). Application of new production philosophy to construction Tech. Rep. No
72, CIFE, Stanford, California
8. Koskela, Lauri (2000). An Exploration towards a production theory and its application to
construction, VTT Publication 408, Finland.
9. Taylor, T.W., (1913) The principles of scientific management, Harper and Brothers, New
York quoted in Formosa, Carlos T et al (2002) Material waste in building industry: main
causes and prevention. In Journal of Construction Engineering and Management, July/ August,
pp. 317
10. Womack, J and Jones, D. (1996). Lean Thinking. Simon & Schuster
WEBSITE:-
www. Leanconstruction.org
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
78
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
APPENDICES
APPENDIX - 1CORRELATION PEARSON R RESULTS FROM SPSS 16
CORRELATIONS :-
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
79
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
APPENDIX 2
ONE WAY T TEST RESULTS FROM SPSS 16.0
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
80
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
APPENDIX 3
(A) SPSS DATA INPUT SHEET (WASTE CONCEPTS)
A1 B1 C1 D1 E1 F1 G1 H1 I1 J1 K1 L1 M1 N1 O1 P1 Q1 R1 S1
1 2 2 2 1 2 2 2 2 2 2 2 2 2 1 1 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
2 1 1 1 1 2 2 2 1 2 2 2 2 2 1 1 1 1 2
2 1 1 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 1 1 1 1 2 2 2 2 2 1 1 1 1 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 1 1 1 2
2 2 1 2 2 2 2 2 2 2 2 1 2 2 1 1 1 1 2
2 2 2 2 2 1 1 1 2 1 1 2 1 1 1 1 1 1 2
2 2 2 2 2 1 1 1 2 2 2 2 2 2 1 1 1 1 2
1 1 1 1 2 1 1 1 2 1 1 1 1 2 2 2 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 2 2
2 2 2 2 1 2 2 2 1 2 2 2 2 2 2 1 1 1 2
1 1 2 2 1 2 2 2 2 1 2 2 2 2 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
1 2 2 2 2 2 2 2 1 2 1 2 2 2 1 1 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 2
1 1 1 1 2 2 2 2 2 2 2 2 2 2 1 1 2 1 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 1 2 1 2 2 2 2 2 2 1 1 1 1 2
2 1 1 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
1 1 1 2 2 2 2 2 2 1 2 2 2 2 1 1 1 1 1
2 2 2 2 1 2 2 1 1 2 2 2 2 2 2 1 2 1 2
2 1 1 1 1 2 2 2 2 2 2 2 2 2 1 1 2 2 2
2 2 2 2 2 1 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 1 1
2 2 2 2 1 1 1 1 2 2 2 2 2 2 1 1 1 1 2
2 1 2 2 2 1 2 2 2 2 2 2 2 2 1 1 1 1 2
1 2 2 2 1 2 2 2 2 2 2 2 2 2 1 1 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
2 1 1 1 1 2 2 2 1 2 2 2 2 2 1 1 1 1 2
2 1 1 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 1 1 1 1 2 2 2 2 2 1 1 1 1 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 1 1 1 2
2 2 1 2 2 2 2 2 2 2 2 1 2 2 1 1 1 1 2
2 2 2 2 2 1 1 1 2 1 1 2 1 1 1 1 1 1 2
2 2 2 2 2 1 1 1 2 2 2 2 2 2 1 1 1 1 2
1 1 1 1 2 1 1 1 2 1 1 1 1 2 2 2 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 2 2
2 2 2 2 1 2 2 2 1 2 2 2 2 2 2 1 1 1 2
1 1 2 2 1 2 2 2 2 1 2 2 2 2 1 1 1 1 1
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
81
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
1 2 2 2 2 2 2 2 1 2 1 2 2 2 1 1 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 2
1 1 1 1 2 2 2 2 2 2 2 2 2 2 1 1 2 1 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 1 2 1 2 2 2 2 2 2 1 1 1 1 2
2 1 1 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
1 1 1 2 2 2 2 2 2 1 2 2 2 2 1 1 1 1 1
2 2 2 2 1 2 2 1 1 2 2 2 2 2 2 1 2 1 2
2 1 1 1 1 2 2 2 2 2 2 2 2 2 1 1 2 2 2
2 2 2 2 2 1 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 1 1
2 2 2 2 1 1 1 1 2 2 2 2 2 2 1 1 1 1 2
2 1 2 2 2 1 2 2 2 2 2 2 2 2 1 1 1 1 2
1 2 2 2 1 2 2 2 2 2 2 2 2 2 1 1 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
2 1 1 1 1 2 2 2 1 2 2 2 2 2 1 1 1 1 2
2 1 1 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 1 1 1 1 2 2 2 2 2 1 1 1 1 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 1 1 1 2
2 2 1 2 2 2 2 2 2 2 2 1 2 2 1 1 1 1 2
2 2 2 2 2 1 1 1 2 1 1 2 1 1 1 1 1 1 2
2 2 2 2 2 1 1 1 2 2 2 2 2 2 1 1 1 1 2
1 1 1 1 2 1 1 1 2 1 1 1 1 2 2 2 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 2 2
2 2 2 2 1 2 2 2 1 2 2 2 2 2 2 1 1 1 2
1 1 2 2 1 2 2 2 2 1 2 2 2 2 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
1 2 2 2 2 2 2 2 1 2 1 2 2 2 1 1 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 2
1 1 1 1 2 2 2 2 2 2 2 2 2 2 1 1 2 1 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 1 2 1 2 2 2 2 2 2 1 1 1 1 2
2 1 1 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 2
1 1 1 2 2 2 2 2 2 1 2 2 2 2 1 1 1 1 1
2 2 2 2 1 2 2 1 1 2 2 2 2 2 2 1 2 1 2
2 1 1 1 1 2 2 2 2 2 2 2 2 2 1 1 2 2 2
2 2 2 2 2 1 2 2 2 2 2 2 2 2 1 1 1 1 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 1 1
2 2 2 2 1 1 1 1 2 2 2 2 2 2 1 1 1 1 2
2 1 2 2 2 1 2 2 2 2 2 2 2 2 1 1 1 1 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
82
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
83
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
2 2 2 2 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 1 1 1 2 2 2 2 2 2 1 2 1 2 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1
2 2 2 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2 1
2 2 1 1 1 2 2 2 1 2 2 2 2 2 2 2 2 2 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 1 2 2 2
2 2 2 2 2 1 1 1 2 2 2 1 1 1 1 2 1 2 1
2 2 2 1 1 2 1 1 1 2 2 2 2 1 2 2 2 2 1
2 2 2 2 1 2 2 2 1 1 1 2 2 2 1 2 2 2 2
2 2 2 2 2 2 2 2 2 1 1 2 2 2 2 1 2 2 1
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 1 2 2 2 2 1 1 2 2 2 2 1 1 2 1
2 2 2 2 2 2 2 2 2 1 1 2 2 2 2 2 2 2 1
2 2 2 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2 1
2 2 2 2 1 2 2 2 2 1 2 2 2 2 2 2 2 2 1
2 2 2 2 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 1 2 2 2 1 1 2 1 2 2 2 2 2 2 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 1 2 2 2 1 1 1 2 2 1 1 1 1 1 1
2 2 2 1 2 1 1 1 2 2 2 1 2 2 1 2 2 2 1
2 2 2 2 1 2 2 2 1 2 2 2 1 1 1 2 2 2 2
2 2 1 1 1 2 2 2 1 2 2 1 2 2 2 2 2 2 2
1 2 1 1 1 2 1 1 1 1 1 1 1 1 1 2 2 2 1
2 2 2 2 1 2 2 2 2 2 2 2 1 1 2 2 2 2 1
2 2 2 2 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 1 1 1 2 2 2 2 2 2 1 2 1 2 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 1
2 2 2 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2 1
2 2 1 1 1 2 2 2 1 2 2 2 2 2 2 2 2 2 2
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 1 2 2 2
2 2 2 2 2 1 1 1 2 2 2 1 1 1 1 2 1 2 1
2 2 2 1 1 2 1 1 1 2 2 2 2 1 2 2 2 2 1
2 2 2 2 1 2 2 2 1 1 1 2 2 2 1 2 2 2 2
2 2 2 2 2 2 2 2 2 1 1 2 2 2 2 1 2 2 1
2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
84
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A3 B3 C3 D3 E3 F3 G3 H3 I3 J3 K3 L3 M3 N3 O3 P3 Q3 R3 S3
3 3 3 2 5 4 4 4 4 3 4 4 3 3 3 3 3 2 4
3 3 2 2 4 3 3 2 4 2 2 3 4 4 3 5 4 3 2
3 3 4 3 4 3 3 3 3 3 3 3 3 3 3 4 4 4 2
4 3 3 3 4 3 4 4 4 4 4 3 4 4 3 5 4 3 3
4 3 4 3 3 3 3 3 3 2 2 2 3 3 2 3 3 4 2
4 4 4 3 3 3 4 3 3 4 4 4 4 4 5 5 5 3 3
3 1 2 1 4 1 2 2 2 4 4 5 4 3 2 5 5 2 3
2 2 2 1 2 3 3 2 1 1 2 2 2 2 2 4 4 2 1
4 3 3 3 3 2 2 2 2 3 3 2 3 3 3 4 3 3 2
3 4 2 3 4 3 4 3 2 4 3 3 3 4 2 4 3 3 3
5 4 5 3 3 3 3 2 4 3 4 3 4 2 2 3 4 3 3
5 3 3 4 4 3 3 1 3 2 2 2 3 3 3 5 5 4 2
3 3 4 4 4 3 3 2 3 3 3 2 3 2 3 3 3 3 3
4 2 3 2 5 2 4 2 4 3 5 5 5 5 3 2 2 4 3
4 4 4 3 5 3 3 3 3 4 3 4 4 4 5 5 4 5 3
4 5 5 4 4 1 2 2 3 3 3 2 3 3 4 5 5 5 2
3 3 2 2 3 1 1 1 1 2 2 2 4 4 3 4 4 1 2
4 4 4 2 4 1 2 1 3 3 3 3 3 3 2 4 3 4 3
4 3 3 3 3 3 3 4 3 4 4 3 4 4 3 4 4 3 3
3 4 4 4 5 2 2 3 5 3 3 3 4 4 3 5 4 3 3
4 4 4 4 4 3 4 2 4 3 3 3 3 4 2 4 3 4 3
4 3 2 1 3 1 3 2 2 3 3 3 2 3 3 4 4 4 1
3 4 5 3 4 3 2 2 2 4 3 4 4 3 4 3 4 4 2
4 2 3 2 3 2 3 2 3 2 1 2 3 3 4 4 3 3 3
4 2 3 2 5 3 2 2 4 3 3 3 3 3 2 3 4 3 2
3 3 3 2 4 2 3 3 3 4 4 4 3 3 3 4 4 2 2
5 3 3 3 4 2 4 3 3 4 4 3 3 4 3 4 4 4 3
3 3 3 2 5 4 4 4 4 3 4 4 3 3 3 3 3 2 4
3 3 2 2 4 3 3 2 4 2 2 3 4 4 3 5 4 3 2
3 3 4 3 4 3 3 3 3 3 3 3 3 3 3 4 4 4 2
4 3 3 3 4 3 4 4 4 4 4 3 4 4 3 5 4 3 3
4 3 4 3 3 3 3 3 3 2 2 2 3 3 2 3 3 4 2
4 4 4 3 3 3 4 3 3 4 4 4 4 4 5 5 5 3 3
3 1 2 1 4 1 2 2 2 4 4 5 4 3 2 5 5 2 3
2 2 2 1 2 3 3 2 1 1 2 2 2 2 2 4 4 2 1
4 3 3 3 3 2 2 2 2 3 3 2 3 3 3 4 3 3 2
3 4 2 3 4 3 4 3 2 4 3 3 3 4 2 4 3 3 3
5 4 5 3 3 3 3 2 4 3 4 3 4 2 2 3 4 3 3
5 3 3 4 4 3 3 1 3 2 2 2 3 3 3 5 5 4 2
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
85
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
3 3 4 4 4 3 3 2 3 3 3 2 3 2 3 3 3 3 3
4 2 3 2 5 2 4 2 4 3 5 5 5 5 3 2 2 4 3
4 4 4 3 5 3 3 3 3 4 3 4 4 4 5 5 4 5 3
4 5 5 4 4 1 2 2 3 3 3 2 3 3 4 5 5 5 2
3 3 2 2 3 1 1 1 1 2 2 2 4 4 3 4 4 1 2
4 4 4 2 4 1 2 1 3 3 3 3 3 3 2 4 3 4 3
4 3 3 3 3 3 3 4 3 4 4 3 4 4 3 4 4 3 3
3 4 4 4 5 2 2 3 5 3 3 3 4 4 3 5 4 3 3
4 4 4 4 4 3 4 2 4 3 3 3 3 4 2 4 3 4 3
4 3 2 1 3 1 3 2 2 3 3 3 2 3 3 4 4 4 1
3 4 5 3 4 3 2 2 2 4 3 4 4 3 4 3 4 4 2
4 2 3 2 3 2 3 2 3 2 1 2 3 3 4 4 3 3 3
4 2 3 2 5 3 2 2 4 3 3 3 3 3 2 3 4 3 2
3 3 3 2 4 2 3 3 3 4 4 4 3 3 3 4 4 2 2
5 3 3 3 4 2 4 3 3 4 4 3 3 4 3 4 4 4 3
3 3 3 2 5 4 4 4 4 3 4 4 3 3 3 3 3 2 4
3 3 2 2 4 3 3 2 4 2 2 3 4 4 3 5 4 3 2
3 3 4 3 4 3 3 3 3 3 3 3 3 3 3 4 4 4 2
4 3 3 3 4 3 4 4 4 4 4 3 4 4 3 5 4 3 3
4 3 4 3 3 3 3 3 3 2 2 2 3 3 2 3 3 4 2
4 4 4 3 3 3 4 3 3 4 4 4 4 4 5 5 5 3 3
3 1 2 1 4 1 2 2 2 4 4 5 4 3 2 5 5 2 3
2 2 2 1 2 3 3 2 1 1 2 2 2 2 2 4 4 2 1
4 3 3 3 3 2 2 2 2 3 3 2 3 3 3 4 3 3 2
3 4 2 3 4 3 4 3 2 4 3 3 3 4 2 4 3 3 3
5 4 5 3 3 3 3 2 4 3 4 3 4 2 2 3 4 3 3
5 3 3 4 4 3 3 1 3 2 2 2 3 3 3 5 5 4 2
3 3 4 4 4 3 3 2 3 3 3 2 3 2 3 3 3 3 3
4 2 3 2 5 2 4 2 4 3 5 5 5 5 3 2 2 4 3
4 4 4 3 5 3 3 3 3 4 3 4 4 4 5 5 4 5 3
4 5 5 4 4 1 2 2 3 3 3 2 3 3 4 5 5 5 2
3 3 2 2 3 1 1 1 1 2 2 2 4 4 3 4 4 1 2
4 4 4 2 4 1 2 1 3 3 3 3 3 3 2 4 3 4 3
4 3 3 3 3 3 3 4 3 4 4 3 4 4 3 4 4 3 3
3 4 4 4 5 2 2 3 5 3 3 3 4 4 3 5 4 3 3
4 4 4 4 4 3 4 2 4 3 3 3 3 4 2 4 3 4 3
4 3 2 1 3 1 3 2 2 3 3 3 2 3 3 4 4 4 1
3 4 5 3 4 3 2 2 2 4 3 4 4 3 4 3 4 4 2
4 2 3 2 3 2 3 2 3 2 1 2 3 3 4 4 3 3 3
4 2 3 2 5 3 2 2 4 3 3 3 3 3 2 3 4 3 2
3 3 3 2 4 2 3 3 3 4 4 4 3 3 3 4 4 2 2
5 3 3 3 4 2 4 3 3 4 4 3 3 4 3 4 4 4 3
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
86
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
D D D
WASTE WASTE WASTE NON NON NON CON
1 2 3 CON 1 CON 2 3 CON 1 CON 2 CON3
18 15 26 11 13 23 5 4 8
17 15 33 13 14 24 3 6 12
17 16 29 9 14 21 3 6 12
18 16 24 11 13 24 3 6 12
14 15 16 13 14 20 3 6 10
18 18 28 13 14 27 3 6 13
17 14 29 12 13 25 3 6 12
12 18 25 12 14 27 3 6 10
15 18 30 13 14 24 3 6 10
12 13 34 9 12 22 4 3 10
18 13 25 13 12 21 4 6 10
17 16 23 13 11 22 3 6 14
16 16 32 10 11 27 3 6 9
18 10 26 13 8 17 3 6 8
16 16 17 12 12 13 3 6 14
18 17 21 14 14 22 4 6 15
18 18 27 9 14 26 4 6 9
18 15 21 12 13 25 3 5 11
16 17 33 13 13 24 3 6 11
18 16 30 11 14 29 3 6 12
16 17 21 10 11 29 3 6 11
16 18 22 13 13 23 4 5 12
18 12 31 9 12 23 5 5 11
17 13 21 13 12 18 3 6 10
17 15 21 13 12 21 4 6 10
15 15 25 12 14 21 3 5 10
17 18 28 12 13 21 3 6 12
18 15 26 11 13 23 5 4 8
17 15 33 13 14 24 3 6 12
17 16 29 9 14 21 3 6 12
18 16 24 11 13 24 3 6 12
14 15 16 13 14 20 3 6 10
18 18 28 13 14 27 3 6 13
17 14 29 12 13 25 3 6 12
12 18 25 12 14 27 3 6 10
15 18 30 13 14 24 3 6 10
12 13 34 9 12 22 4 3 10
18 13 25 13 12 21 4 6 10
17 16 23 13 11 22 3 6 14
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
87
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
16 16 32 10 11 27 3 6 9
18 10 26 13 8 17 3 6 8
16 16 17 12 12 13 3 6 14
18 17 21 14 14 22 4 6 15
18 18 27 9 14 26 4 6 9
18 15 21 12 13 25 3 5 11
16 17 33 13 13 24 3 6 11
18 16 30 11 14 29 3 6 12
16 17 21 10 11 29 3 6 11
16 18 22 13 13 23 4 5 12
18 12 31 9 12 23 5 5 11
17 13 21 13 12 18 3 6 10
17 15 21 13 12 21 4 6 10
15 15 25 12 14 21 3 5 10
17 18 28 12 13 21 3 6 12
18 15 26 11 13 23 5 4 8
17 15 33 13 14 24 3 6 12
17 16 29 9 14 21 3 6 12
18 16 24 11 13 24 3 6 12
14 15 16 13 14 20 3 6 10
18 18 28 13 14 27 3 6 13
17 14 29 12 13 25 3 6 12
12 18 25 12 14 27 3 6 10
15 18 30 13 14 24 3 6 10
12 13 34 9 12 22 4 3 10
18 13 25 13 12 21 4 6 10
17 16 23 13 11 22 3 6 14
16 16 32 10 11 27 3 6 9
18 10 26 13 8 17 3 6 8
16 16 17 12 12 13 3 6 14
18 17 21 14 14 22 4 6 15
18 18 27 9 14 26 4 6 9
18 15 21 12 13 25 3 5 11
16 17 33 13 13 24 3 6 11
18 16 30 11 14 29 3 6 12
16 17 21 10 11 29 3 6 11
16 18 22 13 13 23 4 5 12
18 12 31 9 12 23 5 5 11
17 13 21 13 12 18 3 6 10
17 15 21 13 12 21 4 6 10
15 15 25 12 14 21 3 5 10
17 18 28 12 13 21 3 6 12
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
88
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
A A A A B B B B B B C C C C C C D D D D D D E E E
1 2 3 4 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3
4 4 4 3 3 3 4 3 3 3 3 3 3 3 3 4 3 3 4 4 4 3 3 2 3
3 4 4 2 2 3 2 2 2 3 3 2 2 3 3 3 3 3 2 2 2 3 2 4 3
3 3 3 3 2 2 2 2 2 2 3 2 3 3 2 2 4 3 2 2 2 2 2 3 3
4 3 3 2 3 4 3 2 2 2 2 3 3 3 2 3 2 2 3 2 3 2 3 4 3
3 3 2 2 3 3 3 3 4 2 2 4 3 3 3 3 4 4 4 2 1 2 2 4 4
2 2 2 2 3 3 2 3 3 2 2 3 2 2 2 3 3 3 3 2 3 3 3 3 3
3 4 3 2 2 3 3 2 3 3 2 2 3 3 2 2 3 3 2 4 2 2 3 3 3
4 3 3 3 3 3 3 3 4 4 1 1 3 2 4 3 4 4 3 4 4 4 3 4 4
3 3 3 3 3 3 4 3 3 2 2 2 3 3 3 3 2 3 3 3 3 3 3 4 3
3 3 3 3 4 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3 3
4 4 - 4 4 4 3 4 2 3 3 2 2 2 2 2 4 4 4 4 4 4 4 4 4
4 4 4 3 4 3 3 4 4 3 4 4 4 4 4 3 4 4 3 3 3 3 4 4 3
3 3 3 4 3 4 4 3 3 2 3 2 3 2 3 3 3 4 4 3 3 3 4 4 4
4 4 4 3 3 4 4 3 4 4 4 4 4 4 4 3 4 4 4 4 3 4 4 4 4
4 3 3 3 3 3 4 3 3 3 3 2 3 3 3 3 3 4 4 4 3 3 3 4 3
4 4 4 3 3 3 3 4 4 3 2 2 3 3 3 3 4 4 4 4 4 4 4 4 3
2 2 4 2 2 3 3 3 3 2 3 2 2 2 2 2 2 2 3 3 3 3 3 3 2
4 3 3 3 3 2 2 3 2 3 2 3 3 3 3 4 3 4 4 3 3 4 3 4 4
4 3 3 3 3 3 3 3 3 3 3 3 2 3 4 3 3 4 4 3 3 4 3 4 3
3 3 4 2 3 3 3 2 3 3 3 3 3 3 3 3 4 3 3 4 4 4 4 4 3
4 4 4 3 4 4 3 3 4 3 4 3 3 3 3 4 3 4 4 4 3 3 3 4 4
3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 4 2 2 3 3 4 3
3 4 3 3 3 3 3 3 2 3 2 2 4 3 3 2 3 4 3 3 3 3 3 3 4
3 3 3 2 2 3 3 3 2 3 2 2 2 3 3 2 4 3 3 4 2 2 3 4 3
3 3 3 3 3 3 3 2 3 1 3 3 3 2 2 3 3 3 3 3 3 3 3 3 3
4 3 3 3 2 3 3 3 3 3 2 1 3 2 2 3 4 3 3 3 3 3 3 4 3
3 3 3 3 3 3 3 3 3 2 3 2 3 3 3 3 2 3 2 2 3 3 3 3 3
4 4 4 3 3 3 4 3 3 3 3 3 3 3 3 4 3 3 4 4 4 3 3 2 3
3 4 4 2 2 3 2 2 2 3 3 2 2 3 3 3 3 3 2 2 2 3 2 4 3
3 3 3 3 2 2 2 2 2 2 3 2 3 3 2 2 4 3 2 2 2 2 2 3 3
4 3 3 2 3 4 3 2 2 2 2 3 3 3 2 3 2 2 3 2 3 2 3 4 3
3 3 2 2 3 3 3 3 4 2 2 4 3 3 3 3 4 4 4 2 1 2 2 4 4
2 2 2 2 3 3 2 3 3 2 2 3 2 2 2 3 3 3 3 2 3 3 3 3 3
3 4 3 2 2 3 3 2 3 3 2 2 3 3 2 2 3 3 2 4 2 2 3 3 3
4 3 3 3 3 3 3 3 4 4 1 1 3 2 4 3 4 4 3 4 4 4 3 4 4
3 3 3 3 3 3 4 3 3 2 2 2 3 3 3 3 2 3 3 3 3 3 3 4 3
3 3 3 3 4 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3 3
4 4 - 4 4 4 3 4 2 3 3 2 2 2 2 2 4 4 4 4 4 4 4 4 4
4 4 4 3 4 3 3 4 4 3 4 4 4 4 4 3 4 4 3 3 3 3 4 4 3
3 3 3 4 3 4 4 3 3 2 3 2 3 2 3 3 3 4 4 3 3 3 4 4 4
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
89
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
4 4 4 3 3 4 4 3 4 4 4 4 4 4 4 3 4 4 4 4 3 4 4 4 4
4 3 3 3 3 3 4 3 3 3 3 2 3 3 3 3 3 4 4 4 3 3 3 4 3
4 4 4 3 3 3 3 4 4 3 2 2 3 3 3 3 4 4 4 4 4 4 4 4 3
2 2 4 2 2 3 3 3 3 2 3 2 2 2 2 2 2 2 3 3 3 3 3 3 2
4 3 3 3 3 2 2 3 2 3 2 3 3 3 3 4 3 4 4 3 3 4 3 4 4
4 3 3 3 3 3 3 3 3 3 3 3 2 3 4 3 3 4 4 3 3 4 3 4 3
3 3 4 2 3 3 3 2 3 3 3 3 3 3 3 3 4 3 3 4 4 4 4 4 3
4 4 4 3 4 4 3 3 4 3 4 3 3 3 3 4 3 4 4 4 3 3 3 4 4
3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 4 2 2 3 3 4 3
3 4 3 3 3 3 3 3 2 3 2 2 4 3 3 2 3 4 3 3 3 3 3 3 4
3 3 3 2 2 3 3 3 2 3 2 2 2 3 3 2 4 3 3 4 2 2 3 4 3
3 3 3 3 3 3 3 2 3 1 3 3 3 2 2 3 3 3 3 3 3 3 3 3 3
4 3 3 3 2 3 3 3 3 3 2 1 3 2 2 3 4 3 3 3 3 3 3 4 3
3 3 3 3 3 3 3 3 3 2 3 2 3 3 3 3 2 3 2 2 3 3 3 3 3
4 4 4 3 3 3 4 3 3 3 3 3 3 3 3 4 3 3 4 4 4 3 3 2 3
3 4 4 2 2 3 2 2 2 3 3 2 2 3 3 3 3 3 2 2 2 3 2 4 3
3 3 3 3 2 2 2 2 2 2 3 2 3 3 2 2 4 3 2 2 2 2 2 3 3
4 3 3 2 3 4 3 2 2 2 2 3 3 3 2 3 2 2 3 2 3 2 3 4 3
3 3 2 2 3 3 3 3 4 2 2 4 3 3 3 3 4 4 4 2 1 2 2 4 4
2 2 2 2 3 3 2 3 3 2 2 3 2 2 2 3 3 3 3 2 3 3 3 3 3
3 4 3 2 2 3 3 2 3 3 2 2 3 3 2 2 3 3 2 4 2 2 3 3 3
4 3 3 3 3 3 3 3 4 4 1 1 3 2 4 3 4 4 3 4 4 4 3 4 4
3 3 3 3 3 3 4 3 3 2 2 2 3 3 3 3 2 3 3 3 3 3 3 4 3
3 3 3 3 4 3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 3 3
4 4 - 4 4 4 3 4 2 3 3 2 2 2 2 2 4 4 4 4 4 4 4 4 4
4 4 4 3 4 3 3 4 4 3 4 4 4 4 4 3 4 4 3 3 3 3 4 4 3
3 3 3 4 3 4 4 3 3 2 3 2 3 2 3 3 3 4 4 3 3 3 4 4 4
4 4 4 3 3 4 4 3 4 4 4 4 4 4 4 3 4 4 4 4 3 4 4 4 4
4 3 3 3 3 3 4 3 3 3 3 2 3 3 3 3 3 4 4 4 3 3 3 4 3
4 4 4 3 3 3 3 4 4 3 2 2 3 3 3 3 4 4 4 4 4 4 4 4 3
2 2 4 2 2 3 3 3 3 2 3 2 2 2 2 2 2 2 3 3 3 3 3 3 2
4 3 3 3 3 2 2 3 2 3 2 3 3 3 3 4 3 4 4 3 3 4 3 4 4
4 3 3 3 3 3 3 3 3 3 3 3 2 3 4 3 3 4 4 3 3 4 3 4 3
3 3 4 2 3 3 3 2 3 3 3 3 3 3 3 3 4 3 3 4 4 4 4 4 3
4 4 4 3 4 4 3 3 4 3 4 3 3 3 3 4 3 4 4 4 3 3 3 4 4
3 3 3 3 3 3 3 4 3 3 3 3 3 3 3 3 3 3 4 2 2 3 3 4 3
3 4 3 3 3 3 3 3 2 3 2 2 4 3 3 2 3 4 3 3 3 3 3 3 4
3 3 3 2 2 3 3 3 2 3 2 2 2 3 3 2 4 3 3 4 2 2 3 4 3
3 3 3 3 3 3 3 2 3 1 3 3 3 2 2 3 3 3 3 3 3 3 3 3 3
4 3 3 3 2 3 3 3 3 3 2 1 3 2 2 3 4 3 3 3 3 3 3 4 3
3 3 3 3 3 3 3 3 3 2 3 2 3 3 3 3 2 3 2 2 3 3 3 3 3
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
90
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
APPENDIX 4
CAUSE & EFFECT MATRIX TABLES
A1 A2 A3 A4 B1 B2 B3 B4 B5 B6 C1 C2 C3 C4 C5 C6 D1 D2 D3 D4 D5 D6 E1 E2 E3 F
A 24 21 15 6
B 36 9 3 9 3 6
C 24 9 3 12 15 3
D 3 15 15 15 3 3 3 6 3
E 24 9 6 3 21 3
F 15 15 9 6 6 3
G 30 12 6 9 3 3
H 27 15 21
I 12 18 12 12 6
J 3 3 3 3 3 3 33 9 3
K 3 6 3 3 3 6 3 27 9
L 6 6 6 9 6 6 6 3 12
M 3 3 15 9 9 6 6 3 9
N 3 3 12 6 3 21 15
O 3 27 18 3 12
P 12 6 9 3 15 3 3 3 9
Q 9 21 3 3 12 3 3 9
R 9 3 15 3 6 6 3 3 3 3 3 6
MAJOR CAUSE
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10
91
THE APPLICATION OF LEAN CONSTRUCTION TO REDUCE WASTE IN HIGHWAY PROJECTS
APPENDIX 4
CAUSE & EFFECT MATRIX TABLES
A1 A2 A3 A4 B1 B2 B3 B4 B5 B6 C1 C2 C3 C4 C5 C6 D1 D2 D3 D4 D5 D6 E1 E2 E3 F
A 9 15 15 3 3 3 3 3 3 3 3 3 6 3 6 9 3
B 12 3 6 3 3 9 3 9 9 3 3 3 3
C 15 6 6 3 3 6 15 6 3 12 3 3
D 15 9 9 3 3 6 12 3
E 3 3 3 9 3 3 3 3 3 6 15 18
F 6 6 3 3 3 3 3 3 3 3 3
G 6 3 3 6 12 3 6 3 3 3
H 9 3 3 3 3 15 3 3
I 3 3 3 6 6 3 3
J 3 6 3 3 9 9
K 3 6 9 3 6 6 3 9 9
L 3 6 6 3 3 6 3 3 3 9 3 6
M 3 9 9 3 9 3 3 3 9 12 3 3
N 3 3 3 3 3 3 3 6 3 3
O 3 6 3 6 9 3 3 3
P 3 6 3 3 3 6 3
Q 3 6 3 3 3 3 3 3 3
R 9 3 6 3 6 9 6 3 3 3 3
OTHER CAUSES
SRIKKANT SHAH ( CP2008 ), CONSTRUCTION & PROJECT MANAGEMENT, CEPT UNIVESITY, BATCH 08-10