Professional Documents
Culture Documents
GEOSYSTEMS, L.P.
724-942-0570
A Member
of:
Agenda
1 In the Beginning
1.
2. Some Landmark Projects and Events
3. New Arrivals
4. Studies, Researches and Conferences
5. Final Remarks
1. IN THE BEGINNING
Keyy Dates
1954
1986
Late 1980s
Late 1980s
Early 1990s
1992-1994
1995
1996
1997-1998
1997-2000
1. IN THE BEGINNING
(continued)
Keyy Dates
2000-2003
2001-2005
2003
2005
2006
2006
2006-2007
2007-Present
2008-Present
2010-2011
2012
2013
CO7A1, Boston, MA
(1992--1994)
(1992
225,000 sf
1996
Pascagoola
Pascagoola,
g
, MS
(~1998)
g
Stiff wall to limit ground
movements W 24x162
Permanent groundwater
cutoff
Prevent hydrostatic uplift
from a confined aquifer
Exposed Soil-Cement
Waterproofing Applied
318,000 sf
10
11
12
No p
prior history
poor soils and
y of DMM in the area despite
p very
yp
huge levee infrastructure.
Usual reasons can be cited:
Reliance on traditional solutions.
Lack of funds.
There must be a problem before there is a solution.
USACE raised funds for a classic 3 step research program:
Desk study (feasibility in local soils).
Lab study (properties of mixed soils).
Full
Full--scale field test (performance of columns at different
replacement ratios).
13
Extraction of Column
14
August
2005 Hurricanes Katrina and Rita force the ice to melt.
g
15
C Deep
eep Mixed
ed Cuto
a (p
oposed, not
ot built)
bu t)
IHNC
Cutoff Wall
(proposed,
(Full details of mix designs, quantities, etc., are
provided in the paper.)
16
Dry Mixing
Homeplace Levee Enlargement (P24)
17
Dry Mixing
IHNC Floodwall
18
LPV Production
Some numbers.
PRODUCTION START DATE
PRODUCTION COMPLETION DATE
TOTAL CALENDAR DAYS
TOTAL MONTHS
TOTAL SHIFTS WORKED (as of 3/18/2011)
TOTAL MANHOURS (as of 3/18/2011)
TOTAL DMM ELEMENT INSTALLED
TOTAL VOLUME TREATED
TOTAL CEMENT USED
TOTAL TRUCK-LOADS (approx.)
TOTAL WATER USED
TOTAL CORING
TOTAL UCS TESTS
OVERALL AVERAGE UCS (required = 100 psi)
TOTAL FAILING UCS TESTS (<100 psi)
TOTAL FAILING UCS TESTS (10% allowed)
N
N
N
N
N
CY
SHTON
N
GAL
N
N
PSI
N
%
1/14/2010
3/18/2011
439.00
14 43
14.43
3,309
502,817
18,028
1,681,579
457,693
17,500
136,832,094
506
5,082
292
66
1.30%
19
Observations
3. NEW ARRIVALS
Original Classification of Deep Mixing Methods (FHWA
(FHWA 2000)
DM Methods
Fluid Grouts
Dry Materials
Nature of Material
Placed
Rotary
Shaft Mix
e.g.,
DSM, Trevimix
Schnabel
Rotary
End Mix
End Mix
End Mix
e.g.,
SSM, SCC,
Mectool
Hayward Baker
e.g.,
GeoJet
e.g.,
Lime-Cement
Columns
Mixing/Blending
Principle
Mixing/Blending
Location
U.S. Examples
20
Rotary
Vertical
Axis
Jet
Assisted Vertical
Axis (Turbojet)
Trench Cutting
and Mixing
(TRD)
Horizontal
Axis Cutting
and Mixing
Low
High
Pressure Pressure
(CSM) (CT Jet)
Conventional
TRD (T
(Trench Re-Mixing and Cutting Deep Wall) Method
wide.
Continuous wall created by lateral
motion of vertical chain saw,
installed in a predrilled hole.
21
Blue print
22
A)Standard blade
B)Rounding blade for hard clay
C)Long-nosed blade for boulder
23
TRD
Particular Advantages
Continuous,, homogeneous,
joint
-free wall in all soil and
g
, jointj
(20 ft).
Very quite, modest size support
equipment, clean operation.
TRD
Potential Drawbacks
Sharpp alignment
changes.
g
g
Especially hard/massive/abrasive rock.
Trapping of post in soilcrete or refusal on
boulders/rock.
Only one (excellent) contractor!
24
in 2003
Combines expertise in hydromill and deep mixing.
Rapidly increasing in popularity worldwide (over 30
units in service).
y
p by
y Trevi ((CT Jet).
)
Similar system
developed
Maximum depth 180 feet, 2020-47 inches wide.
25
26
27
CSM at Brunswick, GA
(~2010)
28
CSM
Particular Advantages
CSM
Potential Drawbacks
29
30
31
5. FINAL REMARKS
32