Professional Documents
Culture Documents
vs.
THE INTERMEDIATE APPELLATE COURT and NESTOR B.
SUGA JR.
G.R. No. L-65935 September 30, 1988
FACTS:
Nestor B. Sunga Jr., businessman and owner of the NBS
Machineries Marketing and the NAP-NAP Transit filed a case
for damages alleging that he purchased a passenger minibus
Mazda from the Motor center, Inc. at Calasiao, Pangasinan on
March 21, 1978 and for which he executed a promissory note
to cover the amount of P62,592.00 payable monthly in the
amount of P2,608.00 for 24 months. On the same date,
however, a chattel mortgage was executed by him in favor
of the Motor center, Inc. The Chattel Mortgage and
Assignment was assigned to the Filinvest Credit Corporation
with the conformity of Sunga.
He claimed that on October 21, 1978, the minibus was
seized by two employees of Filinvest Credit Corporation upon
orders of the branch manager Mr. Gaspar de los Santos,
without any receipt, who claimed that he was delinquent in
the payments of his vehicle. The said vehicle was recovered
from the Crisologo Compound which was later released by
Rosario Fronda Assistant Manager of the Filinvest, and Arturo
Balatbat as caretaker of the compound.
Florence Onia of the Filinvest explained that the
minibus was confiscated because the balance was already
past due. After verification that his accounts are all in order,
Florence Onia admitted it was their fault. The motor vehicle
was returned to the plaintiff upon proper receipt.
The trial court ordered Filinvest Credit Corporation to
pay the plaintiff Nestor Sunga Jr. the following damages, to
wit:
a. Moral Damages P30,000.00
b. Loss on Income of the minibus for three days 600.00
FACTS:
In 1996, NAPOCOR began the construction of 29
decagon-shaped steel poles to support overhead high
tension cables in connection with 230 Kilovolt Sucat-AranetaBalintawak Power Transmission. Said transmission line
passes through the petitioners home in Dasmarias Village.
Petitioners scoured the internet of possible adverse
effects of such structures to their health and well-being and
found articles and studies linking the incidence of a fecund
HELD:
Yes. P.D.1818 says, "No court in the Philippines shall
have jurisdiction to issue any restraining order, preliminary
injunction or preliminary order, preliminary mandatory
injunction in any case, dispute or controversy involving an
infrastructure project." This rule is not absolute. The
prohibition extends only to the issuance of injunctions or
restraining orders against administrative acts in
controversies involving facts or the exercise of discretion in
technical cases. On issues outside this dimension and
involving questions of law, courts could not be prevented
from exercising their power to restrain or prohibit
administrative acts.
In this case, there is a violation of petitioners right to
health and NAPOCOR had violated the Local Government
Code provision on prior consultation with the affected
communities. These are veritable questions of law that
invested the trial court with jurisdiction to issue a TRO and a
preliminary injunction. Such these acts divest the case from
the protective mantle of P.D. 1818.
Further, the location of the project is a fragile zone
being proximate to local earthquake faults.
FACTS:
A domestic corporation engaged in the manufacture
and export of charcoal briquette, the Technology Developers,
Inc. received a letter from acting mayor Pablo Cruz,
1) ordering the full cessation of its plant in Guyong, Sta.
Maria, Bulacan until further order,
2) requesting its Plant Manager to bring before the
office of the mayor:
a. Building permit;
b. Mayor's permit;
c. Region III-Pollution of Environment and Natural
Resources Anti-Pollution Permit;
d. other document.
Technology Developers undertook to comply with the
request to produce the required documents. It commenced
to secure "Region III-DENR Anti-Pollution Permit," although
among the permits previously secured prior to the operation
of petitioner's plant was a "Temporary Permit to Operate Air
Pollution Installation" issued by the Environmental
Management Bureau and is now at a stage where the
Environmental Management Bureau is trying to determine
the correct kind of anti-pollution devise to be installed as
part of petitioner's request for the renewal of its permit. It
sent its representatives to the office of the mayor to secure
the same but were not entertained.
However, the acting mayor ordered that the plant
premises be padlocked, which was done without previous
and reasonable notice.
Technology Developers then instituted an action for
certiorari, prohibition and mandamus with preliminary
injunction against the acting mayor with Bulacan RTC,
alleging that the closure order was issued in grave abuse of
discretion.
Marivic Guina, however, recommended that, "Due to
the manufacturing process and nature of raw materials used,
the fumes coming from the factory may contain particulate
matters which are hazardous to the health of the people. As
such, the company should cease operating until such a time
that the proper air pollution device is installed and
operational."
ISSUE:
Whether or not the acting mayor acted with grave
abuse of discretion.
HELD:
The mayor of a town has much responsibility to protect
its inhabitants from pollution, and by virtue of his police
power, he may deny the application for a permit to operate a
business or otherwise close the same unless appropriate
measures are taken to control and/or avoid injury to the
health of the residents of the community from the emissions
in the operation of the business. The action of the Acting
Mayor was in response to the complaint of the residents
directed to the Provincial Governor through channels.
The petitioner has a huge investment in this dollarearning industry. However, that concomitant with the need
to promote investment and contribute to the growth of the
economy is the equally essential imperative of protecting the
health, nay the very lives of the people, from the deleterious
effect of the pollution of the environment.