Professional Documents
Culture Documents
a r t i c l e
i n f o
Article history:
Received 18 June 2016
Received in revised form 5 August 2016
Accepted 6 August 2016
Available online 10 August 2016
Keywords:
Net-zero energy building
Uncertainty
Energy storage
System sizing
Genetic algorithm
a b s t r a c t
Net-zero energy buildings (NZEBs) are considered as an effective solution to current environmental and
energy problems. To achieve expected performance, system sizes in a NZEB must be properly selected.
Parameter uncertainties have been proved to have signicant impacts on system sizing and need to be
systematically considered. Due to complex uncertainty impacts, proper system sizing in a NZEB with
multi-criteria performance is always a real challenge. To deal with the challenge, this study presents a
genetic algorithm-GA based system sizing method for NZEBs. Taking users multi-criteria performance
requirements as constraints, the proposed method aims to minimize total system initial costs by selecting
proper sizes of ve different systems under uncertainties. The ve systems include an air-conditioning
system, photovoltaic panels, wind turbines, a thermal energy storage system and an electrical energy
storage system. The performance requirements come from three diverse criteria which are zero energy,
thermal comfort and grid independence. Using real weather data of 20 years in Hong Kong, the case studies
demonstrate the effectiveness of the proposed method in selecting proper system sizes corresponding
to user specied performance requirements. In addition, the results indicate conventional descriptions
of parameter uncertainties need to be improved for better system sizing of NZEBs.
2016 Elsevier B.V. All rights reserved.
1. Introduction
Building accounts for about 40% energy use in worldwide and
it consumes more than 90% energy in Hong Kong [1,2]. With such
signicant energy consumption, building plays an important role
in energy conservation and environmental protection. Utilizing
renewables to meet their energy demands, net-zero energy buildings (NZEBs) are considered as an effective solution to the worlds
increasing energy and environmental problems [3]. Many countries
have set up clear targets through legislations for promoting NZEB
practical applications. For instance, the U.S. government has set a
zero-energy target for 50% of commercial buildings by 2040 and
for all commercial buildings by 2050 [3]. The Europe has planned
to transfer all its new buildings to be nearly net zero energy buildings after 2020 [4].
Corresponding author.
E-mail address: yongjsun@cityu.edu.hk (Y. Sun).
http://dx.doi.org/10.1016/j.enbuild.2016.08.032
0378-7788/ 2016 Elsevier B.V. All rights reserved.
525
526
Table 1
Base values and uncertainty distributions of the four scenario parameters.
Parameters
Unit
Uncertainty distribution
Truncation
Ambient temperature
Ambient relative humidity
Solar radiation
Wind speed
N (1 , 3.22 )
N (2 , 112 )
N (3 , 562 )
N (4 , 2.32 )
[13,35]
[40,99]
[0,1111]
[0,45]
C
%
W/m2
m/s
(1)
(2)
comfort ) comfort
cdf ([comfort,1 , ...comfort,i , ...comfort,N ]
(3)
grid ) grid
Cgrid cdf ([grid,1 , ...grid,i , ...grid,N ]
(4)
where, i represents the ith year and N is the total years in the
Monte Carlo simulation; cdf indicates the cumulative probabil denotes a user-dened performance threshold; and is the
ity;
expected cumulative probability selected by users.
With regard to the zero energy/energy balance evaluation
(zero ), relative difference between a buildings annual energy
demand (Edem ) and annual energy generation (Esup ) is used, as
described in Eq. (5). If the difference is smaller than a user-selected
(5)
j
(6)
where, j represents the value of the failure time at the jth hour;
CLsup and CL are hourly cooling supply and cooling load.
With regard to the grid dependence evaluation (grid ), the
no-grid interaction probability developed in [35] will be used to
calculate the time percentage of zero energy exchange between
the targeted NZEB and a grid. As calculated by Eq. (7), the no-grid
interaction probability varies in a range from 0 to 1 and a higher
value represents larger grid independence.
grid =
powexchange =0
tot
(7)
527
Table 1 shows the statistical descriptions of the scenario parameter uncertainties. In the table, 1 , 2, 3 and 4 represent the base
values of hourly temperature, RH, solar radiation and wind speed
extracted from the typical year for system design. In the Monte
Carlo simulation, the samples taken from the uncertainty distributions are used. Note that truncation is used to limit the uncertainty
samples within the given ranges by users.
3.2. Air-conditioning system modelling
The air-conditioning system is shown in Fig. 3. In the chiller
plant, constant speed pumps are used on the primary side while
variable speed pumps are used on the secondary side. The temperature set-point for the chilled water supply is 7 C and the supply
air temperature is set to 16 C. The supply air temperature is controlled by adjusting the speed of the pumps in the secondary loop.
The condenser water loop mainly consists of constant speed pumps,
cooling towers equipped with variable speed fans. The outlet water
temperature of cooling towers is set to be 5 C above the wet-bulb
ambient temperature. Such temperature difference is maintained
through adjusting the speed of the fan in the cooling towers.
The main steps for the component power estimations are illustrated as follows. The power consumption of the chiller Powchiller is
calculated according to the nominal COP, its actual supplied cooling Q, and the fraction of full load power-FFLP [36]. Note that Q is
limited by the system capacity, as described in Eq. (9).
Powchiller = FFLP Q/COPnom
(8)
Q = min(CL, CAPAC )
(9)
CAPAC
Cp,w Tchw
(10)
Q + Powchiller
Cp,w Tcow
(11)
where, Tcow ( C) is the temperature difference between the cooling water return and the cooling water supply.
Pipes are selected based on the calculated ow rate, and the
associated pressure drop through each part of the pipes can be estimated [39]. Based on the ow rate and pressure drop, the power
Powpump (W ) for all the pumps is calculated as
r,w h
Powpump = m
(12)
With regard to the AHU fan, its air volumetric ow rate V air
is calculated by Eq. (13). The associated fan power Powfan (W ) is
estimated by Eq. (14).
V air =
CLsup
(hrtn,air hsup,air )
air
Powfan = V air P
(13)
(14)
hsup,air J/kg is the enthalpy of the supply air; P (Pa) is the pres-
sure difference;
air kg/m3 is air density.
528
Fig. 2. Occupancy schedules (a), equipment operating schedules (b) and lighting schedules (c) in the ofce building.
r,cow
m
r,tow,a
m
(15)
Table 2
Parameters used in the PV panel model.
Parameter
Unit
Back resistance
Top emissivity coefcient
Back emissivity coefcient
Absorptance coefcient
Refractive index
Cover conductivity
Cover thickness
Extinction coefcient
m2 K/W
W/ m K
m
1/m
Value
0.28
0.9
0.9
0.9
1.526
18.14
0.00635
4
(16)
PowWT =
Table 3
Performance thresholds and expected cumulative probabilities used in the study.
if U0 3
Cp
air AR U03 otherwise
CAPWT
CLj
n=1
Powcharge,j =
if Powmis < 0
(21)
2%
1 (hour)
0.5
60%/80%/100%
Powcharge,n
Values
zero
comfort
grid
(19)
j1
Symbol
Performance threshold
(18)
Estore,j =
Category
if U0 14
(17)
CAPTS =
529
(23)
530
Table 4
System sizes selected by the proposed method under expected cumulative probabilities.
Expectedcumulative probabilities
CAPAC (kW)
CAPPV (m2 )
CAPWT (kW)
CAPTS (kWh)
CAPES (kWh)
= 60%
= 80%
= 100%
148 ()
150(1.4%)
165(11.5%)
50()
50()
100(100%)
60()
70(16.7%)
100(66.7%)
41()
61(48.8%)
42(2.4%)
80()
90(12.5%)
130(62.5%)
1,114,200()
1,242,600(11.5%)
1,805,200(62.0%)
Fig. 4. Building annual energy use and generation as systems sized under = 60%.
Fig. 5. Building annual energy use and generation as systems sized under = 80%.
531
Fig. 6. Building annual energy use and generation as systems sized under = 100%.
Fig. 7. Discomfort hours (comfort ) in each year as systems sized under different expected cumulative probabilities.
532
Fig. 8. Cooling load proles with load shifting using sized thermal storage systems.
peak load reduction was achieved, i.e. from 172 kW to 149 kW. With
the 150 kW air-conditioning system, the reduced peak cooling load
can be met as = 80%.
4.2.3. Grid independence validation
Fig. 9 shows the no-grid interaction probability (grid ) in each
year as systems sized under different expected cumulative probabilities. The index indicates the time percentage of zero power
interaction between the building and the grid. A larger index value
means higher grid independence of the NZEB. In the study, as the
grid took the value of 0.5, any year
related performance threshold
with grid < 0.5 was considered as a year in which the grid independence constraint was not met. Similarly, the number of years
failing to meet the grid independence constraint was reduced with
the increase of the expected cumulative probability, as shown in
Fig. 9. As increased from 60% to 80%, the number of years failing
to meet the constraint was reduced from 7 (i.e. 35% of all years) to
4 (i.e. 20% of all years). The main reason was that a larger expected
cumulative probability led to an increased capacity of the electrical
energy storage (see Table 4), which enabled more electrical energy
charge and discharge. In the case of = 100%, the size of electrical
energy storage system was much larger which caused much higher
no-grid interaction probabilities in comparison with the other two
cases.
Using the electrical energy storage system, power interactions
between the building and the grid can be reduced. As more renewable energy was generated than the demand, the excessive part can
be stored in the storage system and thus did not need to be exported
to the grid. In contrast, as less renewable energy was generated
than the demand, the insufcient part can be discharged from the
storage system and thus did not need to be imported from grid. It
should be mentioned that the no-grid interaction probability was
not solely determined by CAPES but also inuenced by other system
sizes and actual weather data. For instance, in most of the years, a
larger CAPES resulted in a smaller no-grid interaction probability.
But in the 4th and 15th years, the larger CAPES under = 80% led to
smaller no-grid interaction probabilities than the smaller one with
= 60%.
Fig. 10 shows the load duration curves in one year using the
electrical energy storage systems sized under different expected
cumulative probabilities. As there was no electrical energy storage system, only 20% of the year (i.e. grid = 0.2) had zero power
interaction between the building and the grid. In other words,
the other 80% time required the supports of the grid (e.g. energy
import/export). In this case, the building heavily depended on the
Table 5
Expected cumulative probabilities and actual ones of meeting.
the multi-criteria constraints
Expected
cumulative
probability ()
Actual cumulative
probability in
energy balance
(cdfzero )
Actual cumulative
probability in
thermal comfort
(cdfcomfort )
Actual cumulative
probability in grid
independence
(cdfgrid )
60%
80%
100%
60%
80%
100%
70%
95%
100%
65%
80%
100
grid for normal function. As = 60% and 80%, the sizes of the electrical energy storage systems were selected as 80 kWh and 90 kWh
respectively. Utilizing such sized storage systems, the no-grid interaction probability (grid ) have been increased from 0.2 to 0.5 and
0.51 which achieved the users specied performance requirement,
grid = 0.5. As = 100%, the selected size of the electrical energy
i.e.
storage system was largely increased to 130 kWh and thus the nogrid interaction probability (grid ) has been signicantly inreased
from 0.2 to 0.59.
4.3. Discussions
The above study results demonstrated that as uncertainties
were taken into consideration, the proposed method can effectively nd proper system sizes which well met the established
constraints. As shown in Table 5, the obtained actual cumulative
probabilities were equal to or slightly higher than the expected
cumulative probabilities in terms of energy balance, thermal comfort and grid independence. The slightly higher actual probabilities
were mainly caused by that the uncertainties in reality were different from those used in the GA method. For instance, the wind speed
uncertainty in urban area should consider the increasing effects of
the high-rise buildings. As more tall buildings constructed in the
urban area, less wind energy can be utilized. However, such characteristic has not been considered in the traditional uncertainty
description method using typical statistical distributions. Thus,
uncertainty description/characterization needs to be improved for
better system sizing of NZEBs under uncertainties.
With the increase of the cumulative probability, the variations of
ve system sizes are different and inconsistent. The size increase of
particular systems is much larger than that of others. Such inconsistent system size variations demonstrate the different and complex
impacts of each system on the established performance requirements as uncertainties considered. Meanwhile, as = 100%, the
533
Fig. 9. No-grid interaction probability (grid ) in each year as systems sized under different expected cumulative probabilities.
Fig. 10. Load duration curves in one year using electrical energy storage systems sized under different expected cumulative probabilities.
system sizes were signicantly larger than the other two cases. In
other words, such a high cumulative probability was realized at
the expense of oversized systems and thus excessively high initial
costs.
It is worth noting that the proposed method may also face
some limitations: 1) possible excessive computation load caused
by repeated Monte Carlo simulation; and 2) potential premature
convergence at the local optimum rather than the global optimum.
Regarding the rst limitation, computation load can be lightened by
reducing the associated uncertainty distribution sample size. Latin
Hypercube Sampling, a stratied sampling method, is an effective
means to reduce sample size and help solve the computation problem. Regarding the second limitation, the premature-convergence
problem could be solved by increasing the rate of mutation and/or
using random offspring generation to maintain a diverse population of solutions.
5. Conclusions
Due to complex uncertainty impacts, proper system sizing in
a NZEB with multi-criteria performance considered is a real challenge. In order to deal with the challenge, this study presents
a genetic algorithm-GA based system sizing method for NZEBs.
Impacts of scenario parameter uncertainties have been considered
via Monte Carlo simulation. The tness function has been established to minimize the total initial costs of ve systems while users
performance requirements are considered as constraints.
534
Acknowledgements
The research work presented in this paper is supported by the
Early Career Scheme from the University Grants Committee of Hong
Kong (Project No. 9048038) and China State Construction Engineering Corporation Limited (Project No. CSCEC-2015-Z-15).
References
[1] IEA, IEA Statistics: World Energy Statistics and Balances, http://www.iea.org/
statistics-/topics/energybalances/, 2014.
[2] EMSD, Hong Kong Energy End-use Data http://www.emsd.gov.hk/
lemanager/-en/content 762/HKEEUD2014.pdf, 2014.
[3] D. Crawley, S. Pless, P. Torcellini, Getting to net zero, ASHRAE J. 51 (2009)
1825.
[4] Directive 2010/31/EU of the European Parliament and of the Council of 19
May 2010 on the energy performance of buildings, Ofcial Journal of the
European Union, Legislation, 153, 2010. 1335.
[5] Y.J. Sun, P. Huang, G.S. Huang, A multi-criteria system design optimization for
net zero energy buildings under uncertainties, Energy Build. 97 (2015)
196204.
[6] P. Torcellini, S. Pless, M. Deru, D. Crawley, Zero energy buildings: a critical
look at the denition, in: ACEEE Summer Stud, Pacic Grove, CA USA, 2006.
[7] A.J. Marszal, P. Heiselberg, R.L. Jensen, J. Nrgaard, On-site or off-site
renewable energy supply options? Life cycle cost analysis of a net zero energy
building in Denmark, Renew. Energy 44 (2012) 154165.
[8] S. Attia, E. Gratia, A.D. Herde, J.L.M. Hensen, Simulation-based decision
support tool for early stages of zero-energy building design, Energy Build. 49
(2012) 215.
[9] A. Scognamiglio, F. Garde, H.N. Rstvik, How net zero energy buildings and
cities might look like? New challenges for passive design and renewables
design, Energy Procedia 61 (2014) 11631166.
[10] P. Huang, G.S. Huang, HVAC system design under peak load prediction
uncertainty using multiple-criterion decision making technique, Energy
Build. 91 (2015) 2636.
[11] S.K. Wang, Handbook of Air Conditioning and Refrigeration, 2nd edition,
McGraw-Hill, Two Penn Plaza, NY, USA, 2000.
[12] A.A. Bell, HVAC Equations, Data, and Rules of Thumb, 2nd edition,
McGraw-Hill, Two Penn Plaza, NY, USA, 2007.
[13] D. Woradechjumroen, Y.B. Yu, H.R. Li, D.H. Yu, H.J. Yang, Analysis of HVAC
system oversizing in buildings through eld measurements, Energy Build. 69
(2014) 131143.
[14] E. Djunaedy, K.V.D. Wymelenberg, B. Acker, H. Thimmana, Oversizing of HVAC
system: signatures and penalties, Energy Build. 43 (2011) 468475.
[15] D. Felts, P. Bailey, The state of affairspackaged cooling equipment in
California, ACEEE Summer Study on Energy Efciency in Buildings (2000).
[16] H.A. McLain, D. Goldberg, M.A. Karnitz, S.D. Anderson, S.Y. Ohr, Benets of
Replacing Residential Central Air Conditioning Systems, Washington DC, USA,
American Council for an Energy-Efcient Economy, 1985.
[17] J. Salom, A.J. Marszal, J. Widn, J. Candanedo, K.B. Lindberg, Analysis of load
match and grid interaction indicators in net zero energy buildings with
simulated and monitored data, Appl. Energy 136 (2014) 119131.
[18] G. Bekele, G. Tadesse, Feasibility study of small Hydro/PV/Wind hybrid system
for off-grid rural electrication in Ethiopia, Appl. Energy 97 (2012) 515.
[19] S. Rehman, M.M. Alam, J.P. Meyer, L.M. Al-Hadhrami, Feasibility study of a
windpvdiesel hybrid power system for a village, Renew. Energy 38 (2012)
258268.