SPS allow the transmission system to be operated securely at N
security SPS were noted in draft TTER report as a means for facilitating renewable generation, with acknowledgement, that they have wider application Commission sought submissions on its approach to SPS as outlined in its draft TTER report
Background
The Commission noted the cost effectiveness of SPS versus
upgrading or building new transmission. Are the assumptions the Commission applied realistic? Do you agree that SPS are cost effective? If not why not? Local and international experience is positive Do you have any comments on local and international experience with SPS? Mandatory requirements in case of contingent events. Do you consider that SPS differ from other system operator actions to prevent overloading in the case of contingent events? Why?
Consultation
Generator/retailer submission on the draft TTER were generally
against the permanent substitution of SPS for upgrades, noting: Interim measure only - not a long term solution For Connection only and voluntary Reliability, operational, technical and commercial complexities Environmental constraints Do you consider that the cost, operational and technical issues with SPS result in them not being a viable transmission alternative? What are the technical and operational differences between the deployment of such schemes for connection versus interconnection? Do you consider that deployment of SPS will degrade system security? Why?
Consultation
Submitters noted that security of supply may be degraded through
the application of SPS. The Commission notes that the: secondary systems and generation arrangements required can be designed to be at least as reliable as transmission line SPS may provide an increase in reliability, pass the GIT, where it would not be possible to justify additional primary transmission assets. SPS would need to be engineered to high standards and this should be taken into account when assessing costs Do you consider that deployment of SPS will degrade system security? Why?
Consultation
Generator/retailers submissions noted that any arrangements
should be commercially negotiated as with other ancillary services Why is the provision of runback or ramp up generation in the case of circuit failure an ancillary service? Does the rationale for payment rely on accepting generator claims to capacity rights on use of the interconnected grid? Concern was also expressed about what criteria the SO would use to select which generators are constrained up/down Do you consider that a pre-existing plan is preferable to the system operator dispatching generation based on bid information? What are the regulatory impediments to the greater deployment of SPS?