Tnh Trang Thc Hien


Hang muc
Yeu cau
Ket qua
May vao cong trng co giay
xac nhan tnh trang x dung an
toan cua nhan vien quan ly an
toan.
Day cap nguon x dung cap
PVC/PVC con tot, i day gon,
au day chac. ( luon trong ong
bao ve).
Day han khong nen dai hn
May Han 30m, ung qui cach,khong co
ien
tren 3 au noi day, cach ien
tot.
May dung ngoai tri, dat ni

Ghi chu

cao, phang, co bien phap


chong ma tot, lap tiep at
bao ve
Lap thiet b chong ro ien.
Tu ngoai tri phai chong nc,
co ten ngi quan ly.

Xac nhan
cua

Quan ly An toan:

Ch huy trng Cong trng:

Ngay:

Ngay:

Note:
1. oi trng ien vao ban nay trc khi thi cong, nop cho Chu
nhiem an toan kiem tra, sau khi phe chuan mi c thi cong.
2. Ket qua kiem tra at yeu cau anh dau / trong o, khong at an

Sino-Pacific Construction Consultantcy Co.Ltd.

F 4.8.4 Rev: B; February 2005

SPCC projects dept

Sino-Pacific Construction Consultantcy Co.Ltd.

P 4.8 Safety and Security Plan

F 4.8.4 Rev: B; February 2005

SPCC projects

P4.08 Safety & Security Plan

Electrical Welding Machine Inspection List Before Using on Site


( By Contractor )
Working Team

Date:

Responsible perso
Construction place
Job

Safety Officer:

The Situation of Implementation


Requirements
Checking result

Items

Note

When machine enter the site, it must have


safety confirmation from Safety Officer.
Power supply cable is of PVC/PVC still in
good condition, run in good order and
safety connection.(It may be put in PVC/ GI
conduit)
Welding wire can not be longer than 30m,
big enough and not more than 3 connection
Welding machine heads.
Machine put outdoor should be on flat and
high location, good waterproofing. Install
earthing for protection.
Install ELCB for machine
Outdoor electrical panel must be
waterprooved, with name of responsible
person.

Safety Officer :

Site Manager :

Confirmed by
Date :

Date :

Note:
1. Head of the group fill in this checklist before work, deliver it to Safety Officer. It can only be
used on site after aprroval
2. Meet the requirement stick , if not stick X mark in the blank.

Sino-Pacific Construction Consultantcy Co.Ltd.

F 4.8.4

Issue-3 Rev 0 February 2007

3 /3

You might also like