Professional Documents
Culture Documents
IN INDONESIA
PLNs PERSPECTIVE
No
Description
1.
Installed Capacity
2.
Peak Load
26.665 MW
3.
Energy Production
184 TWh
4.
Energy
Consumption
160 TWh
5.
Number of
Customers
6.
Transmission Line
7.
Distribution Line
8.
Revenue
9.
Electrification Ratio
45,9 m
36.720 kmc
679.424 kmc
21 b USD
74%
26
TWh
62
TWh
2012 2021
IB : 10,3%
37
14 TWh
TWh
IT : 11,1%
132 259
TWh TWh
JB : 7,8%
Electriciy demand is predicted to grow at a average rate of 9,7% per year.
Source : RUPTL PLN 2012-2021
10.000
8.987
9.000
8.976
8.000
Coal : 38 GW
7.000
6.000
Geothermal: 6.4 GW
6.415
5.728
4.744
5.000
3.883
4.000
5.231
5.207
4.311
GT/Gas Eng.: 4 GW
Hydro/Mini Hydro: 5.3 GW
3.844
Others: 0.25 GW
3.000
2.000
1.000
2012
2013
Other
2014
GTPP
2015
CCPP
2016
GeoPP
2017
HEPP
2018
CFPP
2019
2020
2021
Total
350.000
LNG
Gas
300.000
GWh
250.000
200.000
150.000
Coal
100.000
50.000
Geothermal
Hydro
2012
Impor
Biomass
2013
2014
Surya/Hybrid
2015
HSD
2016
MFO
LNG
2017
Gas
2018
Batubara
2019
Geothermal
2020
2021
Hydro
75 GW hydro potential, after strict screening (environmental & social) is about 26.3 GW 167 location,
and further narrow to 12,9 GW 89 location
Source : Hydro Power Potential Study 1983, Hydro Power Inventory Study 1999, Master Plan of Hydro Power Development in Indonesia by Nippon Koei 2011
Sulawesi
Rp 787/kWh
~ 8,2 cUSD/kWh
Sumatra :
Rp 787/kWh
~ 8,2 cUSD/kWh
Kalimantan
Rp 853/kWh
~ 8,8 cUSD/kWh
Java
Rp 656/kWh
~ 6,8 cUSD/kWh
1 USD = Rp 9,700
TAHUN
NO
PEMBANGKIT EBT
SATUAN
TOTAL
2012
1 PLTMH
MW
2 PLT SURYA
2013
2014
2015
2016
2017
2018
2019
2020
2021
40
99
113
112
101
185
188
201
189
260
1488
MWp*)
84
125
150
100
75
75
80
80
80
855
3 PLT BAYU
MW
10
50
50
15
15
20
20
25
25
230
4 PLT BIOMASS
MW
22
40
90
35
40
40
45
45
50
40
447
5 PLT KELAUTAN
MW
27
54
6 PLT BIO-FUEL
MW**)
10
15
15
14
101
7 PLT GAS-BATUBARA
MW
32
81
43
22
22
14
10
10
247
TOTAL
MW
110
331
436
383
276
349
354
365
368
450
3.422
Number
90
7
13
25
14
31
55
13
10
13
9
10
94
9
13
15
30
27
239
29
36
53
53
68
IPP
Installed Capacity (kW)
570,315
21,095
100,858
161,120
85,668
201,574
193,920
37,640
31,700
48,700
39,780
36,100
302,383
2,530
28,180
70,790
93,684
107,199
1,066,618
61,265
160,738
280,610
219,132
344,873
Number
Cumulative
Installed Capacity (kW)
7
20
45
59
90
21,095
121,953
283,073
368,741
570,315
13
23
36
45
55
37,640
69,340
118,040
157,820
193,920
9
22
37
67
94
2,530
30,710
101,500
195,184
302,383
29
65
118
171
239
61,265
222,003
502,613
721,745
1,066,618
Number
39
34
0
0
5
75
43
3
17
12
36
36
0
0
0
150
113
3
17
17
PLN
Installed Capacity (kW) Number
26,570
15,582
34
34
34
10,988
39
117,185
52,330
43
5,500
46
37,700
63
21,655
75
72,768
72,768
36
36
36
36
216,523
140,680
113
5,500
116
37,700
133
32,643
150
Cumulative
Installed Capacity (kW)
15,582
15,582
15,582
26,570
52,330
57,830
95,530
117,185
72,768
72,768
72,768
72,768
140,680
146,180
183,880
216,523
5 years Programme
10
But connecting to the Grid is not always easy, many issues arise
Issue 1. Expanding the Grid to reach them
Connection issues due to remote location
Too remote : islanding operation for local load and doesnt
connect to PLNs grid, forming micro grids
Connecting to 150/20 kV substation
Connecting to nearest 20 kV distribution network
In some cases, PLN needs to build section of 150 kV T/L and
150/20 kV substation, revising on-going transmission expansion
plan
Economic issues : location will greatly affect project viability
11
In some areas, PLN needs to build 150 kV Substation and extend T/L,
revising the on-going power development plan
U
ACSR 2 x 240 mm
11 km 2015
ke
GI Langsa
(NAD)
ACSR 2 x 430 mm
70 km 2013
P. Brandan
G
T. Pura
to
GI Kuta Cane
(NAD)
Binjai 13
ACSR 2 x 430 mm
80 km 2014
12
ACSR 1 x 240 mm
178 km 2014
PLTA Renun
2 x 41 MW
PLTMH Tersebar II
28 MW 2014
D
E
Pakkat
A
Dolok
1 x 240 mm
SanggulACSR
7 km - 2013
PLTMH tersebar V
60 MW 2015/16/17
P
A
Agincourt
Padang
Sidempuan
PLTU
PLTD
PLTG
PLTA
PLTGU
PLTP
Kit Eksisting
Kit Rencana
GU
(Sumatera GIBarat)
Rencana
GI Eksisting
150 kV
GI Eksisting
70 kV
GI Eksisting
150/70 kV
150 kV
GI Rencana
150/70 kV
GI Rencana
275/150 kV
GI Rencana
500/275/150 kV
4 x 430 mm2
DolokACSR
Sanggul:
30 MVA, Ongoing, COD
331
km 2024
PLTP Sipaholon
2013
55 MW 2019
A.
B.
Existing 70 kV
Existing 150 kV
Rencana 150 kV
Rencana 275 kV
Rencana 500 kV
PLTP Sarulla 2
110 MW 2017
Panyabungan
ke
GI Bagan Batu
(Riau)
m2
2m
28 0 20
4x 2
SR km
C
A 175
m
0m
24 14
2 x 20
SR m
AC 70 k
ke
PERENCANAAN
GI SISTEM
Kiliranjao
BIDANG PERENCANAAN
PETA JARINGAN
PROPINSI SUMATERA UTARA
Kota
Pinang
PLTP Sarulla 1
110 MW 2016
220 MW 2017
Gunung
Tua
PLTA Sipan
17 MW & 33 MW
PT PLN (Persero)
PENYALURAN DAN PUSAT PENGATUR BEBAN
SUMATERA
Rantau
Prapat
Sarulla
ke
GI Rantau Prapat
Tarutung
Sibolga
Labuhan
Angin
ke
GI Tebing Tinggi
Aek
Kanopan
Labuhan
Bilik
PLTMH Tersebar I
54,5 MW 2013
Galang
Kuala
Namu
Simangkok
ACSR 2 x 240 mm2
11 km - 2016
Denai
PLTA Hasang
38 MW 2017
Asahan III
Asahan I
Perbaungan
Kisaran
13 km 2014
Titi
D Kuning
Perdagangan
PLTA Asahan I
180 MW
Parlilitan
Sei Rotan
T.Morawa
ACSR 2 x 430 mm2
24 km 2013
Kualatanjung
m2
0m
43 018
4x 2
SR km
AC 248
Salak
Mabar
GIS Listrik
Namurambe
Pematang
Siantar
Sidikalang
Pangururan
Porsea
Tele
ACSR 1 x 240 mm
Lamhotma
KIM
PLTU Belawan
4 x 65 MW
Paya Geli
PLTMH
Tersebar III
32,2 MW
2014
G.Para
Renun
DPM
to
GI Sabussalam
(NAD)
Glugur
Tebing
Tinggi
CU 1000
10 km 2015
Perbaungan
C Negeri
Dolok
Paya Pasir
Binjai
Brastagi
PLTP Sibayak
10 MW
Labuhan
PLTG Glugur
19,85 MW & 12,85 MW
Galang
GU
U
15
A
2
Belawan
10 7
3
9
1
14
16
8
11
PLTGU Belawan
395,3 MW & 422,5 MW
11
PLTG P. Brandan
(Peaker)
200 MW 2014
PLTA Wampu
45 MW 2015
PLTU P.SUSU
2 x 220 MW 2014
2 x 200 MW 2016
AC
S
23 R 2
km x
2
40
20 m
18 m
ke
GI Lhokseumawe
(NAD)
ke
GI Payakumbuh
(Sumatera Barat)
(Riau)
C.
D.
E.
13
voltage regulation;
thermal ratings of equipment being not exceeded;
fault ratings of switchgear and cables being not exceeded;
14
Concluding Notes
Mini hydro improve fuel mix, reduce losses, improve voltage profile on
distribution network
FIT generates positive response from IPP developer
Developers and PLN needs to work out on several issues such as site
overlapping or connection issues
PLN needs to adjust its network expansion plan to accommodate small
hydro
15
16
Thank You
Further Contact :
Suroso Isnandar
Division of System Planning
PLN
Email address : suroso.isnandar@pln.co.id
17