You are on page 1of 68

R.M.

R FOR BUILDING MATERIALS FOR THE YEAR 2015-2016


Convyeance
Basic cost
Lead
S.No
Description of material
Source
in Km
1
40 mm nominal
M-055
Yeleswaram
49
491.57
845.00
2
25 mm nominal
M-054
Yeleswaram
49
491.57
1313.00
3
20 mm nominal
M-053
Yeleswaram
49
491.57
1365.00
4
13.2/12.5 mm nominal
M-052
Yeleswaram
49
491.57
1097.00
5
10 mm nominal
M-051
Yeleswaram
49
491.57
935.00
6
6 mm nominal
M-050
Yeleswaram
49
491.57
735.00
p.no.286
7
Sand (unscreened)
Kulla
46
463.40
85.13
p.no.286
8
Sand (screened)
Kulla
46
463.40
152.13
p.no.286
9
Sand for filling
Kulla
46
463.40
85.13
9
II class bricks
BMT-A.01
Vemagiri
60
1033.14
5200.00
10 Cement
Local
5600.00
11 Mild steel
Local
37500.00
12 HYSD bars -Fe500
do
36000.00
13 HYSD bars -Fe415
do
34500.00
Cost of 20 mm down grade metal

20 mm
12mm
10mm
6mm

0.60
0.15
0.15
0.10

1856.57
1588.57
1426.57
1226.57

Seigniorage

Total

1336.57
1804.57
1856.57
1588.57
1426.57
1226.57
548.53
615.53
548.53
6233.14
5600.00
37500.00
36000.00
34500.00

per cum
per cum
per cum
per cum

1113.94
238.29
213.99
122.66
1688.88

DATA FOR BUILDING ITEMS WITH COMMON SSR 2015-16


Index code
1
BLD-CSTN-1-4

S.no
2
4

Description
3

Unit
4

Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement

kg.

Sand (including 5% wastage)

cum

Seigniorage charges for sand

cum

B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

day

25% on labour for MAA


overheads @ 13.615%
Grand Total

BLD-CSTN-1-5

Cement Mortar (1 : 4)
Unit : 1cum
A. MATERIALS:
Cement

kg.

Sand (including 5% wastage)

cum

Seigniorage charges for sand

cum

B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

day

25% on labour for MAA


overheads @ 13.615%
Grand Total
say

BLD-CSTN-1-6

Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement

kg.

Sand (including 5% wastage)

cum

Seigniorage charges for sand

cum

B. MACHINERY
- Nil -

C. LABOUR:
Man mazdoor for mixing mortar

day

25% on labour for MAA


overheads @ 13.615%
Grand Total

BLD-CSTN-1-7

Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement

kg.

Sand (including 5% wastage)

cum

Seigniorage charges for sand

cum

B. MACHINERY
- Nil -

C. LABOUR:
Man mazdoor for mixing mortar

day

25% on labour for MAA


overheads @ 13.615%
Grand Total

BLD-CSTN-1-8

Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement

kg.

Sand (including 5% wastage)

cum

Seigniorage charges for sand

cum

B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

day

25% on labour for MAA


overheads @ 13.615%
Grand Total

Earth work excavation for foundations and depositing on bank for all lifts and with an initial
10m including all operational, incidental, labour charges such as shoring ,sheeting, planking, st
etc. complete for finished item of work including seigniorage excluding dewatering charges etc
SS - 20 B (APSS 308).

BLD-CSTN-2

BLD-CSTN-2-1

Ordinary Soil-Manual Means-Upto 3 m depth


Unit = cum
Taking output = 1 cum
a) Labour
light mazdoor

day

Add extra of MAA on labour charges


seignirage charges
overheads @ 13.615%

Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations and ba
with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by water
ramming including cost and conveyance of water to work site and all operational, incidental, labour c
hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)

BLD-CSTN-2

BLD-CSTN-2-9

17

Earth filling (ordinary soil)


Unit = cum
Taking output = 1 cum
a) Labour
Mazdoor (Unskilled)
Add extra of MAA on labour charges

day

a&b) Overheads & Contractors Profit

*BLD-CSTN-2

Filling with carting sand in trenches,sides of foundations & basement from approved quarry conso
deposited layer by watering and ramming including cost and conveyance of water to work site
operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (AP
309 & 310)

Unit = cum
sand
a) Labour
Mazdoor (Unskilled)

cum
day

Add extra of MAA on labour charges


a&b) Overheads & Contractors Profit

BLD-CSTN-2

Filling with sand in trenches,sides of foundations & basement from approved quarry consolidating de
layer by watering and ramming including cost and conveyance of water to work site and all ope
incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 &

Unit = 1cum
sand
a) Labour
Mazdoor (Unskilled)
Add extra of MAA on labour charges
a&b) Overheads & Contractors Profit

cum
day

207

BLD-CSTN-14-1

Providing Antitermite treatment as per IS 6315 (Part - 2) 2001 (Pre-constructional chemical treatment measures) alo
internal & external vertical faces of the columns, plinth beams, basement and top surface of the basement filling bel
flooring bed as per the specified procedure conforming to IS 6315 (Part-2) 2001 and other relevant approved specif
duly using Chlorpyriphos/ Lindane emulsifiable concentrate 20% with 1% concentration @ 7.5 Liters/ sqm of the ver
surface & @ 5.0 Liters/ sqm of the horizontal surface of the substructure to a depth of 500 mm around columns & 30
deep around plinth beams, basements & floor filling area including excavation channel along the wall & rodding etc
conveyance of all materials to the site, cost of labour for spraying, rodding etc complete for finished item of work as
approval of the Engineer-in-Charge

Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable concentrate of 20%

BMS-W09
1 liter : 19 Parts water Therefore: 868.55 L /20
Add 12%wastage

Lit
Liters

Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges

Man Mazdoor

day

Sprayer

day

add 25% for MAA


D) Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity

Overheads & Contractors Profit @


BASIC COST per 1 sqm

*BLD-CSTN-2-7

15

Plain Cement concrete (1:5:10) using 40 mm metal with Concrete mixture. All work upto plinth
Unit = 1cum
A. MATERIALS:
Cement

kg

Coarse aggregate 40 mm

cum

Fine aggregate (Sand)

cum

Water (including for curing)

kl

B. MACHINERY
Concrete Mixer 300/200 diesel

hour

25% MAA on crew charges


C. LABOUR:
Mason 1st class

day

Mason 2nd class

day

Mazdoor (unskilled)

day

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total
21

V.R.C.C. M-20 Nominal Mix

NEW

BLD-CSTN-2-13

VRCC M20 grade using 6 to 20mm size graded SS5 gauge hard broken granite metal as per ss 108 wi
necessary reinforcement including cost, seigniorage and conveyance of all materials and water from ap
source to work site and all operational, incidental, labour charges such as centering, form work, mixing
concrete, laying, vibrating, curing etc., complete for finished item of work as per SS 403, but excluding c
reinforcement and its fabrication charges.

FOUNDATIONS

A. MATERIALS:
20mm HBG down graded metal

cum

Sand

cum

Cement

Kgs

water (including for curing)

kl

B. LABOUR:
1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% MAA onlabour charges


hire charges for centering and scafffolding
25% MAA onlabour charges for centering

cum

B. MACHINERY
Concrete Mixer 300/200diesel
25% MAA on crew charges
needle vibrator 40 mm (petrol)

hour

25% MAA on crew charges

Overheads & Contractors Profit @13.615%


BASIC COST per 1 cum
A*

PEDESTALS (Below Plinth)

A. MATERIALS:
20mm HBG graded metal

cum

Sand

cum

Cement

Kgs

water (including for curing)

kl

B. LABOUR:
1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% MAA onlabour charges


hire charges for centering and scafffolding

cum

25% MAA onlabour charges for centering

cum

B. MACHINERY
Concrete Mixer 300/200diesel
25% MAA on crew charges
needle vibrator 40 mm
25% MAA on crew charges

Overheads & Contractors Profit @13.615%

hour

BASIC COST per 1 cum


21
NEW

BLD-CSTN-2-13

V.R.C.C. M-20 Nominal Mix

VRCC M20 grade using 6 to 20mm size graded SS5 gauge hard broken granite metal as per ss 108 wi
necessary reinforcement including cost, seigniorage and conveyance of all materials and water from ap
source to work site and all operational, incidental, labour charges such as centering, form work, mixing
concrete, laying, vibrating, curing etc., complete for finished item of work as per SS 403, but excluding c
reinforcement and its fabrication charges.

Plinth beam

A. MATERIALS:
20mm HBG down graded metal

cum

Sand

cum

Cement

Kgs

water (including for curing)

kl

B. LABOUR:
1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% MAA onlabour charges


hire charges for centering and scafffolding

cum

25% MAA onlabour charges for centering


B. MACHINERY
Concrete Mixer 300/200diesel
25% MAA on crew charges
needle vibrator 40 mm

hour

25% MAA on crew charges

Overheads & Contractors Profit @13.615%


BASIC COST per 1 cum
*B

COLUMNS SECOND FLOOR floor

A. MATERIALS:
20mm HBG down graded metal

cum

Sand

cum

Cement

Kgs

water (including for curing)

kl

B. LABOUR:
1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% MAA on labour charges


10% on labour of FF for each floor
25% MAA on labour charges

hire charges for centering and scafffolding


25% MAA onlabour charges for centering

cum

B. MACHINERY
Concrete Mixer 300/200diesel
25% MAA on crew charges
needle vibrator 40 mm

hour

25% MAA on crew charges

Overheads & Contractors Profit @13.615%


BASIC COST per 1 cum
*B

LINTELS second floor

A. MATERIALS:
20mm HBG down graded metal

cum

Sand

cum

Cement

Kgs

water (including for curing)

kl

B. LABOUR:

1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% MAA on labour charges


10% on labour of FF on each floor
25% MAA on labour charges

hire charges for centering and scafffolding

cum

25% MAA onlabour charges for centering


B. MACHINERY
Concrete Mixer 300/200diesel
25% MAA on crew charges
needle vibrator 40 mm

hour

25% MAA on crew charges

Overheads & Contractors Profit @13.615%


BASIC COST per 1 cum
*C

RCC SLABS second floor

A. MATERIALS:
20mm HBG down graded metal

cum

Sand

cum

Cement

Kgs

B. LABOUR:
1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% on MAA on labour charges


10% on labour of FF for each floor
25% on MAA on labour charges
hire charges for centering and scafffolding
25% MAA onlabour charges for centering
B. MACHINERY
Concrete Mixer 300/200diesel

cum

25% MAA on crew charges


needle vibrator 40 mm

hour

25% MAA on crew charges


water (including for curing)

kl

Overheads & Contractors Profit @13.615%


BASIC COST per 1 cum
*C

RCC BEAMS second floor

A. MATERIALS:
20mm HBG graded metal

cum

Sand

cum

Cement

Kgs

B. LABOUR:
1st Class Mason

day

2nd Class Mason

day

Mazdoor (Both Men and Women)

day

25% on MAA on labour charges


10% on labour of FF for each floor
25% on MAA on labour charges
hire charges for centering and scafffolding

cum

25% MAA onlabour charges


B. MACHINERY
Concrete Mixer 300/200diesel
25% MAA on crew charges
needle vibrator 40 mm

hour

25% MAA on crew charges


water (including for curing)

kl

Overheads & Contractors Profit @13.615%


BASIC COST per 1 cum

BLD-CSTN-3-1

*v

Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class for basement
Unit = 1cum
A. MATERIALS:
Cement

kg

Bricks traditional size 23 x 11 x 7 cms 2nd class

Nos

Fine aggregate (Sand)

cum

Seigniorage charges for F.A

cum

B. LABOUR:
Mason 1st class

day

Mason 2 class

day

Mazdoor (unskilled)

day

nd

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total

BLD-CSTN-3-1

*v

Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class for first floor .23
thickness first floor
Unit = 1cum
A. MATERIALS:
Cement

kg

Bricks traditional size 23 x 11 x 7 cms 2nd class

Nos

Fine aggregate (Sand)

cum

Seigniorage charges for F.A

cum

Hire charges for access scaffolding

cum

25% MAA on labour charges of scaffolding

cum

B. LABOUR:
Mason 1st class

day

Mason 2 class

day

Mazdoor (unskilled)

day

nd

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total
*v

Reinforced Brick Masonary wall of 11.5 cm in CM ( 1:4) using 2nd class brick having a crushing
strength of not less than 35 Kgs and using two mild steel bars of 6 mm dia in every third layer of
masonary with free joints of main brick works including cost, seigniorage and conveyance of all
materials and water from approved source to work site and all operational, incidental labour cha
such as scaffolding, mixing mortar, constructing masonary, lift charges, curing etc., complete fo
finished item of work as per SS 509 for first floor

Unit = 1cum
A. MATERIALS:

old data

Cement mortar (1:4)

cum

Bricks traditional size 23 x 11 x 7 cms 2nd class

Nos

Hire charges for access scaffolding

cum

25% MAA on labour charges of scaffolding

cum

B. LABOUR:
Mason 1st class

day

Mason 2 class

day

Mazdoor (unskilled)

day

nd

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total
61

Plastering to walls with CM 2 coats, 20 mm thick, base coat in CM (1:6), 16mm thick and top coat
(1:4), 4mm thick with Dubara sponze finishing. For first floor
Unit = 10 sqm

BLD-CSTN-6-9

A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement
Fine aggregate (Sand)

kg
cum

Top Coat in CM(1:4), 4 mm thick


Cement

kg

Fine aggregate (Sand)

cum

Seigniorage charges for F.A

cum

Hire charges for access scaffolding

sqm

25% MAA on labour charges for

sqm

B. LABOUR:
Mason 1st class

day

Mason 2nd class

day

Mazdoor (unskilled)

day

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total
62

Plastering to walls with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8 mm thick and top coat
(1:3), 4mm thick with Dubara sponze finishing. For first floor

Unit = 10 sqm
A. MATERIALS:

BLD-CSTN-6-10

Base Coat in CM(1:5), 8 mm thick


Cement

kg

Fine aggregate (Sand)

cum

Top Coat in CM(1:3), 4 mm thick


Cement

kg

Fine aggregate (Sand)

cum

Seigniorage charges for F.A

cum

Hire charges for access scaffolding

sqm

25% MAA on labour charges of scaffolding

sqm

B. LABOUR:
Mason 1st class

day

Mason 2 class

day

Mazdoor (unskilled)

day

nd

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total
62

Plastering to cieling with CM 2 coats, 12 mm thick, base coat in CM (1:5), 8 mm thick and top coa
CM (1:3), 4mm thick with Dubara sponze finishing. For first floor
Unit = 10 sqm

BLD-CSTN-6-10

A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement

kg

Fine aggregate (Sand)

cum

Top Coat in CM(1:3), 4 mm thick


Cement

kg

Fine aggregate (Sand)

cum

Seigniorage charges for F.A

cum

Hire charges for stage scaffolding

sqm

25% MAA on labour charges of scaffolding

sqm

B. LABOUR:
Mason 1st class

day

Mason 2 class

day

Mazdoor (unskilled)

day

nd

25% MAA on labour charges

Overheads & Contractors Profit @13.615%


Grand Total

26 11.7 Providing High Yield strength deformed bars ( Fe 415) of different diameters, wrought and
including cost and conveyance of steel and all wastages such as overlaps, couplings, weld
chairs, spacer bars etc., and its cutting and bending to required sizes and shapes,placing, bind
fixing in position as shown in drawings including cost of binding wire, bending charges and an
incidental charges if any for finished item of work. first floor

Providing High Yield strength deformed bars ( Fe 415) of different diameters, wrought and
including cost and conveyance of steel and all wastages such as overlaps, couplings, weld
chairs, spacer bars etc., and its cutting and bending to required sizes and shapes,placing, bind
fixing in position as shown in drawings including cost of binding wire, bending charges and an
incidental charges if any for finished item of work. first floor

BLD-CSTN-2-18

p.no308

1000 & Unit = t


1200 (a) Material
HYSD bars including 5 per cent for overlaps and wastage
3

Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position

kg

Blacksmith / Bar bender


Mazdoor (Unskilled)
Sundries on Material
Add extra of MAA on labour charges

day
day

Overheads & Contractors Profit @13.615%

Rate per t = a+b+c


15

P.C.C. (1:3:6) using 6mm to 20mm size graded HBG machine crushed metal as per SS 108includi
cost, seigniorage and conveyance of all materials and water from approved sources to work site
all operational incidental, labour charges such as Centering form work mixing cencrete, laying, l
charges curing etc., completed for finished item of work as per SS 402 first floor

Unit = 1cum
A. MATERIALS:

old data

Cement

kg

Coarse aggregate 6mm to 20 mm down graded

cum

Fine aggregate (Sand)

cum

C. LABOUR:
Mason 1st class

day

Mason 2nd class

day

Man Mazdoor

day

Woman Mazdoor

day

25% MAA on labour charges


Concrete Mixer 300/200diesel

hour

25% MAA on crew charges

Overheads & Contractors Profit @13.615%


Grand Total
15

P.C.C. M20) using 6mm to 20mm size graded HBG machine crushed metal as per SS 108includin
seigniorage and conveyance of all materials and water from approved sources to work site and a
operational incidental, labour charges such as Centering form work mixing cencrete, laying, lift
charges curing etc., completed for finished item of work as per SS 402 first floor

Unit = 1cum

old data

A. MATERIALS:
Cement

kg

Coarse aggregate 6mm to 20 mm down graded

cum

Fine aggregate (Sand)

cum

C. LABOUR:
Mason 1st class

day

Mason 2nd class

day

Man Mazdoor

day

Woman Mazdoor

day

25% MAA on labour charges


Concrete Mixer 300/200diesel

hour

25% MAA on crew charges

Overheads & Contractors Profit @13.615%


Grand Total

R.C.C. M20 using 6mm to 20mm size graded HBG machine crushed metal as per SS
with necessary reinforcement including cost, seigniorage and conveyance of all mater
and water from approved sources to work side and all operational incidental, labour ch
such as scaffolding, centering form work mixing concrete lift charges curing etc., com
including plastering 12mm thick in two coats with a base coat of 8mm thick in C.M. 1
Proportionate with dubara sponge finishing for finished item of work as per SS 403 bu
excluding cost of steel and its fabrication charges for sunshades of 75mm thick at fixe
over 50mm thick at free end 0.75m wide sunshade in first floor

Rate of P.C.C. (1:2:4) concrete


Rate of 12 mm thick plastering
75

BLD-CSTN-7-5

cum
sqm

Flooring with vitrified tiles of 1 st quality of size not less than 598 x598 mm x 8 mm thickness set o
base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, includi
neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with wh
cement paste to full depth mixed with pigment of matching shade, including cost of all materials
cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for fin
item of work first floor

Unit = 10 sqm
A. MATERIALS:

BMT-C.59

Vitrified tiles of 1st quality of size

sqm

Cement for CM (1:8) for base coat

kg.

Cement for slurry

kg.

Cement for Pointing with CM (1:3)

kg.

Sand for CM (1:8)

cum

Sand for pointing

cum

Seigniorage charges of sand

cum

B. LABOUR
Mason 1st class

day

nd

Mason 2 class

day

Mazdoor (unskiled)

day

25% MAA on labour charges


Add water charges 1%

Overheads & Contractors Profit @13.615%


Grand Total
90

BLD-CSTN-7-20

BMT-C.15

BMS-W.68

Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal
flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed w
pigment of matching shade , including cost of all materials like tiles, cement, sand and water etc
complete including seigniorage charges, etc., complete for finished item of work, first floor

Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality
Sand for cm 1:5 base coat
Cement for cm 1:5 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskilled)
25% MAA on labour charges
Add water charges 1%

sqm
cum
kgs
kgs
kgs
cum
day
day
day

Overheads & Contractors Profit @13.615%


Grand Total

Providing RCM racks 25mm thick in CM (1:3) proportionate using rabit mesh require
gauge and nominal reinforcement with dubara sponge finish including cost, seigniorag
conveyance of all materials and rabit wire mesh and water to site and all operational,
incidental, labour charges such as centering, form work, mixing , laying, curing etc.,
complete for finished item of work as per SS but excluding cost of reinforcement and
fabrication charges

old data

Cement mortar(1:3)
chicken mesh
Centering & scaffolding charges
Labour charges

cum
sqm
sqm
sqm

25% for MAA

Overheads & Contractors Profit @13.615%

BMT-F.28

Supply & fixing 25 mm thick shabad stone for planks in cupboards including cost and
conveyance charges of all materials to site and labour charges for fixing them in posit
etc.,complete as directed by the Engineer in charge.
shabad stone
Labour charges for fixing in position

sqm
sqm

ON SSR 2015-16
Rate
6

Coefficient
5.00

Amount
7.00

5.60

480.00

2688.00

615.53

1.05

646.31

0.00

1.05

0.00

320.00

0.20

64.00

0.25

64.00

16.00

3414.31

464.86
3879.16

say

3879.16

5.60

360.00

2016.00

615.53

1.05

646.31

0.00

1.05

0.00
0.00

320.00

0.20

0.00
64.00

0.25

64.00

16.00

2742.31

373.37
3115.67
3115.67

5.60

288.00

1612.80

615.53

1.05

646.31

0.00

1.05

0.00

320.00

0.20

64.00

0.25

64.00

16.00

2339.11

318.47
2657.58

say

2657.58

5.60

240.00

1344.00

615.53

1.05

646.31

0.00

1.05

0.00

320.00

0.20

64.00

0.25

64.00

16.00

2070.31

281.87
2352.18

say

2352.18

5.60

180.00

1008.00

615.53

1.05

646.31

0.00

1.05

0.00

320.00

0.20

64.00

0.25

64.00

16.00

1734.31

236.13
1970.43

1970.43

bank for all lifts and with an initial lead of


h as shoring ,sheeting, planking, strutting,
e excluding dewatering charges etc as per

320.00

0.364

116.48

116.48
0.00
145.60

25%
1
13.615%

29.12
0.00
19.82
165.42

trenches, sides of foundations and basement


ating each deposited layer by watering and
nd all operational, incidental, labour charges,
SS NO. 309 & 310)

320.00
166.40

0.520
25%

166.40
41.60

208.00

13.615%

28.32
236.32

asement from approved quarry consolidating


d conveyance of water to work site and all
complete for finished item of work. (APSS NO.

548.53

1.00

548.53

320.00

0.052

16.64

16.64
569.33

25%
13.615%

4.16
77.51
646.84
646.84

rom approved quarry consolidating deposited


ce of water to work site and all operational,
finished item of work. (APSS NO. 309 & 310)

548.53

1.00

548.53

320.00

0.052

16.64

16.64
569.33

25%
13.615%

4.16
77.51
646.84
646.84

ructional chemical treatment measures) along the


and top surface of the basement filling below
2) 2001 and other relevant approved specification
concentration @ 7.5 Liters/ sqm of the vertical
to a depth of 500 mm around columns & 300 mm
ation channel along the wall & rodding etc & cost &
g etc complete for finished item of work as per the

228.00

4.100

934.80

228.00

0.41

93.40

4.51
1028.20

1%

10.28

320.00

3.0

960.00

375.00

0.007

2.63

962.63

25%

240.66

2241.76

10%

224.18

2241.76

3%

67.25

2241.76

1.50%

33.63

2566.82

13.615%

349.47
2916.29
291.63

crete mixture. All work upto plinth level.

5.60

132.00

739.20

1336.57

0.90

1202.91

548.53

0.45

246.84

0.00

1.20

0.00
0.00

338.60

1.00

338.60

206.70

25%

51.68
0.00

420.00

0.07

29.40

375.00

0.03

11.25

320.00

1.39

444.80

485.45

0.25

121.36

3186.04

13.615%

433.78
3619.82

broken granite metal as per ss 108 with


ance of all materials and water from approved
such as centering, form work, mixing
of work as per SS 403, but excluding cost of

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00

1.20

0.000

0.00
0.00

420.00

0.133

55.86

375.00

0.267

100.13

320.00

3.600

1152.00

1307.99

0.250

327.00

750.00
473.00

1.000
25%

750.00
118.25
0.00

338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

6832.94

13.615%

930.30
7763.24

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00

1.20

0.000

0.00

420.00

0.133

55.86

375.00

0.267

100.13

320.00

3.600

1152.00

1307.99

0.250

327.00

1068.00

1.000

1068.00

753.00

25%

188.25
0.00

338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

7220.94

13.615%

983.13

8204.07

broken granite metal as per ss 108 with


ance of all materials and water from approved
such as centering, form work, mixing
of work as per SS 403, but excluding cost of

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00

0.00

1.200

0.00

420.00

0.133

55.86

375.00

0.267

100.13

320.00

3.600

1152.00

1307.99

25%

327.00

2476.00

1.000

2476.00

1141.00

25%

285.25

338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

8725.94

13.615%

1188.04

0.00

9913.97

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00

0.00

1.200

0.00
0.00

420.00

0.167

70.14

375.00

0.167

62.63

320.00

4.700

1504.00

1636.77

25%

409.19

1636.77

10%

163.68

163.68

25%

40.92

1567.00

1.000

1567.00

1338.00

25%

334.50

0.00
338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

8481.76

13.615%

1154.79
9636.55

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00

0.00

1.200

0.00

420.00

0.167

70.14

375.00

0.167

62.63

320.00

4.700

1504.00

1636.77

0.250

409.19

1636.77

0.100

163.68

163.68

0.250

40.92

1713.00

1.000

1713.00

953.00

25%

238.25

338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

13.615%

1161.56

8531.51

9693.07

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00

420.00

0.067

28.14

375.00

0.133

49.88

320.00

2.500

800.00

878.02

0.250

219.50

878.02

0.100

87.80

87.80

0.250

21.95

2593.33

1.000

2593.33

1080.00

25%

270.00

338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

0.00

1.200

0.00

8400.31

13.615%

1143.70
9544.01

1688.88

0.900

1519.99

548.53

0.450

246.84

5.60

350.000

1960.00
0.00

420.00

0.067

28.14

375.00

0.133

49.88

320.00

2.500

800.00

878.02

0.250

219.50

878.02

0.100

87.80

87.80

0.250

21.95

3428.00

1.000

3428.00

1426.00

0.250

356.50
0.00

338.60

1.000

338.60

206.70

25%

51.68

175.40

1.000

175.40

148.80

25%

37.20

1.20

0.00

9321.48

13.615%

1269.12
10590.60

x 7 cms 2nd Class for basement

5.60

36.00

201.60

6233.14

512.00

3191.37

548.53

0.20

109.71

0.00

0.20

0.00

420.00

0.24

100.80

375.00

0.56

210.00

320.00

1.89

604.80

915.60

0.25

228.90

4647.17

13.615%

632.71
5279.89

x 7 cms 2nd Class for first floor .23m

5.60

36.00

201.60

6233.14

512.00

3191.37

548.53

0.20

109.71

0.00

0.20

0.00

374.00

1.00

374.00

268.82

25%

67.21

420.00

0.24

100.80

375.00

0.56

210.00

320.00

1.89

604.80

915.60

0.25

228.90

5088.38

13.615%

692.78
5781.16

2nd class brick having a crushing


rs of 6 mm dia in every third layer of brick
, seigniorage and conveyance of all
all operational, incidental labour charges
ift charges, curing etc., complete for

3115.67

0.20

623.13

6233.14

512.00

3191.37

624.00

1.00

624.00

537.65

25%

134.41

420.00

0.24

100.80

375.00

0.56

210.00

320.00

1.89

604.80

915.60

0.25

228.90

5717.41

13.615%

778.43
6495.84

n CM (1:6), 16mm thick and top coat in CM

5.60

43.00

240.80

615.53

0.18

110.80
0.00

5.60

14.50

81.20

615.53

0.04

24.62

0.00

0.22

0.00

7.17

10.00

71.70

6.18

25%

15.45

420.00

0.63

264.60

375.00

1.47

551.25

320.00

3.90

1248.00

2063.85

0.25

515.96

3124.38

13.615%

425.38

3549.76

n CM (1:5), 8 mm thick and top coat in CM


r

5.60

31.70

177.52

615.53

0.11

67.71
0.00

5.60

19.20

107.52

615.53

0.04

24.62

0.00

0.15

0.00

7.17

10.00

71.70

6.18

25%

15.45
0.00

420.00

0.63

264.60

375.00

1.47

551.25

320.00

3.90

1248.00

2063.85

0.25

515.96

3044.33

13.615%

414.49

3458.82

in CM (1:5), 8 mm thick and top coat in


oor

5.60

31.70

177.52

615.53

0.11

67.71
0.00

5.60

19.20

107.52

615.53

0.04

24.62

0.00

0.15

0.00

14.92

10.00

149.20

12.55

25%

31.38

420.00

0.63

264.60

375.00

1.47

551.25

320.00

3.90

1248.00

2063.85

0.25

515.96

3137.76

13.615%

427.21

different diameters, wrought and putup


such as overlaps, couplings, weld joints
ired sizes and shapes,placing, binding and
nding wire, bending charges and any other

3564.96

34500.00

1.05

36225.00

70.00

6.00

420.00

420.00
320.00

10.00
10.00

4200.00
3200.00

7400.00

25%

1850.00

45895.00

13.615%

6248.60
52143.60

crushed metal as per SS 108including


from approved sources to work site and
form work mixing cencrete, laying, lift
er SS 402 first floor

5.60

220.00

1232.00

1688.88

0.90

1519.99

548.53

0.45

246.84
0.00

420.00

0.06

25.20

375.00

0.14

52.50

320.00

1.80

576.00

320.00

1.40

448.00

1101.70

0.25

275.43

338.60

0.267

90.41

206.70

25%

51.68

4518.04

0.136

615.13
5133.17

rushed metal as per SS 108including cost,


approved sources to work site and all
m work mixing cencrete, laying, lift
er SS 402 first floor

5.60

350.00

1960.00

1688.88

0.90

1519.99

548.53

0.45

246.84
0.00

420.00

0.06

25.20

375.00

0.14

52.50

320.00

1.80

576.00

320.00

1.40

448.00

1101.70

0.25

275.43

338.60

0.267

90.41

206.70

25%

51.68

5246.04

0.136

714.25
5960.28

achine crushed metal as per SS 108


age and conveyance of all materials
operational incidental, labour charges
rete lift charges curing etc., complete
ase coat of 8mm thick in C.M. 1:5
ed item of work as per SS 403 but
sunshades of 75mm thick at fixed end
first floor

5960
3565

0.047
1.5

280.13
534.74
814.88

598 x598 mm x 8 mm thickness set over


lready laid or RCC roof slab, including
gs per sqm & jointed neatly with white
hade, including cost of all materials like
orage charges, etc., complete for finished

635.00

10.10

6413.50

5.60

21.60

120.96

5.60

33.00

184.80

5.60

6.000

33.60

548.53

0.12

65.82

548.53

0.020

10.97

0.000

0.140

0.00
0.00

420.00

0.96

403.20

375.00

2.24

840.00

320.00

3.30

1056.00

2299.20

0.25

574.80

9703.65

1.00%

97.04

9800.69

0.136

1334.36
11135.05

steps with vitrified tiles length equal to


with cement slurry of honey like
ed with white cement paste mixed with
ke tiles, cement, sand and water etc.,
nished item of work, first floor

635.00
548.53
5.60
5.60
29.00

10.10
0.12
34.56
33.00
2.00
0.12

420.00
375.00
320.00

0.96
2.24
3.30
0.25
1.00%
0.136

2299.20
9789.66
9887.56

6413.50
65.82
193.54
184.80
58.00
0.00
0.00
403.20
840.00
1056.00
574.80
97.90
1346.19

11233.75

rtionate using rabit mesh required


finish including cost, seigniorage and
water to site and all operational,
k, mixing , laying, curing etc.,
uding cost of reinforcement and its

3879.16
13
51
180

0.25
10
10
10

969.79
130.00
510.00
1800.00

1800.00

25%

450.00

2760.00

13.615%

375.77

4235.57

in cupboards including cost and


charges for fixing them in position

1084
10

10.05
1.00

1089.42
10.00
1099.42
10sqm
-

S.No
1

Quantity
2

unit
3

nos

nos

Nos

4
2.40
25.00%

Nos
Sqm

2.40
25.00%

Sqm

13.615%

nos

nos

Nos

Nos

1.76

Sqm

1.76
25.00%
13.615%

Sqm

nos

nos

Nos

Nos

1
3.15
25.00%

Nos
Sqm

3.15
25.00%
13.615%

Sqm

5.18

Rm

20.46

Kg

20.46

Kg

25.00%
13.615%

BMT-N.46

BMT-N.45

nos

nos

nos

nos

0.049
2.56

cum
sqm

25.00%
13.615%

0.105

cum

2.03

sqm

25.00%
1.714
1.714

Sqm
Sqm

25.00%
82.720
82.720

kg
Kg

25.00%
82.720

Kg

25.00%
3

nos

Nos

Nos

14.00%

Receipt of deduct cost of salvage for MS fully glazed windows and ventilators cold rolled MS hollow box
with step box and rebate of 35x15mm and internal vertical frames of 40x25mm T section to suit to fix the
square pipe section alround for the shutter of superior quality stell fixed with 4nos of hinges and 4mm pin
Kgs/cms fixing the glass as per standard practise and fixing 2 nos of 100mm MS tower bolts and MS hand
MS flat to MS frame precleaned on both sides with fair hammer including 12mm square safety bars welde
window frame

24

5.78

Rm

8.45

Kgs

16.87

Kgs

10.97

Rm

10.29

Kgs

Nos

nos

Nos

Nos

24

5.78

Rm

8.45

Kgs

16.87

Kgs

10.97

Rm

10.29

Kgs

1.67

Sqm

Nos

nos

Nos

Nos

60.81

Kg

60.81

Kg

107.11

Kg

107.11
2570.64
107.11
2035.09

Kgs
Kgs

Description
4
Supply and fixing flush type door shutters 35mm thick solid core type hot pressed bonded with water proof
phenol formal dehydroxe synthetic resin IS 2202 (part-II) 2983, 4mm thick paint grade commerical plywood
on both sides with internal lipping including cost and conveyance of all materials to work site and including all
taxes, all labour charges for making fixxing of door furniture in position as directed by dept, but including cost
of furniture fittings like tower bolts, aldrop handles etc., whtich would be supplied by the department free of
cost, for different of doors as mentioned in approved drg, for finished item of work.

Door type 4'X7'


3'9" X 6'101/2" = 25.78 Sft or 2.40 Sqm
35 mm thick commercial plywood shutter
BMT-N.17
3'9" X 6'101/2" = 25.78 Sft or 2.40 Sqm
150 mm long Alluminum handles
BMT-G.34
300 mm long Alluminum aldrop
BMT-G.42
150mm long Alluminum tower bolts
BMT-G.08
MS-Powder Coated Butt hinges (IS:205)- 150 mm Long BMT-G.30
Labour charges for making flush door BMM-V.07
25% for MAA on labour charges
Labour charges for fixing Flush door shutters of any thickness to the existing door
frameBMM-V.23
25% for MAA on labour charges
Overheads & contractors profit @ 13.615%

Cost of Door type 4'X7'


Door type 3'X7'
35 mm thick commercial plywood shutter
BMT-N.17
2'9" X 6'101/2" = 18.91 Sft or 1.76 Sqm
150 mm long Alluminum handles
BMT-G.34
300 mm long Alluminum aldrop
BMT-G.42

150mm long Alluminum tower bolts


BMT-G.08
MS-Powder Coated Butt hinges (IS:205)- 150 mm Long BMT-G.30
Labour charges for making flush door BMM-V.07
Labour charges for fixing Flush door shutters of any thickness to the existing door
frameBMM-V.23
25% for MAA on labour charges
Overheads & contractors profit @ 13.615%
Cost of Door type 3'X7'
Cost of Door type 3'X7'
Door (1.5m X2.10m)
1.5m X2.10m = 3.15 Sqm
35 mm thick commercial plywood shutter
BMT-N.17
3'9" X 6'101/2" = 25.78 Sft or 2.40 Sqm
150 mm long brass handles
BMT-G.58
300 mm long brass aldrop
BMT-G.37
150mm long brass tower bolts
BMT-G.02
brass- 150 mm Long BMT-G.22
brass- 150 mm door stopper BMT-G.46
Labour charges for making flush door BMM-V.07
25% for MAA on labour charges
Labour charges for fixing Flush door shutters of any thickness to the existing door
frameBMM-V.23
25% for MAA on labour charges
Overheads & contractors profit @ 13.615%

Door type 3'0" X 7'0"


Cost of door frame ((BMT-F.01)

2X 7'0" + 3'0" = 18'0" = 5.18 Rm

Weight of the frame at 3.95 Kg/Rm


Labour charges for fabrication(.BMM-V14)
Labour charges for fixing the door frame in position(BMM-V.15)

25% for MAA on labour charges


Overheads & contractors profit @ 13.615%

Supply and fixing of door frame made of hollow extruded PVC section (Nandi or equivalent) having
dimensions of 40 X 57mm with the wall thickness of 2mm +/- 0.2mm duly reinforced with seasoned wood
plank at the hinges side. The door frame top 2 corners shall be metri-cut/ welded. PVC DOOR FRAME
(Nandi or equivalent) and Supply and fixing of door shutters made of rigid PVC extruded hollow
section(Nandi or equivalent ) of 20mm X 200 mm with the wall thickness of 1.0mm +/- 0.1mm equally
divided into 4 no's with tongue and groove locking arrangements. The shutter frame is made of 58 X 24 mm
with the wall thickness of 1.5mm +/- 0.15mm section mitre-cut and joined at 4 corners with 125mm X 225mm
plastic brackets. The shutter shall be horizontally reinforced with 2 no's of 8mm PVC rods. Teak wood batons
shall be reinforced inside the door shutter during the fabrication of the door shutter at those points wherever
the hardware is fixed on to the door shutter. PVC DOOR SHUTTER (Nandi or equivalent )

For Door D2 type 2'6" X 7'0"


Cost of Door frame
2'6" + 2 X 7'0" = 16'6" = 5.03 Rm )
Cost of PVC Shutter
2'6" X 7'0" = 17.50 Sft or 1.626 Sqm
100 mm long allumium but hinges
BMT-G.54
200 mm long alluminum aldrop

BMT-G.40
150 mm long alluminum tower bolts
BMT-G.08
100 mm long Alluminum handles
BMT-G.32
Supply and fixing wooden door frame of size 5" X 3" including necessary fixtures including painting as
directed by the departmental officers including cost and conveyance of all materials and all incidental for
finished item of work.
Door frame size 4'0" X 7'0" =1.20m X 2.13m
wood requirement V = 2X2.13X .075 X 0.120
wood requirement H = 1X1.2X .075 X 0.120
total wood
cost of wood (BMT-E.16)
Labour charges for making(.BMM-V07)
25% for MAA on labour charges
Overheads & contractors profit @ 13.615%

Supply and fixing of wooden window of frame of size0 .075 m X 0.10 m and window shutter frame size 0.075m X
0.035m and grill of 10 mm square rods including aluminium tower bolts, aluminium handles,including cost and
conveyance of all materials and all incidental for finished item of work.

I. Alround frame=(1.80m+1.37)*2 = 6.34 Rm


window frame top & bottom
2 X (1.83+0.15+0.15)X 0.075X 0.10
verticals
4X 1.37X .075 X 0.10
wood for shutter
shutter size = 0.548m X 1.265m
shutter vertical = 3 X2X1.265 X .075X .035
shutter horizontal = 3 X2X 0.548 X 0.075X0.035
wooden beading = 10.03 X 0.02 X 0.02
glass = 3X 0.478X1.195 = 1.714 sqm
iron grill 12 mm square rods

verticals = 3 X 6 X 1.265 = 22.77 m


horizontals = 3 X 13 X 0.548 = 21.37m
total steel = 44.140 X 1.12 kg/m
alround frame 40mmX 25mm X 6mm
vertical = 3 X2 X 1.265 = 7.59 m
horizontals = 3 X 2 X 0.548 = 3.29m
total steel = 10.088 X 3.30 kg/m
total
cost of wood (BMT-E.16)
Labour charges for making(.BMM-V07)
25% for MAA on labour charges
5 mm thick green glass (BMT-I.16)
Labour charges for fixing glass to window (BMM-V.24)
25% for MAA on labour charges
cost of grill
Labour charges for fabrication for iron grill (BMM-V14)
25% for MAA on labour charges
Labour charges for fixing grill (BMM-V15)
25% for MAA on labour charges
150 mm long Alluminum handles
BMT-G.34
150mm long Alluminum tower bolts
BMT-G.08
MS-Powder Coated Butt hinges (IS:205)- 150 mm Long BMT-G.30
Overheads & contractors profit @ 14%
each window

educt cost of salvage for MS fully glazed windows and ventilators cold rolled MS hollow box section of 85x35mm for alroun
x and rebate of 35x15mm and internal vertical frames of 40x25mm T section to suit to fix the MS shutters made of 25x25x3m
section alround for the shutter of superior quality stell fixed with 4nos of hinges and 4mm pin headed glass of not less than 7.
ng the glass as per standard practise and fixing 2 nos of 100mm MS tower bolts and MS handles made out of 75x75x1.10mm
MS frame precleaned on both sides with fair hammer including 12mm square safety bars welded at 11.50 cm c/c horizontally .t
me

I. Alround frame
85 x 35 mm section alround = (1.52+1.37)*2 = 5.78 Rm
40 X 25 X 6mm thick T section = 2 X 1.22 = 2.44 @ 3.30 Kg/m =
add extra for corner pieces and cleats

12 mm thick MS safety square bars = 1.37 X 11X 1.12 Kg/m


II. Shutter frame ( 3Nos)
1. 25X25X2mm square MS pipe = 3 X (2x4.35+2x0.45)
2) 20 X 4 mm MS flat alround shutter = 3x(2*1.35+2*0.45)
do for supporting glass
= 3X(0.45*4)
Total length of flat
= 16.46 Rm
Weight of MS flats
= 16.46 @ 0.625 kKg/s
ABSTRACT
85 x 35 mm section alround MS cold rolled section
(BMT-F.01)
MS TEE section
Cost of 12 mm MS square bars
25X25X2mm square MS pipe ( Rate already approved)
20 X 4 mm MS flat alround shutter
MS handles ( BMT-G.35)
Adjustable lug stoppers
Lug fixtures
250 mm long wind stays
Rate per 2.025 Sqm of window
Rate per Sqm of window
Fabrication, supply and fixing of MS fully glazed windows and ventilators cold rolled MS
hollow box section of 85x35mm officers.
Considering a window of size = 1.50 X 1.35
Material requirement:
I. Alround frame
85 x 35 mm section alround = (1.52+1.37)*2 = 5.78 Rm
40 X 25 X 6mm thick T section = 2 X 1.22 = 2.44 @ 3.30 Kg/m =
add extra for corner pieces and cleats

12 mm thick MS safety square bars = 1.37 X 11X 1.12 Kg/m


II. Shutter frame ( 3Nos)
1. 25X25X2mm square MS pipe = 3 X (2x4.35+2x0.45)

2) 20 X 4 mm MS flat alround shutter = 3x(2*1.35+2*0.45)


do for supporting glass
= 3X(0.45*4)
Total length of flat
= 16.46 Rm
Weight of MS flats
= 16.46 @ 0.625 kKg/s
ABSTRACT
85 x 35 mm section alround MS cold rolled section
MS TEE section
Cost of 12 mm MS square bars
25X25X2mm square MS pipe
20 X 4 mm MS flat alround shutter
5 mm thick pin headed glass BMT-I.14
MS handles ( Rate already approved)
Adjustable lug stoppers
Lug fixtures
250 mm long wind stays
Labour charges for fabrication (BMM-V.14)
25% on MAA
Labour charges for fabrication (BMM-V.15)
25% on MAA
Rate per Sqm of window
Fabrication, Supply & fixing of gate using 50mm X 50mm X 2.8mm M.S. square pipe for
alround, 40mm X 40mm X 6mm L-angle for support to expanded metal sheet and 10mm
X 10mm X 2.8mm square rods for top 0.30 m including cost and conveyance of all
materials to site and complete for finished item of work
Considering a double door gate = 3.00 X 2.10 = 6.30 sqm
Material requirement:
I. Alround frame
50mm x 50 mm X 2.80mm square pipe
horizontals = 2X2X 1.50 = 6.00 rm
veticals = 2X2X 2.10 = 8.40 rm
14.40 X 4.37 Kg/m

40mmX40mmX6mm L-angle = 2X2X2.34 = 9.36 X 3.47Kg/m


10mm square rods - 15m X 0.78 Kg/m

ABSTRACT
Total M.S
Labour charges for fabrication BMM-V.14
25% on labour for MAA
Labour charges for fixing BMM-V.17
25% on labour for MAA

Rate per Sqm of gate

Rate
5
ed bonded with water proof
nt grade commerical plywood
s to work site and including all
cted by dept, but including cost
ed by the department free of
ork.

unit
6

Amount
7.00

1848.00

2.4

4435.20

sqm

sqm

140.00

each

280.00

425.00

each

850.00

114.00

each

228.00

44.00

each

550.00
1320.00

sqm

348.00
2485.20
9075.70

sqm

11345
4727

176.00
1320.00
330.00
835.20
621.30
2268.93
11344.63
Each
sqm

1848.00
sqm

1.76
sqm

3252.48

140.00

each

280.00

425.00

each
850.00

114.00

each

228.00

44.00
550.00

each
Sqm

176.00

348.00
1580.48
6762.08

sqm

7683
4365

612.48
395.12
920.66
7682.74
Each
sqm

1848.00

3.15

5821.20

sqm

sqm

335.00

each

670.00

1284.00

each

2568.00

260.00

each

520.00

383.00

each

1149.00

198.00

each

550.00
1732.50

sqm

198.00
1732.50
433.13

348.00
3261.83
15003.48

sqm

5.18

378.00

968.00

1096.20
815.46
3750.87
18754.35
5954

1958.04
Rm

rm

24.00

Kg
491.04

4.00
81.84

Kg

81.84
20.46

2551.38

2899
528

347.37
2898.75
per Each
per rm

5.03

254

1277.62

Rm

Rm

1.63

1923

Sqm

sqm

132.00

each

329.00

each

Say

Rs.

or equivalent) having
forced with seasoned wood
d. PVC DOOR FRAME
extruded hollow
0mm +/- 0.1mm equally
ame is made of 58 X 24 mm
corners with 125mm X 225mm
PVC rods. Teak wood batons
tter at those points wherever
equivalent )

3134.49

396.00

329.00

114.00

each
114.00

84.00

Say Rs.
res including painting as
ials and all incidental for

each

3325

168.00
5419.11
per sqm
-

2.56

0.038

0.011

0.049

69327.00
550.00

cum
sqm

sqm

cum
3397.02
1408.00

1408.00

352.00

5157.02

702.13
5859.15
per Each
per rm

Say

Rs.

5859
1067

indow shutter frame size 0.075m X


nium handles,including cost and

0.032

cum

0.041
0.073

cum

0.019
0.009
0.004
0.105

cum
cum
cum
cum

22.770
21.370
44.140
49.430

m
m
kg

7.590
3.290
33.290
82.720
69327.00
550.00

m
m
kg
kg
cum
sqm

1116.50

747.00
260.00
445.64

Sqm
Sqm

279.13
1280.36
445.64

37500.00
24.00
1985.28

mt
kg

111.41
3102.00
1985.28

4.00
330.88

kg

496.32
330.88

140.00

each

82.72
420.00

114.00

each

684.00

44.00
17851.92

each

264.00

1116.50

7253.68

2499.27
17852
8794

box section of 85x35mm for alround frame


he MS shutters made of 25x25x3mm
in headed glass of not less than 7.124
ndles made out of 75x75x1.10mm thick
ded at 11.50 cm c/c horizontally .to

5.78
8.05
0.40

Rm
Kgs

8.45

Kgs

16.87

Kgs

10.97

Rm

10.29

Kgs

378.00

Rm

2184.84

37.50

Kgs

316.88

37.50

kgs

632.63

65.62

719.85

37.50

Kgs

385.88

15.00

Each

45.00

8.00

Each

24.00

8.00

Each

24.00

35.00

Each

105.00
4438.08
4438.08
2192

5.78
8.05
0.40
8.45

Rm
Kgs

16.87

Kgs

10.97

Rm

Kgs

10.29

Kgs

204.00

Rm

1179.12

0.00

Kgs

0.00

0.00

kgs

0.00

65.62

719.82

0.00

Kgs

0.00

430.00

Sqm

718.10

15.00

Each

45.00

8.00

Each

24.00

8.00

Each

24.00

35.00

Each

105.00

Kg

1459.44
364.86
243.24
60.81
4943.39
2441.18 2441

24.00
1459.44
4.00
243.24

Kg

Say

6.00
8.40
14.40
62.93

Rm
Rm
Rm
Kgs

32.48
11.70
107.11

Kgs
Kgs
Kgs

41.00

Rm

4391.51

24.00
0.25
19.00
0.25

Kgs

2570.64
642.66
2035.09
508.77

Kgs

Say

10148.67
5011.69 5012

SUPPLEMENTAL DATA

S.No

Quantity
2

unit
3

Description
4
Fabrication supply and fixing of railing of height 900
mm and size over stage of court hall, bone for the
accused and witness bone including all labour
charges for making fixxing of grill in position as
directed by dept, but including cost of fittings like
tower bolts, aldrop handles etc., whtich would be
supplied by the department free of cost, as mentioned
in in drg, for finished item of work.

Rate
5

50mm dia G.I pipes


horizontals = 1.84m X 1 no = 1.84 m
verticals = 1.05 m X 3nos = 3.15 m
total = 4.99 m
25 X25mm Square rod
verticals (large)= 1m X 3nos = 3.00 m
verticals (small)= 0.7m X 5nos = 3.5 m
horizontals = 0.7m X 4 no =2.8m
horizontal = 1.84m X 1no = 1.84m
total = 16.13m X 4.9kg/m = 79.04Kg
79.04
5.29
79.04
25%
79.04
25%
13.615%

50mm dia G.I pipes (B - class)


kg Total steel for verticals & horizontals
m 50mm dia G.I pipes (B - class)BMW-F.77
Kg Labour charges for fabrication
BMM-V.16
25% for MAA
Kg Labour charges for fixing in position
25% for MAA
Over heads and contractor's profit

37500.00
475.00
21.00
1659.84
4.00
316.16
7946.75

Fabrication, supply & fxing of fixed grill and sliding


curtain
size of grill assumed = 2.52mX1.3m
outer portion 40 X40X6 L-angle
verticals= 1.3m X 2 nos= 2.60m
horizontals = 2.52mX 2nos = 5.04m

3.28

total = 7.64m X 3.47 kg/m = 26.51 kg


10 mm square rods for fixed portion
verticals= 1.3m X 25 nos= 32.50 m
horizontals = 2.52mX 13nos = 32.76 m
total = 65.26m X.78 kg/m = 50.90 kg
hold fasts flat
.2 X 6 nos= 1.2m X 1.87 kg/m = 2.24 kg
Total steel required= 79.65kg
79.65

kg

79.65

Kg

25%

Total steel for verticals & horizontals


Labour charges for fabrication

37500.00
24.00

BMM-V.14
25% for MAA

1911.60

Labour charges for fixing the door frame in position


79.65
25%
13.615%

4.00

Kg
25% for MAA

477.90

Over heads and contractor's profit

5814.45
per sqm

unit
6

Amount
7.00

mt

2964.00
2512.75

Kg

1659.84

Kg

414.96
316.16
79.04

rm

1112.55
9059.30
4923.53

mt
Kg

2986.88
1911.60
477.90

Kg
318.60
119.48
814.02
6628.47
2021

BUILDING DATAS
Sl. No

SSR Item No

P. No

1
1

Quantity

Description of Item

4
5
Supply and fixing anodised aluminium door fixed with all accessories (stappers, bo
in accordance with the approved drawings with alluminium single shutter with allr
(20102) thick and fixed with alluminium single shutter with vertical styles of s
47.62x44.45x 1.95 mm (19571) lock rail of sized 49.91x44.45x2.01mm (20060 and
with archit clural accessories having section 88x40x3.2 mm (19456) and 5 mm tinte
x0.10mm (19352) for height of 1.20 m pre laminated cement bonded paticle board
hight of 0.91 m at bottom panel PVC/ Rubber beading shutters mounted in heavy d
all materials and accessories including labour charges for fabrication and fixing in p

Size of the door = 1.50 x 2.10 meters ( Single shutters)


Material requirement
Alround frame with single groove (20102)
Vertical member for shutters (19569)
Top rail for the shutters (19571)
Middle rail for shutters (20060)
Bottom rail for shutter (19505)
Architectural accessories (19546)
Glazing clips (19352)
Add for stiffeners and corner pices
9mm thick Novapan shutter (OSL)
5mm thick tinted glass

38.39

Kgs

1.58

Sqm

1.58

Sqm

1.00
2.00

No
No

ABSTRACT
Cost of aluminium section with anodisation (SSR item
No. BMS-W.01)
8mm thick particle board (BMT-K.96)
5mm thick tinted glass

(BMT-I.08)

door closer(BMT-G.63)
Aluminium handlles (BMT-G.32)

3.00

Nos

150mm Aluminium hinges

(BMT-G.2

2.00

Nos

150mm Aluminium tower bolts

1.00
3.15

No
Sqm

Door stopper (BMT-G.57)


Labour charges for making the door and fixing in posit
(BMM-V.07)

(BMT-G.08

Add extra for MAA on

25%

overheads & Contractor profit 13.615%


Rate as per Sqm

BMT-M.77

BISON LAM (Pre Laminated Cement Bonded Particle Board) ALUMINIUM PARTATIONS
partitions using 10MM BISONLAM and 5.50 mm thick plain glass to full height. Using with BIS
remaining height with glass and aluminium sections anodized to 12 to 15 microns and of sec
one meter centre to centre duly fixed with clip beading on both sides including fixing the fram
and conveyance of all materials etc., complete as directed during execution.

1.00

Sqm

Aluminium Glazed Partition

G DATAS
Description of Item

Rate

per

Amount

5
6
7
8
ixed with all accessories (stappers, bolts and stoppers etc.,) with all sizes and sectional
th alluminium single shutter with allround frame section of 101.60 x 44.45 x2.50 mm
ngle shutter with vertical styles of sizes 47.62 x 44.45 x 2.02 mm (19569) top rail
zed 49.91x44.45x2.01mm (20060 and bottom rail of sizes 95.25x44.45x2 mm (19505)
8x40x3.2 mm (19456) and 5 mm tinted glass sheet with glazing chips of size 79x 17.30
aminated cement bonded paticle board ( Bison Lam or equivalent ) of 8mm thick to a
beading shutters mounted in heavy duty floor spring including cost and conveyance of
charges for fabrication and fixing in position as directed by the Engineer in Charge.

Lenth in RM Weight RM

ABSTRACT
m section with anodisation (SSR item

le board (BMT-K.96)
glass

(BMT-I.08)

T-G.63)
lles (BMT-G.32)

Weght
Kg

5.700
4.200
1.500
1.500
1.500
5.100
5.100

1.977
1.052
0.974
1.072
1.519
3.06
0.097

1.500
1.500

1.050
1.050

11.27
4.42
1.46
1.61
2.28
15.61
0.49
37.14
1.25
38.39 Kgs
1.58 Sqm
1.58 Sqm

321.00

kg

12323.19

624.00

sqm

985.92

644.00

sqm

1017.52

1035.00
84.00

each
each

1035.00
168.00

um hinges

um tower bolts

(BMT-G.26)
(BMT-G.08)

MT-G.57)
or making the door and fixing in positin

165.00

each

495.00

114.00

each

228.00

63.00
550.00

each
sqm

63.00
1732.50

1732.50

433.13
18481.26
ds & Contractor profit 13.615%
2516.22
18481.26
18,481.26 / 3.15=
5867.07
Or say
5867.00
1 sqm
article Board) ALUMINIUM PARTATIONS-Supply and fixing of BISON LAM aluminium glazed
ck plain glass to full height. Using with BISON LAM to a height of 0.91 meter at bottom panel and
s anodized to 12 to 15 microns and of sections of size 37mm x 62mm and 1.5mm thickness with
ding on both sides including fixing the frame to pillars by M.S. flats, bolts and nuts including cost
irected during execution.

3435.00

sqm

3435.00
3435.00
1 Sqm

External Painting
6 Painting to New walls with 2 coats of plastic emulsion paint of approved brand and shade over a base coat
of approved cement primer grade I making 3 coats in all to give an even shade after thoroughly brushing
the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of
all materials to work site,and all operational, incidental, labour charges etc. complete for finished item of
work as per SS 912 for external walls for external colouring -Plastic Emulsion Paint - 3 coats. (1st floor)

One Coat Primer


A. MATERIALS :
Supply of water based
cement primer of Exterior
Grade -2
B. LABOUR
1st Class painter
2nd Class painter
Applicable municipal area
allowance(25%)

BMT-J.02

kg

210.00

1.00

CMM-035
CMM-079

1day
1day

480
375
284.55

0.210
0.490
0.250

Two Coats Plastic Emulsion Paint


A. MATERIALS :
Supply of synthetic
polymer plastic emulsion
paint

BMT-J.23

kg

473.00

0.80

CMM-035
CMM-079
CMM-087

day
day
day

480
375
320
764.55

0.210
0.490
1.500
0.250

Scaffolding Hire Charges

10 sqm

9.93

Scaffolding Labour

10 sqm

61.80

B. LABOUR
1st Class painter
2nd Class painter
Light Mazdoor
Applicable municipal area
allowance(25%)

Applicable municipal area


allowance(25%)

618.00

Applicable overheads and


contractors
profit(13.615%)

2771.58

Rate per 10 Sqm


Rate per 1 Sqm

Interior wall Painting

6 Painting to New walls with 2 coats of plastic emulsion paint of approved brand and shade over a base coat
of approved cement primer grade I making 3 coats in all to give an even shade after thoroughly brushing
the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of
all materials to work site,and all operational, incidental, labour charges etc. complete for finished item of
work as per SS 912 for external walls for internal colouring -Plastic Emulsion Paint - 2 coats + 1 coat primer.

One Coat Primer


A. MATERIALS :
Supply of water based
cement primer of Interior
Grade -1
B. LABOUR
1st Class painter
2nd Class painter
Applicable municipal area
allowance(25%)

BMT-J.01

kg

165.00

0.50

CMM-035
CMM-079

1day
1day

480
375
109.65

0.080
0.190
0.250

Two Coats Plastic Emulsion Paint


A. MATERIALS :
Supply of synthetic
polymer plastic emulsion
paint
B. LABOUR
1st Class painter
2nd Class painter
Applicable municipal area
allowance(25%)
Applicable overheads and
contractors
profit(13.615%)
Rate per 10 Sqm
Rate per 1 Sqm

BMT-J.23

kg

473.00

0.80

CMM-035
CMM-079

day
day

480
375
487.80

0.360
0.840
0.250

1207.71

Miscellaneous
Centering and Scaffolding charges Rate as per SSR 2011-12
material hire charges
PNo.93 Scaffolding
FL-1/GF
0.99
charges
FL-2/FF
1.49
FL-3/SF
1.98
FL-4/TF
2.48
FL-5/FF
2.97
Rate for other Floors
FL-1/GF
Rate as worked out above
#REF!
Scaffolding charges
7.17
Rate per 1 Sqm
#REF!
Rate per 10 Sqm
#REF!

Labour Charges
6.18
6.18
6.18
6.18
6.18
FL-2/FF
FL-3/SF
#REF!
#REF!
7.67
8.16
#REF!
#REF!
#REF!
#REF!

Centering charges
7.17
7.67
8.16
8.66
9.15
FL-4/TF
#REF!
8.66
#REF!
#REF!

shade over a base coat


er thoroughly brushing
ost and conveyance of
e for finished item of
- 3 coats. (1st floor)

210.00

100.80
183.75
71.14

378.40

100.80
183.75
480.00
191.14
99.30
618.00
154.50
377.35

3148.92
314.89

shade over a base coat


er thoroughly brushing
ost and conveyance of
e for finished item of
- 2 coats + 1 coat primer.

82.50

38.40
71.25
27.41

378.40

172.80
315.00
121.95

164.43

1372.14
137.21

Centering charges

FL-5/FF
#REF!
9.15
#REF!
#REF!

20

Supply and fixing of mild steel hollow door frames manufactured by cold rolled formed process with
quality MS grade conforming to LS 4351-1976 suitable for single/double leaf frames of section 1
including six Nos of standard lugs made from flat/steel strips not less than 1.6mm thick including base
hinges of size with one side fixed to frame for fixing of shutters 3 Nos rubber bottom inserts in the f
aldrops hole (10" long 12mm dia aldrops ) and tower bolts eyes welded to frame at top and bottom a
frame for wind cleat 1 No assembled by means of welding at coners inlcuding painting to frame as dire
best certificates for raw materials including all tools cost and conveyance of all materials and all inci
item of work

For Door D 1.22 X 2.14


Size of door 1.22 X 2.14m
Frame length in R.M. 5.50
Rate per R.M

5.50
233.00

Cost of Frame
L.S. for Transportation
Total:
4.0% Turn over tax

1301.50

Total cost of Frame


ROUNDING OFF SAY:
For Door D1

0.99 X 2.14

Size of door

0.99 X 2.14m

Frame length in R.M. 5.18


Rate per R.M

5.18
233.00

Cost of Frame
L.S. for Transportation
Total:
4.0% Turn over tax

1226.94

Total cost of Frame


ROUNDING OFF SAY:
For Door D2

0.92 X 1.98

Size of door

0.77 X 1.90m

Frame length in R.M. 4.88


Rate per R.M
Cost of Frame
L.S. for Transportation
Total:
4.0% Turn over tax
Total cost of Frame

4.88
233.00

1157.04
ROUNDING OFF SAY:

ufactured by cold rolled formed process with 1.25mm thick bright CRCA "D"
for single/double leaf frames of section 105mmX60mm with 35mm rebate
ips not less than 1.6mm thick including base of section 50mmX25mm prefixed
hutters 3 Nos rubber bottom inserts in the frames necessary arrangements for
s eyes welded to frame at top and bottom and fixing of 50mm long hinges, to
at coners inlcuding painting to frame as directed by the department along with
and conveyance of all materials and all incidental labour charges for finished

1281.50
20.00
1301.50
52.06
1353.56
ROUNDING OFF SAY:

1354.00

1206.94
20.00
1226.94
49.08
1276.02
ROUNDING OFF SAY:

1276.00

ROUNDING OFF SAY:

1137.04
20.00
1157.04
46.28
1203.32
1204.00

You might also like