You are on page 1of 195

The estimate is prepared as per SSR 2014 - 2015

Dear Member RWS Engineers

An attempt is made by me with my limited knowledge to minimise the work load on RWS Engineers in the
preparation of SVS Estimates. Any suggestions or improvements in the Model estimate is always welcome. If any
mistakes are found or observed kindly intimate me which will be highly appreciated.

The letters in red colour indicates that the rates / data for thes items are as per previous SSR
Note : Requested not to change the values in the sheets after the blank sheet. The estimate is protected. The
pass word for unprotection is
Procedure : Enter required data in the Input data sheet
2. In any sheet if any cell is high lighted with this colour enter the value manually
Note on Lead : It is preferable to give the lead in round figures. If fraction is given the lowest lead is selected. Eg.
If the lead is 9.20 Km then lead charges for 9.00 km is adopted.
If the lead is 9.90 Km then lead charges for 9.00 Km is adopted
The rows which were highlighted with this colour are to be modified manually as per the design requirements.

GOOD LUCK
M. R . SATISH KUMAR
Deputy Executive Engineer
RWS & S Sub Division
Sathyavedu - 2 @ Pichatur
Ph : 8008502473

Engineers in the
always welcome. If any

SSR

te is protected. The

est lead is selected. Eg.

esign requirements.

INPUT DETAILS
Providing Pipeline from water tank
to Bore at HW of Thangellapalem
Village and GP in Thottembedu
Mandal

Name of the Work :


Grant
Sub Program
Est
Part A
Part B
Work ID
SSR
Designation
Dy Exe. Engineer
RWS & S Sub Division

MPLADS 2015-16
2.50

2015-2016
Asst. Engineer,
RWS & S,

Satyavedu - 2
Material

Thottembedu
Lead statement input
Quarry

Lead (Km) Cost

Sand Screened (Plastering etc.,)

Pulikundram

19.00

Sand for filling


Sand Un screened (Concrete
etc.,)
6 to 12 mm HBG metal (MC)
40 mm HBG metal
40 mm HBG metal (MC)
20 mm HBG metal
20 mm HBG metal (MC)
CR Stone
RR stone
Bond stone
Country Brick
(23 x 11 x 7
cm)
Cement per MT
Steel per MT

Pulikundram
Pulikundram

19.00
19.00

GR Kuppam
GR Kuppam
GR Kuppam
GR Kuppam
GR Kuppam
GR Kuppam
GR Kuppam
GR Kuppam
Local Kiln

23.00
23.00
23.00
23.00
23.00
23.00
23.00
23.00
5.00

Pichatur
Pichatur

4100
43000

PM & GM Input
PM
Size
Earthwork, L & J
GM
Size
Earthwork, L & J

90/6

63/6
102.25

Pipe line data


75/6
90/6
103.40
151.45

75/4

63/4
102.25

Pipe line data


75/4
90/4
103.40
151.45

OHSR INPUT
OHSR capacity (kL)
Staging
Cost of steel and Cement for the
month

90
9.6
January

12.80,9.65,6.50
2015

Cost of Cement as on Tech


Sanction month (Rc)
Cost of Steel as on Tech Sanction
month (Rs)

6800
43500

ne data
110/6
153.40

ne data
110/4
153.40

STAGING CALUCULATIONS
Name of the Work : Providing Pipeline from water tank to Bore at HW of
Thangellapalem Village and GP in Thottembedu Mandal
Capacity of OHSR
Diameter
Side wall height
Ringbeam Depth
Bottom slab thickness
Dead storage
Freeboard

20
4.00
1.90
0.25
0.25

0.15
0.20

kL
m
m
m
m
m
m
MWL

82.45 m

LWL

80.75 m

2.70 m
0.45 m
2.70m
0.45 m
2.70m
0.45 m
GL

GL

71.10

Ground level of the OHSR site

71.10

Highest level in the distribution system

72.50

Add Friction and Other losses

0.75

Add head required for a minimum


residual head of 6.00 m including
losses

6.85

LWL Required

80.10

GL at OHSR site

71.10

Staging required

9.00

20kL OHSR

Provide a staging o 9.60

Dy Exe. Engineer

Asst. Engineer,

RWS & S Sub Division


Satyavedu - 2

RWS & S,
Thottembedu

COMPARTIVE STATEMENT

Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
S.No.
1

Description of work
2

Drilling of 13 mm dia Bore well


Supply, delivery, installation and commissioning
2(A) of 3 phase submersible pump set (As per sub
estimate)
Supply, delivery, installation and commissioning
2(B) of Single phase submersible pump set (As per
sub estimate)
Construction of Pedestal type panel board room
3(A)
( As per Sub estimate )
Construction of Panel board room of size 1.80 x
3(B)
2.40 m ( As per Sub estimate )
4
5
6

Proivsion for Pumping main 75 mm * 6 Kg/cm2


ISI make PVC Pipes (As per sub estimate)
Proivsion for Gravity main 75 mm * 4 Kg/cm 2 ISI
make PVC Pipes (As per sub estimate)
Construction of
Lt OHSR of
m
stagging ( As per Sub estiamte )

Qty
3
1
1

As per Original Estimate


Rate
per
Amount
4
6
1
0
1 No
0

1 No

1 No

Qty
7
1
1
1

As per Recast Estimate


Rate
per
Amount
8
10
1
0
50155
1 No
50155
138151

57429

1 No

1 No

Excess
11
0
50155

Less
12
0
0

138151

57429

23790

138151

57429

1 No

23790

1 No

23790

1 No

#VALUE!

1 No

#VALUE!

1 No

40604

1 No

40604

1 No

13732

1 No

13732

1 No

#REF!

1 No

#REF!

#VALUE! #VALUE!

40604

13732

#REF!

#REF!

Provision for Source sustainability

Provision for Power supply charges

Insurance premium for OHSR @ 0.5%

10

QC charges @ 0.5%

#VALUE!

#VALUE! #VALUE! #VALUE!

11

VAT @ 4%

#VALUE!

#VALUE! #VALUE! #VALUE!

12

Unforeseen items of work

#VALUE!

#VALUE! #VALUE! #VALUE!

As per Original Estimate :

Excess :

#VALUE! #VALUE! #VALUE!

#VALUE!

Remarks
13

1
As per Execution

2
:

4
#VALUE!
#VALUE!

6
Less

7
#VALUE!

10

11

12

-1000000
Dy Exe. Engineer

Asst. Engineer,

RWS & S Sub Division

RWS & S,

Satyavedu - 2

Thottembedu

13

GOVERNMENT OF ANDHRA PRADESH


RURAL WATER SUPPLY AND SANITATION DEPARTMENT
Satyavedu - 2

DETAILED ESTIMATE

Work ID

0
Providing Pipeline from water tank to Bore
at HW of Thangellapalem Village and GP in
Thottembedu Mandal

Name of the Work

:-

Est . Cost

:-

2.50 Lakh

Est Cost (Part A)

:-

0.00 Lakh

Est Cost (Part B)

:-

0.00 Lakh

GRANT

:-

MANDAL

:-

Thottembedu

SUB-DIVISION

:-

Satyavedu - 2

MPLADS 2015-16 0

SPECIFICATION REPORT
Specification report to accompany the Recast Estimate for the work "

Grant : NRDWP

Est.Cost :-Rs.

The work
was administratively sanctioned for Rs.______ lakhs under NRDWP (PLAIN / SCP / NTSP) programme vide
Proc.No AEE4/RWS-PLG/NRDWP/SLSSC-1/2009-10/1, Dt.11.05.2010 of the Engineer-In-Chief, RWS&S,
Hyderabad and Technically sanctioned vide DR.No.

/10-11 Dt.

of the Executive

Engineer, RWS & S Division, Tirupati


The estimate is recasted as per SSR 2010 - 11 and Recast estiamte is prepared with the following
provisions.
1 Provision for Drilling of 163 mm dia Bore well
2 Provision for Pumpset with its accessories
3 Construction of 20 KL OHSR with 6.30 m Stagging.
4 Provision for Pumping Main with 75mm dia 6Kg/cm2 PVC pipes
5 Provision for Gravity Main with 75mm dia 4 Kg/cm2 PVC pipes
6 Provision for Public Taps.
7 Provision for Pumproom pedastal
8 Provision for Power Supply Connections
9 Provision for Insurance Premium.
10 Provision for Q.C.Charges @ 0.50%
11 Provision for unforeseen items
The Recast Estimate is prepared as per the Current S.S.R. 20010 - 11
and the work will be executed as per the Standard Specifications of APDSS.
Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

DESIGN CALCULATION
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Population - villge 1

village 2
village 3
Total Population as per Census
Base year
Base year population
Prospective population
Ultimate population

2011

640

2015
640 X (1+1/100)^3

666

(1 + 1/100)10 * Base year population

736

(1 + 1/100)20 * Base year population

813

Taking daily deman as 55 LPCD(including losses)


Prospectie demand (l/day)
Ultimate demand (l/day)

Prosepective population*55

40480

Ultimate population*55

44715

(Prosepective demand)/16*60

42.17

(Ultimate demand)/16*60

46.58

Taking 16 hrs of daily pumping


Prospective discharge (lpm)
Ultimate discharge
Approximate size of pumping main (cm)

0.76(Ultimate discharge)^0.46

4.45

Provide 75 mm * 6 Kg/cm2 PVC pipes


Capacity of Service Reservoir required

Prosepective daily demand/2


Provide OHSR of capacity

Taking total head of water to be lifted from BW


including losses (m)
Assuming efficiency of pump set as 40%

20240
20 KL

110
40
Prospective discharge*Head*100

Capacity of pump set required (HP)

2.85
4500*Efficiency
Provide_______ HP submersible pump set

Dy Exe. Engineer
RWS & S Sub Division
Tirupathi

Asst. Engineer,
RWS & S,
Tirupathi

36420

GENERAL ABSTRACT
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Est.

2.50

Lakhs

Part A

0.00

Lakhs

Part B

0.00

Lakhs

Grant :
S.No

Quantity

Rate

MPLADS
2015-16
per

Sinking of 163 mm dia Bore well

50155

1 No

50155

Provision for Power supply charges

1 Job

Description of work

0
Amount

PART - A

QC charges @ 0.5% for Part - A

VAT @ 5% for Part - A

Unforeseen items of work for Part - A

-50155

PART - B
Supply, delivery, installation and commissioning of 3
phase submersible pump set (As per sub estimate)

138151

1 No

138151

Supply, delivery, installation and commissioning of Single


phase submersible pump set (As per sub estimate)

57429

1 No

57429

Construction of Pedestal type panel board room ( As per


Sub estimate )

23790

1 No

23790

Construction of Panel board room of size 1.80 x 2.40 m


( As per Sub estimate )

#VALUE!

1 No

#VALUE!

Proivsion for Pumping main 75 mm * 6 Kg/cm 2 ISI make


PVC Pipes (As per sub estimate)

40604

1 No

40604

Proivsion for Gravity main 75 mm * 4 Kg/cm 2 ISI make


PVC Pipes (As per sub estimate)

13732

1 No

13732

Construction of 20000 Lt OHSR of 9.6 m stagging (As per


Sub Estimate)

1039813

1 No

1039813

Provision for Source sustainability

Insurance premium for OHSR @ 0.5%

QC charges @ 0.5% for Part - B

#VALUE!

file:///var/www/apps/conversion/tmp/scratch_7/336936782.xls

S.No

Description of work

Quantity

Rate

per

Amount

VAT @ 5% for Part - B

#VALUE!

Unforeseen items of work for Part - B

#VALUE!
Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

#VALUE!

Asst. Engineer,
RWS & S,
Thottembedu

file:///var/www/apps/conversion/tmp/scratch_7/336936782.xls

GENERAL ABSTRACT (PART - A)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Est.

0.00

Grant :
S.No

Description of work

Quantity

Rate

MPLADS
2015-16
per

50155

1 No

Lakhs
0
Amount

50155

Drilling of 163 mm dia Bore well

Provision for Power supply charges

QC charges @ 0.5%

VAT @ 5%

Unforeseen items of work

-50155
Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

Sub Estimate for Bore well


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
S.N
Description of work
No
Measurements
Conte
Rate
per
Amount
o
nts
L
B
D
1 Geological survey charges for drilling of bore well
1*1
1 Job
825
1 Job
825

Drilling of Tube/Borewells by down the hole


hammer to a finished diameter of 163mm
dia in all formations/straaus such as medium
hard rock formation, consolidationformations
etc., including drilling in over burdern soils
to a diameter of not less then 200mm
including insetion of 180mm diameter
including the insetion of unplasticized PVC
Pipe with work pressure not less than 6
kg/sqm as casing pipe confirming to IS
Specification No. 4966/1988 with ISI Mark up
to depth as directed by the department and
flushing 8 hours for Bore development
conducting yield test including transportation
of drilling rigs supporting vehecles including
crew charges and all other charges as
required etc., complete all done to the
satisfaction of the Department and as
stipulated in the technical specification to
theis schedule but excluding the cost of PVC
Casing pipes,couplings and cap, the entire
work should be carried out as per IS 28000
part I and II/1979. The rate is exclusive of all
taxes in rural and urban areas.
Depth of Drilling

1*1

90

90

350

1m

31500

Supply and delivery of 180mm diameter PVC


pipes with working pressure of 6 kg/sqcm as
casing pipe for borewells confirming to IS
1*1
Specification No. 4958/1988 with ISI
mark.inclusive of CED and Cess but
excluding VAT

24

24

712.36

1m

17097

150.00

1 No

150

PVC Borecap suitable for 180mm dia PVC


pipe used for borewells . The rate exclusive 1*1
of all taxes.

Unforeseen items of work

583
Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

50155

GENERAL ABSTRACT (PART - B)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Est.

0.00

Grant :
S.No

Description of work

Quantity

Rate

MPLADS
2015-16
per

Lakhs
0
Amount

1(A)

Supply, delivery, installation and commissioning of 3


phase submersible pump set (As per sub estimate)

138151

1 No

138151

1(B)

Supply, delivery, installation and commissioning of Single


phase submersible pump set (As per sub estimate)

57429

1 No

57429

2(A)

Construction of Pedestal type panel board room ( As per


Sub estimate )

23790

1 No

23790

2(B)

Construction of Panel board room of size 1.80 x 2.40 m


( As per Sub estimate )

#VALUE!

1 No

#VALUE!

Proivsion for Pumping main 75 mm * 6 Kg/cm 2 ISI make


PVC Pipes (As per sub estimate)

40604

1 No

40604

Proivsion for Gravity main 75 mm * 4 Kg/cm 2 ISI make


PVC Pipes (As per sub estimate)

13732

1 No

13732

Construction of
( As per Sub estiamte )

1039813

Provision for Source sustainability

Insurance premium for OHSR @ 0.5%

QC charges @ 0.5%

#VALUE!

VAT @ 5%

#VALUE!

10

Unforeseen items of work

#VALUE!

Lt OHSR of

m stagging

1 No

Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

1039813

#VALUE!

Asst. Engineer,
RWS & S,
Thottembedu

Sub Estimate (Pump set)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Name of Wrok : Providing 3 phse submersible pump set
S.No

Description of work

No

Measurements
L
B
D

Contents

Rate

Supply and dilivery of 5 HP/ 12 Stage


submersible pump set as per ISI standards
1*1
incuding cost and conveyance of all
materials and labour charges etc.

1 No

LS

Cost of Control panel board of approved


one with all accessories suitable for up to
and including 7.50 HP exluding VAT

1*1

1.00

10920.00

1 No

10920

Cost of Control panel board of approved


2(B) one with all accessories suitable for above
7.50 HP exluding VAT

1*1

1.00

18200.00

1 No

18200

Cost of 50 mm GI pipes B Class excluding


VAT

1*1

120

120

317.24

Cost of 2.5 Sq.mm finolex cable wire


excluding VAT

1*1

150

150

83.60

1 Rmt

12540

4(A)

Cost of 4 Sq.mm finolex cable wire


excluding VAT

1*1

150

150

125.40

1 Rmt

18810

Cost of 50mm GI Heavy couplings


excluding VAT

1*20

20

217.80

1 No

4356

Cost of 180mm MS bore cap excluding VAT 1*1

495.00

1 No

495

Cost of 50 mm MS clamp set excluding VAT 1*1

940.50

1 Set

941

Cost of 7/16 Service wire excluding VAT

1*1

90

19.00

1 Rmt

1710

Cost of 50 mm Non return valve excluding


VAT

1*1

545.00

1 No

545

10

Cost of water guard cable excluding VAT

1*1

150

5.00

11

20 mm of flexible pipe excluding VAT

1*1

12

Cost of 50 mm GI Bends excluding VAT

1*1

13

90

150

per

Amount

27720

1 Rmt

1 Rmt

38069

750

14.00

1 Rmt

1.00

142.85

1 No

143

Cost of 50mm MS Flange set excluding VAT 1*1

207.90

14

Being the labour charges for the erection of


submersible pump set with all accessories
1*1
and running the pump set in good condition
etc. complete upto 150 m depth

2678.00 1 Job

16

Unforseen items of work

1 No

208

2678

66
TOTAL

138151

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

Sub Estimate (Single Phase Pump set)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Name of Wrok : Providing Single phse submersible pump set (Excluding VAT)
S.No
1

Description of work

No

Measurements
L
B
D

Contents

Supply and dilivery of ___ HP/____ Stage


Single submersible pump set as per ISI
standards incuding cost and conveyance of 1*1
all materials and labour charges etc.

1 No

Cost of Control panel board of approved


one with all accessories including suitable
for__HP

1.00

1*1

Rate

per

LS

4992.00

Amount

21000

1 No

4992

75/105
3

Cost of OD 32 / 40 mm * 10 Kg / Sq.cm
HDPE pipe (PE - 80 grade) confirming to IS
1*1
4984-1995 standards including all taxes.

120

120

105.00

Cost of 2.5 Sq.mm finolex cable wire

1*1

130

130

83.60

1 Rmt

10868

Cost of 32mm GI Heavy couplings

1*2

67.60

1 No

135

Cost of 180mm MS bore cap

1*1

495.00

1 No

495

Cost of 32 mm MS clamp set

1*1

494.00

1 Set

494

Cost of 7/16 Service wire

1*1

90

15.50

1 Rmt

1395

Cost of 32 mm Non return valve

1*1

436.80

1 No

437

10

Cost of water guard cable

1*1

11

Cost of flexible pipe

1*1

12

Cost of 32 mm GI Bends

1*1

1.00

66.56

13

Cost of 32mm MS Flange set

1*1

104.00

1 No

104

14

Cost of 40 * 32 mm GI Reducer coupling

1*1

78.00

1 No

78

15

Cost of 32 mm GI Union

98.80

16

Cost of 32 mm GI elbow

54.08

17

Cost of 32 mm GM Gate valve

18

Cost of SS collar of size 32 / 40 mm

1*2

1 No

593

19

Cost of 8mm Plastic rope

1*1

20

Being the labour charges for the erection of


submersible pump set with all accessories
and running the pump set in good condition 1*1
etc. complete

22

90
130

120

130

296.40

120

12.48

Provision for Power supply charges


Unforseen items of work

12600

1 Rmt

1 Rmt

1 Rmt

1 No

67

1 Rmt

1498

2500.00 1 Job

2500

173
57429

TOTAL

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

Sub Estimate (Pump set)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Name of Wrok : Providing 3 phse submersible pump set
S.No

2
3

Description of work

No

Measurements
L
B
D

Supply and dilivery of 5 HP/14 Stage


submersible pump set Shakthi make as per
ISI standards incuding cost and
conveyance of all materials and labour
charges etc.
1*1
Cost of Control panel board of approved
one with all accessories suitable for
HP
Cost of 50 mm GI pipes B Class (TATA,
Zenith, Surya Prakash make)

Contents

1 No

1*1

Rate

per

LS

Amount

35000

1.00

7500.00

1 No
1 Rmt

7500

1*1

120

120

375.00

45000

135

135

65.00

1 Rmt

8775

1 No

2080

Cost of 2.5 / 4 Sq.mm finolex cable wire

1*1

Cost of 50mm GI Heavy couplings

1*20

20

104.00

Cost of 180mm MS bore cap

1*1

200.00

1 No

200

Cost of 50 mm MS clamp set

1*1

300.00

1 Set

300

Cost of 7/16 Service wire

1*1

90

15.50

1 Rmt

1395

Cost of 50 mm Non return valve

1*1

514.80

1 No

515

10

Cost of water guard cable

1*1

150

5.00

11

Cost of flexible pipe

1*1

12

Cost of 50 mm GI Bends

1*1

13

Cost of 50mm MS Flange set

14

90

150

1 Rmt

750

13.50

1 Rmt

1.00

150.00

1 No

150

1*1

240.00

Being the labour charges for the erection of


submersible pump set with all accessories
and running the pump set in good condition
etc. complete
1*1

3000.00 1 Job

15

Provision for Power supply charges

16

Unforseen items of work

1 No

240

3000

95
TOTAL

105000

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

Sub Estimate (OHSR)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
S.no
Description of work
Contents
Rate
Per
.
1
2
3
4
5
1 Construction of circular OHSR with VRCC M - 30 Design mix using 20
mm size machine crushed metal for elevated service reservoir of
approved type design with single compartment inside

Amount
6

dia of 4 .00 & 1.9 0 m height side walls


below the top of slab and capable of holding 20000 Lt with
staging of 9.6 m
and with Raft Foundation including CM(1:3) 12 mm thick with 2%
acco proof powder and out side with CM(1:3) 8 mm thick, for a
finished work inculuding 2 coats fo snow cem painting for external
surfaces and Three coats of epoxy paint to inner surfaces of the
reservoir including roof cover slab, including lettering and fixing of
all required fixtures pipes, bends, valves etc. for vertical connections,
but excluding the cost fo pipes, bends and valves etc. complete as per
Dept. designs and drawings, with the following fixtures.

20000

45.76

1 Lt

915200

a) RCC or Aluminium Ladder of width 0.60m inside


b) Spiral stair case out side the reservoir up to 200 KL
c) Lightening arrestor including conductor and earthing
d) Water level indicator of approved pattern with ebonite / copper float
e) RCC Ventilator with copper or stainless steel fly proof mesh
f) DI Manhole cover and cover 0.60 x 0.60 m - 2 Nos
g) Railing to be provided for the gallery and stair case shall be
stainless steel grade 304 for a height of 1.20 m
h) Railing with 32 mm dia GI pipes (A class) in two rows around OHSR
fixed in RCC (1:2:4) posts or MS angles of size 100*75*75 mm with
1.50 m intervals aroung periphery on top of the OHSR
2

Provision for Vertical Connections (As per Sub Estiamte)

Unforeseen items of work

122935

TOTAL

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

1678
1039813

Asst. Engineer,
RWS & S,
Thottembedu

36.4325

1091803.65

SUB ESTIMATE FOR OHSR SPECIALS


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Man
OHSR
S.No Description of the Materials
1(a) 80mm dia CI D/F Pipe 2mts Long

20000 Lt
Weight in
No
Kgs/No

Staging
9.60 m
Total Weight
(Kg)
Rate
per

20

47.00

940.00

80mm dia CI D/F Pipe 0.90 mts Long

11

25.22

277.42

80mm diaCI D/F Pipe 0.60 mts Long

19.28

77.12

80mm dia CI D/F Duck Foot Bend

21.00

105.00

80mm dia CI S/F Semicircular bend

25.00

25.00

80 mm CI Flanged Tee

21.00

21.00

Total

1445.54

Total weight of CI specials including CED


@ 8%, Cess @ 3% but excluding VAT @
5%

Manufacture, Supply and delivery of CI


Wafer Lug type Butterfly Valves conforming
to IS 13095/1991 - 80 mm CI Butter fly
valve

79.77

1 Kg

3812.00

115311

7624

TOTAL

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Amount

Asst. Engineer,
RWS & S,
Thottembedu

122935

SUB ESTIMATE FOR OHSR SPECIALS


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Man
OHSR
S.No Description of the Materials
1(a) 80mm dia CI D/F Pipe 0.60mts Long
b

80mm dia CI D/F Duck Foot Bend

20000 Lt
Weight in
No
Kgs/No

Staging
9.60 m
Total Weight
(Kg)
Rate
per

19.28

77.12

21.00

84.00

Total

161.12

Total weight of CI specials including CED


@ 8%, Cess @ 3% but excluding VAT @
5%

Amount

79.77

1 Kg

12853

S & F 65 mm Nominal Bore GI pipe


Medium Grade properties & weight as
perIS 1239 with GI Fittings sucha as
Couplings, Elbows etc including labour
charges for fittings etc. inlcuding all taxes
but excluding VAT

42 Rmt

892.00

1 Rmt

27762

Cost of 100 mm dia x 15 mm thick Flange


set including Bolts and Nuts, Leather
packing etc complete including all taxes
but excluding VAT

9 Sets

926.00

1 Set

8334

80 mm CI Butterfly valves wafer type


PN - 1.0conforming to IS : excluding VAT
@ 5%

6018.00

12036

TOTAL

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

60985

SUB ESTIMATE ( Spiral stair case)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Man
S.no.
1

Description of work
2
Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for foundation of P.H
For foundation

No
3

1*1

L
4

Mesurements
B
D
5
6

1.50

1.50

1.80
Total

Supply and filling of sand for foundation


basement including labour charges,
watering and tamping etc. complete
For foundation

1*1

1.50

1.50

0.15
Total

CC(1:6:10) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete - For foundation

1*1

1.50

1.50

0.15
Total

VRCC M-30 mix using 20 mm HBG metal


with required quantity of steel per cu.m of
CC including c/c of all materials and labour
charges etc complete. But excluding the cost
of steel and its fabrication charges etc
complete - For Footing
for Trapezoidal portion
(0.25/3)x[1.50^2+0.60^2+{(1.50+0.60)/2}^2]

1*1

1.50

1.50

0.20

Total

Contents

Rate

Per

4.05
4.05 m3

116.48

1 m3

843.40

1 m3

3264.05

1 m3

6488.21

1 m3

0.34
0.34 m3

0.34
0.34 m3

0.45
0.31
0.76 m3

VRCC M-30 mix using 20 mm HBG metal


with required quantity of steel per cu.m of
CC including c/c of all materials and labour
charges etc complete. But excluding the cost
of steel and its fabrication charges etc
complete - For Stair case Column
Below GL

1x1

0.30

0.30

1.05

0.09 m3 22861.00

1 m3

0-5m

1x

0.30

0.30

5.00

0.35 m3 22861.00

1 m3

5-8m

1x

0.30

0.30

3.00

0.21 m3 22995.00

1 m3

8 - 11 m

1x

0.30

0.30

3.00

0.21 m3 23129.00

1 m3

11 - 14 m

1x

0.30

0.30

1.90

0.13 m3 23263.00

1 m3

0-5m

1*2

1.75

0.30

0.20

0.21 m3 23724.50

1 m3

5-8m

1*1

1.75

0.30

0.20

0.11 m3 23858.50

1 m3

VRCC M-30 mix using 20 mm HBG metal


with required quantity of steel per cu.m of
CC including c/c of all materials and labour
charges etc complete. But excluding the cost
of steel and its fabrication charges etc
complete - For Connecting beam / Tie Brace

8 - 11 m

1*1

1.75

0.30

0.20

0.11 m3 23992.50

11 - 14 m

1 m3

m3

VRCC M-30 mix using 12 mm HBG metal


with required quantity of steel per cu.m of
CC including c/c of all materials and labour
charges etc complete. But excluding the cost
of steel and its fabrication charges etc
complete - For Precast steps of size
Rise of 0.20 m tread of 0.75 m length and
of width 0.10 m at one end and 0.3 m at other
end, thickness of 0.05m and length of each
step is 0.75 m
For each Tread
For each rise

0.75
0.75

0-5m

25

0.02

0.01
0.01
0.02
0.50 m3 26365.93

5-8m

15

0.02

0.30 m3 26499.93

1 m3

8 - 11 m

15

0.02

0.30 m3 26633.93

1 m3

11 - 14 m

10

0.02

0.20 m3 26767.93

1 m3

Plastering with CM(1:5) 12mm thick including


c/c of all materials and labour charges etc
For Stair case column

1x

0.30

For Stair case treads

2*60

0.80

For Stair case rises

2*60

0.80

For connecting beam

1.75

0.20
0.05

0.05
0.15
total

12.90
0.20

1 m3

12.15
19.20

0.15
1.00

14.40
7.00
52.75 m2

971.25

10 m2

Painting with snow cem in two coats


including all c/c of all materials and labour
charges etc.

52.75 m2

882.50

10 m2

Cost of steel including fabrication charges

750.00 Kg

Total

52970.00 1000 Kg

Hand railing on top slab and sides of bottom


slab

LS

Unforeseen items of work


Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

ESTIMATE ( Spiral stair case)


nk to Bore at HW of Thangellapalem Village and GP in Thottembedu Manda
Amount
10

472

287

1110

4931

2057
8001
4829
4857
3024

4982
2624

2639

13183
7950
7990
5354

5123

4655
39728

10000
417
134213

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE ( 1000 Lt HDPE Tank)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mand
Mesurements
S.no.
Description of work
No
Contents
Rate
Per
Amount
L
B
D
1
2
3
4
5
6
7
8
9
10
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for foundation of Bed
1*1
2.00
2.00
0.60
2.40
For Plat form
1*1
2.00
0.60
0.20
0.24
Total
2.64 m3
116.48
1 m3
308
3

CC(1:6:10) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete For Levelling course
For Plat form Up to GL
For Plat form above GL

RR masonary in CM(1:6) mix including


c/c of all materials and labour charges etc.
complete for foundation and basement
Above GL
CC (1:2:4) using 20 mm HBG MC metal
including cost and conveyance of all materials
and labour charges etc. complete
Over RR Bed

Plastering with CM(1:5) 20 mm thick including


c/c of all materials and labour charges etc.
complete. All round RR Bed
Top of RR Bed
For Plat form
Alround Plat form rise

1*1
1*1
1*1

1*1
1*1

1*1

1*1
1*1
1*1
1*1

Supply and delivery of 1000 Lt Poly etheylene


water storage tank at all floor level with double
layer approved brand and manufacture with
cover and suitable locking arrangements and
making necessary holes for inlet, outlet and over 1*1
flow pipes but with out fittings and base support
for tanks including all labour cahrges etc.
complete

2.00
1.90
1.90

1.90
1.90

1.90

7.60
1.90
1.90
3.10

2.00
0.60
0.60

1.90
1.90

1.90

0.15
0.20
0.10
Total

0.60
0.23
0.11
0.94 m3

3264.05

1 m3

3075

0.45
0.45
Total

1.62
1.62
3.25 m3

2880.20

1 m3

9358

0.10
Total

0.36
0.36 m3

5557.75

1 m3

2006

0.60

4.56
3.61
1.14
0.31
9.62 m2

1483.70

10 m2

1427

1.90
0.60
0.10
Total

1000

Lt

8.00

Lt

8000

1
8

2
Colour washing with yellow oxide mixed with
janatha cem at 0.50/10 Sq.cm in two coats
including c/c of all materials and labour
charges etc. complete
All round RR Bed
Top of RR Bed
For Plat form
Alround Plat form rise

17 Provision for GI Specials

1*1
1*1
1*1
1*1

7.60
1.90
1.90
3.10

1.90
0.60

0.60

0.10
Total

10

4.56
3.61
1.14
0.31
9.62 m2

10 m2

1 No

1 No

18 Unforeseen items of work

495
TOTAL

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

24669

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE ( Pump Room)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Man
Construction of pump room of size 1.80 * 2.40 m
Mesurements
S.no.
Description of work
No
Contents
Rate
Per
Amount
L
B
D
1
2
3
4
5
6
7
8
9
10
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for foundation of P.H
All round Pump house
1*1
9.32
0.60
0.90
5.03
For steps
1*1
0.90
0.60
0.15
0.08
Total
5.11 m3
116.48
1 m3
595
2 Supply and filling of sand for foundation
basement including labour charges,
watering and tamping etc. complete
For foundation
1*1
9.32
0.60
0.23
1.29
For basement
1*1
2.20
1.60
0.25
0.88
Total
2.17 m3
843.40
1 m3
1830
3

CC(1:6:10) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete All round
for steps

1*1
1*1

9.32
0.90

0.60
0.60

0.23
0.15
Total

1.29
0.08
1.37 m3

3264.05

1 m3

4472

RR masonary in CM(1:8) mix including


c/c of all materials and labour charges etc.
complete for foundation and basement

1*1

9.32

0.45

0.90

3.77 m3

2766.15

1 m3

10428

Country brick masonary in CM(1:6) including


c/c of all materials and labour charges etc.
complete. All round
Deduct for Door
Deduct for Ventilators
Deduct for lintel

1*1
1*1
1*1
1*1

9.32
0.75
0.75
1.2

0.23
0.23
0.23
0.23

2.40
1.80
0.60
0.10
Total

5.14
0.31
0.10
0.03
4.70 m3

4706.80

1 m3

22122

R.C.C. (1:2:4) mix using 20 mm HBG metal


with required quantity of steel per cu.m. of
concrete including c/c of all materials and
labour charges etc. complete, but excluding
the cost of steel and its fabrication charges
etc. complete For Lintel over door

1*1

1.20

0.23

0.10

0.03 m3

7279.75

1 m3

218

R.C.C. (1:2:4) mix using 20 mm HBG metal


with required quantity of steel per cu.m. of
concrete including c/c of all materials and
labour charges etc. complete, but excluding
the cost of steel and its fabrication charges
etc. complete For Roof slab

1*1

3.46

2.86

0.10

0.99 m3

7279.75

1 m3

7207

Weather proof plastering with CM (1:3) mix


20 mm thick with 3% by weight of cement
accoproof powder smooth finishing to lime and
required slope including c/c of all materials
and labour charges etc. complete.
1*1

3.46

2.86

9.90 m2

#VALUE!

10 m2

#VALUE!

24.58
1.35
0.45
22.78 m2

971.25

10 m2

2213

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.
complete. All round (Out side)
Deduct For Door
Deduct For Ventilator

1*1
1*1
1*1

10.24
0.75
0.75

2.40
1.80
0.60
Total

10 Plastering with CM(1:5) 20 mm thick including


c/c of all materials and labour charges etc.
complete. All round (In side)
For steps
For treads
For sides
Deduct For Door
Deduct For Ventilator

11 Pointing with CM(1:3) for full depth of joint in


R.R masonary including receiving of joints
including c/c of all materials and labour
charges etc. complete for Base ment
All round

1*1
3
2
2
1*1
1*1

8.40
0.90
0.90
0.30
0.75
0.75

1*1

11.12

1*1

2.18

2.40
0.15
0.30
1.80
0.60
Total

20.16
0.41
0.54
0.18
1.35
0.45
19.49 m2

1483.70

10 m2

2892

0.45

5.00 m2

562.40

10 m2

281

3.44 m2

2458.00

10 m2

846

2 No

75

1 No

150

1.80
2.40
0.10
1.80
Total

20.16
3.43
1.14
4.32
1.35
24.58
1.26
1.35
52.19 m2

882.50

10 m2

4606

1.80

3.04 m2

1159.00

10 m2

352

0.30

12 Gronolithie Concrete Flooring 20 mm thick with

(1:1:2), using 6mm to 12 mm size hard granite


machine crushed metal laid over CC bed already laid
or RCC roof slab, in alternate panels of size not
exceeding 1.50 m x 1.50 m and finishing the top
surface to required smoothness and slopes and
thread lining including cost of all materials like
cement, metal, sand and water etc., complete,
including seigniorage charges, etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials

charges etc. complete


13 Supply and fixing of RCC ventilators of size
0.75*0.60 m as per approved made and
design including all costs
14 Painting with snow cem in two coats
including all c/c of all materials and labour
charges etc.
Inside all round
Out side ceiling
For ventilator soffits
Ceiling
Deduct : Doors
Out side alround
Slab edge alround
Deduct : Doors

16 Painting with best synthetic enamel paint in


two coats over one coat of wood primary
including all costs and labour
17 Provision towards cost of door of size 0.75*1.8
18 Cost of steel including fabrication

1.58

1*2

1*1

8.40

1*1
1*1
1*1
1*1
1*1

2.40
0.75
10.24
12.64
0.75

2.25

0.75

2.40

1.80

1.00 No

70

70.00 Kg

2500 LS

2500

52970.00 1000 Kg

19 Unforeseen items of work

3708
417

Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

#VALUE!

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE (PEDESTAL PUMP ROOM 1.20 X 0.90 x 0.90 M)

Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village an

Est. Cost :Area


or
Contents

1x1

2.00

1.70

0.60

2.04
Cu.m.

116.48

1M3

1x1

2.00

1.70

0.15

0.51
Cu.m.

843.40

1M3

1x1

2.00

1.70

0.15

0.51
Cu.m.

3264.05

1M3

1x1

1.80

1.50

1.05

2.84
Cu.m.

2766.15

1M3

1x1
1x1

5.12
1.20

0.23
0.23

1.05
0.90

1.24
-0.25
0.99

4706.80

1M3

7279.75

1M3

Measurements
S.N

Description of Item

No

Lakhs
Rate

Per

1 Earth work exacavation and


depositing on bank with intial
lead and lift in HSC soils for
foundations
For Foundation
2 Sand
filling in foundations
including cost and conveyances
and labour charges etc. complete
For Foundation
3 Cement concrete (1:6:10) hand
mixing using 40 mm metal
including cost and conveyances
and labour charges etc.
complete
For Foundation
4 RR Masonary in CM(1:8)using
RR Stone including cost and
conveyances and labour charges
etc. complete
For Basement
5 Brick Masonary in CM(1:6)using
Country bricks including cost and
conveyances and labour charges
etc. complete
All Round
Deduct Door

Total
6 RCC (1:2:4) nominal mix using
20 mm HBG metal including cost
and conveyances of all materials
and labour charges etc. complete
for slab 75mm thick
1x1

1.80

1.40 0.075

0.19
Cu.m

All Round RR Masonary

1x1

6.60

0.75

4.95

All Round outside Brick work


All Round inside Brick work

1x1
1x1

6.04
4.20

1.05
1.05

6.34
4.41

7 Plastering with C.M. (1:5) 20 mm


thick
including cost and
conveyances of all materials and
labour charges etc. complete

Flooring
Slab top
Slab sides
Deduct Door

1x1
1x1
1x1
1x2

1.20
1.80
6.40
1.20

0.90
1.40
0.10
0.90
Total

Painting with Snow cem in two


coats including cost and
conveyances of all materials and
8 labour charges etc. complete
All Round RR Masonary
All Round outside
All Round inside
Slab top
Slab sides
Deduct Door

1x1
1x1
1x1
1x1
1x1
1x2

6.60
6.04
4.20
1.80
6.40
1.20

0.75
1.05
1.05
1.40
0.1
0.90
Total

Supply and fixing of MS Door of


Size 1.20 X 0.90 mts.with MS
Angle frames allround and MS
sheet including synthetic enamel
9 paint two coats over primary coat 1x1
of Red-oxide and cost and
conveyances of all materials and
labour charges etc. complete
including Locking arrangements.

10

Cost of steel including fabrication


1x1
charges

13 Provision for Unforeseen items

15.00
-

1.08
2.52
0.64
-2.16
17.78

1483.70

10 M2

4.95
6.34
4.41
2.52
0.64
-2.16
16.70

882.50

10 M2

1.00

LS

15.00
-

52970.00 1 Mt
-

Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

0.90 M)

hangellapalem Village and GP in Thottembedu Mandal


Lakhs
Amount
9

238

430

1665

7856

4660

1383

2638

1474

1500

795
1151
23790

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE ( Panel board room)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mand
Mesurements
S.no.
Description of work
No
Contents
Rate
Per
Amount
L
B
D
1
2
3
4
5
6
7
8
9
10
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for foundation of P.H
All round Pump house
1*1
4.92
0.60
0.60
1.77
Total
1.77 m3
1164.80
1 m3
2063
3

CC(1:6:10) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete All round

RR masonary in CM(1:8) mix including


c/c of all materials and labour charges etc.
complete for foundation and basement
Above GL
Country brick masonary in CM(1:6) including
c/c of all materials and labour charges etc.
complete. All round
Deduct for Door

1*1

1*1
1*1

1*1
1*1

4.92

4.92
4.92

4.92
0.75

0.60

0.60
0.45

0.23
0.23

R.C.C. (1:2:4) mix using 20 mm HBG metal


with required quantity of steel per cu.m. of
concrete including c/c of all materials and
labour charges etc. complete, but excluding
the cost of steel and its fabrication charges
etc. complete For roof over pump room

1*1

1.76

1.76

Weather proof plastering with CM (1:3) mix


12 mm thick with 3% by weight of cement
accoproof powder smooth finishing to lime and
required slope including c/c of all materials
and labour charges etc. complete.

1*1

1.76

1.76

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.
complete. All round (Out side)
Deduct For Door

1*1
1*1

5.84
0.75

10 Plastering with CM(1:5) 20 mm thick including


c/c of all materials and labour charges etc.
complete. All round (In side)
Deduct For Door

11 Pointing with CM(1:3) for full depth of joint in


R.R masonary including receiving of joints
including c/c of all materials and labour
charges etc. complete for Base ment
All round above GL

1*1
1*1

1*1

4.00
0.75

6.72

0.15
Total

0.44
0.44 m3

3264.05

1 m3

1445

0.60
0.45
Total

1.77
1.00
2.77 m3

2766.15

1 m3

7655

1.00
0.75
Total

1.13
0.13
1.00 m3

4706.80

1 m3

4717

0.075

0.23 m3

7425.55

1 m3

1725

3.10 m2

#VALUE!

10 m2

#VALUE!

1.00
0.75
Total

5.84
0.56
5.28 m2

971.25

10 m2

513

1.00
0.75
Total

4.00
0.56
3.44 m2

1483.70

10 m2

510

0.45

3.02 m2

562.40

10 m2

170

1
2
12 Flooring with 80 mm thick CC(1:6:10) mix
using 40 mm HBG metal over laid with 40 mm
thick CC(1:2:4) using 20 mm thick and top
plastering with CM(1:3) mix 7 mm thick
including c/c of all materials and labour
charges etc. complete
14 White washing with janatha cem in two coats
including all c/c of all materials and labour
charges etc.
Inside all round
Inside side ceiling
Deduct : Doors

1*1

1.00

1.00

1*1
1*1
1*1

4.00
1.00
0.75

1.00

10

1.00 m2

2458.00

10 m2

246

0.75
Total

4.00
1.00
0.56
4.44 m2

882.50

10 m2

392

1.00
0.075
0.75
Total

5.84
0.53
0.56
5.81 m2

882.50

10 m2

512

0.75

1.27 m2

1159.00

10 m2

147

1 No

800

1 No

800

18 Cost of steel

25

25 Kg

43000 1000 Kg

1075

19 Fabrication charges for steel

25

25 Kg

15 Colour washing with yellow oxide mixed with


janatha cem at 0.50/10 Sq.cm in two coats
including c/c of all materials and labour
charges etc. complete
Out side alround
Slab edge alround
Deduct : Doors

16 Painting with best synthetic enamel paint in


two coats over one coat of wood primary
including all costs and labour
17 Provision towards cost of door of size 0.75*0.75

1*1
1*1
1*1

5.84
7.04
0.75

2.25

0.75

1.00

52970.00

1 Kg

20 Unforeseen items of work

1324250
167

TOTAL

Deputy Exe. Engineer,


RWS & S Sub Division,
Pakala

#VALUE!

Asst. Exe. Engineer,


RWS & S, PAKALA

SUB ESTIMATE ( Pump Room)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mand
Construction of pump room of size 1.80 * 2.40 m
Mesurements
S.no.
Description of work
No
Contents
Rate
Per
Amount
L
B
D
1
2
3
4
5
6
7
8
9
10
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for foundation of Toilet block
All round Toilet block
1*1
12.88
0.70
0.60
5.41
For Curtain wall
1*1
2.40
0.45
0.30
0.32
For Divide wall (Out side)
1*1
1.20
0.45
0.30
0.16
2*
For Soak pit
1.50
1.50
1.50
5.30
2*
For Leach pit
1.50
1.50
1.50
5.30
Total
16.49 m3
116.48
1 m3
1921
2 Supply and filling of sand for foundation
basement including labour charges,
watering and tamping etc. complete
For foundation All round toilet block
1*1
12.88
0.75
0.15
1.45
For Flooring
1*1
2.84
3.32
0.15
1.41
2*
For Soak pit
1.50
1.50
0.30
1.06
Total
3.92 m3
843.40
1 m3
3306
3

CC(1:6:10) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete All round Toilet block
For Flooring
Cross wall between Toilet and Urinals
Cross wall at middle
For Curtain wall
For Divide wall

Sand cement stone block masonary with CM(1:6)


using Sand cement blocks inclduing
c/c of all materials and labour charges etc.
complete. All round Toilet block For Foundation
Basement
All round toilet block
Cross wall between Men and Women block
Cross wall between Urinal and Toilet
Screen walls
For Curtain wall
For Divide wall
For Plat form at Urinals block
For Tub in WC
Deduct for Door (Main)
Deduct for Door (Toilet)
Deduct for Ventilators
Deduct for lintel

1*1
1*1
1*2
1*1
1*1
1*1

1*1
1*1
1*1
1*1
1*2
2*3
1*1
1*1
1*2
1*2
1*2
1*2
2*5
1*1

12.88
2.84
1.35
3.32
2.40
1.20

12.88
12.88
12.88
3.32
1.35
0.60
2.40
1.20
1.80
0.90
0.75
0.60
0.30
1.2

R.C.C. (1:2:4) mix using 20 mm HBG metal


with required quantity of steel per cu.m. of
concrete including c/c of all materials and
labour charges etc. complete, but excluding
the cost of steel and its fabrication charges
etc. complete For Roof slab

1*1

3.72

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.
complete. All round (Out side)

1*1

15.44

0.75
3.32
0.20
0.20
0.45
0.45

0.40
0.30
0.14
0.14
0.14
0.14
0.14
0.14
0.50
0.14
0.14
0.14
0.14
0.23

4.20

0.25
0.10
0.10
0.10
0.15
0.15
Total

2.42
0.94
0.05
0.07
0.16
0.08
3.72 m3

3264.05

1 m3

12142

0.30
0.30
3.00
3.00
3.00
0.75
1.80
1.80
0.14
0.75
2.00
2.00
0.30
0.10
Total

1.55
1.16
5.41
1.39
1.13
0.38
0.60
0.30
0.25
0.19
-0.42
-0.34
-0.13
-0.03
11.46 m3

4706.80

1 m3

53940

0.10

1.56 m3

7279.75

1 m3

11356

3.30

50.95

All round inside - Toilet block


All round Urinals
Curtain wall
Divide wall
For Urinal screen walls
For Tubs
For Roof (Toilet)
For Urinals
All round slab projection
Deduct For Door (Main)
Deduct For Door (Toilet)
Deduct for Ventilator

Accoproof Plastering with CM(1:3) 20 mm thick


with 2% accoproof powder inclduing cost and
conveyance of all materials and labour charges
etc. complete

1*2
1*2
1*2
1*2
2*2
2*2
1*2
1*2
1*1
1*2
1*2
1*10

1*1

4.90
6.86
2.54
1.20
1.34
0.90
1.35
1.35
12.64
0.75
0.60
0.30

3.72

3.00
3.00
1.80
1.80
0.75
0.75
1.10
2.08
0.30
2.00
2.00
0.30
Total

4.20

29.40
41.16
9.14
4.32
4.02
2.70
2.97
5.62
7.58
-3.00
-2.40
-0.90
151.57 m2

971.25

10 m2

14721

15.62 m2 #VALUE!

10 m2

#VALUE!

12794

Supply and fixing of 7.30 mm thick ceramic tiles


over a screed of 20mm thick in CM(1:5) and
painting with white cement including
cost and conveyance of all materials and
labour charges etc. Complete
Toilet block flooring
For Urinal block
Toilet block alround for wlls
For Urinal block walls

1*2
1*2
1*2
1*2

1.35
1.35
4.90
2.08

1.10
2.08
0.60
0.75
Total

2.97
5.62
5.88
3.12
17.59

m2

7273.30

10 m2

1*2

2 No

1048.00

1 No

Supply and fixing of Squatting pans

1*3

3 No

450.00

1 LS

Supply and fixing of White glazed flat back bowl


urinals of size 460 x 265 x 315 mm with internal
flushing confirming to IS standards

1*3

3 No

930.00

1 No

Supply and fixing of Bison panel door fo size 060


x 2.00 m with all iron fixtures such as Z Hold fast,
Hinges, Tower bolt and locking arrangement
1*2

3 No

1200.00

1 LS

3600

Supply and fixing of MS Grill gate of size 0.75 x


2.00 m with MS Sheet of 18 gauge including all
iron fixtures etc.

1*2

2 No

1500.00

1 LS

3000

1*10

10 No

75

1 No

750

1*10

10 No

450

1 No

4500

2 No

250

1 No

500

12 Supply and fixing of Indian pattern white glazed


WC with P & S Trap of 580 mm long

13 Supply and fixing of RCC ventilators of size


0.30 x 0.30 m as per approved made and
design including all costs
Supply and fixing of RCC Precast rings of dia
1.20 m and height 0.30 m

1350

2790

Supply and fixing of RCC Precast cover slabs for


leach pit
1*2
14 Painting with snow cem in two coats
including all c/c of all materials and labour
charges etc.

2096

Inside all round


Out side ceiling
For ventilator soffits
Ceiling
Deduct : Doors
Out side alround
Slab edge alround
Deduct : Doors

18 Cost of steel including fabrication

1*1

8.40

1*1
1*1
1*1
1*1
1*1

2.40
0.75
10.24
12.64
0.75

70

2.40

1.80
1.80
2.40
0.10
1.80
Total

20.16
3.43
1.14
4.32
1.35
24.58
1.26
1.35
52.19 m2

100.00 Kg

882.50

10 m2

4606

52970.00 1000 Kg

5297

19 VAT @ 5%

#VALUE!

19 Unforeseen items of work

247
Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

#VALUE!

Asst. Engineer,
RWS & S,
Thottembedu

Sub Estimate (School water supply)

Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembed

S.no.

Description of work

No

S& F 40 mm Nominal Bore GI pipe Medium


Grade properties & weight as per IS 1239 ISI
1*1
mark with GI fittings including the cost of pipe &
its fittings & labour charges complete

Supply and delivery of 500 Lt Poly etheylene


water storage tank at all floor level with double
layer approved brand and manufacture with
cover and suitable locking arrangements and
making necessary holes for inlet, outlet and
over flow pipes but with out fittings and base
support for tanks including all labour cahrges
etc. complete

L
4

Mesurements
B
D
5
6

20.00

1.10

Plastrering with CM(1:5) with 20mm thick


including cost and conveyance of all materials
and labour charges etc. - Alround brick wall

1*

1.10

Top edge

1*

1.00

1.10

Rate

20.00

466.00

500

Lt

8.00

0.15

0.14

m3

4489.75

0.75

2.59

1*500

CC(1:2:4) using 20mm HBG metal including


cost and conveyance of all materials and labour
1*4
charges etc. for base of the Storage tank

Contents

0.10
Total

0.31
2.90

m2

1483.70

Earth work excavation in OG soils with initial


lead and lift for plat form

1*1

3.00

1.50

0.20

0.90

m3

1164.80

CC (1:6:10) using 40mm HBG metal including


cost and conveyance of all materials and labour
1*1
charges etc. For platform

3.00

1.50

0.20

0.90

m3

3264.05

1.00
3.00
3.00
5.60
2.40
0.23

0.10
0.75
1.20
0.30
0.30
0.20
0.10
0.10
0.10
0.30
0.45
0.60
Total

0.24
1.08
0.18
0.06
0.07
0.19
1.82

m3

4706.80

Brick masonay in CM(1:6) including cost and


conveyance of all materials and labour charges
etc. complete
For alround Storage tank
For platform
For step to plat form
For platform Kerb
For Trough
Supports for Trough

1*
1*1
1*1
1*1
1*1
1*3

Supply and fixing of 7.30 mm thick ceramic tiles


over a screed of 20mm thick in CM(1:5) and
painting with white cement including
cost and conveyance of all materials and
labour charges etc. Complete
For Platform
Out side the plat form up to the level of step
Out side the plat form up - Alround including
kerb
Platform kerb - Inside
For wall
Trough Inside
Trough Out side
Trough Top edge
Supports for trough

1*1
1*1

3.00
6.00

1*1
1*1
1*1
1*1
1*1
1*1
1*3

RCC (1:2:4) using 20 mm HBG metal including


cost and conveyance of all materials and labour
1*1
charges etc. For bottom of the trought

10 Provision for cost of steel including fabrication


charges
11 Provision for PVC and GI specials, Valves etc

12 Provision for levelling the site


13 Unforeseen items of work

1*1

0.20

3.60
1.20

5.40

0.20

1.08

4.80
2.50
3.00
3.40
3.20
1.13

0.30
0.45
0.30
0.30

1.44
1.13
0.90
1.02
0.32
2.54
13.23

m2

7273.30

0.08

m3

5557.75

10.00

Kg

52970.00

2.50

10.00

1.20

0.10
0.75
Total

0.45

0.075

ge and GP in Thottembedu Mand

Per

Amount

10

1 m

9320

1 Lt

4000

1 m3

629

10 m2

430

1 m3

1048

1 m3

2938

1 m3

8566

10 m2

9623

1 m3

445

1000 Kg

530

1500

39029

SUB ESTIMATE ( Pumping main)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and
GP in Thottembedu Mandal
S.No
Description of work
No
Measurements Contents
Rate
per
L
B
D
1
Being the supply and delivery of
75mm * 6 Kg/cm2 ISI approved make
PVCpipes including all taxes etc.
1*1
120
120
179.78 1 m
m
2
Earth work excavation in OG soils of
trench size 0.50*0.75 m for laying
and jointing of 75mm * 6 Kg/cm2 PVC
pipes and refilling the trench with
excavated soil and testing the pipe
line to required pressure etc.com
1*1
120
120
151.45 1 m
m
3
Provision for PVC & GI specials
4

Unforeseen items of work


Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Amount

21574

18174
150
706
40604

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE ( Gravity main)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and
GP
in Thottembedu
Mandal of work
S.No
Description
No
Measurements Contents
Rate
per
L
B
D
1
Being the supply and delivery of
75mm * 4 Kg/cm2 ISI approved PVC
including all taxes etc. complete
1*1
60
60
92.14 1 m
2

Earth work excavation in OG soils of


trench size 0.50*0.75 m for laying
and jointing of 75mm * 4 Kg/cm2 PVC
pipes and refilling the trench with
excavated soil and testing the pipe
line to required pressure etc.com

Provision for PVC & GI specials

Unforeseen items of work

1*1

60

60

103.40

1m

Amount

5528

6204
2000

Total

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

13732

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE (Valve Pit)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
Construction of valve pit
Mesurements
S.no.
Description of work
No
Contents
Rate
Per
Amount
L
B
D
1
2
3
4
5
6
7
8
9
10
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for valve pit
1*1
1.46
1.46
0.85
1.81 m3
116.48
1 m3
211
2

CC(1:6:10) using 40mm HBG metal including c/c of all materials and labour charges
etc. for valve pit bottom

1*1

0.1

0.10 m3

3264.05

1 m3

326

Country brick masonary in CM(1:6) including


c/c of all materials and labour charges etc.
complete. For valve pit

1*1

4.92

0.23

0.9

1.02 m3

4706.80

1 m3

4794

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.
complete. All round valve pit - bottom
Inside walls
Top
Out side above GL

1*1
1*1
1*1
1*1

1
4
4.92
5.84

0.15
Total

1.00
3.60
1.13
0.88
6.61 m2

971.25

10 m2

642

0.075

0.16 m3

7279.75

1 m3

1164

0.9
0.23

R.C.C. (1:2:4) mix using 20 mm HBG metal


with required quantity of steel per cu.m. of
concrete including c/c of all materials and
labour charges etc. complete, but excluding
the cost of steel and its fabrication charges
etc. complete For cover slab

1*1

Cost of 80 mm CI sluice valve

1*1

1 No

2100

1 No

2100

Cost of CI surface box

1*1

1 No

150

1 No

150

Cost of GI specials

Cost of steel

10 Fabrication charges for steel

1.46

1.46

250
20

20 Kg

20

20 Kg

43000 1000 Kg
52970.00

860

1 Kg

1059400

TOTAL

1069897

11 Unforeseen items of work

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

SUB ESTIMATE
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
Construction of Tap post
Mesurements
S.no.
Description of work
No
Contents
Rate
Per
L
B
D
1
2
3
4
5
6
7
8
9
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils etc. complete for circular tap post of size
0.75 m dia
1*/4
0.75
0.75
0.20
0.09 m3 116.48
1 m3
2

CC(1:2:4) using 40mm HBG metal including c/c of all materials and labour charges
etc. for tap post below GL
Tap post above GL
Tap post kerb
Plastering with CM(1:5) 12 mm thick including
c/c of all materials and labour charges etc.
complete. Tap post top
All round tap post sides

Being the fixing of tap post with required


specials including c/c of all materials and
labour charges etc. complete

1*/4
1*/4
1*

1*/4
1*

0.75
0.75
0.75

0.75
0.75

0.75
0.75
0.10

0.20
0.30
0.10
Total

0.09
0.13
0.02
0.24 m3

5557.75

0.3
Total

0.44
0.71
1.15 m2

971.25

10 m2

0.75

1*1

1 No

200

m3

No

Unforeseen items of work


TOTAL

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

UB ESTIMATE
Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
Amount
10

10

1334

112

200

1656

Asst. Engineer,
RWS & S,
Thottembedu

OHSR DATA
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
Capacity of Reservoir

20

KL

Staging (St)

9.6

Wind pressure as per estimate (W f

150

Kg/Cm

Cost of steel and cement for the month

January - 2015

Cost of Cement as on Tech Sanction month (Rc)

6800

1 Mt

Cost of Steel as on Tech Sanction month (Rs)

43500

1 Mt

Cost of Cement as per PH SSR

6400

1 Mt

Cost of Steel as per PH SSR

42000

1 Mt

Wind pressure as per PH SSR

350

Kg/Cm2

Type of Foundation (Raft / Individual)

Raft

SSR
S.No

12.80,9.65,6.50
2

Dia (m)

4.00

Side wall height (m)

1.90

2015-2016

Description of work
Rate
per
Amount
Construction of VRCC service reservoir with Raft foundation including out side plastering with CM(1:3),
Epoxy painting inside the reservoir, 2 coats of snowcem painting, lettering, fixing of all required fixtures
excluding the cost of fixtures as per Dept. Designs and drawing etc. including the fixing of the following
fixtures etc.
a) RCC or Aluminium Ladder of width 0.60m inside
b) Spiral stair case out side the reservoir up to 200 KL
c) Lightening arrestor including conductor and earthing
d) Water level indicator of approved pattern with ebonite /
copper float
e) RCC Ventilator with copper or stainless steel fly proof
mesh
f) DI Manhole cover and cover 0.60 x 0.60 m - 2 Nos
g) Railing to be provided for the gallery and stair case shall
be stainless steel grade 304 for a height of 1.20 m

Rate for VRCC OHSR including fixtures with a staging of


10 m. with raft foundation and rate of cement Rs. 4100/per Tonne and Rs. 43000/- per Tonne for Steel.

Add for staging (St - 10) * 0.10*SSR rate

0.00

Deduct for staging ( 10 - St) * 0.05*SSR Rate

-0.89

44.31

Basic Cost
4

1 Lt

44.31

43.42

Variation in cost of cement


(Rc -4100) * 0.00007*Basic rate

1.22

Variation in cost of Steel


(Rs - 43000) * 0.00002*Basic rate

1.30

Deduct for wind pressure at 5% for every


Kg/Cm2
(350 - W f) * 5% * Basic rate/100

100
-4.34

Add 10% for Rural areas

4.16
TOTAL

Dy Exe. Engineer

45.76

Asst. Engineer,

RWS & S Sub Division


Satyavedu - 2

RWS & S,
Thottembedu

DATA SHEET
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
S.No
content
Description of work
Rate
Per
Amount
1
2
3
4
5
6
1
1 cu.m
Earth work excavation for structures as per drawing
116.48
1 cu.m
116.48
and technical specifications clause 305.1 in Ordinary
Soils including setting out ,construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50m and
backfilling in trenches with excavated suitable material
as per technical specification 305 MORD/304 MORTH
Over head charges @14%

0.00

Total
2
1 cu.m

Refillling with excavated soil including breaking


of clods watering, tamping etc. complete
Over head charges @14%

116.50

0.00

1 cu.m

Total
3

1 cu.m

Filling in foundation trenches as per drawing and technical


specification Clause 305.3.9 MORD & 304 MORTH

1 cu.m
1 cu.m

Cost of sand
Cost of refilling charges
Over head charges @14%

0.00

736.50
99.20

1 cu.m
1 cu.m

Total
4

1
1.05
480
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:3)


Cost of sand
Cost of cement
Mixing charges

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:4)


Cost of sand
Cost of cement
Mixing charges

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:5)


Cost of sand
Cost of cement
Mixing charges

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:6)


Cost of sand
Cost of cement
Mixing charges

1024.10
2073.60
64.00
3161.70

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

Total
1
1.05
240
1

1024.10
2764.80
64.00
3852.90

Total
1
1.05
288
1

736.50
99.20
0.00
835.70

Total
1
1.05
360
1

0.00
0.00

1024.10
1658.88
64.00
2746.98

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

1024.10
1382.40
64.00

6
2470.50

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

1024.10
1036.80
64.00

Total
1
1.05
180
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:8)


Cost of sand
Cost of cement
Mixing charges
Total

1 cu.m

0.90
0.45
162
1.2
1
1

cu.m
cu.m
Kg
kL
cu.m
hr

10 m2

0.09 cu.m
0.8 Kg
10 m2

CC (1:4:8) using 40 mm HBG metal includin


c/c of all materials and labour charges etc.
complete (Machine Mixing)
Cost of 40 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges

2124.90

Over head charges @14%

1149.21
438.90
933.12
92.40
486.80
276.80
0.00

Total

3377.25

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Plastering with CM(1:3) 8 mm thick duly mixed


with acco proof powder compound including
c/c of all materials and labour charges etc.
complete
Cost of CM(1:3)
Cost of Acco proof powder
Labour charges
Over head charges @14%

1276.90
975.33
5760.00
77.00
486.80
276.80

3852.90
Deleted
372.80

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 hr

1 cu.m
1 Kg
10 m2

Total
7

10 m2

0.15 cu.m
10 m2

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.
complete
Cost of CM(1:5)
Labour charges
Over head charges @14%

#VALUE!

2746.98
559.20

1 cu.m
10 m2

Total
8

10 m2

0.21 cu.m
10 m2

Plastering with CM(1:5) 20 mm thick including


c/c of all materials and labour charges etc.
complete
Cost of CM(1:5)
Labour charges
Over head charges @14%
Total

346.76
#VALUE!
372.80
#VALUE!

412.05
559.20
0.00
971.25

2746.98
906.80

1 cu.m
10 m2

576.87
906.80
0.00
1483.70

1
9

2
10 m2

0.21 cu.m
2.00 Kg
10 m2

3852.90
Deleted
2038.70

1 cu.m
1 Kg
10 m2

809.11
#VALUE!
2038.70
#VALUE!

Providing impervious coat to exposed RCC roof slab surface


with CM(1:3), 20mm thick with 1kg of water proof compound
per bag of cement laid over roof when it is green including
cost of all materials, seigniorage charges, excluding
conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar,
laying, rendering smooth and thread lining, curing, rounding
off junctions of wall and slab etc,, complete for finished item
of work

Cost of CM(1:3)
Cost of Acco proof powder
Labour charges
Over head charges @14%
Total

10

1 cu.m

0.9
0.45
275
1.2
1

cu.m
cu.m
Kg
kL
cu.m

CC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing)
Cost of 20 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges

#VALUE!

1796.90
975.33
5760.00
77.00
797.20

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m

Basic Cost
11

1 cu.m

0.90
0.45
275
1.2
1
1

cu.m
cu.m
Kg
kL
cu.m
hr

CC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing)
Cost of 20 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

4529.75

1796.90
975.33
5760.00
77.00
486.80
276.80

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 hr

Basic Cost
12

1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing) for Tap post
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%

1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing) for Tap post
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%

1617.21
438.90
1584.00
92.40
486.80
276.80
4496.15

4529.75
1068.00

1 cu.m
1 cu.m

Total
13

1617.21
438.90
1584.00
92.40
797.20

4529.75
1068.00
0.00
5597.75

4496.15
2463.00

1 cu.m
1 cu.m

4496.15
2463.00
0.00

6
6959.15

4529.75
279.00

1 cu.m
1 cu.m

4529.75
279.00
0.00

Total
1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing) for Pump room slab
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%
Total

1 cu.m

1 cu.m
1 cu.m

4808.75

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing) for Pump room slab
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%

4496.15
279.00

1 cu.m
1 cu.m

Total

21

10 m2
3.50 Kg
10 m2

4775.15

Painting Walls with Snowcem or other equal and approved


Water Proof Cement Paint over Priming Coat, 2 Coats (All
Colours)

Cost of Snow cem


Labour charges
Over head charges @14%

1375.00
690.00

1 Kg
10 m2

Total
23

10 m2

0.7
1.1
10
10

Lt
Lt
m2
m2

Painting with best synthetic enamel paint in 2 coats


over one coat of primer including c/c of all materials
and labour charges etc. complete
Cost of primer coat
Cost of paint at 20 Sq.m / 1 Lt
Labour charges for Primer coat
Labour charges for painting with enamel paint
Over head charges @14%

142.00
276.00
294.00
462.00

1 LT
1 LT
10 m2
10 m2

99.40
303.60
294.00
462.00
0.00
1159.00

DATA FOR RCC ITEMS


1 cu.m

4812.50
690.00
0.00
5502.50

Total

24

4496.15
279.00
0.00

VRCC M- 20 (1:1 :3) Nominal mix (Cement:fine


aggregate: coarse aggregate) corresponding to Table 9 of IS
456 using 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour
charges such as machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work, but excluding centering,
shuttering.

1
a

1796.90
975.33
5760.00
1307.99
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

1617.21
438.90
2304.00
1307.99
276.80
92.40
95.48

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges
Basic Cost

COLUMNS,
BUILDINGS

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

6132.78
LINTELS,

WATER

TANKS,

RCC

WALLS

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

IN

1796.90
975.33
5760.00
1636.77
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Basic Cost
c

1617.21
438.90
2304.00
1636.77
276.80
92.40
95.48
6461.56

RCC SLABS, BEAMS

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

1796.90
975.33
5760.00
878.02
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Basic Cost
1 cu.m

1 cu.m
1 Sq.m

5702.81

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. with
required quantity of steel per cum of concrete
but excluding the cost of steel and fabrication
charges etc. complete For Footings
Cost of VRCC M-20
Centering chrges
Over head charges @14%

6461.56
750.00

1 cu.m
1 m2

Total
1 cu.m

1 cu.m
13.33 Sq.m

1617.21
438.90
2304.00
878.02
276.80
92.40
95.48

6461.56
750.00
0.00
7211.60

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. with
required quantity of steel per cum of concrete
but excluding the cost of steel and fabrication
charges etc. complete For Columns up to 5m ht
Cost of VRCC M-20
Centering chrges
Over head charges @14%

6461.56
1099.00

1 cu.m
1 m2

6461.56
14649.67
0.00

6
21111.30

21111.23
134.00

1 cu.m
1 cu.m

21111.23
134.00
0.00

Total
1 cu.m
1 cu.m
1 Lift

-Do- for columns 5 to 8 m


Cost of VRCC M-20 up to 5m height
Add extra for one lift
Over head charges @14%
Total

1 cu.m
10.22 Sq.m

VRCC M-20 for Braces upto 5 m


Cost of VRCC M-20
Centering charges
Over head charges @14%

21245.30

6461.56
1099.00

1 cu.m
1 m2

Total

1 cu.m
1 lift

VRCC M - 20 for Braces between 5 & 8m


Cost of VRCC M - 20 for braces upto 5m
Add extra lift
Over head charges @14%

17693.40

17693.34
134.00

1 cu.m
1 cu.m

Total

1 cu.m
13.33 Sq.m
1 Lifts

VRCC M - 20 for Ring girder


Cost of VRCC M-20
Centering charges
Add extra lift
Over head charges @14%

1 cu.m
1.27 Sq.m

Centering charges
Over head charges @14%

6461.56
1206.00
134.00

1 cu.m
1 m2
1 cu.m

1 cu.m
1 cu.m

Centering charges
Over head charges @14%

6461.56
1099.00

1 cu.m
1 m2

1 cu.m
5 Sq.m
1 Lifts

Centering charges
Add extra lift
Over head charges @14%

6461.56
1713.00

1 cu.m
1 m2

1 cu.m

6461.56
1713.00
0.00
8174.60

6461.56
3260.00
134.00

1 cu.m
1 m2
1 cu.m

Total
VRCC M - 20 for Side walls
Cost of VRCC M-20

6461.56
1395.73
0.00
7857.30

Total
VRCC M - 20 for bottom slab
Cost of VRCC M-20

6461.56
16075.98
134.00
0.00
22671.60

Total
VRCC M - 20 for Raft Slab for foundation
Cost of VRCC M-20

17693.34
134.00
0.00
17827.40

Total
VRCC M - 20 for Raft beam for foundation
Cost of VRCC M-20

6461.56
11231.78
0.00

6461.56
16300.00
134.00
0.00
22895.60

6461.56

1 cu.m

6461.56

2
20 Sq.m
2 Lifts

4
2463.00
134.00

Centering charges
Add extra lift
Over head charges @14%

5
1 m2
1 cu.m

Total

1 cu.m

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

55989.60

VRCC M- 15 (1:2 :4) Nominal mix (Cement:fine aggregate:


coarse aggregate) corresponding to Table 9 of IS 456 using
20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such
as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished
item of work, but excluding centering, shuttering.

COLUMNS,
BUILDINGS

0.90
0.45
275
1
1
1.2
1

LINTELS,

WATER

TANKS,

RCC

WALLS

IN

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

1796.90
975.33
5760.00
1636.77
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Total

1 cu.m
10 Sq.m
2 Lifts

6
49260.00
268.00
0.00

VRCC M -15 for Top slab


Cost of VRCC M -15
Centering charges
Add extra lift
Over head charges @14%

1617.21
438.90
1584.00
1636.77
276.80
92.40
95.48
5741.56

5741.56
1643.00
134.00

1 cu.m
1 m2
1 cu.m

Total

5741.56
16430.00
268.00
0.00
22439.60

Supplying, fitting and placing HYSD/TMT bar reinforcement in


foundation complete as per drawings and technical
specifications for Bars below 36 mm dia including over laps
and wastage, where they are not welded

1.05 Mt
6 Kg
1 Mt

Cost of HYSD / TMT bars including 5% for Over laps and 43000.00
wastage
Binding wire
Labour for cutting, bending, shifting to site, tying and placing
in position

Over head charges @14%


Total

70.00
7400.00

1000

45150.00

1 Kg
1 MT

420.00
7400.00
0.00
52970.00

4
Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

DATA SHEET
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
S.No
content
Description of work
Rate
Per
Amount
1
2
3
4
5
6
1
1 cu.m
Earth work excavation for structures as per drawing
116.48
1 cu.m
116.48
and technical specifications clause 305.1 in Ordinary
Soils including setting out ,construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50m and
backfilling in trenches with excavated suitable material
as per technical specification 305 MORD/304 MORTH
Over head charges @14%

0.00

Total
2
1 cu.m

Refillling with excavated soil including breaking


of clods watering, tamping etc. complete
Over head charges @14%

116.50

0.00

1 cu.m

Total
3

1 cu.m

Filling in foundation trenches as per drawing and technical


specification Clause 305.3.9 MORD & 304 MORTH

1 cu.m
1 cu.m

Cost of sand
Cost of refilling charges
Over head charges @14%

0.00

736.50
99.20

1 cu.m
1 cu.m

Total
4

1
1.05
480
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:3)


Cost of sand
Cost of cement
Mixing charges

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:4)


Cost of sand
Cost of cement
Mixing charges

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:5)


Cost of sand
Cost of cement
Mixing charges

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:6)


Cost of sand
Cost of cement
Mixing charges

1024.10
2073.60
64.00
3161.70

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

Total
1
1.05
240
1

1024.10
2764.80
64.00
3852.90

Total
1
1.05
288
1

736.50
99.20
0.00
835.70

Total
1
1.05
360
1

0.00
0.00

1024.10
1658.88
64.00
2746.98

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

1024.10
1382.40
64.00

6
2470.50

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

1024.10
1036.80
64.00

Total
1
1.05
180
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:8)


Cost of sand
Cost of cement
Mixing charges
Total

1 cu.m

0.90
0.45
162
1.2
1
1

cu.m
cu.m
Kg
kL
cu.m
hr

10 m2

0.09 cu.m
0.8 Kg
10 m2

CC (1:4:8) using 40 mm HBG metal includin


c/c of all materials and labour charges etc.
complete (Machine Mixing)
Cost of 40 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges

2124.90

Over head charges @14%

1149.21
438.90
933.12
92.40
486.80
276.80
0.00

Total

3377.25

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Plastering with CM(1:3) 8 mm thick duly mixed


with acco proof powder compound including
c/c of all materials and labour charges etc.
complete
Cost of CM(1:3)
Cost of Acco proof powder
Labour charges
Over head charges @14%

1276.90
975.33
5760.00
77.00
486.80
276.80

3852.90
Deleted
372.80

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 hr

1 cu.m
1 Kg
10 m2

Total
7

10 m2

0.15 cu.m
10 m2

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.
complete
Cost of CM(1:5)
Labour charges
Over head charges @14%

#VALUE!

2746.98
559.20

1 cu.m
10 m2

Total
8

10 m2

0.21 cu.m
10 m2

Plastering with CM(1:5) 20 mm thick including


c/c of all materials and labour charges etc.
complete
Cost of CM(1:5)
Labour charges
Over head charges @14%
Total

346.76
#VALUE!
372.80
#VALUE!

412.05
559.20
0.00
971.25

2746.98
906.80

1 cu.m
10 m2

576.87
906.80
0.00
1483.70

1
9

2
10 m2

0.21 cu.m
2.00 Kg
10 m2

3852.90
Deleted
2038.70

1 cu.m
1 Kg
10 m2

809.11
#VALUE!
2038.70
#VALUE!

Providing impervious coat to exposed RCC roof slab surface


with CM(1:3), 20mm thick with 1kg of water proof compound
per bag of cement laid over roof when it is green including
cost of all materials, seigniorage charges, excluding
conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar,
laying, rendering smooth and thread lining, curing, rounding
off junctions of wall and slab etc,, complete for finished item
of work

Cost of CM(1:3)
Cost of Acco proof powder
Labour charges
Over head charges @14%
Total

10

1 cu.m

0.9
0.45
275
1.2
1

cu.m
cu.m
Kg
kL
cu.m

CC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing)
Cost of 20 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges

#VALUE!

1796.90
975.33
5760.00
77.00
797.20

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m

Basic Cost
11

1 cu.m

0.90
0.45
275
1.2
1
1

cu.m
cu.m
Kg
kL
cu.m
hr

CC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing)
Cost of 20 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

4529.75

1796.90
975.33
5760.00
77.00
486.80
276.80

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 hr

Basic Cost
12

1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing) for Tap post
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%

1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing) for Tap post
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%

1617.21
438.90
1584.00
92.40
486.80
276.80
4496.15

4529.75
1068.00

1 cu.m
1 cu.m

Total
13

1617.21
438.90
1584.00
92.40
797.20

4529.75
1068.00
0.00
5597.75

4496.15
2463.00

1 cu.m
1 cu.m

4496.15
2463.00
0.00

6
6959.15

4529.75
279.00

1 cu.m
1 cu.m

4529.75
279.00
0.00

Total
1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing) for Pump room slab
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%
Total

1 cu.m

1 cu.m
1 cu.m

4808.75

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing) for Pump room slab
Cost of CC(1:2:4)
Centering Charges
Over head charges @14%

4496.15
279.00

1 cu.m
1 cu.m

Total

21

10 m2
3.50 Kg
10 m2

4775.15

Painting Walls with Snowcem or other equal and approved


Water Proof Cement Paint over Priming Coat, 2 Coats (All
Colours)

Cost of Snow cem


Labour charges
Over head charges @14%

1375.00
690.00

1 Kg
10 m2

Total
23

10 m2

0.7
1.1
10
10

Lt
Lt
m2
m2

Painting with best synthetic enamel paint in 2 coats


over one coat of primer including c/c of all materials
and labour charges etc. complete
Cost of primer coat
Cost of paint at 20 Sq.m / 1 Lt
Labour charges for Primer coat
Labour charges for painting with enamel paint
Over head charges @14%

142.00
276.00
294.00
462.00

1 LT
1 LT
10 m2
10 m2

99.40
303.60
294.00
462.00
0.00
1159.00

DATA FOR RCC ITEMS


1 cu.m

4812.50
690.00
0.00
5502.50

Total

24

4496.15
279.00
0.00

VRCC M- 20 (1:1 :3) Nominal mix (Cement:fine


aggregate: coarse aggregate) corresponding to Table 9 of IS
456 using 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour
charges such as machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work, but excluding centering,
shuttering.

1
a

1796.90
975.33
5760.00
1307.99
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

1617.21
438.90
2304.00
1307.99
276.80
92.40
95.48

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges
Basic Cost

COLUMNS,
BUILDINGS

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

6132.78
LINTELS,

WATER

TANKS,

RCC

WALLS

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

IN

1796.90
975.33
5760.00
1636.77
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Basic Cost
c

1617.21
438.90
2304.00
1636.77
276.80
92.40
95.48
6461.56

RCC SLABS, BEAMS

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

1796.90
975.33
5760.00
878.02
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Basic Cost
1 cu.m

1 cu.m
1 Sq.m

5702.81

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. with
required quantity of steel per cum of concrete
but excluding the cost of steel and fabrication
charges etc. complete For Footings
Cost of VRCC M-20
Centering chrges
Over head charges @14%

6461.56
750.00

1 cu.m
1 m2

Total
1 cu.m

1 cu.m
13.33 Sq.m

1617.21
438.90
2304.00
878.02
276.80
92.40
95.48

6461.56
750.00
0.00
7211.60

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. with
required quantity of steel per cum of concrete
but excluding the cost of steel and fabrication
charges etc. complete For Columns up to 5m ht
Cost of VRCC M-20
Centering chrges
Over head charges @14%

6461.56
1099.00

1 cu.m
1 m2

6461.56
14649.67
0.00

6
21111.30

21111.23
134.00

1 cu.m
1 cu.m

21111.23
134.00
0.00

Total
1 cu.m
1 cu.m
1 Lift

-Do- for columns 5 to 8 m


Cost of VRCC M-20 up to 5m height
Add extra for one lift
Over head charges @14%
Total

1 cu.m
1 cu.m
1 Lift

-Do- for columns 8 to 11 m


Cost of VRCC M-20 up to 8 m height
Add extra for one lift
Over head charges @14%

21245.30

21245.23
134.00

1 cu.m
1 cu.m

Total

1 cu.m
10.22 Sq.m

VRCC M-20 for Braces upto 5 m


Cost of VRCC M-20
Centering charges
Over head charges @14%

21379.30

6461.56
1099.00

1 cu.m
1 m2

Total

1 cu.m
1 lift

VRCC M - 20 for Braces between 5 & 8m


Cost of VRCC M - 20 for braces upto 5m
Add extra lift
Over head charges @14%

VRCC M - 20 for Ring girder


Cost of VRCC M-20
Centering charges
Add extra lift
Over head charges @14%

17693.34
134.00

1 cu.m
1 cu.m

1 cu.m
1.27 Sq.m

Centering charges
Over head charges @14%

6461.56
1206.00
134.00

1 cu.m
1 m2
1 cu.m

1 cu.m
1 cu.m

Centering charges
Over head charges @14%

6461.56
1099.00

1 cu.m
1 m2

1 cu.m
5 Sq.m

Centering charges

6461.56
1395.73
0.00
7857.30

6461.56
1713.00

1 cu.m
1 m2

Total
VRCC M - 20 for bottom slab
Cost of VRCC M-20

6461.56
16075.98
268.00
0.00
22805.60

Total
VRCC M - 20 for Raft Slab for foundation
Cost of VRCC M-20

17693.34
134.00
0.00
17827.40

Total
VRCC M - 20 for Raft beam for foundation
Cost of VRCC M-20

6461.56
11231.78
0.00
17693.40

Total

1 cu.m
13.33 Sq.m
2 Lifts

21245.23
134.00
0.00

6461.56
1713.00
0.00
8174.60

6461.56
3260.00

1 cu.m
1 m2

6461.56
16300.00

2
2 Lifts

4
134.00

Add extra lift


Over head charges @14%

5
1 cu.m

Total

1 cu.m
20 Sq.m
3 Lifts

23029.60

VRCC M - 20 for Side walls


Cost of VRCC M-20

6461.56
2463.00
134.00

Centering charges
Add extra lift
Over head charges @14%

1 cu.m
1 m2
1 cu.m

Total

1 cu.m

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

56123.60

LINTELS,

WATER

TANKS,

RCC

WALLS

IN

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

1796.90
975.33
5760.00
1636.77
276.80
77.00
95.48

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Total

1 cu.m
10 Sq.m
3 Lifts

6461.56
49260.00
402.00
0.00

VRCC M- 15 (1:2 :4) Nominal mix (Cement:fine aggregate:


coarse aggregate) corresponding to Table 9 of IS 456 using
20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such
as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished
item of work, but excluding centering, shuttering.

COLUMNS,
BUILDINGS

0.90
0.45
275
1
1
1.2
1

6
268.00
0.00

VRCC M -15 for Top slab


Cost of VRCC M -15
Centering charges
Add extra lift
Over head charges @14%

1617.21
438.90
1584.00
1636.77
276.80
92.40
95.48
5741.56

5741.56
1643.00
134.00

1 cu.m
1 m2
1 cu.m

Total

5741.56
16430.00
402.00
0.00
22573.60

Supplying, fitting and placing HYSD/TMT bar reinforcement in


foundation complete as per drawings and technical
specifications for Bars below 36 mm dia including over laps
and wastage, where they are not welded

1.05 Mt
6 Kg
1 Mt

Cost of HYSD / TMT bars including 5% for Over laps and 43000.00
wastage
Binding wire
Labour for cutting, bending, shifting to site, tying and placing
in position

70.00
7400.00

1000

45150.00

1 Kg
1 MT

420.00
7400.00

Over head charges @14%


Total

6
0.00
52970.00

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

DATA SHEET
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
SSR
2015-2016
S.No
1
1

content
Description of work
2
3
1 cu.m Earth work excavation for structures as per drawing
and technical specifications clause 305.1 in Ordinary
Soils including setting out ,construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50m

1 Rmt Earth work excavation in OG soils of trench size


0.50*0.75 m with initial lead and lift for laying and
jointing of PVC pipes and refilling the
trench with excavated soil and bringing the
surface to original level and testing the pipe line
to required pressure etc. complete
63 mm PVC Pipe
0.375 m3
Earth work excavation including refilling
Add 120% extra where depth is 1.5 times or
0.375 m3
more than the width
1 Rmt Laying and jointing charges
Over head charges @14%

Rate
4
116.48

Per
5
1 cu.m

Amount
6
116.48

116.48

1 cu.m

43.68

1.2*107.38
6.11

1 cu.m
1 Rmt

52.42
6.11
0.00

Total
75mm PVC Pipe
Earth work excavation including refilling
Add 120% extra where depth is 1.5 times or
0.375 m3
more than the width
1 Rmt Laying and jointing charges
Over head charges @14%
0.375 m3

102.25

116.48

1 cu.m

43.68

1.2*107.38
7.28

1 cu.m
1 Rmt

52.42
7.28
0.00

Total
3

1 Rmt Earth work excavation in OG soils of trench size


0.70*1.00 m with initial lead and lift for laying and
jointing of PVC pipes and refilling the
trench with excavated soil and bringing the
surface to original level and testing the pipe line
to required pressure etc. complete
90mm PVC Pipe
0.7 m3
Earth work excavation
Add 75% extra where depth is less than 1.5 times
0.7 m3
the width
1 Rmt Laying and jointing charges
Over head charges @14%

103.40

116.48

1 cu.m

81.54

0.75*107.38
8.73

1 cu.m
1 Rmt

61.15
8.73
0.00

Total
110mm PVC Pipe
Earth work excavation
Add 75% extra where depth is less than 1.5 times
0.7 m3
the width
1 Rmt Laying and jointing charges
Over head charges @14%
0.7 m3

Total

151.45

116.48

1 cu.m

81.54

0.75*107.38
10.67

1 cu.m
1 Rmt

61.15
10.67
0.00
153.40

1 Rmt

Supply and delivery of UPVC pipes for drinking water


supplies confirming IS : 4985/2000 with socket
including transportation chrges, including CED but
excluding VAT @ 5% (Resin Cost Rs. 65,325/- per MT
as per PH SSR basic rate excluding CED) and for the
month of
July-15
Present Resin Cost = 71214/- per MT
90 mm * 6
Kg/Cm2

75 mm * 63 mm * 6 180 mm *
6 Kg/Cm2 Kg/Cm2
6 Kg/Cm2

Cost of PVC Pipes as per present resin cost

160.00

110.00

81.00

634.00

CED @ 12%

19.20

13.20

9.72

76.08

Cess @ 3%

0.58

0.40

0.29

2.28

179.78

123.6

91.01

712.36

Cost of PVC pipe per Rmt

110 mm * 4 75 mm * 63 mm * 4
Kg/Cm2
4 Kg/Cm2 Kg/Cm2
Cost of PVC Pipes as per present resin cost

162.00

82.00

56.00

CED @ 12%

19.44

9.84

6.72

Cess @ 3%

0.58

0.30

0.20

182.02

92.14

62.92

Cost of PVC pipe per Rmt

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

DATA SHEET
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in
Thottembedu Mandal
SSR
2015-2016
S.No
1
1

content
2

3.64 No

Description of work
3
Earth work excavation for structures as per drawing
and technical specifications clause 305.1 in Ordinary
Soils including setting out ,construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50m and
backfilling in trenches with excavated suitable material
as per technical specification 305 MORD/304 MORTH
Taking Out Put = 10 Cum
Man Mazdoor
Over head charges @13.615%

Rate
4

Per
5

Amount
6

320.00

10 Cum

1164.80
0.00

Total for 10 Cum


1 Cum
2
1 cu.m
1 cu.m
0.12 kL

1164.80

Earthwork excavation for 1 Cum

1164.80

10 Cum

116.48

Refillling with excavated soil including breaking


of clods watering, tamping etc. complete
Cost of refilling charges
Cost of Water
Over head charges @13.615%

0.00
166.40
77.00

1 cu.m
1 cu.m
1 kL

0.00
166.40
9.24
0.00

Total
3

1 cu.m
1 cu.m
1 cu.m
0.1 kL

175.65

Filling in foundation trenches as per drawing and technical


specification Clause 305.3.9 MORD & 304 MORTH

Cost of sand
Cost of refilling charges
Cost of Water
Over head charges @13.615%

736.50
99.20
77.00

1 cu.m
1 cu.m
1 kL

Total
4

1
1.05
480
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:3)


Cost of sand
Cost of cement
Mixing charges

843.40

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

Total
1
1.05
360
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:4)


Cost of sand
Cost of cement
Mixing charges

Cement Mortar (1:5)


Cost of sand
Cost of cement

1024.10
2764.80
64.00
3852.90

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

Total
1 cu.m
1.05 cu.m
288 Kg

736.50
99.20
7.70
0.00

1024.10
2073.60
64.00
3161.70

975.33
5760.00

1 cu.m
1 MT

1024.10
1658.88

2
1 cu.m

3
Mixing charges

4
64.00

5
1 cu.m

Total
1
1.05
240
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:6)


Cost of sand
Cost of cement
Mixing charges

2746.98

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

Total
1
1.05
180
1

cu.m
cu.m
Kg
cu.m

Cement Mortar (1:8)


Cost of sand
Cost of cement
Mixing charges

1 cu.m

0.90
0.45
162
1.2
1

cu.m
cu.m
Kg
kL
cu.m

CC (1:4:8) using 40 mm HBG metal includin


c/c of all materials and labour charges etc.
complete (Hand Mixing)
Cost of 40 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges
Over head charges @13.615%

975.33
5760.00
64.00

1 cu.m
1 MT
1 cu.m

1 cu.m

0.90
0.45
162
1.2
1
1

cu.m
cu.m
Kg
kL
cu.m
hr

10 m2

0.09 cu.m
0.8 Kg
10 m2

CC (1:4:8) using 40 mm HBG metal includin


c/c of all materials and labour charges etc.
complete (Machine Mixing)
Cost of 40 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges

1276.90
886.50
5760.00
77.00
797.20

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m

10 m2

1149.21
398.93
933.12
92.40
797.20
0.00
3370.90

Over head charges @13.615%

1149.21
398.93
933.12
92.40
486.80
456.20
0.00

Total

3516.70

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Plastering with CM(1:3) 8 mm thick duly mixed


with acco proof powder compound including
c/c of all materials and labour charges etc.
complete
Cost of CM(1:3)
Cost of Acco proof powder
Labour charges (469.80 * 8/12)
Over head charges @13.615%
Total

1024.10
1036.80
64.00
2124.90

Total
b

1024.10
1382.40
64.00
2470.50

Total
5

6
64.00

Plastering with CM(1:5) 12 mm thick including


c/c of all materials and labour charges etc.

1276.90
886.50
5760.00
77.00
486.80
456.20

3852.90
Deleted
372.80

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 hr

1 cu.m
1 Kg
10 m2

346.76
#VALUE!
372.80
#VALUE!
#VALUE!

2
0.15 cu.m
10 m2

3
complete
Cost of CM(1:5)
Labour charges
Over head charges @13.615%

2746.98
559.20

1 cu.m
10 m2

412.05
559.20
0.00

Total
8

10 m2

0.21 cu.m
10 m2

Plastering with CM(1:5) 20 mm thick including


c/c of all materials and labour charges etc.
complete
Cost of CM(1:5)
Labour charges
Over head charges @13.615%

971.25

2746.98
906.80

1 cu.m
10 m2

Total
9

10 m2

0.21 cu.m
2.00 Kg
10 m2

1483.70

Providing impervious coat to exposed RCC roof slab surface


with CM(1:3), 20mm thick with 1kg of water proof compound
per bag of cement laid over roof when it is green including
cost of all materials, seigniorage charges, excluding
conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar,
laying, rendering smooth and thread lining, curing, rounding
off junctions of wall and slab etc,, complete for finished item
of work

Cost of CM(1:3)
Cost of Acco proof powder
Labour charges
Over head charges @13.615%

3852.90
Deleted
2038.70

1 cu.m
1 Kg
10 m2

Total
10

1 cu.m

0.9
0.45
275
1.2
1

cu.m
cu.m
Kg
kL
cu.m

CC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing)
Cost of 20 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges

1 cu.m

0.90
0.45
275
1.2
1
1

cu.m
cu.m
Kg
kL
cu.m
hr

CC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing)
Cost of 20 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (including Curing)
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Basic Cost

809.11
#VALUE!
2038.70
#VALUE!
#VALUE!

1796.90
886.50
5760.00
77.00
797.20

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m

Basic Cost
11

576.87
906.80
0.00

1617.21
398.93
1584.00
92.40
797.20
4489.75

1796.90
886.50
5760.00
77.00
486.80
456.20

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 hr

1617.21
398.93
1584.00
92.40
486.80
456.20
4635.55

1
12

2
1 cu.m

1 cu.m
1 cu.m

3
CC / RCC(1:2:4) using 20 mm HBG metal including
c/c of all materials and labour charges etc.
complete (Hand mixing) for Tap post
Cost of CC(1:2:4)
Centering Charges
Over head charges @13.615%

4489.75
1068.00

1 cu.m
1 cu.m

4489.75
1068.00
0.00

Total
13

1 cu.m

1 cu.m
1 cu.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing) for Tap post
Cost of CC(1:2:4)
Centering Charges
Over head charges @13.615%

5557.75

4635.55
1068.00

1 cu.m
1 cu.m

Total
1 cu.m

1 cu.m
10 Sq.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Hand mixing) for Pump room slab up to 150
mm thick
Cost of CC(1:2:4)
Centering Charges for 100 mm thick slab
Over head charges @13.615%

5703.55

4489.75
279.00

1 cu.m
1 Sq.m

Total
1 cu.m

1 cu.m
10 Sq.m

CC / RCC(1:2:4) using 20 mm HBG metal including


c/c of all materials and labour charges etc.
complete (Machine mixing) for Pump room slab up to
150 mm thick
Cost of CC(1:2:4)
Centering Charges for 100 mm thick slab
Over head charges @13.615%

1 cu.m

0.17
0.085
120
10

cu.m
cu.m
Kg
m2

4489.75
2790.00
0.00
7279.75

4635.55
279.00

1 cu.m
1 Sq.m

Total
15

4635.55
1068.00
0.00

4635.55
2790.00
0.00
7425.55

Gronolithie Concrete Flooring 20 mm thick with (1:1:2), using


6mm to 12 mm size hard granite machine crushed metal laid
over CC bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m and finishing
the top surface to required smoothness and slopes and
thread lining including cost of all materials like cement, metal,
sand and water etc., complete, including seigniorage
charges, etc., complete for finished item of work, but
excluding the cost of conveyance of all materials

Cost of 6 to 12 mm HBG MC metal


Cost of Sand
Cost of Cement
Labour charges
Over head charges @13.615%
Total

1081.90
886.50
5760.00
1507.50

1 cu.m
1 cu.m
1 MT
10m2

183.92
75.35
691.20
1507.50
0.00
2458.00

1
16

2
1 cu.m

0.90
0.54
129.60
1.2
1

cu.m
cu.m
Kg
kL
cu.m

3
CC (1:6:10) using 40 mm HBG metal includin
c/c of all materials and labour charges etc.
complete (Hand mixing)
Cost of 40 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (Including Curing)
Labour charges
Over head charges @13.615%

1276.90
886.50
5760.00
77.00
797.20

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m

1149.21
478.71
746.50
92.40
797.20
0.00

Total
b

1 cu.m

0.90
0.54
129.60
1.2
1
1

17

cu.m
cu.m
Kg
kL
cu.m
hr

1 cu.m
0.44
0.50
0.16
0.33
1

cu.m
cu.m
cu.m
cu.m
cu.m

CC (1:6:10) using 40 mm HBG metal includin


c/c of all materials and labour charges etc.
complete (Machine mixing)
Cost of 40 mm HBG metal (M/C)
Cost of sand
Cost of cement
Water (Including Curing)
Labour charges

3264.05

Over head charges @13.615%

1149.21
478.71
746.50
92.40
486.80
456.20
0.00

Total

3409.85

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

RR masonary in CM(1:8) including c/c of all


materials and labour charges etc. complete
Cost of CR Stone
Cost of Rough stone
Cost of Bond stone of size 0.24*0.24*0.39 m 7 Nos
Cost of CM(1:8)
Labour charges
Over head charges @13.615%

1276.90
886.50
5760.00
77.00
486.80
456.20

927.15
611.25
1295.76
2124.90
1144.00

1 cu.m
1 cu.m
1 MT
1 kL
1 cu.m
1 kL

1 cu.m
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Total
18

1 cu.m

0.44
0.50
0.16
0.33
1

cu.m
cu.m
cu.m
cu.m
cu.m

RR masonary in CM(1:6) including c/c of all


materials and labour charges etc. complete
Cost of CR Stone
Cost of CR Stone
Cost of Rough stone
Cost of Bond stone of size 0.24*0.24*0.39 m 7 Nos
Cost of CM(1:6)
Labour charges
Over head charges @13.615%

2766.15

927.15
611.25
1295.76
2470.50
1144.00

1 cu.m
1 cu.m
1 cu.m
1 cu.m

Total
19

1 cu.m

512 No
0.2 cu.m
1 cu.m

Brick masonary in CM(1:6) including c/c of all


materials and labour charges etc. complete
for super structure
Cost of Bricks
Cost of CM(1:6)
Labour charges
Over head charges @13.615%

407.95
305.63
207.32
701.22
1144.00
0.00

407.95
305.63
207.32
815.27
1144.00
0.00
2880.20

6439.57
2470.50
915.60

1000 No
1 cu.m
1 cu.m

3297.06
494.10
915.60
0.00

6
4706.80

3852.90
446.80

1 cu.m
10 m2

115.59
446.80
0.00

Total
20

10 m2
0.03 cu.m
10 m2

Pointing with CM(1:3) to RR masonary including


c/c of all materials and labour charges etc. com
Cost of CM(1:3)
Labour charges
Over head charges @13.615%
Total

21

10 m2
3.50 Kg
10 m2

562.40

Painting Walls with Snowcem or other equal and approved


Water Proof Cement Paint over Priming Coat, 2 Coats (All
Colours)

Cost of Snow cem


Labour charges
Over head charges @13.615%

1375.00
690.00

25 Kg
10 m2

Total
23

10 m2

0.7
1.1
10
10

Lt
Lt
m2
m2

Painting with best synthetic enamel paint in 2 coats


over one coat of primer including c/c of all materials
and labour charges etc. complete
Cost of primer coat
Cost of paint at 20 Sq.m / 1 Lt
Labour charges for Primer coat
Labour charges for painting with enamel paint
Over head charges @13.615%

882.50

142.00
276.00
294.00
462.00

1 LT
1 LT
10 m2
10 m2

Total

10 m2

10.10

sqm

0.12

cum

33.00

kg.

2.00

kg.

10.00

sqm

192.50
690.00
0.00

99.40
303.60
294.00
462.00
0.00
1159.00

Flooring with ceramic tiles, set over base coat of cement


mortar (1:8), 12 mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement,
sand water and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of work, but
excluding the cost of conveyance of all materials.

Over head charges @13.615%

4545.00
254.99
190.08
58.00
2225.23
0.00

Total

7273.30

Ceramic tiles
Cost of CM (1:8)
Cement for slurry
White cement
Labour charges including Water charges

450.00

1 Sq.m

2124.90

1 Cum

5.76

1 Kg

29.00

1 Kg

2225.23

10 Sqm

10 m2

10
0.12
33
6

Sqm
Cum
Kg
Kg

0.77
0.8

Day
Day

4500.00
462.35
190.08
174.00

Providing skirting to internal walls to 15 cm height/risers of


steps with ceramic tiles 7.30 mm thick length equal to flooring
stones, set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white cement paste mixed
with pigment of matching shade to full depth, including cost of
all materials like tiles, cement, sand and water etc., complete
including seigniorage charges, etc., complete for finished
item of work, but excluding the cost of conveyance of all
materials

Ceramic tiles 7.30 mm thick


Cost of CM (1:3)
Cement for slurry
White cement for jointing & pointing
B. LABOUR
Mason 1st class
Mazdoor (unskiled)

450.00

1 Sq.m

3852.90

1 Cum

5.76

1 Kg

29.00

1 Kg

420.00

0.77

320.00

0.80

Over head charges @13.615%

323.40
256.00
0.00

Total

5905.90
DATA FOR RCC ITEMS

24

1 cu.m

Supply and placing of the VRCC - M 30 Design Mix


Concrete corresponding to IS 456 using WEIGH
BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including
all operational, incidental and labour charges such as
weigh batching, machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No. 402)with minimum cement content as per IS code
from standard suppliers approved by the department
including pumping, centering, shuttering, laying
concrete, vibrating, curing etc. complete but excluding
cost of steel and its fabrication charges for finished
item of work.

For Design Mix concrete allow cement as follows (For


estimation purpose only)

Grade
M 20
M 25
M 30
M 35
M 40

Kg
350.00
380.00
400.00
420.00
430.00

1796.90

1 cu.m

1437.52

886.50

1 cu.m

354.60

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

0.80 cu.m
0.40 cu.m

Cost of 20 mm HBG metal (M/C) of Specific gravity


2.64
Cost of sand with a specific gravity 2.60

2
400 Kg
1 cu.m
1.333 Hour
1.2 kL

3
Cost of cement specific gravity 3.15
Labour charges
Weigh batcher Hire charges (Machine mixing) charge 0.5
Cum

Water charges W/C ratio 0.42

4
5760.00
1627.99
503.90

5
1 MT
1 cu.m
1 cu.m

6
2304.00
1627.99
671.70

77.00

1 cu.m

92.40

Basic Cost
COLUMNS,
BUILDINGS

0.80 cu.m
0.40
400
1
1.333

cu.m
Kg
cu.m
Hour

1.2 kL

6488.21
LINTELS,

WATER

TANKS,

RCC

WALLS

IN

Cost of 20 mm HBG metal (M/C) of Specific gravity


2.64
Cost of sand with a specific gravity 2.60
Cost of cement specific gravity 3.15
Labour charges
Weigh batcher Hire charges (Machine mixing) charge 0.5
Cum

Water charges W/C ratio 0.42

1796.90

1 cu.m

1437.52

886.50
5760.00
1924.77
503.90

1 cu.m
1 MT
1 cu.m
1 cu.m

354.60
2304.00
1924.77
671.70

77.00

1 cu.m

92.40

Basic Cost

6784.99

RCC SLABS, BEAMS

0.80 cu.m
0.40
400
1
0.308

cu.m
Kg
cu.m
Hour

1.2 kL

Cost of 20 mm HBG metal (M/C) of Specific gravity


2.64
Cost of sand with a specific gravity 2.60
Cost of cement specific gravity 3.15
Labour charges
Weigh batcher Hire charges (Machine mixing) charge 0.5
Cum

Water charges W/C ratio 0.42

1796.90

1 cu.m

1437.52

886.50
5760.00
1060.42
503.90

1 cu.m
1 MT
1 cu.m
1 cu.m

354.60
2304.00
1060.42
155.20

77.00

1 cu.m

92.40

Basic Cost

5404.14

Note : Quantity of cement proposed for various mixes is for


estimating purpose only. Actual quantity will be as per
approved mix design. Similarly quantity for coarse aggregate
is for estimating purpose and the exact quantity shall be as
per the mix design.

24

1 cu.m

VRCC M- 20 (1:1 :3) Nominal mix (Cement:fine


aggregate: coarse aggregate) corresponding to Table 9 of IS
456 using 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour
charges such as machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and its fabrication
charges for finished item of work, but excluding centering,
shuttering.

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

0.90
0.45
400
1
1

cu.m
cu.m
Kg
cu.m
Hour

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

1796.90
886.50
5760.00
1307.99
456.20

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m

1617.21
398.93
2304.00
1307.99
456.20

2
1.2 kL
1 Hour

4
77.00
132.70

Water charges
Vibrating charges

5
1 cu.m
1 cu.m

Basic Cost
b

COLUMNS,
BUILDINGS

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

6309.43
LINTELS,

WATER

TANKS,

RCC

WALLS

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

IN

1796.90
886.50
5760.00
1636.77
456.20
77.00
132.70

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Basic Cost
c

6638.21

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

1796.90
886.50
5760.00
878.02
456.20
77.00
132.70

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

Basic Cost
1 cu.m

1 cu.m
1 cu.m

1 cu.m

1 cu.m
1 cu.m

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Foundation
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

6309.43
750.00

1 cu.m
1 cu.m

6309.43
750.00
0.00
7059.45

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Pedestal
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

6309.43
1068.00

1 cu.m
1 cu.m

Total
26

1617.21
398.93
2304.00
878.02
456.20
92.40
132.70
5879.46

Total
26

1617.21
398.93
2304.00
1636.77
456.20
92.40
132.70

RCC SLABS, BEAMS

0.90
0.45
400
1
1
1.2
1

25

6
92.40
132.70

1 cu.m

VRCC M - 20 using 20 mm HBG MC metal including

1 cu.m

c/c of all materials and labour charges etc. but


excluding cost of steel and its fabrication charges
etc. complete for Plinth
Basic Cost of M - 20 nominal mix

6309.43
1068.00
0.00
7377.45

6309.43

1 cu.m

6309.43

2
1 cu.m

3
Centering charges
Over head charges @13.615%

4
2476.00

5
1 cu.m

Total
26

1 cu.m

1 cu.m
1 cu.m

8785.45

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Column
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

6638.21
1567.00

1 cu.m
1 cu.m

Total
27

1 cu.m

1 cu.m
1 cu.m

1 cu.m
1 cu.m

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Lintel
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

6638.21
1713.00

1 cu.m
1 cu.m

1 cu.m
1 cu.m

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for RCC slabs up to 150 mm thick
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

5879.46
1099.00

1 cu.m
1 cu.m

5879.46
1099.00
0.00
6978.50

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Beams
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%
Total

5879.46
2464.00

1 cu.m
1 cu.m

5879.46
2464.00
0.00
8343.50

DATA FOR GLSR


1 cu.m

6638.21
1713.00
0.00
8351.25

Total
1 cu.m

6638.21
1567.00
0.00
8205.25

Total
1 cu.m

6
2476.00
0.00

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Bottom slab

2
1 cu.m
1 cu.m

3
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

4
6638.21
750.00

5
1 cu.m
1 cu.m

Total
1 cu.m

1 cu.m
1 cu.m

7388.25

VRCC M - 20 using 20 mm HBG MC metal including


c/c of all materials and labour charges etc. but
excluding cost of steel and its fabrication charges
etc. complete for Bottom slab
Basic Cost of M - 20 nominal mix
Centering charges
Over head charges @13.615%

6638.21
750.00

1 cu.m
1 cu.m

Total
VRCC M - 20 (1:1 :3) using 20 mm HBG metal including

1 cu.m

c/c of all materials and labour charges with


required quantity of steel per cu.m of CC but
excluding the cost of steel and its fabrication
charges etc. complete for Side walls
VRCC M - 20 Nominal mix
Centering charges
Over head charges @13.615%

6638.21

1 cu.m

6638.21

1115.00

1 m2

22300.00
0.00

Total
25

1 cu.m

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

28938.25

VRCC M- 15 (1:2 :4) Nominal mix (Cement:fine aggregate:


coarse aggregate) corresponding to Table 9 of IS 456 using
20mm size graded machine crushed hard granite metal
(coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials
including all operational, incidental and labour charges such
as machine mixing, laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication charges for finished
item of work, but excluding centering, shuttering.

COLUMNS,
BUILDINGS

0.90
0.45
275
1
1
1.2
1

LINTELS,

WATER

TANKS,

RCC

WALLS

Cost of 20 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges
Total

26

1 cu.m

6638.21
750.00
0.00
7388.25

1 cu.m

20 m2

6
6638.21
750.00
0.00

VRCC M-15 (1:2:4) using 20 mm HBG metal


including c/c of all materials and labour charges
with required quantity of steel per cu.m of CC but
excluding the cost of steel and its fabrication

IN

1796.90
886.50
5760.00
1636.77
456.20
77.00
132.70

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

1617.21
398.93
1584.00
1636.77
456.20
92.40
132.70
5918.21

2
1 cu.m
10 Sq.m

3
charges etc. complete for Top slab of GLSR
VRCC M - 15 Nominal mix
Centering charges
Over head charges @13.615%

5918.21
279.00

1 cu.m
1 Sq.m

5918.21
2790.00
0.00

Total
29

8708.25

Supplying, fitting and placing HYSD/TMT bar reinforcement in


foundation complete as per drawings and technical
specifications for Bars below 36 mm dia including over laps
and wastage, where they are not welded

1.05 Mt
6 Kg
1 Mt

Cost of HYSD / TMT bars including 5% for Over laps and 43000.00
wastage
Binding wire
Labour for cutting, bending, shifting to site, tying and placing
in position

70.00
7400.00

1000

45150.00

1 Kg
1 MT

420.00
7400.00

Over head charges @13.615%

0.00

Total

52970.00
DATA FOR HELICAL STAIR CASE

1 cu.m

1 cu.m
13.33 cu.m

VRCC M - 30 design mix using 20 mm HBG metal


for stair case column including centering charges
etc. complete for Column
Cost of VRCC M - 30 design mix for column

6784.99

1 cu.m

6784.99

Centering charges for Column

1206.00

1 cu.m

16075.98

0.30

Total
1 Cu.m

1 cu.m

1 cu.m
16.67 cu.m

RCC Lift charges

22861.00
134.00

1 cu.m

134.00

VRCC M 30 design mix 0 - 5 m

1 cu.m

22861.00

VRCC M 30 design mix 5 - 8 m

1 cu.m

22995.00

VRCC M 30 design mix 8 - 11 m

1 cu.m

23129.00

VRCC M 30 design mix 11 - 14 m

1 cu.m

23263.00

VRCC M - 30 design mix using 20 mm HBG metal


for stair case column including centering charges
etc. complete for Tie beam
Cost of VRCC M - 30 design mix for Tie beam

0.30
5404.14

0.20
1 cu.m

5404.14

Centering charges for Column

1099.00

1 cu.m

18320.33

Total
1 Cu.m

RCC Lift charges

23724.50
134.00

1 cu.m

134.00

VRCC M 30 design mix 0 - 5 m

1 cu.m

23724.50

VRCC M 30 design mix 5 - 8 m

1 cu.m

23858.50

VRCC M 30 design mix 8 - 11 m


1 cu.m

1 cu.m

23992.50

1 cu.m
1 cu.m
1 MT
1 cu.m
1 cu.m
1 cu.m
1 cu.m

973.71
398.93
2304.00
1307.99
456.20
92.40
132.70

VRCC M- 20 (1:1 :3) Nominal mix (Cement:fine


aggregate: coarse aggregate) using 12mm size graded
machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as machine
mixing, laying concrete, curing etc.,complete but excluding
cost of steel and its fabrication charges for finished item of
work, but excluding centering, shuttering.

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

0.90
0.45
400
1
1
1.2
1

cu.m
cu.m
Kg
cu.m
Hour
kL
Hour

Cost of 12 mm HBG metal (M/C)


Cost of sand
Cost of cement
Labour charges
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Water charges
Vibrating charges

1081.90
886.50
5760.00
1307.99
456.20
77.00
132.70

Basic Cost

5665.93

VRCC M-20 Nominal mix with 12 mm HBG metal


including c/c of all materials, centering charges etc
complete for steps of thick ness 0.05 m for Steps
1 Cum

0.05

Cost of VRCC M -20 with 12 mm HBG Metal

5665.93

1 cu.m

5665.93

20 Sq.m

Centering charges for Treads

345.00

1 Sq.m

6900.00

40 Sq.m

Centering charges for Rises

345.00

1 Sq.m

13800.00

Basic Cost
1 Cu.m

26365.93

RCC Lift charges

134.00

1 cu.m

134.00

VRCC Steps of M - 20 mix 0 - 5 m

1 cu.m

26365.93

VRCC Steps of M - 20 mix 5 - 8 m

1 cu.m

26499.93

VRCC Steps of M - 20 mix 8 - 11 m

1 cu.m

26633.93

VRCC Steps of M - 20 mix 11 - 14 m

1 cu.m

26767.93

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

LABOUR RATES FOR THE YEAR 2015 - 2016

S.No Description

Skilled

Semiskill
ed

Un
skilled

Water
charge Rural
s @ Areas
1%

Municipal Municipal
areas
Corporation
(20%)
(25%)

Reference

Unit

BLD-CSTN-1-1

1 Cum

0.200

64.00

76.80

80.00

Mixing mortar

Sand filling

1 Cum

0.310

99.20

119.04

124.00

Earth filling

1 Cum

0.520

166.40

199.68

208.00

CC(1:4:8), CC(1:6:10),CC(1:5:10)
Hand mixing

BLD-CSTN-2-1 1 Cum

0.100

2.360

797.20

956.64

996.50

CC(1:4:8), CC(1:6:10),CC(1:5:10)
Machine mixing

BLD-CSTN-2-2 1 Cum

0.100

1.390

486.80

584.16

608.50

RCC (Foundation,Plinth, Pedestal Below plinth lelvel)- Nominal mix

BLD-CSTN-2-13 1 Cum

0.133

0.267

3.600

1307.99

1569.58

1634.98

RCC (Column, Lintels, Water tanks,


BLD-CSTN-2-13 1 Cum
RCC Walls in Buildings) - Nominal mix

0.167

0.167

4.700

1636.77

1964.12

2045.96

RCC Slabs & Beams - Nominal mix

BLD-CSTN-2-13 1 Cum

0.067

0.133

2.500

878.02

1053.62

1097.52

RCC (Foundation,Plinth, Pedestal Below plinth lelvel)- Design mix

BLD-CSTN-2-14 1 Cum

0.133

0.267

4.600

1627.99

1953.58

2034.98

10

RCC (Column, Lintels, Water tanks,


RCC Walls in Buildings) - Design mix

BLD-CSTN-2-14 1 Cum

0.167

0.167

5.600

1924.77

2309.72

2405.96

11

RCC Slabs & Beams - Design mix

BLD-CSTN-2-14 1 Cum

0.067

0.133

3.070

1060.42

1272.50

1325.52

12

Fabrication charges for bars below 36


mm

10.000

7400.00

8880.00

9250.00

13

BM Masonary

1.890

915.60

1098.72

1144.50

14

RR Masonary

15

1 MT

10.000

1 Cum

0.240

BLD-CSTN-4-8 1 Cum

1.200

2.000

1144.00

1372.80

1430.00

CRS Masonary - 1 Sort

1 Cum

2.500

2.320

1792.40

2150.88

2240.50

16

CRS Masonary - 2 Sort

1 Cum

1.500

2.320

1372.40

1646.88

1715.50

17

Flush Pointing

BLD-CSTN-5-2 10 Sq.m

0.500

0.740

446.80

536.16

558.50

18

Raised Pointing

BLD-CSTN-5-2 10 Sq.m

0.500

0.740

446.80

536.16

558.50

19

Plastering 12 mm thick

BLD-CSTN-6-1 10 Sq.m

0.600

0.960

559.20

671.04

699.00

20

Plastering 20 mm thick

BLD-CSTN-6-7 10 Sq.m

0.940

1.600

906.80

1088.16

1133.50

21

Gronolithic Flooring

BLD-CSTN-7-13 10 Sq.m

1.250

0.060

3.000

1507.50

1809.00

1884.38

22

Flooring with Ceramic or Vitrified tiles

10 Sq.m

0.960

2.240

3.000

2225.23

2670.28

2781.54

23

Roofing with 6mm thick Corrugated


AC Sheet

10 Sq.m

0.430

0.540

334.05

400.86

417.56

24

Imperviou coat

BLD-CSTN-8-25 10 Sq.m

0.660

1.540

3.700

2038.70

2446.44

2548.38

25

Painting with Snow cem over primer


coat - 2 Coats (All colours)

BLD-CSTN-10-4 10 Sq.m

0.500

1.500

690.00

828.00

862.50

26

Painting with Snow cem over primer


coat - 1 Coats (All colours)

BLD-CSTN-10-3 10 Sq.m

0.500

1.500

690.00

828.00

862.50

27

White washing One coat

10 Sq.m

0.110

0.220

111.65

133.98

139.56

28

White washing Two coat

10 Sq.m

0.160

0.320

162.40

194.88

203.00

29

Primer coat for New Iron work

294.00

352.80

367.50

BLD-CSTN-3

BLD-CSTN-10-7 10 Sq.m

0.700

0.560

22.03

30
31

Painting New Iron work with One coat BLD-CSTN-10-12 10 Sq.m

0.700

294.00

352.80

367.50

Painting New Iron work with Two


coats of Synthetic enamel paint

1.100

462.00

554.40

577.50

BLD-CSTN-1012

10 Sq.m

LEAD STATEMENT
Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
SSR :
2015-2016
S.No Name of the material
Source
Unit
Lead
Lead
Initial Cost Seigniorage Loading
Unloading
charges
charges

2
Sand Screened
(Plastering etc.,)
Sand for filling

3
Pulikundram

4
1 Cu.m

Km
5
22.00

Rs
6
293.50

Rs
7
677.00

8
40.00

Rs
11
35.17

Rs
12
975.33

Pulikundram

1 Cu.m

20.00

268.70

460.00

40.00

32.20

736.50

Sand Un screened
(Concrete etc.,)

Pulikundram

1 Cu.m

20.00

268.70

610.00

40.00

32.20

886.50

6 to 12 mm HBG
metal (MC)
40 mm HBG metal

GR Kuppam

1 Cu.m

34.00

433.90

650.00

50.00

52.00

1081.90

GR Kuppam

1 Cu.m

34.00

433.90

620.00

50.00

52.00

1051.90

40 mm HBG metal
(MC)
20 mm HBG metal

GR Kuppam

1 Cu.m

34.00

433.90

845.00

50.00

52.00

1276.90

GR Kuppam

1 Cu.m

34.00

433.90

1036.00

50.00

52.00

1467.90

GR Kuppam

1 Cu.m

34.00

433.90

1365.00

50.00

52.00

1796.90

20 mm HBG metal
(MC)
CR Stone

GR Kuppam

1 Cu.m

23.00

305.90

567.90

50.00

30.30

15.15

42.10

927.15

10

RR stone

GR Kuppam

1 Cu.m

23.00

305.90

252.00

50.00

30.30

15.15

42.10

611.25

11

Bond stone

GR Kuppam

1 Cu.m

23.00

305.90

936.51

50.00

30.30

15.15

42.10

1295.76

12

Country Brick
(23 x 11 x 7 cm)
Cement

Local Kiln

1000 No

25.00

530.90

5850.00

38.50

47.60

47.60

75.03

6439.57

1
1
2

5
6
7
8

13

Pichatur

1 MT

5760.00

Rs
9

Rs
10

Deduct
Net rate at
Overheads
site
@ 13.615%
already
included in
6 , 9 & 10

5760.00

6439.57

14

Steel

Pichatur

1 MT

43000.00

43000.00

Certified that the lead allowed in the estimate are correct and shortest to the best of my knowledge

Dy Exe. Engineer
RWS & S Sub Division
Satyavedu - 2

Asst. Engineer,
RWS & S,
Thottembedu

STANDARD SCHEDULE OF RATES 2015-16

S.No

1
2

Description of work

Rates of Materials
Sand for mortar and plastering (excluding
Seigniorage charge) (Screened)
Sand for filling (excluding Seigniorage cahrge) Un
screened
Fine Sand for concrete (excluding Seigniorage
charge) Un screened

Rate

per

2015-2016

Ref

677.00

1 Cu.m

M-005

460.00

1 Cu.m

M-004

610.00

1 Cu.m

M-006

Gravel (Excluding Seigneiorage cahrge)

103.00

1 Cu.m

M-008

Morram (Including Loading charges but excluding


Seigniorage charges)

128.00

1 Cu.m

M-007

12 mm HBG metal

20 mm HBG metal (HBG)

1036.00

1 Cu.m

20 mm HBG metal (Machine Crushed)(Excluding


Seigniorage , including blasting charge Rs. 70/-,
Machine crushing charge 25%)

1365.00

1 Cu.m

40 mm HBG metal

620.00

1 Cu.m

40 mm HBG metal (Machine Crushed)(Excluding


Seigniorage , including blasting charge Rs. 70/-,
Machine crushing charge 25%)

845.00

10

65 mm HBG metal

11
12
13
14
15
16
17
18
19
20

RR stones (Granite) (Including Loading charges but


Excluding Seigniorage charges)
CR stones (Excluding Seigniorage charges) 0.30 x
0.30 x 0.45 size
Bond stones (Including loading charges but
Excluding Seigniorage)
Granite stone slab (High polished 16 to 18 mm black)
Revetment 225 mm (Including Loading charges but
excluding Seigniorage charges)
Bricks Country (23 * 11 * 7 cm) including material
VAT, loading but excluding conveyance, unloading
and stacking
Flay ash Cement Solid blocks class 7.5 of size 290 x
225 x 140 mm
Flay ash Cement Solid blocks class 7.5 of size 290 x
200 x 140 mm
Flay ash Cement Solid blocks class 7.5 of size 290 x
112/100 x 140 mm
Cement (May/13)

1 Cu.m

M-053

M-055
1 Cu.m

252.00

1 Cu.m

M-148

567.90

1 Cu.m

13 Irrigation

936.51

1 Cu.m

77 Irrigation

2352.00

1 Cu.m

BMT-B-11

140.00

1 Cu.m

Misc

5200.00

1000 Nos

BMT-A-01

25.00

1 No

BMT-A-03

23.00

1 No

BMT-A-04

14.00

1 No

BMT-A-06

6400.00

1 MT

M-081

21

Steel (May/13)

42000.00

1 MT

M-179

22

Acco proof powder

Deleted

1 Kg

BMT-H-01

Integral Cement Waterproofing Liquid Conforming to


IS: I.S. 2645-2003

210.00

1 Lt

BMT-H-115

23

Water proof paint cement (Snow cem)

1375.00

25 Kg

BMT-J-26

24

White lime (Surya cem / Janatha cem)

600.00

25 Kg

BMT-J-27

25

Polished black cuddapaha slabs 15 mm thick

1379.00

10 Sq.m

BMT-B-06

26

Mastic pad (0.6m * 1.20m *2.54cm)

991.00

1 Sq.m

BMS-W.20

27

AC Sheet 6mm corrugated

222.00

1 Sq.m

BMT-E.17

28

Water (Rural)

77.00

kL

M-189

29

Water (Urban)

103.00

kL

M-189

Labour cahrges
1

Blasting charges

70.00

1 Cu.m

Blasting charges for RR stone

70.00

1 Cu.m

Hand drilling of holes in Hard granite 20 mm

136.00

1 Rmt

R&B 138

Hand drilling of holes in Hard granite 25 mm

144.00

1 Rmt

R&B 139

Cutting open CC road surface

1822.00

1 Cu.m

PH 25

EW in OG soils SS 20 - A

116.48

1 Cu.m

RBR-FNDN-1

EW in OG soils SS 20 - B

1 Cu.m

EW in HG soils SS 20 - A

1 Cu.m

EW in HG soils SS 20 - B

1 Cu.m

10

Clearing of light jungle

11

Vibrating charges

1 Cu.m

12

Machine mixing charges of concrete

1 Cu.m

13

Mixing of cement mortar

1 Cu.m

14

Machine mixing of cement mortar

1 Cu.m

15

Hoisting & Lowering of slabs

105.00

1 Cu.m

BMS-W-52

16

Refilling with excavated sand (labour charges only)

99.20

1 Cu.m

RBR-FNDN-2

17

Refilling with excavated soil

1 Cu.m

18

Fabrication charges for steel

1 Kg

19

Binding wire

1
2
3
4
5
6

Laying and jointing of PVC pipes (With out Over


head charges)
50mm PVC / HDPE pipe (Including earth work up to
a deptha of 0.50m)
40mm PVC / HDPE pipe (Including earth work up to
a deptha of 0.50m)
32mm PVC / HDPE pipe (Including earth work up to
a deptha of 0.50m)
25mm PVC / HDPE pipe (Including earth work up to
a deptha of 0.50m)
20mm PVC / HDPE pipe (Including earth work up to
a deptha of 0.50m)
63 mm PVC Pipe

2.80

1 Sq.m

70.00

1 Kg

31.00

1 Rmt

31.00

1 Rmt

31.00

1 Rmt

28.00

1 Rmt

26.00

1 Rmt

6.11

1 Rmt

R&B 110

72 Irrigation

PH 12(b)

75 mm PVC Pipe

7.28

1 Rmt

90 mm PVC Pipe

8.73

1 Rmt

110 mm PVC Pipe

10.67

1 Rmt

10

125 mm PVC Pipe

12.13

1 Rmt

11

140 mm PVC Pipe

13.58

1 Rmt

Laying and jointing of GI pipes


Lowering and Jointing G.I. pipes and specials /
fittings including excavation of trench of 0.5m width
and 0.50 m depth in all soils except rock requiring
blasting and refilling trenches after laying and jointing
pipes and also including cost of jointing materials but
excluding the cost of pipes. Reference to
specifications. BIS No.783/85
1

50 mm GI pipe

46.14

1 Rmt

40 mm GI pipe

46.14

1 Rmt

32 mm GI pipe

42.04

1 Rmt

25 mm GI pipe

42.04

1 Rmt

20 mm GI pipe

36.86

1 Rmt

15 mm GI pipe

36.86

1 Rmt

Hire charges for Centering & Scaffolding ( For


Building works) up to 3.66 m with casurina
scaffolding
Footings

750.00

1 Cu.m

Pedestal

1068.00

1 Cu.m

Plinth beam

2476.00

1 Cu.m

Lintel

1713.00

1 Cu.m

Columns

1567.00

1 Cu.m

Beam

2464.00

1 Cu.m

Slabs of 150mm thick

279.00

1 Sq.m

Slabs of thickness ( 150 to 300 mm)

287.00

1 Sq.m

Helical stair case

345.00

1 Sq.m

PHE-LJGI-7

Civil items
Blds SSR

Centering charges ( OHSR)


1

Slabs of thickness (150 to 300 mm)

3260.00

1 Sq.m

Slabs of thickness above 300 mm

6518.00

1 Sq.m

Side walls curved surfaces

2463.00

1 Sq.m

Side walls Straight surface

2192.00

1 Sq.m

Dome

2670.00

1 Sq.m

Roof slab

1643.00

1 Sq.m

Column footing

750.00

1 Cu.m

Columns braces and beams

1099.00

1 Sq.m

Circular braces, ring beam and circular column

1206.00

1 Sq.m

Public health
item 31

Civil items
Blds SSR

Centering charges ( GLSR) Unsupported height


of 3.66 m using casurina, bamboos etc.
1

Bottom slab (Same as Footing)

750.00

1 Cu.m

Building SSR

Roof slabs of 150mm thick

279.00

1 Sq.m

Building SSR

RCC vertical walls - plane surface up to 3m ht.

876.00

1 Sq.m

1115.00

1 Sq.m

134.00

1 Cu.m

4
5

RCC vertical walls - Circular faces up to 3m ht.(30%


extra over Vertical walls)
Lifting of CC for RCC works for every 1mt or part
over the initial lift of 3 m

Public health
item
Public health
item
Public health
item

OTHER ITEMS
1

Red oxide Grade I for iron works

142.00

1 Lt

BMT-J-03

Synthetic enamel paint of all shades Grade - I

276.00

1 Lt

BMT-J-30

Wood primer

158.00

1 Lt

BMT-J-05

White cement

29.00

1Kg

BMS-W.68

Cement Jolli - 25 mm thick

226.00

1 Sq.m

BMS-W-15

Supply of Syntex tank inculuding labour charges

1 Lt

BMS-W-29

450.00

1 Sq.m

BMT-C-54

660.00

1 Sq.m

BMT-C-54

7
8

Non porcelain tiles (Ceramic tiles) 7 to 8mm thick of


size 300 x 300 mm 1 st quality (Floor tiles)
Non porcelain tiles (Ceramic tiles) 6 mm thick of size
200 x 300 mm 1 st quality (Wall tiles)

8.00

Diesel

57.00

1 Lt

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

456.20

1 Hr

892.00

1 Rmt

BMW-F.91

503.00

1 Rmt

BMW-F.89

67.00
466.00
44.00

1 Rmt
1 Rmt
1 Rmt

BMW-F.90
BMW-F.87
BMW-F.88

-Do- 32 mm GI Pipe

417.00

1 Rmt

BMW-F.85

- Do - Labour chrges only

41.00

1 Rmt

BMW-F.86

GI PIPES

3
4

S & F 65 mm Nominal Bore GI pipe Medium Grade


properties & weight as per IS 1239 with GI fittings
such as elbows tees couplings, nipples, plugs
including excavation for trenches and refilling the
trenches complete except for GI bends union and GI
connectors with checkout and socket Tata or Zenith
make or equivalent
a) S& F 50 mm Nominal Bore GI pipe Medium Grade
properties & weight as per IS 1239 ISI mark with GI
fittings including the cost of pipe & its fittings & labour
charges complete
- Do - Labour chrges only
-Do- 40 mm GI Pipe
- Do - Labour chrges only

-Do- 25 mm GI Pipe

297.00

1 Rmt

BMW-F.83

- Do - Labour chrges only

41.00

1 Rmt

BMW-F.84

-Do- 20 mm GI Pipe

227.00

1 Rmt

BMW-F.81

- Do - Labour chrges only

41.00

1 Rmt

BMW-F.82

3812.00

1 No

ELEC-9.5.52

1048.00

1 No

BMW-D.01

1860.00

1 No

BMW-D.13

930.00

1 No

BMW-D.33

Manufacture, Supply and delivery of CI Wafer Lug


type Butterfly Valves conforming to IS 13095/1991
(Reaffirmed 1998) excluding transportation, CED and
taxes etc., complete. Operation done with worm
actuator ISI marked Rate at Ex-Factory
80 mm Valve
Sanitary appliances
Supply and fixing of Indian pattern white glazed WC
with P & S Trap of 580 mm long
Supply and fixing of Europeon WC pattern white
glazed WC with P
Supply and fixing of White glazed flat back bowl
urinals of size 460 x 265 x 315 mm with internal
flushing

Note : Red
indicated
rates as per
Previous
year SSR
Specific
Gravity
Cement

3.15

Sand

2.60

Coarse
Aggregate

2.50

1036.00

620.00

567.90
936.51

As on 6/08

4400

As on
7/08

4400

8-Sep

4600

41500

32.8

44500

50800

116.48

Data

99.20

For dia 20
to 50
earth work
is to be
added

Including Earth work up to 0.5 m


width and 0.50 m depth
50mm dia
nominal
bore
a)
Labour

Qty

Plumber
2nd class

day

0.160

Man
mazdoor

day

0.330

E.W.Excav
ation
&
refilling
b) Material
10x0.50x0.
50=2.50cu
G.I. pipes
m

cum

2.500

10.000

white lead,
hemp yarn,
oil etc.
c)
Machinery

L.S.

for 50 mm & 40 mm
Rate

375.00

Amt

32mm dia
nominal
bore
a)
Labour
Plumber

day

0.120

Man

day

0.250

E.W.Excav
&
refilling
b) Material
10x0.50x0.
50=2.50cu
G.I. pipes
m

cum

2.500

10.000

white lead,
hemp yarn,
oil etc.
c)
Machinery

L.S.

60 2nd class

320.00

105.6 mazdoor

116.48

291.2 ation

Nil

Nil

(d) Total =
a+b+c

(d) Total =
a+b+c

(e) Add for


water
charges @
(f) Total =
1%
on
d+e
Labour &
(g) Overheads & Contractors Profit
Testing
Charges
(h) Cost for
100
rmt
(f+g)

Qty

(e) Add for

4.57 water

charges @
(f) Total =
1%
on
d+e
Labour &
(g) Overheads & Contractors Profit
Testing
Charges
(h) Cost for
100
rmt
(f+g)

Rate
rmt
h/100

per
=

Rate

46.14 rmt

h/100

per
=

BMW-G.01 Rs (6+ 1)

actors Profit

for 32 mm & 25 mm
Rate

Amt

for 20 mm & 15 mm
20mm dia
nominal
bore
a)
Labour
Plumber

day

0.060

Man

day

0.160

E.W.Excav
&
refilling
b) Material
10x0.50x0.
50=2.50cu
G.I. pipes
m

cum

2.500

10.000

white lead,
hemp yarn,
oil etc.
c)
Machinery

L.S.

375.00

45 2nd class

320.00

80 mazdoor

116.48

Qty

291.2 ation

Rate

Amt

375.00

22.5

320.00

51.2

116.48

291.2

Nil
(d) Total =
a+b+c
(e) Add for

4.16 water

charges @
(f) Total =
1%
on
d+e
Labour &
(g) Overheads & Contractors Profit
Testing
Charges
(h) Cost for
100
rmt
(f+g)

3.65

Rate

42.04 rmt

h/100

per
=

36.86

STANDRAD SCHEDULE OF RATES 2015-2016


Supply and delivery of UPVC pipes for drinking water supplies confirming IS : 4985/2000 with socket
including transportation chrges, including CED and Cess but excluding VAT @ 5% (Resin Cost Rs.
79,179/- per MT as per PH SSR)
Month

Dia
(mm) /
mm
63/4
75/4
90/4
110/4
125/4
140/4
160/4
180/4
200/4
225/4
250/4
280/4
315/4
63/6
75/6
90/6
110/6
125/6
140/6
160/6
180/6
200/6
225/6
250/6
280/6
315/6

July-15

Test pressure
Kg/C m2
4
4
4
4
4
4
4
4
4
4
4
4
4
6
6
6
6
6
6
6
6
6
6
6
6
6

Present
Resin Cost

71214.00

Revised Cost of
Basic Cost
PVC pipe as
as per 2014per new resin
15 SSR
cost
1 Rmt
56.00
82.00
111.00
162.00
211.00
264.00
348.00
443.00
539.00
716.00
833.00
1090.00
1380.00
81.00
110.00
160.00
231.00
295.00
380.00
492.00
634.00
772.00
1034.00
1269.00
1603.00
2015.00

1 Rmt
56.00
82.00
111.00
162.00
211.00
264.00
348.00
443.00
539.00
716.00
833.00
1090.00
1380.00
81.00
110.00
160.00
231.00
295.00
380.00
492.00
634.00
772.00
1034.00
1269.00
1603.00
2015.00

CED

Cess

@ 12%
6.72
9.84
13.32
19.44
25.32
31.68
41.76
53.16
64.68
85.92
99.96
130.80
165.60
9.72
13.20
19.20
27.72
35.40
45.60
59.04
76.08
92.64
124.08
152.28
192.36
241.80

@ 3%
0.20
0.30
0.40
0.58
0.76
0.95
1.25
1.59
1.94
2.58
3.00
3.92
4.97
0.29
0.40
0.58
0.83
1.06
1.37
1.77
2.28
2.78
3.72
4.57
5.77
7.25

Total

62.92
92.14
124.72
182.02
237.08
296.63
391.01
497.75
605.62
804.50
935.96
1224.72
1550.57
91.01
123.60
179.78
259.55
331.46
426.97
552.81
712.36
867.42
1161.80
1425.85
1801.13
2264.05

Descsription
Manufacture, Supply and delivery of of Cast Iron pipes and Fittings (Spls.,) confirmed to IS
No. 7181/1986, 5531/1988, 3950/1979 and CID joints confirming to IS No. 8794/1988 at site
of work any where in AP including, Loading, Unloading, Transportation to site of work
stacking at site transit risk and package, excluding taxes and duties.

Rate / Kg

73.70

Weight of PVC Pipes


Month
Existing price of raw material per MT(A1) as
per SSR
Revised price of raw material per MT(A2)
Revised Price (P2)
CED %
ED Cess %
VAT %

Chapter 39 / 3917
http://www.eximguru.com
plastemart.com

July-15
71214.00
71214.00
P1+(A2-A1)/1000*M*0.95
12
3
5

Dia of pipe
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
380
315
355
400

Wt of Pipe in Kg/m (M)


4 Kg/ Sq.Cm

0.468
0.655
0.924
1.323
1.722
2.144
2.799
3.581
4.331
5.511
6.674
8.453
10.682

Wt of Pipe in Kg/m (M)


6 Kg/ Sq.Cm 10 Kg/ Sq.Cm Month

0.666
0.923
1.321
1.902
2.511
3.116
4.012
5.134
6.351
7.975
9.886
12.4
15.72

1.01
1.439
2.032
3.062
3.929
4.905
6.414
8.092
10.001
12.675
15.586
19.616
24.732

June-15
July-15
August-15
September-15
October-15
November-15
December-15
January-16
February-16
March-16
April-16
May-16
June-16

Resin Cost

With effect from

71214
71214

5760

Gauge

RATES OF PVC PIPES FOR THE MONTH 2015-2016


Month
Jul-15 Resin cost
Basic Rate Revised rate
Dia of Pipe
CED
ED cess
(P1)
(P2)
mm
RS
Rs
12%
3%

Rs. 71214.00
VAT%
5%

Total

4 Kg/Sq.cm

20

4 Kg/Sq.cm

25

4 Kg/Sq.cm

32

4 Kg/Sq.cm

40

4 Kg/Sq.cm

50

4 Kg/Sq.cm

63

56.00

56.00

6.72

0.20

3.15

66.07

4 Kg/Sq.cm

75

82.00

82.00

9.84

0.30

4.61

96.75

4 Kg/Sq.cm

90

111.00

111.00

13.32

0.40

6.24

130.96

4 Kg/Sq.cm

110

162.00

162.00

19.44

0.58

9.1

191.12

4 Kg/Sq.cm

125

211.00

211.00

25.32

0.76

11.85

248.93

4 Kg/Sq.cm

140

264.00

264.00

31.68

0.95

14.83

311.46

4 Kg/Sq.cm

160

348.00

348.00

41.76

1.25

19.55

410.56

4 Kg/Sq.cm

180

443.00

443.00

53.16

1.59

24.89

522.64

4 Kg/Sq.cm

200

539.00

539.00

64.68

1.94

30.28

635.90

4 Kg/Sq.cm

225

716.00

716.00

85.92

2.58

40.23

844.73

4 Kg/Sq.cm

250

833.00

833.00

99.96

3.00

46.8

982.76

4 Kg/Sq.cm

380

1090.00

1090.00

130.80

3.92

61.24 1285.96

4 Kg/Sq.cm

315

1380.00

1380.00

165.60

4.97

77.53 1628.10

4 Kg/Sq.cm

355

1814.00

1814.00

217.68

6.53

101.91 2140.12

4 Kg/Sq.cm

400

2288.00

2288.00

274.56

8.24

128.54 2699.34

6 Kg/Sq.cm

20

6 Kg/Sq.cm

25

6 Kg/Sq.cm

32

6 Kg/Sq.cm

40

34.00

34

4.08

0.12

1.91

40.11

6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm

50
63
75
90
110
125
140
160
180

50.00
81.00
110.00
160.00
231.00
295.00
380.00
492.00
634.00

50
81
110
160
231
295
380
492
634

6
9.72
13.2
19.2
27.72
35.4
45.6
59.04
76.08

0.18
0.29
0.4
0.58
0.83
1.06
1.37
1.77
2.28

2.81
4.55
6.18
8.99
12.98
16.57
21.35
27.64
35.62

58.99
95.56
129.78
188.77
272.53
348.03
448.32
580.45
747.98

6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
6 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm
10 Kg/Sq.cm

200
225
250
380
315
355
400
20
25
32
40
50
63
75
90
110
125
140
160
180
200
225
250
380
315

772.00
1034.00
1269.00
1603.00
2015.00
2633.00
3351.00
16.00
23.00
36.00
55.00
84.00
122.00
176.00
249.00
372.00
485.00
602.00
789.00
1010.00
1230.00
1645.00
2002.00
2534.00
3198.00

772
1034
1269
1603
2015
2633
3351
16.00
23.00
36.00
55.00
84.00
122.00
176.00
249.00
372.00
485.00
602.00
789.00
1010.00
1230.00
1645.00
2002.00
2534.00
3198.00

92.64
124.08
152.28
192.36
241.8
315.96
402.12
1.92
2.76
4.32
6.60
10.08
14.64
21.12
29.88
44.64
58.20
72.24
94.68
121.20
147.60
197.40
240.24
304.08
383.76

2.78
3.72
4.57
5.77
7.25
9.48
12.06
0.06
0.08
0.13
0.20
0.30
0.44
0.63
0.90
1.34
1.75
2.17
2.84
3.64
4.43
5.92
7.21
9.12
11.51

43.37
58.09
71.29
90.06
113.2
147.92
188.26
0.9
1.29
2.02
3.09
4.72
6.85
9.89
13.99
20.9
27.25
33.82
44.33
56.74
69.1
92.42
112.47
142.36
179.66

910.79
1219.89
1497.14
1891.19
2377.25
3106.36
3953.44
18.88
27.13
42.47
64.89
99.10
143.93
207.64
293.77
438.88
572.20
710.23
930.85
1191.58
1451.13
1940.74
2361.92
2989.56
3772.93

51

4.2024

mar
503.56
20.1424

471.09
18.8436

STANDRAD SCHEDULE OF RATES 2015-2016


Rates of OHSR including
fixtures wilth a stagging of
10 m
10000
15000
20000
40000
60000
90000
100000
120000
150000
200000
250000
300000
350000
400000
450000

Rate / Lt
65.56
45.09
44.31
39.22
29.76
28.04
27.47
26.79
25.76
24.05
23.31
22.57
21.24
19.90
17.25

Values were interpolated


NOTE :
The above rates are applicable for Raft foundation with Spiral stair case out
side the Reservoir.
Cement - Rs. 6400Mt
Steel - Rs. 42000 / 1 Mt
The structure is M-30 Grade Concrete
For staging
For every metre of stagging less than 10 m Reduce - 0.05 Ps per litre
For every metre of stagging more than 10 m Increase - 0.10Ps per litre
Variation in cost of cement = (Rc - 6400) * 0.00007*Basic rate
Variation in cost of steel = (Rs - 42000)* 0.00002*Basic rate
For Rural areas the above rates are incresed by 10%
The above rates for wind pressure up to 350 Kg/Sq.m for decrease in wind
pressure the rate has to be decreased by 5% for every 100 Kg/Sq.m

6400
42000

PHE

Statement Showing Comparative Data


Drinking Water Supply Schemes (Public Health)
Index-code

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day
day

3.000
3.000

420.00
375.00

1260.00
1125.00

Hire chargers for Hydralic field test pressure testing including days
transportation of water @ Rs. 1200/- (1000+200) / day

3.000

1
Sub Analysis

PHE-LCIF-2A

2 A Sub Analysis : (Basic Data)


OBSERVED DATA FOR TESTING OF 450 MM DIA PSC MAIN :
Pumping main to Hydralic field test pressure including
transportation of Water with minimum lead of 500 M

(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Labour
Fitters (2 x 3 days)
Fitters I Class
Fitters II Class
Machinery

Materials
Nos
Pressure guage
RM
3/4" G.I. Pipe (20 mm)
Ls
Specials
No.
Dummies
Lts.
Diesel (2 Lts. / Hr) 30 Hrs.
(T) Total Rate per 500 Mts.
(r) Rate per 1 Rmt for 450 mm dia
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
Note : Proportionate Testing Charges may be arrived,
keeping the diametre of pipe based on this analysis, for an
varities of pipes for various Dia Pipes.
11

PHE-LJUP-11

0.050
3.000

186.00

558.00

0.100
57.000

57.00

3249.00
9392.00
18.78
0.42

Lowering, laying, jointing and testing to hydralic test pressure


including cost of water with minimum water lead of 500m for
UPVC pressure pipes in ready made trenches true to alignment
and gradient including all sundries but excluding cost &
conveyance of pipes from source of supply and jointing materials
as per BIS No. 7634 - Part III - 1975
Sub Analysis for 160 mm Dia :
Taking output : Length - 500 m ; Joints - 83 Nos
(a) Labour
For lowering / sub surface transport
day
Mazdoor
Jointing
day
Fitter
day
Mazdoor
Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and labour,
Materials needed for testing (as per Sub Analysis 2 A)
Total
(b) Material
Add for Water charges at 1% on Labour & Testing
(c) Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/500
Rate per 10 mm / 1rm

All Classes pipes :

63 mm dia pipe
Weight of 1m length = (0.468+0.666+1.01)/3 =0.715 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3 =1.005 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit

ii

3200.00

7.000

320.00

2240.00

2.000
4.000

420.00
320.00

840.00
1280.00

500.000

6.72

3360.00

Lt

77.20
7797.20
15.59
0.97

rm

6.300

0.97

6.11

rm

7.500

0.97

7.28

864

Index-code

S No
1
iii

iv

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

rm

9.000

0.97

8.73

rm

11.000

0.97

10.67

rm

12.500

0.97

12.13

Rate per metre a+b


90 mm dia pipe
Weight of 1m length = (0.924+1.321+2.032)/3 =1.426 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
110 mm dia pipe
Weight of 1m length = (1.323+1.902+3.062)/3 =2.096 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
125 mm dia pipe
Weight of 1m length = (1.722+2.511+3.929)/3 =2.72 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b

865

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

rm

14.000

0.97

13.58

rm

16.000

0.97

15.52

rm

18.000

0.97

17.46

rm

20.000

0.97

19.40

rm

22.500

0.97

21.83

rm

25.000

0.97

24.25

rm

28.000

0.97

27.16

rm

31.500

0.97

30.56

day

4.000

day
day

1.000
2.000

day
day
day

1.000
2.000
1.000

vi

140 mm dia pipe


Weight of 1m length = (2.144+3.116+4.905)/3 =3.388 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
vii 160 mm dia pipe
Weight of 1m length = (2.799+4.012+6.414)/3 =4.408 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
viii 180 mm dia pipe
Weight of 1m length = (3.581+5.134+8.092)/3 =5.602 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
ix 200 mm dia pipe
Weight of 1m length = (4.331+6.351+10.001)/3 =6.894 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
x 225 mm dia pipe
Weight of 1m length = (5.511+7.975+12.675)/3 =8.72 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
xi 250 mm dia pipe
Weight of 1m length = (6.674+9.886+15.666)/3 =10.742 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
xii 280 mm dia pipe
Weight of 1m length = (8.453+12.404+19.616)/3 =13.491 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
xiii 315 mm dia pipe
Weight of 1m length = (10.682+15.723+24.732)/3 =17.046 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
12

PHE-LJHE-12

Laying and jointing of HDPE pipes by butt fusion welding as per


IS:7634 part-II/1975 as amended from time to time to the
alignment and gradient and testing the pipeline to the required
pressure.
Note : Specialized labour is needed for execution of laying &
jointing for HDPE Pipes with buttfusion welding technique as per
IS Specification.

63 mm Dia
Taking output : Length - 480 m ; Joints - 40 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total

866

Index-code

PHE

S No
1

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

1.000

Lt
Lt
Lt
day

4.000
8.000

day

4.000

day
day

1.000
2.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

4.000
8.000

day

5.000

day
day

1.000
2.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

5.000
8.000

day

6.000

day
day

1.000
2.000

(b) Machinery

Hirecharges of Generator Set & Hydraulic Testing Equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/480
ii

1.000

75 mm Dia
Taking output : Length - 456 m ; Joints - 38 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/456
iii

90 mm Dia
Taking output : Length - 432 m ; Joints - 36 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/432
iv

1.000

1.000

110 mm Dia
Taking output : Length - 384 m ; Joints - 32 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor

867

Index-code

PHE

S No
1

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

6.000
8.000

day

7.000

day
day

2.000
3.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

7.000
8.000

day

7.000

day
day

2.000
3.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

8.000
8.000

Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/384
v

1.000

125 mm Dia
Taking output : Length - 348 m ; Joints - 29 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/348
vi

1.000

140 mm Dia
Taking output : Length - 300 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/300

1.000

868

Index-code

S No
1
vii

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

7.000

day
day

2.000
4.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

9.000
8.000

day

8.000

day
day

2.000
4.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

10.000
8.000

day

10.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

11.000
8.000

160 mm Dia
Taking output : Length - 303 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/303
viii 180 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total Labour
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

ix

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
200 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
225 mm Dia

1.000

1.000

1.000

869

Index-code

S No
1

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

10.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

12.000
8.000

day

11.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

13.000
8.000

day

12.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

14.000
8.000

Taking output : Length - 216 m ; Joints -18 Nos


(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

xi

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
250 mm Dia
Taking output : Length - 216 m ; Joints - 18 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
xii 280 mm Dia
Taking output : Length - 192 m ; Joints - 16 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/192
xiii 315 mm Dia

1.000

1.000

1.000

Taking output : Length - 180 m ; Joints - 15 Nos

870

Index-code

S No
1

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

12.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

15.000
8.000

day

14.000

day
day

2.000
8.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

16.000
8.000

day

0.600

day

1.400

day

3.000

day

1.000

each/
rm
t/kg

50.000

cum

0.045

kgs

4.500

(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/180
xiv 355 mm Dia

1.000

Taking output : Length - 144 m ; Joints - 12 Nos


(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/144
13

PHE-LJSW-13

1.000

Lowering and laying in ready made trench true to alignment and


gradient, jointing, and testing of stone ware pipes including cost of
jointing material such as cement mortar (1:1) proportion and hemp yarn
but excluding cost and conveyance of pipe. (Reference to specifications
BIS No. 6530/72)

Detail cost for 30 meters


100 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
100 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b

0.065

871

Index-code

S No
1

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

0.900

day

2.100

day

4.000

day

1.000

each

50.000

0.097

cum

0.068

kgs

9.000

day

1.050

day

2.450

day

4.500

day

1.250

each
t

50.000
0.130

(d) Add for water charges @ 1% on Labour & Testing


Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
ii

iii

iv

150 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
150 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
200 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
200 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
230 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
230 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges

cum

0.091

kgs

12.000

day

1.200

day

2.800

day

5.000

day

1.500

each

50.000

0.146

cum

0.102

kgs

13.500

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30

872

Index-code

PHE

S No
1
v

vi

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

250 mm dia
(a) Labour
Mason 1st class

day

1.350

Mason 2nd class

day

3.150

Man mazdoor
Woman mazdoor (Water carrier)
b) Material
250 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges

day

5.500

day

1.500

each

50.000

0.162

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
300 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
300 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vii 350 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
350 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges

cum

0.113

kgs

15.000

day

1.500

day

3.500

day

6.000

day

1.500

each

50.000

0.194

cum

0.136

kgs

18.000

day

1.650

day

3.850

day

7.000

day

1.750

each
t

50.000
0.225

cum

0.159

kgs

21.000

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30

873

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

(a) Labour
Mason 1st class

day

1.800

Mason 2nd class

day

4.200

Man mazdoor
Woman mazdoor (Water carrier)
b) Material
400 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges

day

8.000

day

1.750

each

50.000

0.256

viii 400 mm dia

ix

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
450 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
450 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges

cum

0.181

kgs

24.000

day

2.100

day
day
day

4.900
10.000
2.000

each
t

50.000
0.293

cum

0.204

kgs

27.000

day

0.465

day

1.094

day

2.480

kgs

35.470

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30

PHE-CISP14(sub_analys
is)

14

Sub Analysis :
Labour charges for laying in position S&S or flanged C.I.
specials such as tees, bends, collars tapers and caps etc
10 No. Tees of 200x150mm dia
Weight = 10x70kgs = 700 kgs
(a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
Cost for 700 kgs
Cost for 1kg

PHE-CISV-15

15

Lowering, keeping in position and fixing C.I. sluice valves (with cap / with
hand wheel & reflex valves) excluding cost of bolts, nuts, rubber
insertion, sluice valve and tail pieces

Details of cost for 1No


80 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex valves
- Weight (32.3+34.1+40)/3=35.47

ii

Overheads & Contractors Profit


Rate per 1 Sluice valve
100 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - Weight (44.3+47+50)/3=47.1

47.100

(g) Overheads & Contractors Profit


Rate per 1 Sluice valve

874

Index-code

S No
1
iii

iv

vi

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

125 mm dia meter


(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - Weight (56.3+59+70)/3=61.77
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
150 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (72.5+77+90)/3=79.83
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
200 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (121.5+128.6+145)/3=131.7
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
250 mm dia meter
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (179.9+186.6+195)/3=187.16

(g) Overheads & Contractors Profit


Rate per 1 Sluice valve
vii 300 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (242.4+257+300)/3=266.46
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
viii 350 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (430+470)/2=450

ix

xi

Overheads & Contractors Profit


Rate per each
400 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (525+580)/2=552.5
Overheads & Contractors Profit
Rate per each
450 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (635+810)/2=722.5
Overheads & Contractors Profit
Rate per each
500 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (775+900)/2=837.5

Overheads & Contractors Profit


Rate per each
xii 600 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - (1220+1625)/2=1422.5

61.770

79.830

131.700

187.160

266.460

450.000

552.500

722.500

837.500

1422.500

Overheads & Contractors Profit


Rate per each

875

Index-code

PHE-DAAV-16

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

kgs

20.000

day

0.180

day
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
Labour charges for fixing Air valves including boring the mains
and threading the bore fixing nipple etc., complete.

0.180

16
Providing and fixing double acting air valves including boring the
A main threading the bore and fixing nipple etc.,excluding the cost

of rubber insertions, bolts & nuts, air valve & flanged tail pieces
complete
Details of cost for each
i

16
B
i

ii

17

PHE-SFHD-17

50 mm dia meter
(a) Labour
Labour for laying air valve
Plumber 2nd class

Unit each
40 mm dia
(a) Labour
Lowering charges for air valve
Boring main & threding etc
Plumber 2nd class
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
25 mm dia
(a) Labour
Lowering charges for air valve
Boring main & threding etc
Plumber 2nd class
Man mazdoor
Overheads & Contractors Profit
Rate per each valve

kgs

27.000

day

0.140

day

0.140

kgs

20.000

day

0.110

day

0.110

Providing and fixing spindle fire hydrant with 65 mm outlet.


Complete with bolts, nuts, and rubber insertion etc. complete but
excluding cost of Materials.
Details of cost for 1fire hydrants

PHE-DSFH-18

65 mm dia
(a) Labour
day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each fire hydrant
Note : For other sizes proportionately allow the Data.
18 Dismantling of spindle fire hydrant including stacking of useful
materials within 50m lead
Details of cost for 10 Nos
65 mm dia
(a) Labour
Fitter 1st class
Fitter 2nd class
Man mazdoor
Overheads & Contractors Profit
Rate per each

0.750
1.750
4.000

day

0.750

day

1.750

day

4.000

876

Index-code

PHE-URCI-19

S No

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

19

Uprooting of C.I. pipes by melting lead, loosening the joints, separating


the
pipes, hoisting and keeping within a lead of 10 metres but
excluding earth work excavation and refilling

day

0.500

day

4.000

q
litre

0.373
0.379

day

0.630

day

4.500

ii

iii

iv

Details of cost for 40.26 m


80mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
100mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
125mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
150mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
200mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

0.466

litre

0.379

day

0.760

day

5.000

0.559

litre

0.562

day

0.830

day

5.500

0.663

litre

0.568

day

1.100

day

6.500

0.840

litre

0.757

877

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

1.300

day

7.500

vi

250mm dia metre


(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
vii 300mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
viii 350mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
ix 400mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
x 450mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

1.026

litre

1.137

day

1.500

day

8.500

1.120

litre

1.515

day

1.750

day

9.500

1.231

litre

1.515

day

2.000

day

10.500

1.306

litre

1.894

day

2.250

day

11.500

1.400

litre

2.273

878

Index-code

S No
1
xi

xii

20

PHE-URRC-20

ii

iii

iv

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

500mm dia metre


(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
600mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

day

2.500

day

12.500

1.492

litre

2.652

day

3.000

day

14.500

1.580

litre

3.410

day

0.100

day

0.400

day

0.450

day

0.100

day

0.490

day

0.560

day

0.100

day

0.490

day

0.670

day

0.100

day

0.490

day

0.790

Uprooting of R.C.C. Pipes including breaking the collars, loosing


the joint, scraping the pipe, hoisting and keeping within a lead of
10 M but excluding earthwork excavation and refilling
Taking output 10.00 Rmt
100mm dia
(a) Labour
Fitter 2nd class
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
150mm dia
(a) Labour
Fitter 2nd class
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
225mm dia
(a) Labour
Fitter 2nd class
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
300mm dia
(a) Labour
Fitter 2nd class
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10

879

Index-code

S No

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

21

Uprooting of old S.W. pipes including breaking of joints and bed


concrete stacking of useful materials near the site with in 50m
lead and disposal of un serviceable materials in to municipal
dumps excluding the cost of earth work excavation. (Reference
to specifications BIS No.)

day

0.490

day

0.360

day

0.490

day

0.450

day

0.490

day

0.510

day

0.490

day

0.540

day

0.490

day

0.570

day

0.490

day

0.630

day
day

0.490
0.690

PHE-URSW-21

Details of cost for 10 m


100mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10

ii

150mm dia metre


(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
iii 200mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
iv 230mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
v 250mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
vi 300mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
vii 350mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10

880

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

0.660

day

0.750

day

0.660

day

0.810

day

0.130

day

0.260

day

0.060

day

0.060

day

0.080

day

0.080

day

0.110

day

0.110

day

0.150

day

0.150

viii 400mm dia metre

PHE-URGI-22

(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ix 450mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
22 Removing old G.I.pipes and specials / fittings and cleaning,
scraping the pipes, hoisting and keeping with in 50m lead but
excluding earth work excavation of trenches and refilling
Details of cost for 10 m
15 to 40mm dia
(a) Labour
Plumber
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ii Above 40mm dia
(a) Labour
Plumber
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
23 Cutting C.I. / D.I. pipes without water in mains
Details of cost for one cutting
i
80 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
ii 100 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
iii 125 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
iv 150 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
i

PHE-CCIP-23

881

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

0.200

day

0.200

day

0.250

day

0.250

day

0.300

day

0.300

day

0.350

day

0.350

day

0.400

day

0.400

day

0.450

day

0.450

day

0.500

day

0.500

day

0.600

day

0.600

200 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
vi 250 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
vii 300 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
viii 350 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
ix 400 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
x 450 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
xi 500 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
xii 600 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m

PHE-DTCI-24

24

ii

iii

Drilling and tapping C.I./D.I. main and fixing brass screw down
ferrule and C.I.mouth cover.(Labour charges only)
Details of cost for one no
15 mm dia
(a) Labour
day
Plumber
(b) Overheads & Contractors Profit
Rate per each m
20 mm dia
(a) Labour
day
Plumber
(b) Overheads & Contractors Profit
Rate per each m
25 mm dia

0.130

0.150

882

Index-code

PHE-SHST-25

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

0.170

day

0.570
1.100

(a) Labour
Plumber
(b) Overheads & Contractors Profit
Rate per each m
25 Shoring and strutting of trenches for water and sewer lines
(A) Single staging from 0 to 8-0 ( 0 to 2.5 Metre)

Depth not exceeding 1.5 M


Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 sqm
(a) Labour
Carpenter 2nd class
Man mazdoor
b) Material
Polling boards and ballies
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038)
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5

day
sqm
cum
cum

DeductCredit for materials after use @ 80% of the cost of materials


=0.8 x X

c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(B) Double staging from 8 to 14 ( 2.5 to 4.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 Sqm
(a) Labour
Carpenter 2nd class
Man mazdoor
b) Material
Polling boards and ballies
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038 =
0.57 cum)

day
day

0.500
1.320

sqm
cum

0.110

Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 = 1.1 cum
cum

0.220

Deduct Credit for materials after use @ 80% of the cost of


materials = 0.8 x X
c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(C) Triple staging beyond 14 for every 2 meter (beyond 4.5 M)
Depth not exceeding 1.5 M.
Note : Add for every 2 Mts (difference of single and double
staging) for staging beyond 4.5 mts.
26

PHE-BHLW-26

Barricading, hoarding, lighting and watching etc., for water


supply and sewerage works for trenches of depths upto 6-0 (2
Meter) below G.L
Taking output 3 Rmt
Material
Bamboos of 1 dia 2.5 M long (5 ft c/c = 3 x 2.5)
Baboom of 1 dia 3.66 M long (5 ft c/c = 3x 3.66)
Cost of Bamboos
(a) Usage of Material 5 times. Thus Cost of Material taken as
20%

rmt
rmt

7.50
10.98

883

Index-code

S No
1

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

0.500

day

0.750

day

0.250

day

2.000

day

2.000

each
m

1.000
0.500

cum

0.920

cum

0.100

(b) Labour
Man mazdoor
(c) Sundries for Coir rope, nails, @ 1%
(d) Sundries for lighting and watching etc at 1%
Overheads & Contractors Profit
Cost for 3rmt (a+b+c+d)
Rate per each rmt = (a+b+c+d)/3
27

PHE-RCVS-27

Providing RCC spun vent shaft with cowl 140 mm and 200 mm internal
and external dia respectively at top, 300 and 450 mm internal and
external dia respectively at bottom and 9.10m overall length. Bottom
1.25 m below ground level fixed in a pit 90cmx90cm x150 cm with
cement concrete 1:4:8, 25cm in bed and minimum 20cm all-round with
top 15cm in cement concrete 1:2:4. Junction of vent shaft and concrete
grouted with cement mortar 1:1 including making connection with sewer
manhole with 150 mm dia metre cement concrete pipe of required
length complete as per standard design

Details of cost for one vent shaft


(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor (bhandani)
Man mazdoor (beldar)
b) Material
RCC went shaft with cowl
RCC pipe 150 mm dia 0.50 m (NP-2 class)
Cement Concrete 1:4:8(plain)
0.90 x 0.90 x 135 = 1.094 cum
Less for shaft 22/7 x 4 x 0.452 x 1.1= 0.175cum = 0.919 cum
Cement Concrete 1:2:4 (plain)
0.90 x 0.90 x 0.15 = 0.122 cum
Less for shaft 22/7x4 x 0.452 x 0.15= 0.024cum = 0.098 cum
(c) Total (a+b)
(d) Add for water charges @ 1% on Labour & Testing
Charges on Labour Charges

PHE-WSNP-28

1%

(e) Total = c+d


(f) Overheads & Contractors Profit
(g) Cost for 1 No = e+f
Well Sinking
28 Well sinking in sandy and other loose soils under water either by
manual labour, divers or dredgers weighting the top of staining to
assist sinking etc., including dewatering and other incidental
charges such as hire charges for mechanical equipment etc.,
complete upto 4.0 m dia (For non perennial rivers)
i

ii

iii

Upto 2.0 m below G.L. :


(a) Labour
Man mazdoor
(b) Total
Rate per Rm = b/2
2.0 to 4.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
4.0 to 6.0 m below G.L. :
(a) Labour

day

105.000

day

70.000
35.000

day
hour
hour
hour
L

16.000
56.000
56.000
70.000

884

Index-code

PHE-WSOW29

PHE

S No

Description

Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iv 6.0 to 8.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
v 8.0 to 10.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
29 Sinking of RCC 12 m dia well in sandy soils, soft disintegrated
rock, loamy and clayey soils etc; under water by manual or
mechanical means including dewatering until the completion of
sinking of the well to the required depth, the dummies of the
weep holes pipes are opened for seepage of water into well,
including all hire charges complete as per SS and as directed by
the departmental officers (Open well excavation)

ii

Upto 2.0 m below G.L. :


(a) Labour
Man mazdoor
(b) Total
Rate per Rm = b/2
2.0 to 4.0 m below G.L. :
(a) Labour
Man mazdoor
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

56.000
35.000

day
hour
hour
hour
L

day
day
hour
hour
hour
L

day
day
hour

56.000
56.000
56.000
105.000

56.000
35.000
56.000
56.000
56.000
140.000

64.000
40.000

64.000
64.000
64.000
140.000

day

168.000

day

178.000
11.000

hour
hour

day
hour
hour
L

88.000
88.000
440.000

885

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day

157.000
48.000
12.000

iii

PHE-WSPR-30

4.0 to 6.0 m below G.L. :


(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iv 6.0 to 8.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
v 8.0 to 10.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
vi 10.0 to 12.85 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2.85
30 Well sinking in sandy and other loose soils under water either by
manual labour, divers or dredgers weighting the top of steining to
assist sinking etc., including dewatering and other incidental
charges such as hire charges for mechanical equipment etc.,
complete upto 7 m dia (In Perennial Rivers only)

Upto 2.0 m below G.L. :


(a) Labour
Man mazdoor
Well sinkers
b) Machinery

day
day
hour
hour
hour
L

day
day
day
hour
hour
hour
L

day
day
day
hour
hour
hour
L

day
day
day
hour
hour
hour
L

day
day

96.000
102.000
96.000
1056.000

195.000
120.000
15.000
120.000
124.000
120.000
1334.000

272.000
204.000
17.000
124.000
124.000
136.000
1344.000

360.000
288.000
24.000
192.000
198.000
160.000
2148.000

32.000
64.000

886

Index-code

S No
1

ii

iii

iv

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

day
Hire charges of set of Helmets & Air circulating pipes / valves
4.00
hour
Hire charges for crane
32.00
hour
Hire charges for compressors
32.00
L
Diesel
120.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
2.0 to 4.0 m below G.L. :
(a) Labour
day
Man mazdoor
40.000
day
Well sinkers
80.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
5.00
hour
Hire charges for crane
40.00
hour
Hire charges for compressors
40.00
L
Diesel
150.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
4.0 to 6.0 m below G.L. :
(a) Labour
day
Man mazdoor
48.000
day
Well sinkers
96.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
6.00
hour
Hire charges for crane
48.00
hour
Hire charges for compressors
48.00
L
Diesel
180.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
6.0 to 8.0 m below G.L. :
(a) Labour
day
Man mazdoor
56.000
day
Well sinkers
112.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
7.00
hour
Hire charges for crane
56.00
hour
Hire charges for compressors
56.00
L
Diesel
210.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
8.0 to 10.0 m below G.L. :
(a) Labour
day
Man mazdoor
64.000
day
Well sinkers
128.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
8.00
hour
Hire charges for crane
64.00
hour
Hire charges for compressors
64.00
L
Diesel
240.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
Note : This data shall be adopted for well sinking in perennial rivers.
For other rivers, data available for 4.0 m dia infiltration well may be
adopted for guidance

887

Index-code

PHE-CCCP-31

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

31

Curing of CC pavement for 21 days including cost and


conveyance of water, labour charges, etc., complete

day

42.000

Areas Considered 3 . 5 x 100 mts = 350 sqm


Units = 1 sqm
Mud quantity is required = 14% of CC area x 5 cm
(a) Labour
Man mazdoor (21 x 2).
b) Machinery
Carting earth for 3 kms
Hire charges for Water Drum (5 x 21 days)
c) Material
Earth Work (100 x 3.5 x 14/100 x .05)
Supply of Water (240 Lts / cum / day)
Overheads & Contractors Profit
(d) Total = a+b+c
Rate per sqm =d/350

cum

2.450

each

105.000

cum

2.450

18900.000

Note : 1. When Curing compound is used @ 1.97 kgs/cum, water

requirement is 206 Lts / cum per 14 days.


2. This data is for urban areas only

PHE-CSHR-32

32

Cutting sheet rock including stocking of excavated material.


Quality of sheet rock as per stock measurement = 36.53 cumm
(taking out put = 36.53 cum)

PHE-EXRW-33

(a) Labour
Man mazdoor
b) Machinery
Drilling of holes
Hire charges for JCB
MS Nokkulu
Overheads & Contractors Profit
(c) Total = a+b
Rate per cum =c/36.53
33 Excavation in Hard Rock (blasting prohibited)

day

60.000

each

342.000

hr

3.000

each

10.000

Excavation for roadway in hard rock (blasting prohibited) with


rock breakers including breaking rock, loading in tippers and
disposal with all lifts and lead upto 1000 metres, trimming
bottom and side slopes in accordance with requirements of lines,
grades and cross- sections as per Technical Specification
Clause 302.3.5
(A) Manual Means

Unit = cum
Taking output = 1 cum
a)Labour
Mate
Mazdoor (Unskilled)
Chiseller (Hammer Man)
Blacksmith
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour
Credit for excavated rock found suitable for use @ 50 per cent of
excavated quantity

day

day

1.100

day

1.500

day

0.060

hour

0.180

cum

0.500

Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small quantity.
3. In case some rock is issued to contractor at site, the item of carriage shall be
omitted to the extent of quantity issued to the Contractor.

888

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

(B) Mechanical Means

Unit = cum
Taking output = 1 cum
a)Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum with rock breaker attachment @ 6 hour
cum per hour

0.289
0.167

Tipper 5.5 cum capacity tipper, 1 trip per hour

hour

0.180

Credit for excavated rock found suitable for use @ 50 per cent of
excavated quantity

cum

0.500

Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : 1. The quality and availability of rock shall be checked before affording
credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall
be restricted/reduced to that extent.
3. Being small quantity, manual loading will be economical in this case and has
been provided accordingly.
34

PHE-LUSS-34
i

ii

iii

iv

Loading or Unloading materials such as C.I / D.I Pipes, R.C.C.


Pipes, P.V.C. pipes, A.C. Pressure pipes and Specials less than
300 mm upto 4 mts in length including stacking.
C.I Pipes and Specials (load per truck =6.50 T)
Taking Output = 13.00 MT (Load for each Truck 6.5 MT)
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 13 MT
Rate per MT
RCC Pipes and Collars (load per truck =7.205 T)
Taking Output = 14.41 MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 14.41 MT
Rate per MT
AC Pipes and Collars (load per truck = 5.40 T)
Taking Output = 10.8 MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 10.8 MT
Rate per MT
Stone ware pipes (load per truck = 5.40 T)
Taking Output = 10.8 MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 10.8 MT
Rate per MT

day

6.000
1%

day

6.000
1%

day

6.000
1%

day

6.000
1%

889

Index-code

S No

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

35

Loading or unloading materials such as C.I / D.I. Pipes, stone


ware pipes, R.C.C. pipes, A.C. Pressure pipes and specials from
300 mm to 600 mm dia upto 4 mts in length including stacking.

day

6.000

PHE-LUMS-35
i

PHE-LUGS-36

C.I. / D.I. Pipes (load per truck = 5.5 T)


Taking Output = 11 MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 11 MT
Rate per MT
ii RCC Pipes and Collars (load per truck =5.75 T)
Taking Output = 11.5 MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 11.5 MT
Rate per MT
iii AC Pipes
Taking Output = 1MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
iv Stone ware pipes
Taking Output = 1MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
36 Loading or unloading materials such as CI / DI Pipes, A.C.
pressure pipes less than 300 mm dia above 4.00 M in length
including stacking

1%

day

6.000
1%

day

0.700
1%

day

0.700
1%

PHE-LUBS-37

C.I. / D.I. Pipes (load per truck = 8.46 T)


Taking Output = 1 MT
a)Labour
day
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 1 MT
ii AC Pipes (load per truck = 3.78 T)
Taking Output = 1MT
a)Labour
day
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
37 Loading or Unloading materials such as C.I / D.I. Pipes, A.C.
Pressure pipes from 300 to 600mm dia above 4.00 m including
stacking
i

AC Pipes (load per truck = 4.3 T)


Taking Output = 1 MT
a)Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 1 MT

day

0.710
1%

0.790
1%

0.714
1%

890

Index-code

PHE

S No

Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

ii

PHE-CSRC-38

C.I. Pipes (load per truck = 3.85 T)


Taking Output = 1MT
a)Labour
day
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
38 Centering and scaffolding charges for R.C.C. members including
all materials and labour charges for forming and dismantling
A

For R.C.C. Elevated Service Reservoir of Staging upto 40 Ft.


below G.W.L.

Side wall straight surfaces:


Details cost for 15 M long and 1 M height wall
Surface area = 2 x 15 x 1 = 30 Sqm
a) Materials
i) Planks 33 mm thick
2 x 15 x 1 =
30.00 sqm
Add 5% wastage = 1.5
=31.50 sqm
31.50 x 0.038 = 1.197 Cum
ii) Batters 75 x 50 mm
2 x 13 x 0.075 x 0.05 = 0.095 cum
iii) Ballies 125 dia for strutting
ver
13 x 1.5 = 19.5
13 x 4.5 = 58.5
= 78.00

0.780
1%

cum

1.197

cum

0.095

5% for wastage = 3.9


= 81.90
cum
81.90 x x 0.1252 / 4 =1.005 Cum
Assuming that timber shall become unserviceable after being
used for 5 times

ii

Cost for 5 times


Rate per 1 time
b) Labour
Labour charges for assembling, erection, dismantling and
cleaning
day
Carpenter 2nd class
day
Man Mazdoor
Sundries for nails etc
Overheads & Contractors Profit
c) Cost for 30 Sqm
Rate per sqm =c/30
Side walls curved surfaces

1.005

7.500
6.000

Considering 4 M internal dia and 1 Meter depth. Consider 30 mm thick.

Surface area:
Outside x 4.40 x 1.00 = 13.83 Sqm
Inside area = x 4 x 1 = 12.57 Sqm
= 26.40 Sqm
a) Materials
i) Planks 33 mm
26.40 x 0.038
=
1.003 cum
Extra & Wastage @ 20%
=
0.201 cum
=
1.204 Cum
ii) Hattens 75 x 38 mm
Inside 2 x 25 x 0.50 x 0.075 x 0.075 = 0.1406
Outside 2 x 28 x 0.50 x 0.075 x 0.175 = 0.1575
= 0.2981
Add 5% wastage
= 0.0149
= 0.3130 cum

cum

1.204

cum

0.313

891

Index-code

S No

PHE
Description

Unit

Quantity

Rate Rs.

Amt Rs.

Remarks

iii) Ballion 125 mm dia


Inside 25 x 1 = 25 m
Outside 28 x 1 = 28 m
= 53.00 m
Add 5% wastage = 2.65 m
cum
55.65 x 0.1252 = 0.68 cum
Assuming that timber shall become unserviceable after being
used for 5 times

0.680

Cost for 5 times


Rate per 1 time
b) Labour
Add labour charges for assembling, erection and dismantling
etc., @ 1/6 cost of materia

B
i

c) Total
Overheads & Contractors Profit
c) Cost for 26.04 Sqm
Rate per sqm =c/26.04
For Ground level works
R.C.C. vertical wells of plane surface upto 3 meters height such
as G.L. tanks clarifiers and sludge digestor etc,

Rate per Sqm (as arrived in item A (i) above)


R.C.C. Vertical walls of circular faces upto 3 meters height
Rate per Sqm (as arrived in item A (ii) above)
39 Hoisting of S.S. Girders in pump house etc.
Detail cost of S.S. Joist = 300 x 140 mm - 6 M long
Wt. 44.2 Kgs/M
= 6 x 44.20
= 265.20 kgs
Tolerances @ 5%
= 13.26 kgs
= 278.46 kgs
a) Labour
Labour for hoisting inn position:
ii

PHE-HSSG-39

PHE-LCVS-40

day
Mason 2nd class
day
Man Mazdoor
Total
(b) Overheads & Contractors Profit
c) Cost for 278.46 Sqm
Rate per sqm =c/278.46
Cost for 50 Kg
40 Labour charges for fixing ventilating shafts in sewerage
scheme complete with all accessories

Unit Each
a) Labour
Mason 1st class
Mason 2nd class
Plumber 2nd Class
Man Mazdoor
Overheads & Contractors Profit
Rate

1.000
2.750

day

0.150

day

0.350

day

0.600

day

2.000

892

STANDARD SCHEDULE OF RATES 2015 - 2016


Description of work
Rate
Seigneiorage cahrges

S.No

per

Building stone

50.00

1 Cu.m

Rough stone

50.00

1 Cu.m

20mm metal

50.00

1 Cu.m

40 mm metal

50.00

1 Cu.m

Gravel / Ordinary earth

22.00

1 Cu.m

Sand

40.00

1 Cu.m

Bricks

38.50

1000 Bricks

Stacking charges
1

Earth, Sand & Gravel

2 stacking

Metal

2 stacking

Bricks

1 stacking

No stacking charges

Conveyance rates for the year 2015-2016


Loading and Unloading by Manual means
( including idle hire charges of trucks)

Transportation of materials by trucks and tippers


S.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

Lead
(Km)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

Sand/Earth/
Gravel
(Cu.m)
31.00
43.40
57.90
70.30
82.70
95.10
107.50
119.90
132.30
144.70
157.10
169.50
181.90
194.30
206.70
219.10
231.50
243.90
256.30
268.70
281.10
293.50
305.90
318.30
330.70
343.10
355.50
367.90
380.30
392.70
403.00
413.30
423.60
433.90
444.20
454.50
464.80
475.10
485.40
495.70
506.00
516.30
526.60
536.90
547.20
557.50
567.80
578.10
588.40
598.70

Metal /
Stone
(Cu.m)
29.90
41.90
57.90
70.30
82.70
95.10
107.50
119.90
132.30
144.70
157.10
169.50
181.90
194.30
206.70
219.10
231.50
243.90
256.30
268.70
281.10
293.50
305.90
318.30
330.70
343.10
355.50
367.90
380.30
392.70
403.00
413.30
423.60
433.90
444.20
454.50
464.80
475.10
485.40
495.70
506.00
516.30
526.60
536.90
547.20
557.50
567.80
578.10
588.40
598.70

Water/
1000 Lt
18.40
25.80
34.40
41.80
49.20
56.60
64.00
71.40
78.80
86.20
93.60
101.00
108.40
115.80
123.20
130.60
138.00
145.40
152.80
160.20
167.60
175.00
182.40
189.80
197.20
204.60
212.00
219.40
226.80
234.20
240.30
246.40
252.50
258.60
264.70
270.80
276.90
283.00
289.10
295.20
301.30
307.40
313.50
319.60
325.70
331.80
337.90
344.00
350.10
356.20

Bricks /
S.No
1000 Nos
49.80
69.80
93.00
112.90
132.90
152.80
172.70
192.60
212.50
232.40
252.30
272.20
292.10
312.00
331.90
351.80
371.70
391.60
411.50
431.40
451.30
471.20
491.10
511.00
530.90
550.80
570.70
590.60
610.50
630.40
647.00
663.60
680.20
696.80
713.40
730.00
746.60
763.20
779.80
796.40
813.00
829.60
846.20
862.80
879.40
896.00
912.60
929.20
945.80
962.40

1
2

Description of item
Loading
Un Loading

Sand/Eart
h/Gravel
(Cu.m)
108.20
38.60

NOTE
The lead, Loading, Un loading charges are
inclusive of 14% Contractor profit,
Over head charges
Loading and Unloading not payable for
conveyance by head load

1
2
3
4
5

NOTE
The lead, Loading, Un loading charges are
Loading and Unloading not payable for con
Loading and Unloading not payable for con
Loading charges are not payable for conve
materials beyond initial lead of 50 m where
Loading and Unloading charges are not pa
disposal of excavated materials beyond in

51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100

51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100

609.00
619.30
629.60
639.90
650.20
660.50
670.80
681.10
691.40
701.70
712.00
722.30
732.60
742.90
753.20
763.50
773.80
784.10
794.40
804.70
815.00
825.30
835.60
845.90
856.20
866.50
876.80
887.10
897.40
907.70
918.00
928.30
938.60
948.90
959.20
969.50
979.80
990.10
1000.40
1010.70
1021.00
1031.30
1041.60
1051.90
1062.20
1072.50
1082.80
1093.10
1103.40
1113.70

609.00
619.30
629.60
639.90
650.20
660.50
670.80
681.10
691.40
701.70
712.00
722.30
732.60
742.90
753.20
763.50
773.80
784.10
794.40
804.70
815.00
825.30
835.60
845.90
856.20
866.50
876.80
887.10
897.40
907.70
918.00
928.30
938.60
948.90
959.20
969.50
979.80
990.10
1000.40
1010.70
1021.00
1031.30
1041.60
1051.90
1062.20
1072.50
1082.80
1093.10
1103.40
1113.70

362.30
368.40
374.50
380.60
386.70
392.80
398.90
405.00
411.10
417.20
423.30
429.40
435.50
441.60
447.70
453.80
459.90
466.00
472.10
478.20
484.30
490.40
496.50
502.60
508.70
514.80
520.90
527.00
533.10
539.20
545.30
551.40
557.50
563.60
569.70
575.80
581.90
588.00
594.10
600.20
606.30
612.40
618.50
624.60
630.70
636.80
642.90
649.00
655.10
661.20

979.00
995.60
1012.20
1028.80
1045.40
1062.00
1078.60
1095.20
1111.80
1128.40
1145.00
1161.60
1178.20
1194.80
1211.40
1228.00
1244.60
1261.20
1277.80
1294.40
1311.00
1327.60
1344.20
1360.80
1377.40
1394.00
1410.60
1427.20
1443.80
1460.40
1477.00
1493.60
1510.20
1526.80
1543.40
1560.00
1576.60
1593.20
1609.80
1626.40
1643.00
1659.60
1676.20
1692.80
1709.40
1726.00
1742.60
1759.20
1775.80
1792.40

Unloading by Manual means


dle hire charges of trucks)
Metal /
Stone
(Cu.m)
124.20
62.10

Loading and Unloading by Mechanical means


( including idle hire charges of trucks)
S.No
1
2

Description of item
Loading
Un Loading

Sand/Eart
h/Gravel
(Cu.m)
52.50
15.90

Metal /
Stone
(Cu.m)
105.00
15.90

NOTE
, Un loading charges are
Contractor profit,
s

Unloading not payable for


yance by head load

NOTE
Loading, Un loading charges are inclusive of 13.615 % Contractors profit and Over head charges
nd Unloading not payable for conveyance by head load
nd Unloading not payable for conveyance by head load
harges are not payable for conveyance by mechanical means for disposal of excavated
beyond initial lead of 50 m where ever specified
nd Unloading charges are not payable for conveyance by mechanical means for
of excavated materials beyond initial lead of 1 KM where ever specified

Sub estimate ( OHSR - 20000 Lt)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu
Name of Work : Construction of 20000 LT OHSR of 9.65 m staging
Est. : Rs. 3.00 Lakhs
401
Description of work
Grant :
No
Contents
Rate
Amount
L
B
D
1
2
3
4
5
6
7
8
10
1 Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils, hard red earth soils etc. complete
for foundations
1* 0.785 6.30
6.30
2.40
74.78 m3
116.50
8712
2

Supply and filling of sand including watering


and ramming etc. complete
For foundation

1* 0.785

6.30

6.30

0.30

9.35 m3

835.70

7814

CC(1:4:8) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete for foundation

1* 0.785

6.25

6.25

0.30

9.20 m3

3377.25

31071

VRCC (1:1 :3) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Raft slab

1* 3.14

4.00

1.35

0.20

3.39 m3

8174.60

27712

1* 3.14

4.00

0.40

0.35

1.76 m3

7857.30

13829

1* 4
1* 4

0.30
0.30

0.30
0.30

1.25
5.00
Total

0.45
1.80
2.25 m3

21111.30

47500

4(a) '- Do - VRCC (1:1 :3) for Raft Beam

VRCC (1:1 :3) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges for columns
Columns up to GL
Columns up to 5 m above GL

-Do- ColoumnsUpto 8m level

1* 4

0.30

0.30

3.00

1.08 m3

21245.30

22945

-Do- ColoumnsUpto 8m -12 m level

1* 4

0.30

0.30

1.65

0.59 m3

0.00

VRCC (1:1 :3) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges for Braces
Brace up to 5m level
GL Brace
1st Brace

1* 4
1* 4

2.6
2.6

0.25
0.25

0.45
0.45
Total

1.17
1.17
2.34 m3

17693.40

41403

22671.60

21311

Brace up to 5m - 8m level
2nd Brace

1* 4

2.6

0.25

0.45

1.17

VRCC (1:1 :3) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Ring beam

1* 3.14

4.00

0.30

0.25

0.94 m3

#VALUE!

#VALUE!

1
9

2
VRCC (1:1 :3) using 20 mm HBG metal
with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Bottom slab
For Cantilever slab alround the tank

1* 0.785
1* 3.14

4.20
5.10

4.20
0.90

0.25
0.15

10 VRCC (1:1 :3) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Side walls

1* 3.14

4.10

0.15

11 VRCC (1:2 :4) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Top slab

1* 0.785

4.80

4.80

12 Plastering with CM(1:3) 8 mm thick with 2%


acco proof powder including c/c of all
and labour charges etc. complete.
Inside of the tank - Bottom slab
Inside of the tank - Side walls
Top slab

1* 0.785
1* 3.14
1* 0.785

4.00
4.00
4.50

4.00

10

3.46 m3
2.16 m3

22895.60
22895.60

79219
49454

#VALUE!

1.90

3.67 m3

55989.60

205482

#VALUE!

0.13

2.26 m3

22439.60

50713

#VALUE!

12.56
23.86
15.90
52.32 m2

#VALUE!

#VALUE!

1.90
4.50
Total

13 Fly proof ventilator with 2 fold nylon mesh


including c/c of all materials and labour
charges etc. complete.

1* 1

1 No

150

150

14 CI light type manhole cover with frame of


600*600 mm

1* 2

2 No

450

900

15 RCC pheniol of 600 mm dia including all


charges etc. complete

1* 1

1 No

600

600

16 RCC precast ladder of 450mm width inside the


reservoir from floor level to roof level embeded
in bottom slab as per standard pattern
including c/c of all materials and labour
charges etc. complete.

1* 1

1 No

700

700

17 Supply and fixing of lightening arrestor of


approved pattern with necessary earth
connections including all charges

1* 1

1 No

4500

4500

18 Supply and fixing of GI hand railing with MS


angular posts at top alround the tank

1* 2

2 No

3500

7000

19 Supply and fixing of MS ladder of 450mm


width as per approved design with MS angles
and 20mm dia MS bar and GI pipe for hand
railings for the outside of the reservoir from
GL to roof slab including painting with
synthetic enamel paint of approved make and
colour for 2 coats over primary coat of red
oxide including c/c of all materials and labour
charges etc. complete

1* 1

750

9000

20 Labour charges for fixing of Inlet, Outlet, Over

12

12 m

2
flow and scour arrangements upto GL

3
1* 1

7
1 No

8
4000

10
4000

10

21 Cost of inlet,outlet,overflow and scour


arrangements including valves, bell mouths,
duck foot bends etc.

1* 1

1 No

22 Construction of drains for scour, overflow


arrangements of standard size

1* 1

1 No

1000

1000

23 Painting with snow cem 2 coats over primary


coat of white cement including c/c of all
materials and labour charges etc. complete.

1* 1

1 No

3500

3500

24 Provision for painting the name board with


synthetic enamel paint

1* 1

1 No

500

500

25 Cost of steel includng fabrication cahrges

1* 1800

52970.00

158910

3000 Kg

26 Unforeseen items of work

104
TOTAL

Deputy Exe. Engineer,


RWS & S Sub Division,
Pakala

Asst. Exe.
Engineer,
RWS
& S,
PAKALA

#VALUE!

Sub estimate ( OHSR - 20000 Lt)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
Name of Work : Construction of 20000 LT OHSR of 6.30 m staging
Est. : Rs. 3.00 Lakhs
Measurements
Description of work
Grant :
No
Contents
Rate
Per
Amount
L
B
D
1
2
3
4
5
6
7
8
9
10

Construction of circular OHSR with VRCC M 20 Design mix using 20 mm size machine
crushed metal for elevated service reservoir of
approved type design with single compartment
inside
dia of ______&_______ m height side walls,
the LWL being 0.15 m above bottom slab, a
free board of 0.15 m below top slab and
capable of holding ___________ Lt with a
staging of ______ m and with Raft foundation
including CM (1:3) 12mm thick with 2%
acco proof powder and out side with CM(1:3) 8
mm thick, for a finished work inculuding 2 coats
fo snow cem painting for external surfaces and
Three coats of epoxy paint to inner surfaces of
the reservoir including roof cover slab, including
lettering and fixing of
1 *1

20000 Lt

45.76

1 Lt

915200

all required fixtures pipes, bends, valves etc.


for vertical connections, but excluding the cost
fo pipes, bends and valves etc. complete as per
Dept. designs and drawings, with the following
fixtures.
a) RCC or Aluminium ladder inside 0.45 m wide
b) Spiral stair case out side the reservoir
c) Lightening arrestor, including flat copper
conductor and earthing etc.
d) RCC ventilators with copper wire fly proof
mesh
e) Manhole frame and cover 0.75 * 0.75 m with
frame as per IS specifications ( Light duty ) - 2
Nos
f) Railing with 32 mm dia GI pipes (A class) in
two rows around OHSR fixed in RCC (1:2:4)
posts or MS angles of size 100*75*75 mm with
1.50 m intervals aroung periphery on top of the
OHSR
g) Water level indicator of good quality with
ebonite / copper float of approved pattern - 1
No
Dedut : For raft foundation
2

Earth work excavation and depositing on


the banks with intial lead and lift in O.G.
soils, hard red earth soils etc. complete
for foundations

1* 0.785

5.20

5.20

2.40

50.94 m3

116.50

1 m3

5935

Supply and filling of sand including watering


and ramming etc. complete
For foundation

1* 0.785

5.20

5.20

0.30

6.37 m3

835.70

1 m3

5323

CC(1:4:8) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete for foundation

1* 0.785

5.20

5.20

0.30

6.37 m3

3377.25

1 m3

21513

1
5

10

VRCC (1:1 :3) using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Raft slab

1* 3.14

3.00

2.00

0.20

3.77 m3

8174.60

1 m3

30818

'- Do - VRCC (1:1 :3) for Raft Beam

1* 3.14

3.00

0.40

0.35

1.32 m3

7857.30

1 m3

10372

Quantity of steel and fabrication charges


for Raft slab and Raft beam

Kg

52970.00

1 Kg

Sub Total for Raft

73961

Add : For Isolated footing


Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils, hard red earth soils etc. complete
for foundations

1* 4

2.15

2.15

2.85

52.70 m3

116.50

1 m3

6140

Supply and filling of sand including watering


and ramming etc. complete
For foundation

1* 4

2.15

2.15

0.30

5.55 m3

835.70

1 m3

4638

CC(1:4:8) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete for foundation

1* 4

2.15

2.15

0.30

5.55 m3

3377.25

1 m3

18744

VRCC M - 20 Nominal mix using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
Column footing
1* 4
Trapezoidal portion
1* 4

1.85
4.32

1.85
0.25

0.15
0.33
Total

2.05
1.43
3.48 m3

7211.60

1 m3

25096

52970.00

1 Kg

Quantity of steel and fabrication charges


for Raft slab and Raft beam

Kg

Sub Total for Isolated Footing

54618

TOTAL

895857

Cost of _________ Kl OHSR of ______m


staging with Isolated Footing including
cost of steel and fabriation cahrges etc

44.79

Deputy Exe. Engineer,


RWS & S Sub Division,
Pakala

Asst. Exe. Engineer,


RWS & S, PAKALA

Sub estimate ( OHSR - 20000 Lt)


Name of the Work : Providing Pipeline from water tank to Bore at HW of Thangellapalem Village and GP in Thottembedu Mandal
Name of Work : Construction of 20000 LT OHSR O 9.45 m staging
S.No
1
1

Description of work

No
3

Measurements
L
B
D
4
5
6

Contents

Rate

Per

2
Earth work excavation and depositing on
the banks with intial lead and lift in O.G.
soils, hard red earth soils etc. complete
for foundations

1* 4

2.15

2.15

2.85

52.70 m3

116.50

1 m3

Supply and filling of sand including watering


and ramming etc. complete
For foundation

1* 4

2.15

2.15

0.30

5.55 m3

835.70

1 m3

CC(1:4:8) using 40mm HBG metal including c/c of all materials and labour charges
etc. complete for foundation

1* 4

2.15

2.15

0.30

5.55 m3

3377.25

1 m3

VRCC M - 20 Nominal mix using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
Column footing
1* 4
Trapezoidal portion
1* 4

1.85
4.32

1.85
0.25

0.15
0.33
Total

2.05
1.43
3.48 m3

7211.60

1 m3

1.85
5.00
Total

0.67
1.80
2.47 m3

21111.30

1 m3

VRCC M - 20 Nominal mix using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges for columns
Columns up to GL
1* 4
Columns up to 5 m above GL
1* 4

0.30
0.30

0.30
0.30

-Do- ColoumnsUpto 8m level

1* 4

0.30

0.30

3.00

1.08 m3

21245.30

1 m3

-Do- ColoumnsUpto 11 level

1* 4

0.30

0.30

1.45

0.52 m3

21379.30

1 m3

VRCC M - 20 Nominal mix using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges for Braces
Brace up to 5m level
GL Brace
1* 4
1st Brace
1* 4

1.82
1.82

0.25
0.25

0.45
0.45
Total

0.82
0.82
1.64 m3

17693.40

1 m3

Brace up to 8m level

1* 4

10 VRCC M - 20 Nominal mix using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Ring beam
1* 3.14

1.82

0.25

0.45

0.82 m3

17827.40

1 m3

3.00

0.30

0.10

0.28 m3

22805.60

1 m3

1
11

2
3
VRCC M - 20 Nominal mix using 20 mm HBG metal
with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Bottom slab
1* 0.785

4.20

4.20

0.20

2.77 m3

23029.60

1 m3

12 VRCC M - 20 Nominal mix using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Side walls
1* 3.14

4.10

0.10

2.00

2.57 m3

56123.60

1 m3

13 VRCC M - 15 using 20 mm HBG metal


with required quantity of steel per cu.m of
concrete including c/c of all materials and
labour charges but excluding the cost of
steel and its fabrication charges
For Top slab

1* 0.785

4.50

4.50

0.10

1.59 m3

22573.60

1 m3

14 Plastering with CM(1:3) 8 mm thick with 2%


acco proof powder including c/c of all
and labour charges etc. complete.
Inside of the tank - Bottom slab
Inside of the tank - Side walls
Top slab

1* 0.785
1* 3.14
1* 0.785

4.00
4.00
4.50

4.00

12.56
25.12
15.90
53.58 m2

#VALUE!

10 m2

2.00
4.50
Total

15 Fly proof ventilator with 2 fold nylon mesh


including c/c of all materials and labour
charges etc. complete.

1* 1

1 No

150

1 No

16 CI light type manhole cover with frame of


600*600 mm

1* 1

1 No

450

1 No

17 RCC pheniol of 600 mm dia including all


charges etc. complete

1* 1

1 No

600

1 No

18 RCC precast ladder of 450mm width inside the


reservoir from floor level to roof level embeded
in bottom slab as per standard pattern
including c/c of all materials and labour
charges etc. complete.

1* 1

1 No

700

1 No

19 Supply and fixing of lightening arrestor of


approved pattern with necessary earth
connections including all charges

1* 1

1 No

4500

1 No

20 Supply and fixing of GI hand railing with MS


angular posts at top alround the tank

1* 1

1 No

3500

1 No

21 Supply and fixing of MS ladder of 450mm


width as per approved design with MS angles
and 20mm dia MS bar and GI pipe for hand
railings for the outside of the reservoir from
GL to roof slab including painting with
synthetic enamel paint of approved make and
colour for 2 coats over primary coat of red
oxide including c/c of all materials and labour

2
charges etc. complete

3
1* 1

4
16

7
16 m

8
750

9
1 No

1
2
22 Labour charges for fixing of Inlet, Outlet, Over
flow and scour arrangements upto GL

1* 1

1 No

1000

1 No

23 Cost of inlet,outlet,overflow and scour


arrangements including valves, bell mouths,
duck foot bends etc.

1* 1

1 No

35000

1 LS

24 Construction of drains for scour, overflow


arrangements of standard size

1* 1

1 No

1000

1 No

25 Painting with snow cem 2 coats over primary


coat of white cement including c/c of all
materials and labour charges etc. complete.

1* 1

1 No

3500

1 No

26 Provision for painting the name board with


synthetic enamel paint

1* 1

1 No

500

1 No

27 Cost of steel including fabrication cahrges

1* 2000

2000 Kg

52970.00

1000 Kg

29 Unforeseen items of work


TOTAL

Deputy Exe. Engineer,


RWS & S Sub Division,
Pakala

Asst. Exe. Engineer,


RWS & S, PAKALA

mate ( OHSR - 20000 Lt)


e at HW of Thangellapalem Village and GP in Thottembedu Mandal
staging
Amount
10

6140

4638

18744

25096

52145
22945
11117

29017
14618

6386

10

10

63792

144238

35892

#VALUE!

150

450

600

700

4500

3500

10
12000

10
1000

35000

1000

3500

500
105940
633
#VALUE!

OHSR Capacity (KL)


20
40
60
90
120

Staging

Dia

Height

12.80,9.65,6.50
9.75 , 12.90
9.80 , 12.95
9.60 , 12.75
9.60 , 12.75

4.00
5.00
5.00
7.00
7.00

1.90
2.40
3.45
3.00
3.75

9.75 , 12.90

7.00

4.40

9.90 , 13.05
10.05 , 13.20

9.00
9.00

3.75
4.55

Bottom
Slab
Ring beam Thicknes
depth
s
0.25
0.30
0.30

0.25
0.30
0.35

150
200
250

Specials for 20KL 9.65m stagging


80mm dia
CID/F Pipe
2mts Long
INLET
OUTLET
SCOUR
OVERFLOW

5
5
5
5
20

80mm dia
CID/F
Pipe 0.90
mts Long
3
1
4
3
11

80mm
80mm dia
80mm dia CI
diaCID/F CID/F Duck CIS/F
Flanged
Pipe 0.60 Foot Bend Semicircul Tee
mts Long
ar bend
1
1
1
1
1
2
1
1
1
1
4
5
1
1
Specials for 40KL 9.75m stagging

80mm dia
CID/F Pipe
2mts Long
INLET
OUTLET
SCOUR
OVERFLOW

5
5
5
5
20

80mm dia
CID/F
Pipe 0.90
mts Long
3
1
4
3
11

80mm
80mm dia
80mm dia CI
diaCID/F CID/F Duck CIS/F
Flanged
Pipe 0.60 Foot Bend Semicircul Tee
mts Long
ar bend
1
1
1
1
1
2
1
1
1
1
4
5
1
1

Specials for 60KL 9.80m stagging


80mm dia
CID/F Pipe
2mts Long
INLET
OVERFLOW
SCOUR

5
5
5
15

80mm dia
CID/F
Pipe 0.90
mts Long
3
3
4
10

80mm
80mm dia
80mm dia CI
diaCID/F CID/F Duck CIS/F
Flanged
Pipe 0.60 Foot Bend Semicircul Tee
mts Long
ar bend
1
1
1
1
1
2
1
1
3
4
1
1

OUTLET

100mm dia
5
5

100mm
dia
1
1

100mm
dia
1
1

100mm dia
1
1

100mm
dia
0

INLET

OUTLET

Dia/Lengt
h
0.6
0.9
2
2.75
Duck Foot
Bend
Semicircul
ar Bend

5/8x3/4
Bolts and
nuts

5/8x4'' Leathers
Bolts and
nuts

Butterfly
valves

76

19

76

19

5/8x3/4
Bolts and
nuts

5/8x4'' Leathers
Bolts and
nuts

Butterfly
valves

76

19

76

19

5/8x3/4
Bolts and
nuts
76

76

5/8x4'' Leathers
Bolts and
nuts
8

Butterfly
valves

19

19

1
1

SCOUR

OVERFL
OW

1
1

Month
7/14
8/14
9/14
10/14
11/14
12/14
1/15
2/15
3/15
4/15
5/15
6/15

Rates of Steel and Cement


Cost of Cement / 1
Date of GO
Mt
3/9/2014
5600
19/08/2014
6000

Cost of Steel / 1
MT
46500
48000

SL No.

1
2
3
4
5

Discription of Item/ Dia of Sluice valve

Size of pipeline
Size of Valve chamber
Class of valve

DI D/F Gate Valves (Soft Seated) Resilient seated soft sealing gate valves (Sluice valves) with body bonnet of ductile cast iron
equivalent grade as per I.S.3896-part2-1985 and subsequent revisions, wedge fully rubber lined with EPDM food grade qua
valves should be of vacuum tight and 100% leak proof with face to face dimensions as per BS5163-89/IS14846-2000/DIN 320
with Electrostatic powder coating both inside and outside pocket less body passage. Drilled as per IS
Transportation chargers (5% of basic cost)
Jointing of DI S/S 2 Jobs Labour
Lowering of valve and keeping in postion
Grand total

Asst. Engineer,
RWS&S,
Project

Dy. Exe. Engineer,


RWS&S, Sub division ,
Srikalahasthi.

100 mm

150 mm

250 mm

on 100mm dia line 150mm line

250mm line

0.90x0.90x 1.40m 0.90x0.90x 1.40m

1.05x1.20x 1.70m

PN-16

PN-16

PN-16

11779

18546

34750

588.95
284.34
82.89
12735

927.3
423.56
140.5
20037

1737.5
564.2
329.4
37381

, Executive Engineer,
. RWS&S Division ,
Tirupathi

You might also like