Professional Documents
Culture Documents
(b) Detailed Project Report (DPR) forms the foundation on which the entire
project is built. Discuss
various elements to be included in a DPR for the success of a project.
2. Discuss various software used for project scheduling and monitoring. Discuss
the inputs and
output of each one of them.
3. Write
(a)
(b)
(c)
(d)
short notes
Scope creep
Earned value analysis
Project appraisal
Linear Responsibility chart
4. Case Study: Please read the case study given below and answer questions given
at the end.
Case Study
(a)
Activity
(Days)
(Days)
Cost Rs.
Cost Rs.
A
B
C
A
Predecessor
Crash Time
Normal
Crash
Normal Time
3
2
5
8000
12000
20000
2
1
3
14000
19000
28000
D
E
F
G
B
C,D
C,D
F
5
6
2
2
3
4
1
1
15000
18000
6000
5000
23000
28000
10000
10000
i)
ii)
iii)
iv)
v)
vi)
the
(b)
Activity
Immediate
Predecessors
Optimistic
Time duration in days
Most Likely
Pessimistic
A
6
8
22
B
A
40
60
80
C
A
12
21
24
D
A
20
30
40
E
B
10
15
20
F
C & E 1 / 2 1
3 / 2
G
D & E 8
10
12
H
F & G 4
5
6
i)
Draw the appropriate PERT network
ii)
Identify the critical path and project duration
iii)
Calculate the earliest start time, earliest finish time, latest start ti
me, latest finish time, and slack of each of the activities.
iv)
What is the Probability of completing the project in 120 days?
Assignment C
(Objective Questions)
Question No: 1
The act of doing anything that will help to bring future project performance int
o line with the project plan is called
Budget update
Revised cost estimate
Corrective action
Contingency planning
Question No: 2
Project A has an internal rate of return (IRR) of 21 percent. Project B has an I
RR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of ig
percent. Which of these would be the BEST project?
Project A
Project B
Project C
Project D
Question No: 3
When checking the calendar of a team member to schedule a meeting, you see she h
as scheduled a meeting with a key stakeholder that you were not informed of. The
best approach would be to
Avoid mentioning it to the team member but continue to watch her activities
Notify your boss about the problem
Address the concern with the team member's boss
Address the concern with the team member
Question No: 4
The program evaluation and review technique (PERT) method of scheduling differs
from the critical path method (CPM) because the PERT method:
Question No: 5
A project manager would like to manage his project in such a way that he will be
able to identify specific tasks that should be watched and managed more closely
than others. The project manager should use which method?
Question No: 6
A project manager is using a cause and effect diagram with the team to determine
how various factors might be linked to potential problems. In what part of the
quality management process is the project manager involved?
Quality analysis
Perform quality assurance
Perform quality control
Quality planning
Question No: 7
. In, ____________we see whether return or benefits on this investment are more
than its cost from point of view of society in which we are living
Question No: 8
Resource leveling will generally
Question No: 9
If all planned work has been completed or earned, What is the schedule variance?
0.01
0
0.1
0.5
Question No: 10
A project whose acceptance does not prevent or require the acceptance of one or
more alternative projects is referred to as __________
Question No: 11
When operating under a single-period capital-rationing constraint, you may first
want to try selecting projects by descending order of their __________ in order
to give yourself the best chance to select the mix of projects that adds most t
o firm value.
Question No: 12
Which of the following statements is correct regarding the internal rate of retu
rn (IRR) method?
Question No: 13
Which of the following is not a potential for a ranking problem between two mutu
ally exclusive projects?
Question No: 14
The three phases involved in the management of large projects are
Question No: 15
With respect to PERT and CPM, slack
Question No: 16
A dummy activity is required when
The network contains two or more activities that have identical starting and end
ing events
Two or more activities have different ending events
Two or more activities have the same ending events
Two or more activities have the same starting events
Question No: 17
Which of the following is a basic assumption of PERT?
There is only one complete route from the start of a project to the end of a pro
ject
No activity in the network must be repeated.
Activity completion times are known with certainty
Only critical path activities in the network must be performed
Question No: 18
PERT analysis computes the variance of the total project completion time as
Question No: 19
Which of the following managers develop operational plans for the project?
Top Managers
Middle Manager
Line Managers
Supervisors
Question No: 20
Which of the following is a direct responsibility of the project manager?
Question No: 21
Which of the following is the benefit of the network analysis approach?
Question No: 22
A project can be considered to have failed if it
Question No: 23
Which of the following is not a reason to reduce project completion time?
Question No: 24
Which of the following is especially useful for monitoring project progress agai
nst plan?
Question No: 25
An individual with a diverse set of skills--management, leadership, technical, c
onflict management, and customer relationship--who is responsible for initiating
, planning, executing, and closing down a project best defines:
Question No: 26
Identifying, assessing, and managing the risks and day-to-day changes that occur
during a project best defines which of the following project manager activities
?
Conflict management
Risk and change management
Team management
Customer relations
Question No: 27
Optimistic time refers to
best guess of the amount of time the activity actually will require fo
Question No: 28
An example of a project management system is
Word Perfect
Microsoft Office
Lotus 1-2-3
Oracle
Question No: 29
Which of the following is not a true statement regarding Network diagrams?
Question No: 30
Which of the following slack times indicates that an activity is on the critical
path?
1
10
0
2
Question No: 31
A project manager that dictates all decisions and does not allow for any partici
pation by the workers would be using which leadership style.
Passive
Participative/democratic
Autocratic
Laissez-faire
Question No: 32
The shortest time necessary to complete all of the activities in a network is ca
lled the:
Question No: 33
Question No: 34
The calculation of the total cost of a product, from R&D to operational support
and disposal, is called:
Birth-to-death costing
Life-cycle costing
Summary costing
Depreciation costing
Question No: 35
Which is the first stage in the project management model?
Project definition
Understanding the project environment
Project control
Project planning
Question No: 36
Successful project management does NOT include which of the following factors?
Question No: 37
A critical path network diagram does not:
Calculate earned-value
Help determine the amount of float
Calculate the duration of the whole project
Identify the particularly important activities
Question No: 38
Which of the following statements gives the Technical definition of Project Plan
ning?
use of resources
Question No: 39
Which of the following is the responsibility of proposed project manager?
Question No: 40
The main purpose of a _______________ is to function as a blueprint for the grou
p s business operations.
Business Plan
Scope statement
Feasibility Study
Work Breakdown Structure
Contact www.solvedcare.com for best and lowest cost solution or email solvedcare
@gmail.com