You are on page 1of 22

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.

23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

PROPOSED HOUSING ASSISTANCE FOR SELECTED RESIDENTS OF


& VENNMANI VILLAGES, NAGAPATTINAM DISTRICT

ORATHUR

DETAILED SPECIFICATIONS & SCHEDULE OF QUANTITIES FOR HOUSE TYPE 1MT Type 1MT : Madras Terrace with Staircase to Terrace & full Parapet Walls
DETAILED SPECIFICATIONS & SCHEDULE OF QUANTITIES
SUMMARY OF COST ESTIMATES
1
2
3
4

HOUSE TYPE 1MT - Materials


HOUSE TYPE 1MT - Labour
TOILET UNIT - Materials
TOILET UNIT - Labour
ESTIMATED COST PER UNIT

380.19 Sft
32.06 Sft

:
:
:
:

412.25 Sft

Construction Management & Supervision Costs


@ 4.5% of Estimated Cost per Unit
Archirtectural Consultancy Services
0.5% of Estimated Cost per Unit

ESTIMATED PROJECT COST PER UNIT

Rs. 154,991.72
Rs.
54,985.25
Rs.
9,650.89
Rs.
4,056.93
Rs. 223,684.79
Rs.

10,065.82

Rs.

1,118.42

Rs. 234,869.03

* Plinth Area per Unit = 412.25 Sft.

DETAILED SPECIFICATIONS & SCHEDULE OF QUANTITIES FOR HOUSE TYPE 1RC*


Type - 1RC : RCC Filler Slab with
Staircase to Terrace & full Parapet Walls
DETAILED SPECIFICATIONS & SCHEDULE OF QUANTITIES
SUMMARY OF COST ESTIMATES
1
2
3
4

HOUSE TYPE 1RC - Materials


HOUSE TYPE 1RC - Labour
TOILET UNIT - Materials
TOILET UNIT - Labour
ESTIMATED COST PER UNIT

380.19 Sft
32.06 Sft

:
:
:
:

412.25 Sft

Construction Management & Supervision Costs


@ 4.5% of Estimated Cost per Unit
Archirtectural Consultancy Services
0.5% of Estimated Cost per Unit

ESTIMATED PROJECT COST PER UNIT


* Plinth Area per Unit = 412.25 Sft.

Rs. 146,819.29
Rs.
52,706.18
Rs.
9,650.89
Rs.
4,056.93
Rs. 213,233.29
Rs.

9,595.50

Rs.

1,066.17

Rs. 223,894.95

No.

No.

13 Making Door frames & shutters

14 Preparing rafter & tie frames

Description of Work

KEY
Batch 1 : 40 Units

Batch 2 : 60 Units

19-11-06
20-11-06
21-11-06
22-11-06
23-11-06
24-11-06
25-11-06
26-11-06
27-11-06
28-11-06
29-11-06
30-11-06
01-12-06
02-12-06
03-12-06
04-12-06
05-12-06
06-12-06
07-12-06
08-12-06
09-12-06
10-12-06
11-12-06
12-12-06
13-12-06
14-12-06
15-12-06
16-12-06
17-12-06
18-12-06
19-12-06
20-12-06
21-12-06
22-12-06
23-12-06
24-12-06
25-12-06
26-12-06
27-12-06
28-12-06
29-12-06
30-12-06
31-12-06

Description of Work

19-11-06
20-11-06
21-11-06
22-11-06
23-11-06
24-11-06
25-11-06
26-11-06
27-11-06
28-11-06
29-11-06
30-11-06
01-12-06
02-12-06
03-12-06
04-12-06
05-12-06
06-12-06
07-12-06
08-12-06
09-12-06
10-12-06
11-12-06
12-12-06
13-12-06
14-12-06
15-12-06
16-12-06
17-12-06
18-12-06
19-12-06
20-12-06
21-12-06
22-12-06
23-12-06
24-12-06
25-12-06
26-12-06
27-12-06
28-12-06
29-12-06
30-12-06
31-12-06

PROPOSED HOUSING ASSISTANCE FOR TSUNAMI AFFECTED RESIDENTS OF PATTINAPAKKAM, CHENNAI


SCHEDULE OF WORK

1 Site Clearing

2 Marking

3 Earthwork & Foundation PCC

4 Foundation & plinth brickwork

5 Sand filling in plinth.

6 RCC Plinth Band

7 Brickwork in superstructure

8 RCC Lintel Band

9 Brickwork over lintel incl. gables

10 Roof carpentry, incl. of fixing tiles

11 PCC(1:4:8) in flooring.

12 Fixing Door, Jallis & Flooring etc.

Preparatory Carpentry Work

6 C
8 C

16 C
24 C

10 C

24 C

Batch 3 : 80 Units

31-12-06

31-12-06

PROPOSED HOUSING ASSISTANCE FOR TSUNAMI AFFECTED RESIDENTS OF PATTINAPAKKAM, CHENNAI

2 Sand filling in plinth.

303.40

Cft

3 PCC(1:5:10) in foundation.

62.67

Cft

232

31

5 RCC(1:2:4) in plinth & lintel


level ties.

19.15

Cft

176

6 Brick masonry in CM(1:5) in


foundation, plinth & steps.

193.57

Cft

426

11 Steel in RCC works and


corner vertical reinforcement.

73.75

Kg

21 Precast RCC jalli.

24.00

Sft

350

2567
205

320

62
18

52

48
8

Quantities upto Plinth Level per Unit


Unit

834

205

320

48 2567

92

18

62

Kg

Rft

417
Bags

8 350

Rft

Rft

No.

Cft

Cft

Cft

No.

5125

8000

1200

64

2300

450 1550

200

Rft

Rft

Rft 1000's

Cft

16.7
Bags
Batch/No. of Units/Start Earth
Work Date

1 Batch 1: 25 Units (20-21/11)

Order On Supply
Before

20/11

21/11
Unit

2 Batch 2M*: 50 Units(27-29/11)

22-25/11 26/11

834 10250 16000

Unit

3 Batch 2S*: 20 Units(27-29/11)

22-25/11 26/11
Unit

4 Batch 3M*: 60 Units (5-7/12)

31/11 &
1-2/12

3/12

* M = Mullimanagar

31/11 &
1-2/12

3/12

*S = Srinivasapuram

Bags

Rft

Rft

334

4100

6400

Bags

Rft

Rft

1001 12300 19200

Unit

5 Batch 3S*: 20 Units (5-7/12)

Unit

Bags

Rft

Rft

334

4100

6400

Bags

Rft

Rft

2400

128

4600

Rft 1000's

Cft

960

51

1840

Rft 1000's

Cft

2880

154

Rft 1000's
960

Cft

Cft

No.

900 3100

400

Cft

Cft

No.

360 1240

160

Cft

No.

5520 1080 3720

480

Cft

51

1840

Rft 1000's

Cft

Cft

Cft

Cft

No.

360 1240

160

Cft

Cft

4 PCC(1:4:8) in flooring.

43.34

Cft

213

7 9 thick brick masonry pillars


in CM(1:5) in superstructure.

56.25

Cft

123

746

15

337.88

Sft

193

1724

24

11.72

Cft

27

156

178.81

Sft

132

8 4" thick brick masonry in


CM(1:5) in superstructure.
9 Cornice & coping brickwork in
CM(1:5) over gable walls.
10 Flooring in CM(1:5), 1 thick.

Quantities in Superstructure per Unit

688
Unit

21

Blue Metal 40mm - Cft.

Blue Metal 20mm - Cft.

River Sand - Cft.

Quantity Unit

Cement - Kg.

Description

Burnt Bricks - Nos.

SCHEDULE OF MATERIAL QUANTITIES IN SUPERSTRUCTURE FOR INDENT/SUPPLY (Type - B1 : On Highground)

No.

42

16
0 2626

79

No.

Cft

Cft

344

66

1975

1050

Bags

1000's

Cft

Cft

688

131

3950

2100

Bags

1000's

Cft

Cft

275

53

1580

840

Bags

1000's

Cft

Cft

826

158

4740

2520

Kg

42

13.8
Bags
Batch/No. of Units/Start
Superstructure Date

Order On Supply
Before

1 Batch 1: 25 Units (27-28/11)

22-25/11 26/11
Unit

2 Batch 2M*: 50 Units(4-6/12)

31/11 &
1-2/12

3/12
Unit

3 Batch 2S*: 20 Units(4/12)

31/11 &
1-2/12

3/12
Unit

4 Batch 3M*: 60 Units (11-13/12)

7-9/12

10/12

Filling Sand - Cft.

RCC Jalli 18"x24" - Nos.

Blue Metal 40mm - Cft.

Blue Metal 20mm - Cft.

River Sand - Cft.

Burnt Bricks - Nos.

Steel 8mm TOR - Rft.

Quantity Unit

Steel 6mm MS - Rft.

Description

Cement - Kg.

No.

Steel 10mm TOR - Rft.

SCHEDULE OF MATERIAL QUANTITIES UPTO PLINTH LEVEL FOR INDENT/SUPPLY (Type - B1 : On Highground)

No.

Cft

Unit

5 Batch 3S*: 20 Units (11/12)


* M = Mullimanagar

7-9/12

10/12

*S = Srinivasapuram

Unit

Bags

1000's

Cft

Cft

275

53

1580

840

Bags

1000's

Cft

Cft

12 Palmyrah wall plates, 4"x3".

40.00

Rft

13 Palmyrah/Coconut rafters,
5"x2" & collar ties, 4"x2".

300.00

Rft

14 Silverwood reepers, 2"x1".

378.00

Rft

15 Mangalore tiles.

435.00

No.

20.00

No.

435.00

No.

1.50

Kg.

5"x3/8" bolt, nut w/washers.

39.00

No.

4"x3/8" bolt, nut w/washers.

9.00

No.

19.50

Sft

16 Mangalore ridge tiles.


17 GI wire hooks.
18 Nails.

20 Neem framed door with


Silverwood battened shutter.

Silver Oak 11"x1"x6'-6" - Nos.

Neem 3"x2"x2'-6" - Nos.

Neem 4"x3"x3'-0" - Nos.

Neem 4"x3"x6'-6" - Nos.

Eucalyp. Reep. 2"x1"x7'-0" - Nos.

Palmyrah CT 4"x2"x6'-6" - Nos.

Palmyrah Raft. 4"x2"x8'-0" - Nos.

Palmyrah WP 4"x3"x10'-0" - Nos.

Ridge Tiles - Nos.

Mangalore Tiles - Nos.

6"x2"x1/4" MS Swivel Catch Nos.

8"x1/2" MS Aldrop Nos.

39"x2"x1/4" MS Strap Hinges Nos.

4"x3/8" Bolt, Nut & Washers Nos.

5"x3/8" Bolt, Nut & Washers Nos.

2" Nails Nos.

Quantity Unit

6" Nails Nos.

Description

No.

16 gauge x 12" GI Wire Nos.

SCHEDULE OF MATERIAL QUANTITIES IN DOOR & ROOF WORK FOR INDENT/SUPPLY (Type - B1 : On Highground)

4
26 13
54
435
20
450
1

0.5
40
10
2

Quantities in Door & Roof Work per Unit


Unit

450

0.5

40

10

435

26 13

Rft

Kg.

Kg.

No.

No.

No.

No.

No.

No.

No. No.

20

No. No.

54

11250

25

13

1000

250

50

25

25 10875

500 100

650 325 1350

Rft

Kg.

Kg.

No.

No.

No.

No.

No. No.

No. No.

No. No. No. No. No.

Batch/No. of Units/Start Door & Order On Supply


Before
Roof Frame Work Date

1 Batch 1: 25 Units (1&4/12)

20-21/11 30/11
Unit

2 Batch 2M*: 50 Units(7&9/12)

20-21/11 6/12
Unit

2 Batch 2S*: 20 Units(7&9/12)

20-21/11 6/12
Unit

3 Batch 3M*: 60 Units (14-16/12)

22-24/12 12/12
Unit

3 Batch 3S*: 20 Units (14-16/12)


* M = Mullimanagar

22-24/12 12/12

*S = Srinivasapuram

Unit

No.

No.

22500

50

25

2000

500

100

50

Rft

Kg.

Kg.

No.

No.

No.

No.

No.

No.

9000

20

10

800

200

40

20

20

8700

Rft

Kg.

Kg.

No.

No.

No.

No.

No.

No.

27000

60

30

2400

600

120

60

Rft

Kg.

Kg.

No.

No.

No.

No.

50

No. No.

No. No.

400

520 260 1080

No. No.

No. No.

No.

9000

20

10

800

200

40

20

20

8700

Rft

Kg.

Kg.

No.

No.

No.

No.

No.

No.

No. No.

400

520 260 1080

80

No. No.

50 150 150

40

20

60

60

No. No. No. No. No.

No. No.

No. No.

75

No. No. No. No. No.

60 26100 1200 240 1560 780 3240 120


No.

75

No. No. No. No. No.

50 21750 1000 200 1300 650 2700 100

80

25

60 180 180

No. No. No. No. No.


40

20

60

60

No. No. No. No. No.

SCHEDULE OF ADDITIONAL MATERIAL QUANTITIES UPTO PLINTH LEVEL FOR INDENT/SUPPLY (Type - C : On Riverfront)

2 Sand filling in plinth.

433.44

Cft

5b RCC(1:2:4) in strip footing.

80.44

Cft

711

6 Brick masonry in CM(1:5) in


foundation & plinth.

63.77

Cft

141

130.00

Kg

11 Steel in RCC strip footing.

37
846

17

74

758

188

758

188

846

54

74

Rft

Rft

No.

Cft

Cft

85

3790

940

270

370

Bags

Rft

Rft 1000's

Cft

Cft

852
Unit

Kg

17.0
Bags

1 Batch 2S*: 5 Units(27-29/11)


*S = Srinivasapuram

Filling Sand - Cft.

500

Additional Quantities upto Plinth Level per Unit

Batch/No. of Units/Start Earth


Work Date

Blue Metal 40mm - Cft.

Blue Metal 20mm - Cft.

River Sand - Cft.

Burnt Bricks - Nos.

Steel 10mm TOR - Rft.

Quantity Unit

Steel 6mm MS - Rft.

Description

Cement - Kg.

No.

Steel 8mm TOR - Rft.

With RCC Strip Raft Footing & Plinth Level at 4'-6" above Existing Ground Level

Order On Supply
Before

22-25/11 26/11
Unit

0 500
Cft

SCHEDULE OF MATERIAL QUANTITIES UPTO LINTEL LEVEL FOR INDENT/SUPPLY (Type - A : Raising & Repairing Walls & Floor)

4 PCC(1:4:8) in flooring.

43.34

Cft

213

8 4" thick brick masonry in


CM(1:5) in superstructure.

150.00

Sft

88

10 Flooring in CM(1:5), 1 thick.

178.81

Sft

132

Quantities in Superstructure per Unit

772

Blue Metal 40mm - Cft.

Blue Metal 20mm - Cft.

River Sand - Cft.

Burnt Bricks - Nos.

21

42

11
16

433
Unit

Steel 8mm TOR - Rft.

Steel 6mm MS - Rft.

Quantity Unit

Cement - Kg.

Description

No.

Steel 10mm TOR - Rft.

Additional Height & Repair of Damaged Walls & Raising Floor with Sub-grade

772

48

No.

Cft

Cft

43

240

210

Bags

1000's

Cft

Cft

173

15

960

840

Bags

1000's

Cft

Cft

Kg

42

8.7
Bags
Batch/No. of Units/Start
Superstructure Date

Order On Supply
Before

1 Batch 2M*: 5 Units(4-6/12)

31/11 &
1-2/12

3/12
Unit

2 Batch 2S*: 20 Units(4/12)


* M = Mullimanagar

31/11 &
1-2/12

3/12

*S = Srinivasapuram

Unit

12 Palmyrah wall plates, 4"x3".

40.00

Rft

13 Palmyrah/Coconut rafters,
5"x2" & collar ties, 4"x2".

300.00

Rft

14 Silverwood reepers, 2"x1".

378.00

Rft

15 Mangalore tiles.

435.00

No.

20.00

No.

435.00

No.

1.50

Kg.

5"x3/8" bolt, nut w/washers.

39.00

No.

4"x3/8" bolt, nut w/washers.

9.00

No.

16 Mangalore ridge tiles.


17 GI wire hooks.
18 Nails.

* M = Mullimanagar

Sd/K. Sudhir

Eucalyp. Reep. 2"x1"x7'-0" - Nos.

Palmyrah CT 4"x2"x6'-6" - Nos.

Palmyrah Raft. 4"x2"x8'-0" - Nos.

Palmyrah WP 4"x3"x10'-0" - Nos.

Ridge Tiles - Nos.

Mangalore Tiles - Nos.

6"x2"x1/4" MS Swivel Catch Nos.

8"x1/2" MS Aldrop Nos.

39"x2"x1/4" MS Strap Hinges Nos.

54
435
20
450
1

0.5
40
10

450

40

10

435

Rft

Kg.

Kg.

No.

No.

No.

2250

200

50

2175

20

26 13

54

No. No.

No. No.

No.

100

130

65

270

No. No.

No. No.

No.

400

520 260 1080

Order On Supply
Before

20-21/11 6/12
Unit

2 Batch 2S*: 20 Units(7&9/12)

4"x3/8" Bolt, Nut & Washers Nos.

26 13

Unit

1 Batch 2M*: 5 Units(7&9/12)

5"x3/8" Bolt, Nut & Washers Nos.

Quantities in Roof Work per Unit


Batch/No. of Units/Start Roof
Frame Work Date

2" Nails Nos.

Quantity Unit

6" Nails Nos.

Description

No.

16 gauge x 12" GI Wire Nos.

SCHEDULE OF MATERIAL QUANTITIES FOR CHANGE OF ROOF FOR INDENT/SUPPLY (Type - A : Tiled Roof)

20-21/11 6/12

*S = Srinivasapuram

Unit

Rft

Kg.

Kg.

No.

No.

No.

9000

20

10

800

200

8700

Rft

Kg.

Kg.

No.

No.

No.

20

80

No. No.

No. No.

No.

Architect - Director
20 November, 2006

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.

23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

PROPOSED HOUSING ASSISTANCE FOR SELECTED RESIDENTS OF


ORATHUR & VENNMANI VILLAGES, NAGAPATTINAM DISTRICT

3725 4445

Total Quantities per Unit 1MT


Unit

Kg

1 Earth work excavation.

370.00

Cft

2 Excavated earth filling in plinth.

Kg

67 147

59

12694

681

Kg

Kg

No.

Cft

Kg

29 4700

23 630 6600

Cft

Cft

Cft

250.00

Cft

54.00

Cft

4 PCC(1:5:10) in foundation.

74.00

Cft

313

37

74

5 PCC(1:4:8) in flooring.

87.00

Cft

431

42

84

6 RCC(1:2:4) in staircase footing beam


and plinth, lintel & roof level ties,
inclusive of steel.

48.00

Cft

442

7 RCC(1:2:4) in staircase waist &


landing slabs, inclusive of steel.

30.00

Cft

8 RCC(1:2:4) in pre-cast loft slab, 2"


thick inclusive of steel.

19.00

9 Ferro-Cement(1:1) in pre-cast joists


for Madras Terrace & brackets,
6"x1 thick, inclusive of steel.

No.

No.

No.

18 7.59
No.

Cft

96 288

91 1.31 0.91 66 20 131 75 4.00

Rft

Rft

Rft

Cft

Cft Sft Kg.

Sft Sft

65

67

62

22

44

276

29

41

14

27

Sft

32

131.00

Rft

201

47

10 Brick masonry in CM(1:6) in


foundation, plinth & steps.

288.00

Cft

510

3744

76

11 9 thick exposed brick masonry in


GM(1:2:9) in superstructure.

474.00

Cft

746

574

6162

125

12 9 thick brick masonry in GM(1:2:9) in


parapet walls.

107.00

Cft

168

129

1391

28

13 4" thick brick masonry in CM(1:5) in


superstructure.

93.00

Sft

53

465

14 3" thick brick masonry in CM(1:4) in


CB fin etc.

18.00

Sft

61

15 Corbelled brickwork in CM(1:4) at roof


level.

35.00

Cft

95

455

10

16 Brickwork in CM(1:4) in steps on waist


slab.

13.00

Cft

43

182

17 Coping brickwork in CM(1:5)


(including plaster) over gable walls.

79.00

Rft

117

234

14

160.00

Sft

1682

19 BJLC(1:3) for 2 average thickness


over Madras Terrace.

23.00

Cft

198

20 Pressed tiles 9"x9" laid & pointed in


CM(1:4) for weathering course.

148.00

Sft

157

16

21 GCC(1:1:3) flooring 1 thick.

267.00

Sft

482

21

22 Flooring in CM(1:5), 1 thick.

16.00

Sft

17

23 Cudappa stone slabs 1" thick in


shelving, sunshades & chajja fixed in
CM(1:4).

75.00

Sft

14

131

65

4700

23
270
29

75

Lit.

Reclaimed Mangalore Tiles - Nos.

Enamel Paint - Litres.

Cudappa Slabs 1" thick - Sft.

GI Chick. Mesh 22SWGx1"hole-Sft.

Nails - Kg.

Jackwood Planks 1" thick - Sft.

Jackwood 3"x2"/2"x1" - Cft.

CW Battens 3"x2" - Cft.

CW Reepers 2"x1" - Rft.

CW Reepers w/rebate 2"x1"-Rft.

Palmyrah Rafters 5"x3" - Rft.

Neem WP & DW Frames 4"x3"-Cft.

Mangalore Ridge Tiles - Nos.

Pan Tiles - Nos.

Pressed Terrace Tiles 9"x9"-Nos.

Broken Brick jelli 10-20mm - Cft.

Kandi Bricks 7"x4"x1" - Nos.

75 158
Cft

3 Sand filling in plinth.

18 6 thick Madras Terrace brickwork with


Kandi bricks in two layers, in LM(1:1).

Blue Metal 6-10mm - Cft.

Blue Metal 40mm - Cft.

Blue Metal 20mm - Cft.

River Sand - Cft.

Burnt Bricks - Nos.

Steel 10mm TOR - Rft.

Steel 8mm TOR - Rft.

Steel 6mm MS - Rft.

Labour Only

Quantity Unit

Cement - Kg.

Description

No.

Calcined Lime - Kg.

SCHEDULE OF MATERIAL QUANTITIES (Type - 1MT* : Madras Terrace with Staircase to Terrace & full Parapet Walls)

0
No.

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.

23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

24 Steel in corner vertical reinforcement.

14.00

Kg

25 Neem wood wall plates, 4"x3".

35.00

Rft

26 Palmyrah hand-hewn rafters,


5"x3"/2".

96.00

Rft

27 CW reepers, 2"x1" provided with


rebates, to detail.

288.00

Rft

28 Pressed tiles 9"x9" in under- layer.

207.00

Sft

29 Pan tiles in two layers.

207.00

Sft

30 Mangalore ridge tiles.

18.00

Rft

5.00

Kg.

32 Neem framed door with Jackwood


battened shutter.

39.00

Sft

2.67

0.63 39

1.75

33 Neem framed window with Jackwood


battened shutters.

27.00

Sft

2.00

0.28 27

1.25

34 Frameless gate & trellis in veranda


with CW reepers.

36.00

Sft

1.00

122.00

Sft

54

42

36 GM(1:2:9) wall plaster thick, for


internal faces of walls and external
faces of plinth & parapet walls.

1508.00

Sft

662

509

111

37 Lime wash for all plaster surfaces.

1630.00

Sft

215

203.00

Sft

1.00

LS

31 Nails & fixing bolts.

35 GM(1:2:9) ceiling plaster thick, for


soffits of Madras Terrace roof.

38 Enamel paint for all joinery.


39 Provision for demolition of existing
house & clearing site.

14
2.92
96
288
360
6600
18
5

91 1.31

/
3725 4445

Total Quantities per Unit 1MT


Unit

Kg

Kg

67 147

59

12694

681

Kg

Kg

No.

Cft

Kg

75 158

29 4700

23 630 6600

Cft

Cft

Cft

Cft

No.

No.

No.

18 7.59
No.

Cft

96 288

91 1.31 0.91 66 20 131 75

Rft

Rft

Rft

Cft

Cft Sft Kg.

Sft Sft

Lit.

No.

* Plinth Area per Unit = 380.19 Sft.

SCHEDULE OF MATERIAL QUANTITIES (Type - 1RC* : RCC Filler Slab with Staircase to Terrace & full Parapet Walls)
B/F Total Quantities per Unit 1MT

3725 4445

75 158

29 4700

23 630 6600

No.

Cft

Cft

Cft

Cft

53

49

97

-9

ADD

681

Kg

RCC(1:2:4) in filler roof slab, 4" thick


with reclaimed Mangalore tiles as filler
units, inclusive of steel.

173.25

Sft

990

Less

12694

Kg

RCC(1:2:4) in roof level tie, inclusive


of steel.

-10.00

Cft

-92

-8 -14

-5

Less

59

Kg

Ferro-Cement(1:1) in pre-cast joists


for Madras Terrace & brackets,
6"x1 thick, inclusive of steel.

-131.00

Rft

-201

-47

-8

Less

67 147

Kg

6 thick Madras Terrace brickwork with


Kandi bricks in two layers, in LM(1:1).

-160.00

Sft

###

Less

Kg

GM(1:2:9) ceiling plaster thick, for


soffits of Madras Terrace roof.

-122.00

Sft

-54

ADD

Unit

CM(1:4) ceiling plaster 1 thick, for


soffits of Filler Slab roof.

135.00

Sft

Total Quantities per Unit 1RC


Unit

-42

-9

168

17

Kg

68 139

59

12694

Kg

Kg

No.

Kg

No.

No.

18 7.59
No.

Cft

96 288

91 1.31 0.91 66 20 131 75

Rft

Rft

Rft

Cft

Cft Sft Kg.

Sft Sft

Lit.

No.

###

-4700

660 163 158


Cft

No.

168

-65

1989 5268
Kg

Cft

Cft

Cft

29

Cft

No.

23 630 6600
Cft

No.

No.

18 7.59
No.

Cft

96 288

91 1.31 0.91 66 20

Rft

Rft

* Plinth Area per Unit = 380.19 Sft.

SCHEDULE OF MATERIAL QUANTITIES (Typical Toilet Unit with shared Twin Leach Pit & Inspection Chamber)

Rft

Cft

Cft Sft Kg.

0 75
Sft Sft

4 168
Lit.

No.

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.

Total Quantities per Toilet Unit

56

313

992

49

17

16

Unit

Kg

Kg

Kg

Kg

Kg

No.

Cft

Cft

Cft

Cft

Set

Kg

Kg

Sft

Rft

16

1 Earth work excavation.

38.00

Cft

7.00

Cft

3 PCC(1:5:10) in foundation & floor.

14.00

Cft

59

4 Brick masonry in CM(1:6) in


foundation, plinth & steps.

27.00

Cft

48

351

117.00

Sft

67

585

6 Flooring in CM(1:5), 1 thick.

25.00

Sft

26

7 Frameless door with cement-bonded


particle board , 10mm thick mounted
on ISA 25x25x4 frame.

12.00

Sft

8 GM(1:2:9) wall plaster thick, for


4'-0" high dado on internal faces of
walls and external faces of plinth.

87.00

Sft

39

12

2 Sand filling in plinth.

5 4" thick brick masonry in CM(1:5) in


superstructure.

9 Lime wash for all plaster surfaces.

87.00

Sft

10 Enamel paint for ISA frame in door.

7.00

Sft

11 Vitreous China IWC with P-Trap &


Footrests

1.00

Set

12 PVC Pipe 4" dia. (4 Kg/Sq.Cm)

7.00

Rft

13 Leach Pit with 36"IDx12"Hx2" thick


pre-cast RCC well rings for 4'-0"
depth, incl. of RCC cover slab 3" thk.

1.00

No.

14 Inspection Chamber 18"x18"x18"


deep, in 4 thick brickwork in CM
(1:5), inclusive of benching, plastering
& RCC cover slab 3" thk.

1.00

No.

Enamel Paint - Litres.

4 0.30
No.

Lit.

/
9
7

14

30

0.30
1
7
23

60

Total Quantities per Toilet Unit

56

313

992

49

17

16

Unit

Kg

Kg

Kg

Kg

Kg

No.

Cft

Cft

Cft

Cft

Set

Kg

Kg

Sft

Rft

* Plinth Area per Unit = 32.06 Sft.

Pre-cast RCC Well Rings - No.

PVC Pipe 4" dia.

BISON Panel 10mm thick - Sft

MS Flat 25x4 & Pivots - Kg.

ISA 25x25x4 - Kg.

IWC Pan, P-trap & footrests - Set

Broken Brick jelli 20-50mm - Cft.

Blue Metal 40mm - Cft.

Blue Metal 20mm - Cft.

River Sand - Cft.

Burnt Bricks - Nos.

Steel 10mm TOR - Kg.

Steel 8mm TOR - Kg.

Steel 6mm MS - Kg.

Labour Only

Quantity Unit

Cement - Kg.

Description

No.

Calcined Lime - Kg.

23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

56

4 0.30
No.

Lit.

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

PROPOSED HOUSING ASSISTANCE FOR SELECTED RESIDENTS OF ORATHUR &


VENNMANI VILLAGES, NAGAPATTINAM DISTRICT
MATERIAL COST ESTIMATE FOR HOUSE TYPE 1MT* (with accessible Madras Terrace)
For delivery at Orakkadu/Vennmani Villages, Nagapattinam District
No

Description

Quantity Cost (July/09) Unit

1 Calcined Lime (Freshly burnt limestone >75% pure) 3,725.00


Jeyamkondam
2 Cement (PPC)
4,445.00
3 Steel MS
67.00
4 Steel HYSD Tor40
206.00
5 Ground Moulded Country Bricks
12,694.00
6 River Sand - Kollidam
681.00
7 Blue Metal Aggregate 20mm/3/4"[15-20mm] - Karur
75.00
8 Blue Metal Aggregate 40mm/1 1/2"[20-50mm] - Karur
158.00
9 Blue Metal Aggregate 10mm/1/2"[10-15mm] - Karur
29.00
10 Kandi Bricks (Country clamp-fired)
4,700.00
11 Broken Brick Aggregate 20mm/3/4"[10-20mm]
23.00
12 Pressed Clay Terrace tiles 9"x9"
630.00
13 Reclaimed/New Pan Tiles for roof
6,600.00
14 Mangalore Ridge Tiles
18.00
15 Neem Wall Plate & Door/Window Frames 4"x3"
7.59
16 Palmyrah Rafters 5"x2"/3" >50% hardened fibre
96.00
17 CW Reepers with rebates 2"x1"
288.00
18 CW Reepers 2"x1"
91.00
19 CW Battens 3"x2"
1.31
20 Jackwood 3"x2"/2"x1"
0.91
21 Jackwood Planks 1" thick
66.00
22 Nails, Screws, Bolts, Strap Hinges & other hardware.
20.00
23 GI Chicken Mesh (22 SWG x 3/4" holes)
131.00
24 Cudappa Slabs 1" thick
75.00
25 Enamel Paint for Joinery only
4.00
26 Miscellaneous & Contingency
150,477.40

3.00

Kg

5.20 Kg
33.00 Kg
34.00 Kg
3.35 No.
15.00 Cft
28.00 Cft
26.00 Cft
26.00 Cft
2.00 No.
19.00 Cft
9.50 No.
1.00 No.
36.00 No.
700.00 Cft
16.00 Rft
12.00 Rft
7.50 Rft
500.00 Cft
1000.00 Cft
100.00 Sft
45.00 Kg
4.00 Sft
35.00 Sft
250.00 Litres
0.03 Cost

Material Cost Estimated per House Type 1MT

Amount
11,175.00
23,114.00
2,211.00
7,004.00
42,524.90
10,215.00
2,100.00
4,108.00
754.00
9,400.00
437.00
5,985.00
6,600.00
648.00
5,313.00
1,536.00
3,456.00
682.50
655.00
910.00
6,600.00
900.00
524.00
2,625.00
1,000.00
4,514.32

154991.72

* Plinth Area per Unit = 380.19 Sft.

MATERIAL COST ESTIMATE FOR HOUSE TYPE 1RC* (w/accessible RCC Filler Slab)
For delivery at Orakkadu/Vennmani Villages, Nagapattinam District
No
1
2
3
4
5
6

Description
Calcined Lime (Freshly burnt limestone >75% pure)
Cement (PPC)
Steel MS
Steel HYSD Tor40
Ground Moulded Country Bricks
River Sand - Kollidam

Quantity Cost (July/09) Unit

Amount

1,989.00
5,268.00
68.00
198.00
12,694.00
660.00

5,967.00
27,393.60
2,244.00
6,732.00
42,524.90
9,900.00

3.00
5.20
33.00
34.00
3.35
15.00

Kg
Kg
Kg
Kg
No.
Cft

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

7
8
9
10
11

Blue Metal Aggregate 20mm/3/4"[15-20mm] - Karur


Blue Metal Aggregate 40mm/1 1/2"[20-50mm] - Karur
Blue Metal Aggregate 10mm/1/2"[10-15mm] - Karur
Broken Brick Aggregate 20mm/3/4"[10-20mm]
Reclaimed/Reject Mangalore Tiles for Filler Slab roof

163.00
158.00
29.00
23.00
168.00

28.00
26.00
26.00
19.00
6.00

Cft
Cft
Cft
Cft
No.

4,564.00
4,108.00
754.00
437.00
1,008.00

12
13
14
15
16
17
18
19
20
21
22

Pressed Clay Terrace tiles 9"x9"


Reclaimed/New Pan Tiles for roof
Mangalore Ridge Tiles
Neem Wall Plate & Door/Window Frames 4"x3"
Palmyrah Rafters 5"x2"/3" >50% hardened fibre
CW Reepers with rebates 2"x1"
CW Reepers 2"x1"
CW Battens 3"x2"
Jackwood 3"x2"/2"x1"
Jackwood Planks 1" thick
Nails, Screws, Bolts, Strap Hinges & other hardware.

630.00
6,600.00
18.00
7.59
96.00
288.00
91.00
1.31
0.91
66.00
20.00

9.50
1.00
36.00
700.00
16.00
12.00
7.50
500.00
1000.00
100.00
45.00

No.
No.
No.
Cft
Rft
Rft
Rft
Cft
Cft
Sft
Kg

5,985.00
6,600.00
648.00
5,313.00
1,536.00
3,456.00
682.50
655.00
910.00
6,600.00
900.00

23 Cudappa Slabs 1" thick


24 Enamel Paint for Joinery only
25 Miscellaneous & Contingency

75.00
4.00
142,543.00

35.00 Sft
250.00 Litres
0.03 Cost

Material Cost Estimated per House Type 1RC

2,625.00
1,000.00
4,276.29

146819.29

* Plinth Area per Unit = 380.19 Sft.

PROPOSED TOILET UNIT* WITH HOUSE PROTOTYPE FOR SELECTED


RESIDENTS OF ORATHUR & VENNMANI VILLAGES, NAGAPATTINAM DISTRICT
MATERIAL COST ESTIMATE FOR TOILET UNIT WITH HOUSE PROTOTYPE
delivery at Orakkadu/Vennmani Villages, Nagapattinam District
No

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Calcined Lime (Freshly burnt limestone >75% pure)


Cement (PPC)
Steel HYSD Tor40
Ground Moulded Country Bricks
River Sand - Kollidam
Blue Metal Aggregate 20mm/3/4"[15-20mm] - Karur
Blue Metal Aggregate 40mm/1"[20-50mm] - Karur
Broken Brick Aggregate 40mm/1"[20-50mm]
Pre-cast RCC Well Rings 36"IDx12"H
ISA 25x25x4 and MS Flats 25x4 for Toilet Door Shutte
BISON Panel (Cement bonded particle board) 10mm t
Enamel Paint for MS Door Shutter Frame only
Vitreous China IWC with P-Trap & Footrests
PVC Pipe 4" dia. (4 Kg/Sq.Cm)
Miscellaneous & Contingency

Material Cost Estimated per Toilet Unit


* Plinth Area per Unit = 32.06 Sft.

Quantity Cost (July/09) Unit


56.00
313.00
8.00
992.00
49.00
4.00
17.00
1.00
4.00
10.00
16.00
0.30
1.00
9.00
9,369.80

3.00 Kg
5.20 Kg
34.00 Kg
3.35 No.
15.00 Cft
28.00 Cft
26.00 Cft
15.00 Cft
300.00 No.
35.00 Kg
30.00 Sft
250.00 Litre
300.00 Set
30.00 Rft
0.03 Cost

For
Amount
168.00
1,627.60
272.00
3,323.20
735.00
112.00
442.00
15.00
1,200.00
350.00
480.00
75.00
300.00
270.00
281.09

9650.894

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

PROPOSED HOUSING ASSISTANCE FOR SELECTED RESIDENTS OF ORATHUR &


VENNMANI VILLAGES, NAGAPATTINAM DISTRICT
LABOUR COST ESTIMATE FOR HOUSE TYPE 1MT*
Type- 1MT : Madras Terrace with Staircase to Terrace & full Parapet Walls
No

Description

Quantity Materl. Cost

Labour Cost

Unit

Amount

1 Marking foundation & plinth


band.
2 Earth work excavation.

380.00 Rs.

Rs.

2.00

Sft

Rs.

760.00

370.00 Rs.

Rs.

2.67

Cft

Rs.

986.67

3 Excavated earth filling in plinth.

250.00 Rs.

Rs.

1.33

Cft

Rs.

333.33

4 Sand filling in plinth.

54.00 Rs.

Rs.

1.33

Cft

Rs.

72.00

5 PCC(1:5:10) in foundation.

74.00 Rs.

Rs.

6.00

Cft

Rs.

444.00

6 PCC(1:4:8) in flooring.

87.00 Rs.

Rs.

6.67

Cft

Rs.

580.00

7 RCC(1:2:4) in staircase footing


beam and plinth, lintel & roof
level ties, inclusive of steel.

48.00 Rs.

Rs.

42.00

Cft

Rs.

2,016.00

8 RCC(1:2:4) in staircase waist &


landing slabs, inclusive of steel.

30.00 Rs.

Rs.

38.00

Cft

Rs.

1,140.00

9 RCC(1:2:4) in pre-cast loft slab,


2" thick, inclusive of steel.

19.00 Rs.

Rs.

22.00

Sft

Rs.

418.00

10 Ferro-Cement(1:1) in pre-cast
joists for Madras Terrace &
brackets, 6"x1 thick, incl. of
steel & mesh.
11 Brick masonry in CM(1:6) in
foundation, plinth & steps.

131.00 Rs.

Rs.

14.00

Rft

Rs.

1,834.00

288.00 Rs.

Rs.

8.00

Cft

Rs.

2,304.00

12 9 thick exposed brick masonry


in GM(1:2:9) in superstructure.

474.00 Rs.

Rs.

12.00

Cft

Rs.

5,688.00

13 9 thick brick masonry in


GM(1:2:9) in parapet walls.

107.00 Rs.

Rs.

12.67

Cft

Rs.

1,355.33

14 4" thick brick masonry in


CM(1:5) in superstructure.

93.00 Rs.

Rs.

7.00

Sft

Rs.

651.00

15 3" thick brick masonry in


CM(1:4) in CB fin etc.

18.00 Rs.

Rs.

6.67

Sft

Rs.

120.00

16 Corbelled brickwork in CM(1:4)


at roof level.

35.00 Rs.

Rs.

16.00

Cft

Rs.

560.00

17 Brickwork in CM(1:4) in steps on


waist slab.

13.00 Rs.

Rs.

60.00

Cft

Rs.

780.00

18 Coping brickwork in CM(1:5)


(including plaster) over
gable/parapet walls.

79.00 Rs.

Rs.

24.00

Rft

Rs.

1,896.00

19 6 thick Madras Terrace


brickwork with Kandi bricks in
two layers, in LM(1:1).

160.00 Rs.

Rs.

13.33

Sft

Rs.

2,133.33

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

20 BJLC(1:3) for 2 average


thickness over Madras Terrace.

23.00 Rs.

Rs.

16.00

Cft

Rs.

368.00

21 Pressed tiles 9"x9" laid &


pointed in CM(1:4) for
weathering course.
22 GCC(1:1:3) flooring 1 thick.

148.00 Rs.

Rs.

8.00

Sft

Rs.

1,184.00

267.00 Rs.

Rs.

6.67

Sft

Rs.

1,780.00

23 Flooring in CM(1:5), 1 thick.

16.00 Rs.

Rs.

4.00

Sft

Rs.

64.00

24 Cudappa stone slabs 1" thick in


shelving, sunshades & chajja
fixed in CM(1:4).

75.00 Rs.

Rs.

16.00

Sft

Rs.

1,200.00

25 Steel in corner vertical


reinforcement.
26 Neem wood wall plates, 4"x3".

14.00 Rs.

Rs.

8.00

Kg

Rs.

112.00

35.00 Rs.

Rs.

8.00

Rft

Rs.

280.00

27 Palmyrah hand-hewn rafters,


5"x3"/2".
28 CW reepers, 2"x1" provided
with rebates, to detail.

96.00 Rs.

Rs.

12.00

Rft

Rs.

1,152.00

288.00 Rs.

Rs.

3.00

Rft

Rs.

864.00

207.00 Rs.

Rs.

3.00

Sft

Rs.

621.00

207.00 Rs.

Rs.

5.00

Sft

Rs.

1,035.00

18.00 Rs.

Rs.

16.00

Rft

Rs.

288.00

5.00 Rs.

Rs.

Kg

Rs.

33 Neem framed door with


Jackwood battened shutter.

39.00 Rs.

Rs.

80.00

Sft

Rs.

3,120.00

34 Neem framed window with


Jackwood battened shutters.

27.00 Rs.

Rs.

73.33

Sft

Rs.

1,980.00

35 Frameless gate & trellis in


veranda with CW reepers.

36.00 Rs.

Rs.

60.00

Sft

Rs.

2,160.00

122.00 Rs.

Rs.

7.20

Sft

Rs.

878.40

1508.00 Rs.

Rs.

4.80

Sft

Rs.

7,238.40

1630.00 Rs.

Rs.

1.00

Sft

Rs.

1,630.00

203.00 Rs.

Rs.

4.00

Sft

Rs.

812.00

37039.00 Rs.

Rs.

740.78

703.00 Rs.

Rs.

0.02 Civil
labo
ur
2.00 Sft

Rs.

1,406.00

1.00 Rs.

Rs.

Rs.

2,000.00

29 Pressed tiles 9"x9" in underlayer.


30 Pan tiles in two layers.
31 Mangalore ridge tiles.
32 Nails & fixing bolts.

36 GM(1:2:9) ceiling plaster


thick, for soffits of Madras
Terrace roof.
37 GM(1:2:9) wall plaster thick,
for internal faces of walls and
external faces of plinth &
parapet walls.
38 Lime wash for all plaster
surfaces.
39 Enamel paint for all joinery.
40 Provision for curing.
41 Provision for scaffolding.
42 Provision for demolition of
existing house & clearing site.

Labour Cost Estimated per House Type 1MT


* Plinth Area per Unit = 380.19 Sft.

2,000.00

LS

Rs. 54,985.25

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

LABOUR COST ESTIMATE FOR HOUSE TYPE 1RC*


Type - 1RC : RCC Filler Slab with Staircase to Terrace & full Parapet Walls
No

Description

Quantity Materl. Cost

Unit

Amount
54,985.25

Rs.

29.33

Cft

Rs.

1,906.67

Rs.

42.00

Cft

Rs.

(420.00)

ADD

Less

Less

Less

ADD

Rs.

Less

B/ Labour Cost Estimated per House Type A2MT


F
RCC(1:2:4) in filler roof slab,
65.00 Rs.
4" thick with reclaimed
Mangalore tiles as filler units,
inclusive of steel.
RCC(1:2:4) in roof level tie,
-10.00 Rs.
inclusive of steel.

Labour Cost

Ferro-Cement(1:1) in pre-cast
joists for Madras Terrace &
brackets, 6"x1 thick, inclusive
of steel.
6 thick Madras Terrace
brickwork with Kandi bricks in
two layers, in LM(1:1).

-131.00 Rs.

Rs.

14.00

Rft

Rs.

(1,834.00)

-160.00 Rs.

Rs.

13.33

Sft

Rs.

(2,133.33)

GM(1:2:9) ceiling plaster


thick, for soffits of Madras
Terrace roof.
CM(1:4) ceiling plaster 1 thick,
for soffits of Filler Slab roof.

-122.00 Rs.

Rs.

7.20

Sft

Rs.

(878.40)

135.00 Rs.

Rs.

8.00

Sft

Rs.

1,080.00

Labour Cost Estimated per House Type 1RC

Rs. 52,706.18

* Plinth Area per Unit = 380.19 Sft.

PROPOSED TOILET UNIT* WITH HOUSE PROTOTYPE FOR SELECTED RESIDENTS


OF ORATHUR & VENNMANI VILLAGES, NAGAPATTINAM DISTRICT
LABOUR COST ESTIMATE FOR TOILET UNIT WITH HOUSE PROTOTYPE
IWC & Bath with 6'-0" Enclosure Walls & Shared Twin Leach Pit Disposal System
No

Description

1 Earth work excavation.

Quantity Materl. Cost

Labour Cost

Unit

Amount

38.00 Rs.

Rs.

2.67

Cft

Rs.

101.33

7.00 Rs.

Rs.

1.33

Cft

Rs.

9.33

14.00 Rs.

Rs.

6.00

Cft

Rs.

84.00

27.00 Rs.

Rs.

8.00

Cft

Rs.

216.00

117.00 Rs.

Rs.

7.00

Sft

Rs.

819.00

6 Flooring in CM(1:5), 1 thick.

25.00 Rs.

Rs.

4.00

Sft

Rs.

100.00

7 Frameless door with cement


bonded particle board fixed to
ISA frame.

12.00 Rs.

Rs.

60.00

Sft

Rs.

720.00

2 Sand filling in plinth.


3 PCC(1:5:10) in foundation &
flooring.
4 Brick masonry in CM(1:6) in
foundation & plinth.
5 4" thick brick masonry in
CM(1:5) in superstructure.

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

8 GM(1:2:9) wall plaster thick,


for internal faces of walls upto 4'0" high and external faces of
plinth.
9 Lime wash for all plaster
surfaces.
10 Enamel paint for door.

87.00 Rs.

Rs.

4.80

Sft

Rs.

417.60

87.00 Rs.

Rs.

1.00

Sft

Rs.

87.00

7.00 Rs.

Rs.

4.00

Sft

Rs.

28.00

1732.93 Rs.

Rs.

34.66

12 IWC with foot rests and trap.

1.00 Rs.

Rs.

Rs.

400.00

13 4"dia. PVC pipe connection to IC


& Leach Pit.

7.00 Rs.

Rs.

20.00

Rft

Rs.

140.00

14 Leach Pit of 36" inner dia. and


48" deep, in 2 thick pre-cast
RCC well rings and provided
with a RCC cover slab 3" thick.

1.00 Rs.

Rs.

500.00

Set

Rs.

500.00

15 Inspection Chamber (shared) of


size 18"x18" and 18" deep, in
4 thick brickwork in CM (1:5),
inclusive of benching and
plastering and provided with a
RCC cover slab 3" thick.

1.00 Rs.

Rs.

400.00

Set

Rs.

400.00

11 Provision for curing.

Labour Cost Estimated per Toilet Unit


* Plinth Area per Unit = 32.06 Sft.

0.02 Civil
labo
ur
400.00 Set

Rs.

4,056.93

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

Rs.

26,921.00

Rs.

9,746.80

Rs.

36,667.80

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

PEOPLES ARCHITECTURE COMMONWEAL (Pvt.) Ltd.


23 (Old No. 10), 7th. Cross Street West, Shenoy Nagar, Chennai - 600 030. Tel. 2622 3347 2626 0797

Rs.

1,732.93

You might also like