Professional Documents
Culture Documents
Abstract
A transmission line trip during a power swing may
cause instability of a power system. It is necessary
to recognize the power swing from fault. Based on
stability boundary, the power swing blocking d a y s
must be set. To do that, first power swing should be
analyzed. Second a way of probability of occurrence
of fault must be found. Third, the critical condition
under which the stability of a power system h a s a
been disturbed is recognized. Finally the setting of
the power swing relays are calculated. In this paper
analysis of the power swing occurrence has been
made. By defining transmissions and generators
sensitivities coefficients, the way of making the line
under consideration full load is found. The way of
minimization of distance between load impedance
and the last zone of distance protection is given and
the setting of the power swing relays are
calculated.
Keywords: Power system stability, Power swing
protection, Semitivity analysis.
1
Introduction
References [47]
have analyzed power
swing
performance. References [S,91 focused on the new
ways of detection of power swing. In reference 1101
steady -state security control using sensitivity
approach is described.
In this paper, first the change of the parameters are
specified and sensitivity coefficients both for
transmission lines and generators are identified.
Then the way of minimization of distance between
load impedance and the last zone of protection is
given. This procedure for outage of the influenced
line is done. Finally a computer simulation for the
approach and whether power swing exists or not,
has been developed. If power swing occurs the
settings of the power swing relays are calculated.
The computer program was tested on some real
power system networks including Azarbayjan
network, and final result showed that the method
was successful. Some useful results plus analysis
will be given below [4, 101.
2
The stability
1410
4'i
(1)
ApL
=-
=-e
Q~~
as
d,
is distribution outage coefficient for
supervision on line L because of line outage k.
APL is power variation in h e L and PR is power
of line K before outage. If power flow in lines L and
K before outage is known, the power of line L after
outage of K is computed easily by d, :
APL
(5)
L
Equation (6) which is extracted from load flow
study for n busbar network is given by141 :
d,, =-
(31
f L * = f L +aLiAPi
fL
Where:
X , is the line reactance of K.
Condition
4 =-p:
l i d
The last
Gcncrat
Computer algorithm
1411
Testresult
I
I
Gilan
Station
0.592
I Generation
Taghidizeh
Ahartaghidize
h n e l -Taghidize
I .oo
1.m
Lines coefficient
Poonel Taghldizeh
hhtGila
1 .M)
1 .oo
Rasht-Poonel
. Poonel-
Shahid
RajaeeTabriz
a436
Shahid
Raj=Tabriz
0.620
1412
I
conclusions
8 Refrences
[l] Isolation of
Azarbayjan network from
Iranilnterconnectedpower system on 17 Feb.
1413