JAN 2011
REV 0
QUALITY MANUAL
Page 1
JAN 2011
REV 0
Deliverables
Inputs
Prelim. Reports
Issue BoD
Prelim. Drawings
Visit site
Who is responsible for council plan
approval
Reports
Preliminary Design
Structural loads
Architectural impacts/aesthetics?
External services required (steam
compressed air
Co-ordination
Architect
Electrical Engineer
Plumbing/Drainage consultant
Structural Engineer
Fire consultant
Client to confirm any changes
QUALITY MANUAL
Page 2
JAN 2011
REV 0
Deliverables
Inputs
Drawings
Ducting
Dust extract
Piping
AHU plantrooms
properties (U-values)
Chiller/refrigeration plantrooms
Design
Airflow schematics
P&ID schematics (CW, HW, Steam, CA,
etc.)
Zone concepts
Pressure cascades
Door schedules
AHU sizing
Chiller/refrigeration plant sizing
Pump sizing
AHU Failure/start-up matrix
Spatial design for duct and plant fit
Identify any deep beam or truss
constrictions
Spatial design for plant egress into
building
Determine battery limits for services by
others
QMS documentation in place
Specifications
Resolve Form of Contract with QS or
client
Contractual specs. - Parts 1, 2 & 3
QUALITY MANUAL
Page 3
JAN 2011
REV 0
Margins Correct
QUALITY MANUAL
Co-ordination
Detailed co-ordination required with
other disciplines, site conditions, etc.:
Elec. Eng.: Co-ordinate light fittings
Electr. Eng.: Smoke detectors & PA
systems
Fire: Co-ordinate with sprinklers
CRm. Panelling: Co-ordinate with
electrical
conduits, maglocks, break-glass units,
etc.
Page 4
JAN 2011
REV 0
QUALITY MANUAL
Page 5
QUALITY MANUAL
JAN 2011
REV 0
Page 6
JAN 2011
REV 0
Prepare IQ Plan
QUALITY MANUAL
Page 7
Site Administration:
Installation Qualification Check
Lists
Description
No
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
Actio
Remarks
n
1 General
1.1Masonry holes by others, provided &
correct
1.2Plinths provided & correct
1.3Electrical supplies in correct positions
1.4Potable water supplies in correct
positions
1.5Building access suitable for equipment
egress
1.6
1.7
2 AHUs & Fans
2.1General - unit free of rust, obvious
damage and is clean
2.2Fan belt guard in place
2.3Fan discharge safety screen fitted
2.4Fan inlet safety screen fitted
2.5Fan AV mounts
2.6Fan flexible connections
2.7Fan transport mountings removed
2.8Fan local isolator or L.O.S installed
2.9Name plate ratings correspond with
submissions
2.10
AHU pressure test certificate
2.11
Cooling coil drip tray sloped
2.12
Cooling coil drain & trap
2.13
Coil drip tray length ok for collection
carry-over
2.14
Coil drip tray insulated
2.15
Control valves (2 or 3-way) correctly
installed
2.16
Intermediate drip tray if coil higher
than 1200mm
2.17
Anti freeze thermostats (DX coil only)
QUALITY MANUAL
Page 8
Site Administration:
Installation Qualification Check
Lists
2.18
Refrigerant pipes installed in trunking?
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
2.19
Seal on coil flashing ok
2.20
Drip tray condensate drain insulated for
1st 5m
2.21
Coil fins damaged - requires combing
2.22
Filter frame flashing sealed ok
2.23
Filter frame stifening supports installed
(large banks)
2.24
Filter clips/clamps all in place - Primary
2.25
Filter clips/clamps all in place Secondary
2.26
Primary filters installed are of the
correct efficiency & depth
2.27
Secondary filters installed are of the
correct efficiency
2.28
HEPA filters installed are of the correct
efficiency
2.29
Filter clamps all in place - HEPA
2.30
All filter gaskets installed
2.31
AHU plenum clean & in good condition
2.32
Plenum doors & DOP panel in place &
correct size
2.33
Door swing direction (pressure holds
closed)
2.34
Doors well sealed - gaskets undamaged
2.35
Door handles work
correctly/satisfactorily
2.36
Door port holes (VPs) installed and
airtight/waterproof
2.37
Door latches opening direction marked
2.38
Doors can open from inside?
2.39
Commissioning data/reports and fan
performance
2.40
AHU scratches need to be touched up
2.41
RA & FA dampers installed
2.42
WMS on FA grille
2.43
Bulkhead lights installed in each
compartment
2.44
Light switch with LED fitted.
QUALITY MANUAL
Page 9
Site Administration:
Installation Qualification Check
Lists
2.45
DOP valve fitted to fan plenum
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
2.46
Pressure diferential ports installed for
each component
2.47
Magnahelics installed for each filter
bank
2.48
Magnahelics operating correctly
2.49
Magnahelics piping silicone, neat and
no kinks
2.50
Magnahelics red-lined & green lined
2.51
Spacer frame fitted for close coupled
filters
2.52
AHUs, ducting and plant room to be
cleaned thoroughly.
2.53
All AHUs are labelled according to the
labelling specification
2.54
Correct scale Magnahelic gauges have
been installed on the filter banks. Preprimary, primary filters (0-500 Pa) and
Secondary & HEPA filters (0-750 Pa)
2.55
Magnahelic
gauges
have
been
calibrated
2.56
All conduit junctions have cover plates
installed.
2.57
Each HEPA filter has been provided with
its own factory test certificate in
accordance with clause 4.17.4.5.6
2.58
HEPA Integrity/DOP test certificates
issued
2.59
Primary and secondary filters shall be
provided with SABS filter efficiency
certificates from the manufacturer.
2.60
The control wiring is neat and
complete.
2.61
Fan cable entry through panel sealed
2.62
AHU panel joints sealed adequately
2.63
Sound attenuators installed
2.64
DBs marked red (essential) and orange
(non essential)
2.65
Danger signs for all moving equipment
3 Ducting & Air Terminals
3.1Installed as per approved drawings
3.2Duct sheet-metal gauge correct
3.3Hanger spacing correct
QUALITY MANUAL
Page 10
Site Administration:
Installation Qualification Check
Lists
3.4Hanger angles painted
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
QUALITY MANUAL
Page 11
Site Administration:
Installation Qualification Check
Lists
4 Piping & Pipe Fittings
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
QUALITY MANUAL
Page 12
Site Administration:
Installation Qualification Check
Lists
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
4.27
4.28
5 Chillers, Condensing Units &
Pumps
5.1Installed as per approved drawings
5.2Mark of all fittings on P&ID against
actual
5.3Mounted on springs or AV pads as
specified
5.4Hail guards installed on exposed
condenser coils
5.5Bases painted or suitable corrosion
control
5.6Drains led to nearest outlet
5.7Drains of adequate size
5.8Joints acceptable (flange, screwed or
unions)
5.9All drives fitted with local isolator or
L.O.S
5.10
All fridge piping installed in trunking
5.11
Fridge piping insulation correct
5.12
Fridge unit vacuum tests
5.13
Pump strainers fitted
5.14
Strainer has bleed valve
5.15
Pump low-flow protection fitted
5.16
Shut-of valves as per drawing
5.17
Pump drip tray fitted
5.18
Make-up tanks installed
5.19
Expansion line open (not valved)
5.20
Make-up tank installed at adequate
height
5.21
Bladder expansion/make-up vessels
5.22
Bladder vessel PRV at correct setting
5.23
5.24
6 BMS/Controls
QUALITY MANUAL
Page 13
Site Administration:
Installation Qualification Check
Lists
6.1All sensors/controllers labelled
JAN 2011
REV 0
Project:
..
...
Date of Inspection:
Chec
...
k
QUALITY MANUAL
Page 14
JAN 2011
REV 0
7 Architecture/Cleanroom Panelling
7.1All door frames mitre joints are neat
and flush
7.2All door hinges dont make a noise
when opening and closing the doors.
7.3All door catches are set correctly and
operate smoothly.
7.4All door hardware is complete as per
the door schedule.
7.5Door closers adequate to latch doors
against room pressure
7.6Wall, Ceiling and Coving joints are
sealed neatly with food-grade sealant
only
7.7Door interlocks functioning
7.8Coving joints at corners acceptable
7.9Door closers fitted with hold-open
devices where specified
7.10
Cut-out edges capped or mastic
treated
7.11
Cut-outs fitted with T-frames for SAD
mounting where required.
7.12
Silicon joint seal recess <1mm (Clause
4.18.4.2)
7.13
Silicon clean and matches panel
colour
7.14
Doors dont catch on floor and frame
7.15
Doors have butt or re-bated meeting
styles
7.16
Gap at bottom of door acceptable
7.17
Gap between meeting styles
acceptable
7.18
Gap between door and frame
acceptable
7.19
Gaskets fitted to door frames
7.20
Locks fitted where specified
7.21
Locks with individual keys or master
keys?
7.22
Maglocks fitted and operational
7.23
Maglock breakglass units fitted
7.24
Magnahelic gauges neatly fitted
7.25
Magnahelic gauges connected with
silicone tubing
7.26
Magnahelic gauges zeroed
7.27
Magnahelic gauges red-lined or colour
coded
7.28
Magnahelic pressure tolerances
indicated
QUALITY MANUAL
Page 15
JAN 2011
REV 0
7.29
Magnahelic calibration certificates
received
7.30
Light fittings installed flush with
ceiling
7.31
Light fittings installed air-tight
7.32
All light fittings screws in place
7.33
No exposed wiring on prismatic
difusers
7.34
All corner caps fitted
7.35
End stops fitted and secure
7.36
Scratches or dents on panelling
7.37
Bump rails or bump plates fitted
7.38
No sharp edges on bump plates on
doors and walls.
7.39
Ceilings level/sagging?
7.40
Walls & ceilings have correct
insulation fill
7.41
Fire certificates for walls issued (if
applicable)
7.42
Viewing panels have desiccant fill
7.43
Viewing panels correct size
7.44
Pass-through hatches have stainless
steel floor
7.45
PTHs maglocks interlocks functioning
correctly
7.46
7.47
= item inspected and acceptable
N = no
Y = yes
QUALITY MANUAL
Page 16