13.2MWSolarPlantBuiltUsing3DMeasurementSolarPowerPlantBusiness
13.2MWSolarPlantBuiltUsing3DMeasurement
Workloadalleviatedbyaccuratemeasurementofundulations
ShinichiKato,NikkeiBPCleanTechInstitute
2015/09/1617:30
The"NagasakiTadewaraMegaSolarPowerPlant"isamega(largescale)solarpowerplantwithanoutputof
about13.2MWthatwasconstructedinthemountainsinTadewaramachi,NagasakiCity(Fig.1).Itwaslocatedona
sitethathadpreviouslybeenplannedforagolfcourse,andwascompletedinApril2015.
Fig.1:"NagasakiTadewaraM egaSolarPowerPlant"situatedonasitethathadoriginally
beenplannedasagolfcourse.A13.2M Woutputmegasolarpowerplantwasconstructedin
themountainsinTadewaramachi,NagasakiCity.(source:NikkeiBP)
Thepowerproduceris"NagasakiTadewaraSolarJV,"aspecialpurposecompany(SPC)financed50%by
MitsubishiCorp'swhollyownedsubsidiaryDiamondSolarJapanKK(Chiyodaku,Tokyo),40%byTodaCorpand
10%byMitsubishiUFJLease&FinanceCoLtd.
http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe_print
1/6
9/1/2016
13.2MWSolarPlantBuiltUsing3DMeasurementSolarPowerPlantBusiness
Regardingtheformergolfcoursedevelopmentofabout112ha,roughly28hawasusedforthemegasolarpower
plant(Fig.2).Partofthelandhadalreadybeenreclaimed.
Fig.2:About28haoutofthe112haformergolfcoursedevelopmentwasused.Ittookabout
oneyeartoacquirepermissionandapproval.(source:Toda)
Constructionloadalleviatedbyaplanbasedonaccurateprojectionsof
undulations
Thesitehadbeenroughlyreclaimedatthetimeofgolfcoursedevelopment.Grasshadevenbeenplantedonfour
holes.Thesitehad,however,beenabandonedformorethan20years,andwascoveredbyplantsandtreesasa
result.TheJVrepeatedlydiscussedhowtoboostbusinesssustainabilityusingsuchland.Ittackledtheissueof
howtoarrayasmanysolarpanelsaspossibletoincreasepowersales,whilelimitinglandreclamationworkasmuch
aspossibletocontainconstructioncosts.
Thecompanyconsideredthataccuratelyunderstandingtheland'sundulationswascrucialtomaketheapproach
successful.Asasolution,Todaadoptedthreedimensional(3D)laserscannerbasedmeasurements.Thismethod
enablesuserstoobtain3Dcoordinatedataofterrainandbuildingsusinglaser.Bydistributingpanelsbasedon
accurateunderstandingoftheterrain,theplantcouldpreventtheamountofpowergenerationfromdecreasing
becauseofunexpectedshadeandminimizeonsiteconstructionworkatthesametime.
Shouldaplantbedesignedwithoutaccuratecomprehensionoftheundulations,etc,onsitemeasurementand
positioningworkwouldbecomecomplicatedwheninstallingfoundations,mountingsystemsandpanels,resulting
inaheavierworkloadinmanycases.Todadevelopedatechnologytoincorporatetheterraindataaccurately
measuredbythe3Dlaserscannerwith3DCAD.Usingitsoriginalsolarpanelarrayplacementprogram,Toda
determinedthepanelplacementandproducedprojections.
Actually,Todameasuredtheterrainwiththe3Dlaserscannerafterroughlyreclaimingthelandandcuttingdown
thegrassandtrees,andcreatedhighprecision3DlanddatausingXYZ(depth,width,height)coordinateaxes.The
companyarrangedthespacebetweenthepanelrowsinconsiderationoftheeffectofshade.
http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe_print
2/6
9/1/2016
13.2MWSolarPlantBuiltUsing3DMeasurementSolarPowerPlantBusiness
Thankstothismethod,Todasucceededineliminatingtheimpactofshadeontherowsbehindevenathourssuch
as9amand3pmonthewintersolstice,whentheshadegrowslong.Thepanelsweretiltedto8.Asthismethodis
highlyversatile,TodaadopteditatitsmegasolarpowerplantbeingdevelopedonahillsideinMiyazakiPrefecture.
Asaresult,theoverallpaneloutputdeclinedfromtheinitial14MWtoabout13.2MW(Fig.3).Thiswasbecause,
forexample,someareashadbeenfoundtoslopetoomuchtoinstallpanels.
Fig.3:Todaboosteddesignaccuracytopreciselypredictthenumberofpanelstoinstall.
Panelswereplacedsoastonotshadetherowsbehind.(source:NikkeiBP)
AccordingtoToda,the3Dlaserscannerbasedmeasurementcostsmore,yetthebenefitofboostingthedesign
accuracyandbeingabletoconfirmthenumberofpanelstoinstallissignificant.
Ifitturnedoutthatthepanelscouldnotbeinstalledasplannedwhentheywerebeingconstructedonsite,the
constructormighthavehadtoreclaimthelandagaintoexpandtheareatosetupthepanels.The3Dlaserscanner
alsofacedsomechallenges.Forexample,itcouldhavemeasuredplantsandtreesasterrain.Accordingly,Toda
implementedsomeadjustmentsandremovedweedsandotherdataasnoise.
http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe_print
3/6
9/1/2016
13.2MWSolarPlantBuiltUsing3DMeasurementSolarPowerPlantBusiness
Ittookabouttwomonthstodeterminethepanelplacementafterthelandreclamationandmeasurement.Toda
decidedtoarray50,554unitsof261WoutputsolarpanelsmanufacturedbyMitsubishiElectricCorp.Twentyunits
of500kWoutputPVinvertersmanufacturedbyToshibaMitsubishiElectricIndustrialSystemsCorp(TMEIC)were
alsoinstalled.Thecompanyselectedthepowergenerationsystemfocusingoncollaborationwithtrusteddomestic
companies.
Foundationcombinesaconcretesquarepostandapile
Thefoundationcombinedaconcretesquarepostandapiledriven1mintotheground(Fig.4).Todacallsit
"independentfooting",becauseeachfoundationsupportsonepileofthemountingsystem.Ontheotherhand,the
typethatsupportsmultiplepileswithonefoundationiscalled"continuousfooting."
Fig.4:Afoundationthatcombinesaconcretesquarepostanda1mdeeppilewasadopted.It
achievedastrongholdingeffect,whileoffsettingthevariationinthepanelheight.(source:
NikkeiBP)
Giventheinstallationonthemountainside,thefoundationwasrequiredtofirmlyholdthemountingsystem,which
isitsoriginalpurpose,aswellastoabsorbthevariationinthepanelheight.
Todainitiallyconsideredadoptingthe"continuousfooting"methodbymoldinglongstripsofconcreteinthewest
eastdirection(Fig.5).However,iteventuallyadoptedthe"independentfooting"consideringthatcontinuous
footingwasnotgoodforabsorbingtheundulationsinthepanel'ssidewaysdirectionandthattheindependent
footingwaseasiertoconstructandthecostwaslower.Withtheaimofboostingthepulloutstress,thepileswere
dugintothegroundundertheconcretefoundations.
http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe_print
4/6
9/1/2016
13.2MWSolarPlantBuiltUsing3DMeasurementSolarPowerPlantBusiness
Fig.5:"Independentfooting"(left)and"continuousfooting"(right)."Independentfooting"
wasadoptedbecauseitwasmorebeneficialintermsofabsorbingthepanelheightvariation,
constructionefficiencyandcost.(source:Toda)
Whensettinguppanelsinaccordancewiththeterrainonhillsides,pilefoundationsaremostlyadoptedingeneral.
Todaalsoconsideredadoptingpilefoundations,butgaveupontheideabecauseitcouldnotdrivepilesintothe
groundusingheavymachineryinmanyareasthatslopedsharply.
Eacharrayconsistedof5rowsx3panels(Fig.6)andwassupportedbysixfoundations.Whenformingthe
foundations,Todadugaholeanddroveapileintothegroundbeforepouringconcreteintoamold.
Fig.6:Eacharrayconsistsof5rowsx3panelsandissupportedbysixfoundations.(source:
NikkeiBP)
http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe_print
5/6
9/1/2016
13.2MWSolarPlantBuiltUsing3DMeasurementSolarPowerPlantBusiness
Facilityoverview
URL:http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe
Copyright2016NikkeiBusinessPublications,Inc.Allrightsreserved.
AlleditorialcontentandgraphicsonthisWebsitemaynotbereproducedinwholeorinpartwithouttheexpresspermissionofthecopyrightowner.
http://techon.nikkeibp.co.jp/atclen/news_en/15mk/091600043/?ST=msbe_print
6/6