Professional Documents
Culture Documents
Geological Formations
Taek-Kon Kim1, Sang-Hwan Kim2, Inn-Joon Park3
1
Civil Marketing Management Team, SK Engineering & Construction, Seoul, Korea, 110-300
Dept. of Civil Engineering, Hoseo University, Asan, Korea, 336-795
3
Dept. of Civil Engineering, Hanseo University, Seosan, Korea, 356-706
2
ABSTRACT
A new railway line of about 17km length was planned between Dongbaeksan and the neighboring
town Dokye to improve the existing decrepit railway system. New line about 18km of the distance will
almost be in circular alignment tunnels owing to the difference of elevation about 380m. Since the
geology of the area is rather unusual compared to the normal in South Korea, extensive geological
investigations have been carried out to prepare geological maps and profiles along the planned tunnel
routes. The tunnel will almost be in sedimentary rock formations, such as limestone, sandstone, shale,
coal etc and be near abandoned mines. Various rock formations have the complicated, altered those
rocks, but are well developed with laminated formations. Each rock formations have been classified
using the Q-system and the cost of tunnel excavation, support has been estimated and compared for
three alternative lines in the design stage. Based on these estimates, the final route of the railway line
was chosen.
1. INTRODUCTION
A new railway line of about 17km length named as Solan Tunnel was planned between
Dongbaeksan and the neighboring town Dokye to improve the existing decrepit railway system in the
Youngdong Railway located at Taeback
City, Kangwon-Do in South Korea as
shown in Figure 1. New line about 17km of
the distance will almost be in circular
alignment tunnels owing to the difference
of elevation about 380m. New tunnel was
designed to increase the transportation
capacity of the existing railway to 35 trains
per day by changing the old switch-back
Figure 1. Location (KTA 2003)
system in the existing railway.
Since the geology of the area is rather unusual compared to the normal in South Korea and the tunnel
was located in a complex geological region with faults, cavities and coal mines, extensive geological
investigations have been carried out to prepare geological maps and profiles along the planned tunnel
routes.
The tunnel will almost be in sedimentary rock formations, such as limestone, sandstone, shale,
coal etc and be near abandoned mines. Various rock formations have the complicated, altered those
rocks, but are well developed with laminated formations. In the design stage, each rock formations
have been classified using the Q-system and the cost of tunnel excavations, support has been estimated
and compared for three alternative lines. Based on these estimates, the final route of the railway line
was chosen.
Table 1. Historical description for rock formation at the project area in Korea
Geologic Time
Era
Period
Cenozoic Quaternary
Mesozoic
Super
Group
Alluvium
Quartz
porphyry
Paebungsan
Volcanic rock
Cretaceous Kyonsang
Heungjun
Symbol
Qa
KTP
KTh
Triassic
Permian
Kohan
Tosagok
Hambaeksan
Pg
Pd
Ph
Changsong
Pj
Kumchon
Ck
Manhang
Cm
Carboniferous
CambrianOrdovician
Great
Limestone.
Unconformity
Choson
Kc
Kt
TRd
Pyongan
Rock Descriptions
Kqp
Jukgakri
Tongi
Tonggo
Paleozoic
Legend:
Formation
ol
10
20
60
10
80
71
29
Geological Formation
37
63
27
39
24
37
10
55
48
37
77
15
23
88
13
10
70
12
87
20
Great Limestone
Manhang Formation
70
Kumchon Formation
Density (%)
60
50
Hanbaeksan Formation
Tonggo Formation
40
30
20
10
0
< 0.04
0.04 ~ 0.1
0.1 ~ 0.4
0.4 ~ 1
Q-value
1~4
4 ~ 10
10 ~ 40
> 40
Concrete
Lining
20 m3
Reinforced ribs of
shotcrete
Fibrereinforced
4.0 m3
11.0 m3
8.0 m3
5.6 m3
3.3 m3
2.2 m3
1.4 m3
Shotcrete
Bolts
Spiling bolts
14.0
24
13.0
17
8.4
13
6.3
9
6
5
3
1.4 m3
2
Note: Costs should be given with a accuracy of 20% at this stage of planning
0.5 number
Cost Rate/m
(CR/m)
6.624
6.402
4.261
3.137
1.500
1.000
0.706
0.517
0.118
With the help of Figure 5 and the available geological sections the tunnel length in each of the Qintervals can be estimated. The cost rate for tunnel support can then be calculated for the three
alternatives. The meter cost rate for water tightening is also calculated based on the distance in each
tightening category the costs are determined. The base for calculation for the excavation is the price
per meter for drill and blast and transport of musk out of the tunnel. For distances with low Q-values,
extra costs for spiling volts and reduced length of the blast rounds are added. In the way the cost rate
3
for excavation and support and water tightening can be compared for the different alternatives. The
cost rate is defined as the ratio of construction cost for the given Q-intervals relative to that for Qinterval of 1 to 4. At this stage of planning the intention is that the costs should be given with an
accuracy of 20%.
Table 3 gives the unit construction cost rate for the different rock formations. The unit
construction cost rates are estimated using the results of composition rate of rock type for geological
formations (see Figure 3), Q-value distribution of the different geological rock formations (see Figure
5) and unit cost rate given in Table 2.
Table 3. Unit construction cost rate for the different rock formations
Cost Rate/m
Q-intervals
Great Limestone
Manhang
Kumchon
Volcanic Rock
Changsong
Hanbaeksan
Tonggo
Kohan
6.402
< 0.04
4.261
0.04~0.1
1%
1%
3.137
0.1~0.4
2%
15 %
9%
9%
7%
69 %
3%
1.500
0.4~1
7%
19 %
10 %
17 %
37 %
14 %
33 %
4%
1.000
1~4
21 %
6%
20 %
34 %
31 %
17 %
50 %
92 %
0.706
1~10
17 %
12 %
15 %
25 %
17 %
0.517
10~40
31 %
33 %
39 %
15 %
8%
0.118
40 <
22 %
15 %
6%
17 %
P S
. 1 0
=
1 m
K 2
8 .1
6 8
0
. P
E
= 1 1
0 K
m2
8 6
2 9
.1
C .P
= 1 1
0 K
m2 5
.6 5
0
slightly smaller than the base design loop. The Dokye end of the tunnel remains in the west wall of the
valley. By do so, same of the main tunnel will avoid the coal measures area and the poor ground
conditions.
Access to the tunnel will be through three ventilation shafts and two portals. A 1-km-long adit
may be needed at the Dokye end because of the very poor ground and likelihood of missing the project
completion in the prescribed duration. The alignment will cross 11 fault zones, 0.9 km of coal
measures, and includes 1.9 km of limestone. Figure 8 shows the geological profile to be passed
through this alterative tunnel alignment. Figure 8 shows the geological profile to be passed through
this alterative tunnel alignment.
Alternative 2
Statistical Distribution(%)
1
2
3
40.5
39.5
40.2
17.6
24.9
6.7
12.5
13.8
2.3
13.4
11.3
6.6
7.5
7.1
4.5
3.2
3.4
7.4
2.8
0
30.2
2.5
0
2.1
In the results of the alternative analysis given in Table 3, the tunnel length, amount of poor
ground, amount of good ground, and numbers of openings for each alternative are considered. Based
on the results, the features of three alternatives are summarized in Table 4. It can be seen from the
table that the tunnel alignment 1 (Alternative 1) will be very good for construction tunnel line in the
project area.
Table 4. Comparison of the three tunnel alternatives
Item
Length of main tunnel
Number of access points
Type of access
Length of access
Number of fault crossings
Number of coal measures
Length of coal measures
Length of limestone
Evaluation Value (Evaluation)
Alternative 1
15.76 km
5
Shafts, portals, adit
1.47 km
13
7
1.8 km
1.9 km
0.978 (Very Good)
Alternative 2
14.59 km
5
Shafts, portals, adit
1.47 km
11
3
0.9 km
1.9 km
0.981 (Good)
Alternative 3
17.81 km
10
Shafts and portals
0.9 km
11
3
2.5 km
7.8 km
1.050 (Fair)
7. CONCLUSIONS
The determination method of economical and feasible tunnel construction route in the complex
geological formations is introduced in this paper. In the study, three possible tunnel alignments are
evaluated.
Due to the complicated geology prevalent in the project area, extensive geological investigations have
been carried out and reviewed. Relatively accurate geological profiles are estimated from various rock
formations developed in the area. Since the bedding is often sub-horizontal, it can be deduced that
small changes in the tunnel level and route may lead to serious consequences for the stability of the
tunnel.
In order to perform this study, various rock formations have been classified using the Q-system and the
cost of tunnel excavation, support has been estimated and compared for three alternative lines in the
design stage. Based on these estimates, the final route of the railway line was chosen. In this project,
the following tunnel alignment (Alternative 1) is chosen and under construction (KTA 2003).
In order to perform a more detailed evaluation of the geological condition for the proposed tunnel
lines, it is also suggested that DAT analysis will be very useful for accurately determining the tunnel
route. The DAT program namely Decision Aid in Tunneling was developed by Professor Einstein at
MIT. The concept of the program is to identify the geotechnical conditions a tunnel or tunnels will
encounter. With each ground class there will be an uncertainty or risk. The ground conditions could be
worst than expected. The result is a delay in construction and advance rates reduced. The delays can
lead to high costs. The ground conditions can also be better, allowing portions of the tunnels to be
completed ahead of schedule.
ACKNOWLEDGEMENT
This paper was funded by the Korea Institute of Construction and Transportation Technology
Evaluation and Planning under the Ministry of Construction and Transportation in Korea (Grant No.
04-C01).
REFERENCES
Loset, F. and Rui, L., 1999. Geological investigation for Ringeriksbanen. Challenges for 21st
Century, Alten et al.(eds), pp. 87-94
KTA(Korean Tunnelling Association), 2003. Tunnelling in Korea. ITA WTC 2006 Bidding
Committee, pp. 38-45
Kim, S.H., 1999. Taeback-Dokye Railway Tunnel Project Report. Dong-Ah Construction Company
6