Professional Documents
Culture Documents
Sherief Mekawey
Principal MDS Engineer
GE-Bently Nevada
Contents
Background
Technical Data and Acceptance Criteria
Contractual Vibration Points
Vibration Measurement Locations at Field
Analysis
Conclusions from Investigation
Proposed Actions
Final Vibration Results
Lessons Learnt
2
Background
Four numbers of Fire Water Pumps supplied newly failed to
pass SAT in 2006 due to high vibration on the Pump Head.
2 vibration consultants were involved to solve the problems
without success.
3rd vibration consultant (GE) was involved in Oct 2009,
implementation of recommendations started in 2010, hand
over in 2012.
Acceptance Criteria:
As per NFPA 20 article 7.6.1.5
which refers to Hydraulic Institute
Standard (5.84 mm/s rms) at
Pump Head
Drive Shaft :
Double Universal Joint Cardan Shaft
Gearbox:
750 HP, 1750 RPM,
1:1 Ratio, Right Angle
Threaded Coupling Type
Diesel Engine:
12 Cylinders, DITA, 800HP, 1750
RPM
Analysis
Pump A
Comparison of vibration
signatures of Pumps A,
B & D on the GB output
Vertical location
Pump B
Observation#1:Vibration
signature
on
Gearbox
indicated that a significant
energy components getting
transmitted from the Diesel
Engine at 1X, 3X, 3.5X and
6X
Pump D
Reason could be: vibration isolators are not installed either under
the engine feet nor under the frame on which the engine is
mounted.
Pump-A
Pump-B
Pump-D
10
Pump-A
Pump-B
Observation#4:
High
frequency spectrum on
GB indicated 1X GMF
with sidebands, possibly
due to wear of gear
teeth/excessive
backlash.
Pump-D
11
12
Proposed Actions
In situ balancing of gearbox cordon shaft and GB O/P
shaft.
Installation of vibration isolators below the engine feet or
the base frame
Modify the Gearbox structure to shift the natural
frequency with 30% separation margin.
Inspection of Gearbox for excessive gear wear/backlash.
13
Actions in Sequence
14
Waterfall signature
1X component
before balancing
before balancing
Waterfall signature
after balancing
15
Action#2: The engine stand was replaced with a new stand with vibration isolators
16
17
18
GB TOP
Pump head
19
Action#4: Gearbox inspected and found only 70% teeth contact. GB OEM
brought to site, gear backlash was checked and adjusted to conform to OEM
specifications
20
Now
21
22
Lessons Learned
All contractual limits must be carefully acknowledged
during design and verified during FAT.
Solving the problems in factory is much easier than
doing it on site.
Get the right consultant involved at the first chance.
Understand the size of problem since beginning could
save time, cost and efforts.
Major modifications might be a solution whenever the
problem is complex.
23
24