Professional Documents
Culture Documents
Shaping Australias
Energy Future
National Cost Benefit Assessment
July 2014
7
149
237
Appendix 1
Appendix 2
Appendix 3
Appendix 4
289
349
437
483
ACKNOWLEDGEMENTS
1 Wayfinding
This document presents the findings of the national cost benefit assessment for smart grid technologies
and products based on the outcomes of the Smart Grid, Smart City program. The document is presented in
three distinct parts which, when combined, provide the reader with the required context and information to
understand the results and the corresponding conclusions and recommendations. In this sense, the document
is intended to be accessible to readers with a reasonably technical background but no experience with either
the electricity sector or smart grid technologies. Readers who are already familiar with the electricity sector
and the history of the Smart Grid, Smart City program, may wish to skip straight to the findings in later parts.
0 1 2
PART TWO:
The Business
Case for
Smart Grids
in Australia
PART ONE:
Smart Grid,
Smart City
Trials
Executive
Report
Start here if
Start here if
Start here if
Go to page 07
Go to page 149
3 4
PART THREE:
Conclusions and
recommendations
smartgridsmartcity.com.au/
Technical
Compendia
Start here if
Start here if
Go to page 237
Part 1
Smart Grid,
Smart City Trials
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 7
Part 1 Contents
1
1
Wayfinding
The Smart Grid, Smart City Program
4
12
1.1
Introduction
12
1.2
12
1.3
13
1.4
1.5
Smart Grid, Smart City Information Clearing House
19
1.6
20
1.7 The Smart Grid, Smart City: National Cost Benefit Assessment Report
23
24
2.1
24
2.2
25
2.3
26
27
3.1
29
3.2
Smart Grid, SmartCity work streams and trial technologies
32
33
4.1
What is a commonplatform?
33
4.2
33
4.3 The Common Platform and NBN Interoperability Project and the Smart Grid, Smart City
trial objectives and timelines
35
4.4
Smart Grid, Smart City common platform and NBN interoperability trials
36
4.5
38
5
6
41
43
6.1
43
6.2
43
6.3
44
6.4
45
6.5
Smart Grid, SmartCity AVVC trials
45
49
6.6
8 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
52
7.1
52
7.2
53
7.3
FDIR and the Smart Grid, Smart City trial objectives and timelines
54
7.4
55
7.5
Smart Grid, SmartCity FDIR trials
56
7.6
58
61
8.1
61
8.2
61
8.3
SFM and Smart Grid, Smart City trial objectives and timelines
62
8.4
64
8.5
Smart Grid, SmartCity SFM trials
64
8.6
68
73
9.1
73
9.2
73
9.3 WAM Smart Grid, Smart City trial objectives and timelines
75
9.4
76
9.5
Smart Grid, SmartCity WAM trials
78
79
9.6
81
81
82
10.3 The electric vehicle Smart Grid, Smart City Trial objectives and timelines
83
84
10.5
Smart Grid, SmartCity Electric Vehicle trials
88
91
93
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 9
95
11.1
95
95
11.3 Smart meter infrastructure and the Smart Grid, Smart City trial objectives and timelines
96
98
11.5
Smart Grid, Smart City smart meter infrastructure trials
102
103
What are smart meters and smart meter infrastructure (SMI) technologies?
12 Customer Applications
109
109
110
12.3 Customer applications objectives and timelines in the Smart Grid, Smart City Project
110
112
12.5
Smart Grid, Smart City customer application trials
113
127
134
134
13.2 The role for distribution generation and distributed storage in a smart grid
136
137
139
13.5
Smart Grid, Smart City distribution generation and distributed storage trials
139
143
10 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 11
12 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2 The climate zones used for the purposes of the Smart Grid,
Smart City Project were based on those produced by the
Australian Building Codes Board, http://www.abcb.gov.au/
en/major-initiatives/energy-efficiency/climate-zone-maps last
published in December 2012.
14 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
The greater Newcastle area was selected as the focal point for the trial, due to
its good mix of regional and suburban characteristics, representative geography,
climate, socioeconomic and demographic factors of the broader Australian
population. The customer demographics and socioeconomic indicators of the
area closely reflect the demographics of a typical Australian city.
Sydney CBD
Part of the City of Sydney Local Government Area (LGA), this area provided
additional high density residential buildings and large scale co-generation.
Ku-Ring-Gai area
Situated on the north shore of Sydney, this area provided additional testing of
high income demographics. The area also provided a high number of customers
with swimming pools (approximately 36 per cent in some areas of the Local
Government Area) for testing new products.
Newington area
Part of the Auburn LGA, this area provided a typical Western Sydney climate
zone and suburban environment for broad testing. The suburb added a high
multicultural population and contains the highest penetration of customer
photovoltaic energy generation, assisting in the trial of renewable generation and
storage applications.
Scone area
Part of the Upper Hunter LGA, this area provided additional rural characteristics
and a more extreme climate zone. The area provided a rural network to perform
end of feeder trials and much lower levels of internet use representative of more
rural geographies.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 15
16 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Table 1-2 Work streams for the Smart Grid, Smart City trial
Grid Applications
Customer Applications
Distributed Generation
and Distributed Storage
Supporting Information
and Communication
Technology platforms
(Common Platforms)
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 17
Figure 1-2 Overview of Smart Grid, Smart City trial technologies and participants
18 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 19
20 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 21
Figure 1-3 Structured reporting and access to information for the Smart Grid, Smart City trial
Part Two
Part One
Part Three
Conclusions and
recommendations
Supporting Documents
22 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Modeling Inputs
Compendium
Wide Area
Measurement
Smart Meter
Infrastructure
Active Volt
VAr Control
Common Platform
Study
Fault
Detection
Isolation and
Restoration
Electric
Vehicles
Substation
and Feeder
Monitoring
Customer
Applications
Grid Applications
Distributed
Generation and
Storage Applications
Technical Compendia
2 An introduction to
transitioning Australias
electricity distribution networks
2.1 Defining a smart grid
This need for more advanced decision-making
abilities for network operators is reasonably consistent
throughout the world. As a consequence a range of
innovative information and communication systems
have been developed and are now driving an electricity
grid modernisation often termed a smart grid.
24 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
26 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Table 1-3 Summary of global existing smart grid trials including key technologies and Government funding (USD)
Technology Focus
Country/
Australia
National Energy
China
Strong and
EU
FP7
France
Region
Program
Smart Grid
Efficiency
Start
End
SMI
DG
DS
EV
SFM
FDIR
AVVC
Programme
2013
$100
million
2011
2020
$100
billion
2007
2013
$520
million
2010
2014
2010
2015
$1.2
billion
2011
2013
$50
million
2009
2015
$200
million
2010
2015
$480
million
2009
2015
$3.4
billion
2009
2015
$325
million
(CAN)
Smart Grid
Korea
Koreas Smart
UK
Ontario
Demonstration
South
Japan
Smart
Community
Fund
Grid Project
Low Carbon
Networks Fund
US
Smart Grid
Investment
Grants
US
Smart Grid
Demonstration
(USD)
2010
Initiative
Smart Grid
Funding
$600
million
Program
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 27
1.80
8.00
1.60
7.00
1.40
6.00
1.20
5.00
1.00
4.00
0.80
3.00
0.60
2.00
0.40
1.00
0.20
0.00
2013
2014
2015
NA
2016
EU
2017
JTK
2018
Cumulative
28 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2019
2020
Figure 1-4 Commitment investment smart grid technology by region (USD $billion)
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 29
30 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Table 1-4 Summary of global smart grid policies, targets and regulatory frameworks
Jurisdiction
EU
Smart
Grid
Roadmap
Targets
Programs
Voluntary
DG
EV
DS
Mandatory R&D
Grants
SMI
Denmark
Finland
France
Germany
Regulations
Standards
DG FiTs
Opt-out
Privacy
Overall
SMI
Security
Data
Italy
Netherlands
Spain
Sweden
United
Kingdom
Rest of the
World
Australia
Canada
British
Columbia
Ontario
China
Japan
New Zealand
South Korea
US
Texas
California
DG= distributed generation, EV= electric vehicle, DS = distributed storage, SMI = smart meter infrastructure (smart meters), DG FiTs = distributed generation
feed-in-tariffs
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 31
32 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 33
Advanced
Automation
Wide Area
Control
AVVC
FDIR
Dynamic
Ratings
Demand
Response
Pricing &
Feedback
Network
State Viability
& Actuation
Capability
Transmission
Monitoring
Substation
Monitoring
Distribution
Monitoring
Distribution
Control
Wind Area
Measurement
Smart Meter
Infrastructure
Common
Platform
IT
Infrastructure
Communications
Infrastructure
Security
Architecture
34 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Operational
Model
Design
Standards
36 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 37
38 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Security
Although the smart grid introduces many potential
benefits in terms of reduced demand, asset
utilisation and power quality, the extensive use of
ICT infrastructure does make the electricity network
more exposed to cyber-attack. The large number of
intelligent devices and associated communication
networks distributed over a wide area represents a
significant opportunity for cyber-attack and a challenge
to protect.
At the worst extreme, cyber-attacks could potentially
render the grid inoperative, steal confidential
information or damage vital infrastructure.
Data protection requirements for each smart grid
domain and application need to be clearly defined so
that manufacturers, operators and other stakeholders
participating in the smart grid technology development
and implementation can establish the necessary
security controls and the appropriate technologies to
protect smart grid data.
Data flow encryption, tunnelling, authentication and
non-repudiation, digital certificates, firmware validation
and patch management are areas that should
be addressed.
Privacy
The Smart Grid, Smart City trials identified a
scenario in which multiple organisations including
DNSPs, energy retailers and third parties were able
to co-operate to deliver services to customers and
therefore share access to customer information
securely. This may be possible with a number of
feedback or demand management technologies for
example, where identifying information, tariff details or
consumption patterns may be exchanged.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 39
40 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
5 Grid applications
workstream an overview
The Grid Application work stream included a
combination of projects which trialled grid-facing smart
technologies within Ausgrids distribution network. The
intent of the Grid Application trials was to deploy and
integrate smart grid technologies (generally) with the
existing infrastructure at various points on the electrical
network.
The Grid Application technology trials aimed to assess:
Whether smart grid monitoring and control
technologies could reduce the cost of running an
electrical network
Abbreviation
AVVC
FDIR
SFM
WAM
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 41
Figure 1-6 shows the physical locations where the technologies were deployed.
Figure 1-6 Physical locations of operating technologies installed under the Grid Applications Project
SCONE
MUSWELLBROOK
SINGLETON
NELSON BAY
CESSNOCK
NEWCASTLE
WYONG
GOSFORD
HORNSBY
SYDNEY
OATLEY
Legend
Active Volt-Var Control
LGA Boundary
Customer Applications
Main Roads
Towns
42 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
6 Active Volt-Var
Control(AVVC)
6.1 What are Active
Volt-Var Control
(AVVC) technologies?
Active Volt-VAr Control (AVVC) is a term for a collection
of technologies which use automated voltage
regulating and reactive power controls to measure and
maintain acceptable voltages and high power factor
atall points in the distribution network under varying
load conditions.
Network voltage, which moves up and down in
response to load and source fluctuations, needs to
becontrolled to ensure it remains within an acceptable
range specified by the Australian standards17. To
minimise electrical losses in the network, and ensure
that the network assets are used optimally, the power
factor should be maintained as close to unity
as possible.
Traditionally, distribution utilities have achieved a
degree of control over the network voltage and
reactive power via Volt-VAr control devices such
as switched capacitor banks and tap-changing
transformers. These rely on localised measurement of
voltage and current to determine the control actions
of the device. They have a simple control objective (for
example, keep local voltage within a pre-determined
range), and operate independently of other similar
devices deployed at other points in the network.
The smart grid provides an opportunity to continually
monitor the voltage and current in the grid at various
locations, and to use this information to control the
distributed voltage and reactive power control devices
using sophisticated control algorithms.
As these control algorithms, known as Integrated VoltVAr Control (IVVC), can access multiple measurement
and control points across the network, they have the
ability to implement very sophisticated
44 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2009
2010
2011
2012
2013
3 1
6.5.2 Technologies
Volt-VAr control is required to maintain an acceptable
voltage profile and power factor in the distribution
network despite the heterogeneous nature of network
feeders. Although a group of feeders may originate at
a common source, and have been designed to exhibit
similar characteristics, the evolving nature of the load
often leads to a situation where the characteristics of
one feeder constrain the optimisation of the system
as a whole.
AVVC technology relies on the measurement of
voltage and current at many points in the network
and the coordinated activation of multiple control
points to achieve a specific objective function. This
measurement and control cycle is repeated at
predetermined intervals, to maintain the objective
function under changing network state, load and
generation conditions.
An AVVC control algorithm can be configured to
optimise one or more objective functions, including:
Maintaining an acceptable voltage profile.
Maintaining the voltage within the mandated range
is a minimum requirement of any Volt-VAr control
system. In addition, flattening the voltage profile
of voltage-constrained feeders provides scope
to operate other feeders in the zone at closer to
nominal levels, reducing the power throughput and
maximising plant utilisation and asset life.
46 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 47
48 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
The field trials evaluated the CVR factor using day-onday-off testing. The results showed a CVR factor of
0.65, consistent with trials described in the literature.
In the Australian context however, the benefits of CVR
need to be considered in the light of the transition of
the nominal domestic electricity supply voltage from
240 V to 230 V. In 2000 the nominal mains voltage
in Australia was reduced from 240 V to 230 V. The
upper tolerance on the nominal 230 V level was set
to include the previous 240 V range. Because of this,
many electricity providers have been slow to adjust
their voltage regulation equipment to accommodate
the 230V nominal voltage. As and when providers
adjust their voltage regulating plant to the new nominal
level, many of the benefits of CVR will be automatically
captured, without the need for a full-scale deployment
of AVVC technology.
Given the high level of monitoring on the low-voltage
network, for example through the deployment of smart
meters, the transition to 230 V could be managed with
a high degree of precision, maximising the CVR benefit
without significant additional capital investment.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 49
50 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 51
Power Restored to
Healty Part of Feeder
Fault
Occurs
Field Staff
On Site
Fault
Located
Investigation and
Feeder Patrol
20-40 min
20-40 min
Manual
Switching
10-20 min
50-100 min
52 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Repairs
Power Restored to
All Customers
Fault
Detection,
Isolation and
Restoration
(FDIR)
Bulk Supply Point
Subtransmission
Substation
Zone Substation
Distribution
Substation
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 53
2009
2010
2011
2012
2013
2 3 4 5
6 7
ne IntelliRuptor commissioned
9 O
(10072)
54 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
7.4.2 International
A number of international trials have been undertaken
to establish if there are measurable improvements in
responding to grid outages by deploying FDIR. The trials
to date have predominantly taken place in the US under
the DOE Smart Grid Investment Grant Program.
56 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 57
0%
-5%
-10%
% Change
-15%
-20%
-25%
-30%
-35%
-40%
-45%
-50%
SAIDI
SAIFI
58 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Automated FDIR
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 59
60 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Subtransmission
Substation
Zone Substation
Distribution
Substation
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 61
62 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2009
2010
2011
2012
2013
5 Distributed Temperature
Sensing Trial Start
11 8
3 Environmental monitoring at
distribution substations Trial Start
3 2
1 5 7
10
11
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 63
64 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 65
8.5.3 Substation
MonitoringTrials
Electrical substations are important nodes in the
electricity supply network. Substations contain
transformers that convert the incoming high voltage
into a lower voltage for distribution further out into the
network. They also contain equipment that performs
switching, protection and control functions.
As well as the primary electrical system, substations
can contain one or more secondary systems. A
secondary system is defined as any system that
supports the safe, secure and efficient operation of the
primary system. Typical secondary system functions
include protection, monitoring and control. Tertiary
systems, which do not directly support the primary
electrical system, such as enterprise connectivity and
voice communications are also deployed
in substations.
The role of the protection systems is to detect fault
conditions, isolate faults to prevent damage to the
rest of the network, and to de-energise equipment
or conductors that may be in an unsafe condition.
The protection system will also attempt to maintain
electricity supply to as many customers as possible
during the fault. The reliable operation of the protection
systems is therefore critical for the safe operation of
the network.
66 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
8.5.4 Distribution
MonitoringTrials
Distribution networks carry electricity from
zone substations to customers. They consist of
underground and overhead feeders and lines that
carry the electricity, as well as distribution substations,
transformers and switching and monitoring equipment.
The distribution substation steps down the voltage
before the electricity reaches the customer. In
Australia, the majority of customers receive electricity
at around 230 volts.
The role of the distribution network is the costeffective, safe and reliable transportation of energy
to the end-customer. Achieving this goal requires
accurate information about the network state and the
health and utilisation of assets on the network.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 67
68 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 69
70 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 71
72 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Subtransmission
Substation
Zone Substation
Distribution
Substation
Past
Current
Opportunity
Future
Peak
Modelling
Months
Static Loads
in Real-Time
Minutes
Dynamic
Modelling of
Interacting
Components
Seconds
Transient
Analysis
Cycles
74 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2009
2010
2011
2012
2013
3 4 56 7
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 75
76 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 77
78 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 79
80 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 81
Figure 1-17 An electric vehicle from the Smart Grid, Smart City trial charging
82 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2009
2010
2011
2012
2013
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 83
84 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 85
86 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
The US EV Project
The US EV Project37 was the worlds largest
deployment of electric vehicle charging infrastructure
and is being used to support thousands of electric
vehicles over 21 major cities. This trial investigated the
use of time-of-use tariffs to shift charging demand
to off-peak.
Green eMotion
The European Green eMotion trial38 includes ten
demonstration regions where deployment of more
than 2,500 charging stations is underway. The trial
investigated usage patterns to suggest the likely
impact of electric vehicles on system peak.
36
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 87
Charging
Infrastructure
Deployment
Road Trails
Uptake and
Behaviour
Model
Individual
charging profiles
(by location)
Charging
Characteristics
Trial
Outputs
Charging
infrastructure
cost and
feasibility
Travel behaviour
Travel behaviour
(by location
Australia wide)
Operating costs
and GHG
emissions
Uptake rates
(by location
Australia wide)
Grid
Simulations
88 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Aggregated
charging profiles
(by network level
over time)
Grid impact
(by network level)
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 89
90 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 91
92 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
10.7 Further
considerations for
Electric Vehicle
deployment for
Australia
10.7.1 Need for pricing signals
Should the uptake of electric vehicles occur in the
future as modelled by the Smart Grid, Smart City
Electric Vehicle Project, the electricity supply industry
will need to take action to manage the increased
load these vehicles will place on the grid. Failing to
adequately manage electric vehicle charging has the
potential to result in a number of negative impacts.
Proactive action in the form of pricing signals and
metering arrangements when electric vehicle numbers
begin to increase would reduce the likelihood of
requiring significant policy changes or costly grid
impacts in the future. Where appropriate charging
schemes are in place, electric vehicles also offer
potential benefits to in the form of improved network
utilisation and therefore the economic efficiency of
network operations. This need for action has also been
identified by AEMC in their December 2012 report
into energy market arrangements for electric vehicles,
principally in relation to the role of pricing signals and
metering arrangements.
94 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
11 Smart Meter
Infrastructure (SMI)
11.1 What are smart
meters and smart meter
infrastructure (SMI)
technologies?
43 Note that hot water load control scheduling using SMI was
not applied to Ausgrid customers during the Smart Grid,
Smart City Program due to software issues that occurred
which meant that updating of the meter schedule caused
the loss of billing data or the meter to stop responding.
These issues are discussed in the Smart Grid, Smart City
Customer Applications Technical Compendium
96 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Table 1-6 Smart Grid, Smart City Smart Meter Infrastructure Project timelines
Task
End
Mid 2011
Technology Testing
April 2011
June 2013
Technology
Procurement
Sept 2011
July 2012
Communications
Medium Rollout
Early 2013
Back Office IT
System Integration
2010
2013
Meter Rollout
Customer Applications
Network Trial rollout
Oct 2011
Aug 2012
Nov 2012
July 2013
Sept 2011
TBC
April 2011
TBC
De-provisioning of
communications
March 2014
March 2014
De-provisioning
of SMI
Description
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 97
98 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
100 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
49 www.greenbuttondata.org
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 101
102 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Observation
Discussion
Conclusion
Testing of
smart meter
infrastructure
Training and
equipping of staff
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 103
Observation
Discussion
Conclusion
Technology
selection and
maturity
Smart meter
infrastructure
technology was
found to be
relatively immature
104 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Observation
Discussion
Conclusion
Technology risk
management
The ability of a
business to meet its
business as usual
metering and billing
requirements is
significantly reliant
on the selection
and integration
of its metering,
communications, IT
software and back
office systems.
Standardisation
of customer side
infrastructure
The size of the
smart meter board
was problematic
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 105
Observation
Discussion
Conclusion
Standardisation
and competition
Minimum
functionality
standards
The lack of
standardisation
created a range of
issues in the trial
The level of
competition in the
market for smart
meters is relatively
low
106 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Observation
Discussion
Conclusion
Separating the
smarts from the
meter
Installing separate
meter and
communications
devices provides
flexibility in the
operation of
smart meter
infrastructure
Market driven
rollout of
smart meter
infrastructure
The Smart Grid, Smart City trial found that the costs
of installing meters and communications equipment
varied significantly for a variety of reasons, including
access issues, insufficient meter board space and
poor signal strength. The issue of how to equitably
distribute the cost of upgrading private shared
equipment is one of the key challenges for any
market driven rollout.
If the issues associated with a market-led (also
called customer-led in this report) rollout of SMI
arent able to be overcome then the benefits from
the products and applications that SMI enables will
not be realised.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 107
108 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
12 Customer Applications
12.1 What are
customer application
technologies?
The Smart Grid, Smart City Customer Applications
Program trialled different methods of interacting with
customers purchasing electricity as part of the broader
Smart Grid, Smart City Program. Historically, traditional
spinning disc electricity meters have been installed in
the majority of residential homes in Australia, which
are read manually on a quarterly basis. This meant
that network operators and retailers only had access
to quarterly information meaning that both network
operators and retailers were limited in their ability to offer
tariff incentives or use other tools that could encourage
behaviour change to improve the efficient use of the
grid to meet electricity demand and moderate growth
in peak demand. With the introduction of smart meter
infrastructure, more accurate, real time, information
is becoming available to all participants in the market
place, providing an opportunity for more innovative
tariffs, technologies and customer information products.
Three groups of products were trialled as part of
the Smart Grid, Smart City Customer Applications
Program:
1. A Network Trial measured the effectiveness of
smart meter based products without changing the
customers retailer or electricity retail tariffs.
The network trial tested feedback technologies,
financial incentives (rebates) and provided a lifestyle
audit. Eight products were offered to customers either
individually or as a bundle. The products consisting of
an online portal, an in home display, appliance control
and sub-metering devices, an interruptible load (air
conditioning) control rebate, a dynamic peak rebate
and a lifestyle audit. Further information on these
products is discussed in the following sections.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 109
12.3 Customer
applications objectives
and timelines in the
Smart Grid, Smart City
Project
Electricity customers in most Australian markets are
currently provided with limited information, incentives
and tools to manage their own domestic electricity
use. In most cases, a quarterly electricity bill is the
main source of customer communication. The bill
shows them the total amount of energy used during
the previous three month block and provides limited
information on their electricity usage patterns and
therefore limited opportunity to systematically modify
their behaviour in order to save electricity and money.
The majority of residential customers in Australia have
no visible price signal on which to respond to the true
cost of energy supplied at times of peak demand.
Unlike other parts of Smart Grid, Smart City Program
which focused on specific in-grid or supplementary
generation and storage methods of managing peaks, the
Customer Applications Program was focused on how
behaviour changes by residential customers enabled by
smart technologies, applications and products, could
contribute to peak demand management and overall
reductions in electricity consumption. The Customer
Applications Program evaluated the following aspects
relating to smart meters:
Customer acceptance of a smart meter installation
The attractiveness of the selected smart meter
based products to customers
The effectiveness of the selected smart meter
based products in assisting customers to better
understand and manage their electricity usage or
shift electricity load from peak periods, which may
in turn help them to reduce electricity costs
110 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Figure 1-20 Timelines and processes for the Smart Grid, Smart City Customer Applications Program
2010
2011
2012
2013
2014
Enabling technologies
Sampling and trial design
Network Trial meter deployment
Network Trial customer acquisition
Network Trial
Network Trial Extension
Retail Trial customer acquisition
Retail Trial meter deployment
Retail Trial
Retail Trial Extension
Sydney Water Trial customer acquisition
Sydney Water Trial meter deployment
Sydney Water Trial
1
Milestones
3 4
5 6 7
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 111
112 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 113
Enabling technologies
A set of technologies were deployed to enable
selected customers to trial the customer applications
products. These enabling technologies were specific
to the Smart Grid, Smart City Program and had to be
defined, selected, built, tested and deployed before
customers could commence trialling the products.
These enabling technologies included:
The Smart Grid, Smart City smart meter (17,134
smart meters were deployed as part of the
Customer Applications trial)
The various communications technologies required
to transport data to and from the smart meter, the
feedback technologies and the back office systems
The firmware that controlled how the smart meter
interacted with the meters communication module
The meter management system (MMS)
Back office operational systems at Ausgrid,
EnergyAustralia and Sydney Water
The customer acquisition application
114 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Feedback technologies
One of the objectives of the Smart Grid, Smart City
Customer Applications Program was to measure the
behavioural changes of electricity customers based on
their use of a variety of different feedback technologies.
Five individual feedback technologies were selected to
form part of the products that were trialled as part of the
Smart Grid, Smart City Program including:
1. Customer web portal including a mobile
device application the customer portal was
an online electricity management website giving
customers access to information about their
household electricity usage and costs to assist
them in finding ways of reducing electricity bills.
This information included the customers own
meter data (usage and cost) in near real time in
time as well as increments of a week, a month or a
year. It also allowed households to compare their
electricity usage with other households.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 115
Figure 1-22 Components of the appliance control and sub metering trial
116 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
118 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Education products
Because the Smart Grid, Smart City Customer
Applications Program was focussed on enabling
customers to make informed decisions about their
energy usage, in addition to technologies, the
Program also provided educational material. The
Smart Grid, Smart City Customer Applications
Program Home Energy Assessment included a free
assessment of a customer home electricity usage with
recommendations for reducing electricity costs along
with gas and water consumption. Recommendations
that were selected as part of this process were
intended to be implemented without adversely
affecting a customers lifestyle.
By providing the education assessment, the Customer
Applications Program sought to evaluate whether
customers would change their behaviour as a result of
directed education about what was driving electricity
usage and costs in their dwelling.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 119
Figure 1-24 Dynamic Peak Pricing tariff used for Smart Grid, Smart City PriceSmart trial participants
Existing Pricing
Price Inc-GST
All time
26.84c/kWh
13.09c/kWh
24.53c/kWh
24.53c/kWh
330.00c/kWh
Saving
12am
7am
2pm
8pm
10pm 12am
8pm
10pm 12am
12am
13.09c/kWh
Price Inc-GST
Price Inc-GST
Time of Use
52.55c/kWh
21.34c/kWh
7am
2pm
Time (weekdays)
12am
7am
2pm
Time (weekdays)
120 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
8pm
10pm 12am
Figure 1-25 Seasonal ToU tariff used for Smart Grid, Smart City PriceSmart trial participants
Existing Pricing
With current price structures, customers on an All Time plan pay the
same rate all day, every day. For customers on a Time of Use plan,
the rate varies according to the time of day.
12am
Price Inc-GST
Price Inc-GST
All time
7am
2pm
7am
2pm
Price Inc-GST
Price Inc-GST
Saving
Time of Use
12am
21.34c/kWh
21.34c/kWh
12am
13.09c/kWh
13.09c/kWh
21.34c/kWh
7am
2pm
Time (weekdays)
12am
13.09c/kWh
74.47c/kWh
52.55c/kWh
21.34c/kWh
7am
2pm
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 121
Table 1-8 Seasonal ToU tariff used for Smart Grid, Smart City PriceSmart trial participants
Balance
24.90
26.38
28.48
Incl. GST
27.39
29.018
31.328
47.77
19.86
11.97
52.547
21.846
13.167
Time-of-use
Ex GST
Incl. GST
Utility interoperability
122 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 123
Trial
BudgetSmart Plan
BudgetSmart Plan with PowerSmart Monitor
BudgetSmart Plan with PowerSmart Online Portal
BudgetSmart Plan with PowerSmart Online Portal and Home Control System
PriceSmart tariff
PriceSmart tariff with PowerSmart Monitor
PriceSmart tariff with PowerSmart Online Portal
PriceSmart tariff with PowerSmart Online Portal and Home Control System
SeasonSmart tariff
SeasonSmart tariff with PowerSmart Monitor
SeasonSmart tariff with PowerSmart Online Portal
SeasonSmart tariff with PowerSmart Online Portal and Home Control System
FlowSmart tariff
124 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 125
Trial management
The trial management process describes all aspects of
managing both the Network and Retail Trials, following
on from the provisioning and activation of the products.
Trial management activities undertaken throughout the
Network and Retail trials included the following:
Customer retention activities
Ongoing general customer support
Managing those customers wishing to opt out of
the trial
Ongoing product management
126 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Pricing structures
The Smart Grid, Smart City Customer Applications
Program trialled a series of pricing structures (tariff,
rebate or reward) that were developed to address
the key Program objectives of testing the ability of
customers to make informed decisions on their overall
electricity usage and usage during peak
demand periods.
Frontier Economics were retained by the Smart Grid,
Smart City Program to perform econometric modelling
to estimate customer uptake of the products trialled
in the Customer Applications Program and customer
responses to the trialled products with respect to
electricity consumption patterns61.
The full results of all of the pricing structures is described
in the Customer Applications Technical Compendium,
and notable results are described below.
128 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Technologies
As part of the Smart Grid, Smart City Program
analysis, a customer survey was commissioned. The
full results of this survey are presented in the Institute
for Sustainable Futures (ISF) customer research report
which is available on the Information Clearing House
https://ich.smartgridsmartcity.com.au.
The IHD was considered by customers to have been
the easiest to set up (with 77 per cent of survey
participants finding it easy or very easy to set up)
and the IHD became easier to use over time. The HAN
was considered the least simple to set up and use,
however the difference in customer survey responses
was not statistically significant which suggests that
while the HAN was more complex to set up and
operate, this did not strongly impact on customers
ability to use the technology.
Empirical evidence showed that elderly and nonEnglish speaking customers had the most difficulty
in completing the set up process and effectively
operating the IHD.
130 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Demographic analysis
The following conclusions were able to be drawn from
an analysis of customer survey data in regards to the
responses of differing demographic groups to the
Customer Application Program trials:
Low energy users had a lower probability of
reporting that participation in the trials had
increased their ability to reduce bills. This could be
attributable to this demographic group having less
discretion over their usage
Financially vulnerable households were less likely
than other households to perceive that they could
shift a large portion of their usage to outside peak
times. This demographic group was also more
likely to recommend the products they trialled
Pensioners were generally more likely than other
customers to perceive that they could shift a
large portion of their usage to outside peak times;
however they were only slightly more able than
other demographic groups to actually be able to
shift usage to outside peak times
A substantially higher proportion of households
with children reported feeling unable to pay their
electricity bill, compared to households with no
children. However households with older children
were more likely to report perceived savings. This
indicates that households with young children may
have been more vulnerable to pricing regimes
For all demographic groups, the pricing structure
trialled was the primary driver of overall reduction
in usage and peak demand reduction. Feedback
technologies on their own had little effect
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 131
Product satisfaction
Overall, customers were positive about the products
they trialled. Most products were viewed very positively
by customers, in particular the DPR products.
Customers who participated in the Network Trial
with an IHD only reported the lowest average level of
satisfaction. Customers were found to have formed
their opinion on their product after a short period of
time and this opinion did not change much over the
course of the trial.
In terms of overall product satisfaction (not related to
any particular product), the following conclusions were
able to be made:
Customers with English as their first language were
more likely to be satisfied with their products
Product satisfaction was higher for customers who
stated they understood and were able to obtain the
benefits of their products. Whether this is a cause
or effect however is unclear, although customers
who understood the benefits of their product
were more likely to demonstrate active engagement
and behaviour change, which resulted in
financial savings
132 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Change in usage
An analysis of change in usage data indicated that
customers who trialled the following products achieved
the greatest reductions in overall electricity usage:
BudgetSmart (average overall reduction of 3.5 per
cent across all offered BudgetSmart products)
PriceSmart (average overall reduction of 2 per cent
across all offered PriceSmart products)
SeasonSmart (average overall reduction of 1.8 per
cent across all offered SeasonSmart products)
These results indicate that a top up reward pricing
structure was the most effective in reducing overall
customer electricity usage.
An analysis of change in usage data indicated that
customers who trialled the PriceSmart products
achieved the greatest peak demand reductions, with
an average peak reduction of 38.9 per cent across all
offered PriceSmart products. Whilst customers who
trialled pricing structures also achieved reductions in
peak demand, as these customers were not notified of
peak events, there could have been no relevant peak
demand analysis over their usage and reductions in
usage were able to be calculated on an overall basis
only. Analysis of trial results showed that the DPP
product was the most effective in reducing customer
peak demand. Despite this finding, there remains the
practical challenges of network operators and retailers
in managing issues associated with non-firm demand
response. This has been discussed in greater detail in
Part Two of this report.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 133
Subtransmission
Substation
Zone Substation
Distribution
Substation
134 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Subtransmission
Substation
Zone Substation
Distribution
Substation
64
AEMO Rooftop PV Information Paper, National
Electricity Forecasting 2012
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 135
136 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
13.3 Distribution
generation and
distributed storage
objectives and timelines
in the Smart Grid,
Smart City Project
The Smart Grid, Smart City DGDS Project was
initiated to provide critical data and information to help
understanding the implications of a commercial scale
rollout of distributed storage integrated with distributed
generation and other smart grid technologies.
The DGDS Project sought to:
Understand the maturity and suitability of
DGDS devices
Assess the impacts on the grid from increased
penetration of DGDS devices
Understand the value DGDS devices can potentially
deliver for network operators and customers
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 137
138 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
2009
2010
2011
2012
2013
1 Community Consultation
3 4
5 6 7 8 9 10
etwork Monitorng
3 N
devicesinstalled
4 Community Update
9 Community Update
6 Community Update
11
12
13 14
15
12 Community Update
etwork Simulation Model
13 N
developed
iesel Generator (Solar Farm
14 D
Simulation) Commissioned
ewcastle 2 Turbines
15 N
Commissioned
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 139
140 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
142 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 143
Redflow battery
The RedFlow battery is a developmental technology
using a flow process based on zinc bromine. This
product was just emerging from the research and
development phase when the Smart Grid, Smart City
Program started. The relative immaturity of the product
meant that many of the challenges in trialling this
technology stemmed from the lack of demonstrated
practical applications and lack of experience
implementing this type of technology in the field.
The DGDS project trialled the RedFlow R510 zinc
bromine flow battery. The customer battery storage
was sized to store up to 10kWh of electricity, or about
half the daily requirements of a typical household.
The trial found that battery characteristics including
the discharge/charge profile, full cycle efficiency, and
ambient temperature performance all impacted the
battery output.
One key aspect of these batteries is they are net
consumers of energy. The customer based batteries
used in the trials consumed 300W in float mode,
and this loss of energy had an impact on overall
performance.
Another challenge was that the storage capacity
of the batteries was quite limited which meant that
correctly predicting when the network peak was
going to occur was important so that the batteries
were able to be used for peak demand management.
The trial found that if the customer based batteries
were dispatched too early, particularly on hot days
when high temperatures reduced the effective battery
capacity, the battery output dropped off before the
peak demand event occurred, or had ended. Similarly
if the batteries were dispatched too late the peak may
have already occurred.
The predictability of network peaks is generally better
for larger sections of the distribution network (i.e.
where network operators are predicting the behaviour
on average of a larger number of customers over a
greater geographical area), compared to load profiles
at individual feeder or customer level. This suggests
the scheduling of grid-embedded batteries for charge
and discharge connected higher up in the network
Fuel cells
Although slightly more mature than the Redflow
batteries, the Solid Oxide (BlueGen) fuel cells were
a relatively new technology at the commencement
of the trial. The BlueGen solid oxide fuel cells
that were trialled in this project were at the precommercialisation stage of development.
One of the key constraints for installations of the
BlueGen fuel cell was the requirement for the cell to be
connected to all utilities: i.e. electricity, gas and water.
To incentivise customers to trial the product they were
provided with hot water during the trial at no charge.
The units provided continuous electrical output of
1.5kW and waste heat for hot water. A gas hot water
booster was also installed to ensure hot water supply
quantity and temperature satisfied the customers
requirements. Trial participants were very enthusiastic
about their involvement in the DGDS project and
willingness to trial the technology was high. Their
feedback at the end of trial was generally very
positive and many indicated disappointment when
the units were decommissioned (it is important to
note customers were not liable for any of the capital
or operating costs of the units during the trial, and did
receive the financial benefits associated with free hot
water produced by the fuel cells).
144 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
Grid batteries
As previously discussed, implementation issues
prevented the installation and trialling of a grid
battery during the Smart Grid, Smart City trial
period. However, advanced modelling and PS+EDGE
simulations were performed in order to investigate the
potential network value of grid batteries in reducing
peak demand, reducing network capital expenditure
and improving asset utilisation.
Advanced modelling using PS+EDGE model was
performed for the Newcastle trial area with a large
grid battery with a rated capacity of 1MVA and battery
storage capacity of 2MWh. In addition, a PS+EDGE
simulation of a smaller grid battery (60kVA/ 120kWh)
was performed for the Newington trial area by the
University of Newcastle.
The objectives of the grid battery PS+EDGE simulation
were to determine:
If the introduction of a BESS had the ability to
reduce the peak demand on the local network
(11kV feeder load)
What impact using the BESS as a reactive load
or source can have on the voltage deviation of
the network
The impact of increased rooftop solar PV
penetration and the possibility of reverse power flow
The models and calculations were based on field
measurement data from the Homebush Bay zone 11kV
feeder for the Newington trial area, collected at 10
minute intervals, for the period from December 2011 to
December 2012. A load forecast tool was developed in
MATLAB for predicting the next days half-hourly load
demand of the Newington feeder, based on historical
temperature and load data. This tool was then used to
determine when to discharge the battery to maximise
the potential reduction in feeder peak demand.
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 145
146 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP
National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP 147
148 National Cost Benefit Assessment: Part One Smart Grid, Smart City Trials ARUP