Professional Documents
Culture Documents
Vice President, Teekay Norway AS (Retired), 2 Chief Hydrodynamicist, BMT Defence Services Ltd, 3 Technical Manager, MOL
Techno-Trade
ABSTRACT
1.
INTRODUCTION
Keywords
Propulsive efficiency
Comparison Model-Full scale tests
Propeller Boss Cap Fins, PBCF
Fuel Economy
2.
BACKGROUND
PBCF CONCEPT
3.1 Working mechanism of PBCF
10
CNT
FRY+PCC
G/C+RFR+FSR
O/T+PC+LGC
Chp+B/C
Avg. Line
2
Shaft Force Power (Ps)
0
0
10,000
20,000
30,000
40,000
test the propeller so that the shaft goes into the front of
the propeller. This is done by reversing the opens boat
and mounting it ahead of the propeller. This is called a
Reverse POT in this report.
However, the presence of the opens boat disturbs the flow
into the propeller and this affects the results. In order to
be able to correct for these effects, the following tests
need to be performed:
POT1 - Normal POT with propeller without PBCF
POT2 - Reverse POT with propeller without PBCF
POT3 - Reverse POT with propeller with PBCF.
Comparison of POT1 and POT2 enables the effect of the
Reverse POT to be established. Corrections can then be
made to POT3 to obtain an estimate of what the Normal
POT result would be for the propeller with PBCF if the
full hub vortex and PCBF effect could be modelled.
4.2.2 Investigation of Scale Effect
1.2E+06
Reynolds Number
1.0E+06
8.0E+05
6.0E+05
4.0E+05
2.0E+05
0.0E+00
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
Vs
(knots)
Baseline
% Reduction
Baseline +
PBCF
1802.7
1720.4
4.6%
14
9364.6
8970.5
4.2%
16
15123.4
14511.1
4.0%
(knots)
Baseline
% Reduction
Baseline +
PBCF
1073
1036.1
3.4%
14
6128.7
5899.1
3.7%
16
9676.8
9352.5
3.4%
From the model results, the pay-back period for the PBCF
device was calculated based on the cost of the PBCF
device and installation and the then-fuel-oil-price of
$600/tonne. It was estimated that at a 4% increase in
efficiency (or reduction of fuel use), the pay-back period
would be about 6 months.
5.
16
14
12
10
8
6
4
Trial 1
Trial 2
0
0
10
11
12
Month
20
Trial B1
Trial A1
15
10
5
Trial A2
Trial B2
0
0
10
11
12
13
14
15
Month
However, methods of determining performance from inservice data are not particularly precise, and it is possible
that this approach would not yield reliable results.
Early discussions with the supplier of PBCF (MOL TechTrade) suggested that the device had to be fitted in dock, but
it was subsequently agreed that this could in fact be done
with the vessel afloat but ballasted to raise the propeller boss
out of the water. Once this was known, it was decided that
the tests would be done using one vessel, and on further
thought, it was agreed that this could be done on a vessel
while in service without any prior docking at all. This meant
that the hull condition would be that of the vessel after
whatever period of service it had undertaken since its last
docking.
The vessel selected for this work was the Kilimanjaro Spirit,
which at the time of the trials was some 4 years and 9
months out of dock and could thus expect to be fouled and
to have a degraded performance. In one sense, this was
useful as it would show how the device worked with a
fouled ship, but it also means that it would be less easy to
relate the results to those obtained from the model tests.
Figure 9, seen below, has been constructed to illustrate the
trial sequence used. The indicative changes in powering
levels shown are based on those measured in the actual
trials.
27.5
27
26.5
26
25.5
25
24.5
24
23.5
23
22.5
Trial 1
Trial 2
0
10
11
12
Month
92rpm
iv
97rpm
v 101rpm
Just prior to the trial, the direction of the wind/waves was
established and the mile course was selected as being on a
heading of 135/315 degrees. This put the mile run nearly
directly in/out of the wind during the trial. There was
some cross current, but because we had accurate GPS
data, it was possible to resolve the distance run in the
vessel heading direction, thus removing the effect of any
cross current. Throughout the first trial, the wind was
generally less than about 15 knots true and the sea was
less than sea state 2, giving nearly ideal trial conditions.
The handling of the vessel throughout the trial was
exemplary, and the target trial course was adhered to.
Turns were conducted in such a manner to give minimum
speed loss and the trial runs were conducted in essentially
the same area of sea. No problems were encountered with
other vessels in the trial area, the captain having
successfully identified a zone with very little vessel
traffic. The first trial took some 10 hours from start of the
first run to completion of the last run.
The vessel was then taken into Bijela and the PBCF
device was fitted over a three day period (see Figure 10).
The device was fitted under the supervision of the captain
and the chief engineer, but the opportunity was also taken
by BMT to witness the fitting and to validate the correct
alignment of the device. BMT can confirm that in terms
of device alignment, the device was correctly fitted. The
vessel was then ballasted back to the trial condition and
taken back out to sea. The second trial was conducted in
the same wayas the first trial, except that the trial was run
on a 75/225 degree course, but in the same area as for trial
1. The weather conditions again were ideal, the true wind
being generally less than 10 knots and the sea state being
glassy (or about sea state 1).
12000.0
10000.0
Curve 2 Shipyard
trial less 0.5
knots
8000.0
6000.0
4000.0
2000.0
0.0
13.5
14.0
14.5
15.0
15.5
16.0
Vs (knots)
The fact that the results are close to the model test results
indicates that no scale effect is present. The full details
of all the previous trials that have been conducted on
these devices are not known. However, what can be said
is that the work here has been conducted in such a way as
to try and make sure the hull condition is the same for
both trials as far as possible. It may be possible that the
scale effect found in other cases is in fact partly due to
the improvement in hull condition that usually results
when a vessel is docked and painted, as it may well be the
case that some previous trials are comparing the no
device fitted to a fouled hull with device fitted to a clean
hull. The implication being that much of the benefit
being found may be due to the cleaning of the hull and
not the fitting of the device.
This change in shaft power, while being significant in
terms of fuel reduction (it should translate nearly into a
like-for-like reduction in fuel use, i.e., about 3.5% in
ballast and 4% in load), is actually quite a small change to
detect from in-service fuel returns and in-service
performance monitoring (Dinham-Peren 2010).
ACKNOWLEDGEMENTS
8.
REFERENCES
Ouchi, K., Ogura, M., Kono, Y., Orito, H., Shiotsu, T.,
Tamashima, M. & Koizuka, H. (1988). A Research
and Development of PBCF (Propeller Boss Cap
Fins) - Improvement of Flow from Propeller Boss.
Journal of the Society of Naval Architects of Japan,
163, 1988, pp. 66-78.
Ouchi, K. & Tamashima, M.. (1989). Research and
Development on PBCF (Propeller Boss Cap Fins).
Technical Paper for PBCF presented at PRADS 89,
October, 1989 Varna, Bulgaria,
Tanaka, Y., Nojiri, T. & Koh, T. (2009). Effect and
Application of PBCF (Propeller Boss Cap Fins).
International Symposium on Ship Design &
Construction - Environmentally Friendly Ships,
September 1st and 2nd 2009, organised by
JASNAOE, JIME, JIN & RINA.
Yokoo, M. & Nojiri, T. (2007). Fuel Saving Effect of
Propeller Boss Cap Fins evaluated from Actual
Vessel Data. JASNAOE spring meeting, 2007.
Table 3:
Mean
Ship
speed
through
Water
Mean
Mean
Corrected
Corrected
Shaft Power Revs
Mean
Ship
speed
through
Water
Mean
Corrected
Shaft Power
Mean
Corrected
Revs
Vs
Ps
Ns
Vs
Ps
Ns
Kts
kW
kW
Kts
kW
kW
14.300
8740.1
92.08
14.385
8612.3
92.15
14.882
10261.9
97.07
15.054
10354.2
97.59
15.406
11706.3
101.25
15.647
11831.1
101.96
15.588
12131.7
102.22
15.728
12077.8
102.42
15.619
12165.4
102.47
15.889
12477.4
104.00
Trial 1 - No PBCF
Change in Power
and Revs
Vs
Ps
Ns
Vs
Ps
Ns
% Ps
(knots)
(kW)
(RPM)
(knots)
(kW)
(RPM)
% Ns
14.4
9003.4
92.99
14.4
8653.5
92.30
-3.89%
-0.74%
14.6
9541.1
94.79
14.6
9173.0
93.90
-3.86%
-0.93%
14.8
10073.8
96.49
14.8
9690.5
95.49
-3.80%
-1.04%
15.0
10601.6
98.10
15.0
10205.9
97.06
-3.73%
-1.06%
15.2
11124.4
99.62
15.2
10719.4
98.61
-3.64%
-1.01%
15.4
11642.3
101.04
15.4
11230.8
100.15
-3.53%
-0.89%
15.6
12155.2
102.38
15.6
11740.2
101.67
-3.41%
-0.69%