You are on page 1of 144

TYPE-A

TYPICAL CROSS SECTION OF DADPUR- RUPRA ROAD (ODR) FROM KM 0/135 TO 2/300, 2/445 TO 3/060 & 4/200 TO 8/500

0/135 TO 2/300KM
2/445 TO 3/060
4/200 TO 8/500KM
TOTAL LENGTH

EXISTING
CRUST

2165.00m
615.00m
4300.00m
7080.00m

PROPOSED CRUST

10000

25 MM THICK SDBC
250 MM THICK WMM IN TWO LAYER
175 MM THICK GSB CLOSE GRADED GR-III
200 MM THICK GSB COARSE GRADED GR-II
2750

1000

1250

150MM THICK MOORUM IN SHOULDER


150MM THICK SAND INVERTED CHOKE
650 150MM THICK PLUGGED AGGREGATES

SLOPE 2.5%

2250

1830

EARTH

20mm PMC

650 MM

PROPOSED CRUST=
300

WBM- 150MM

1:1.5

2475

1:1.5

1830

3920

700 Avg

1350

450

2900
3050
1895
5130

7025

###

Junior Engineer
East (R&B) Section No.II
Bhawanipatna

Assistant Engineer
Kalahandi East (R&B) Sub-Divn
Bhawanipatna

Executive Engineer
Kalahandi (R&B) Divison
Bhawanipatna

TYPE-B
TYPICAL CROSS SECTION OF DADPUR- RUPRA ROAD (ODR) FROM KM 8/500 TO 11/00
8/500 TO 11/000 2500.00m

TOTAL LENGTH 2500.00m

EXISTING
CRUST

PROPOSED CRUST

10000

MM THICK SDBC
MM THICK WMM IN TWO LAYER
MM THICK GSB CLOSE GRADED GR-III
MM THICK GSB COARSE GRADED GR-II
150MM THICK MOORUM IN SHOULDER
250MM THICK SAND INVERTED CHOKE
650 250MM THICK SPLUGGED AGGREGATES
25
250
175
200

2750

1000

1250

SLOPE 2.5%

2250

1830

EARTH

650 MM

PROPOSED CRUST=

20mm PMC
300

WBM GR-III 150MM

1:1.5

2700

WBM GR-II- 150MM

1:1.5

1830

700 Avg

4070

1350

450

2900
3050
1895
5130

7025

###

Junior Engineer
East (R&B) Section No.II
Bhawanipatna

Assistant Engineer
Kalahandi East (R&B) Sub-Divn
Bhawanipatna

Executive Engineer
Kalahandi (R&B) Divison
Bhawanipatna

TYPE-C
TYPICAL CROSS SECTION OF DADPUR- RUPRA ROAD (ODR) BRIDGE SHORT APPROACH FROM KM 3/060 TO 3/595 & 3/735 TO 4/200

3/060 TO 3/595 535.00m


3/735 TO 4/200 465.00m
TOTAL LENGTH 1000.00m

PROPOSED CRUST
10000

MM THICK SDBC
MM THICK WMM IN TWO LAYER
MM THICK GSB CLOSE GRADED GR-III
MM THICK GSB COARSE GRADED GR-II
150MM THICK MOORUM IN SHOULDER
150MM THICK SAND INVERTED CHOKE
650 150MM THICK PLUGGED AGGREGATES
25
250
175
200

1500

3500
SLOPE 2.5%

EARTH

EARTH

PROPOSED CRUST=

650 MM

300

WBM- 150MM

1:1.5

5750
700 Avg

5750
3650

EARTH

3800

450

1350

3650
3800

7025

7025

###

Junior Engineer
East (R&B) Section No.II
Bhawanipatna

Assistant Engineer
Kalahandi East (R&B) Sub-Divn
Bhawanipatna

Executive Engineer
Kalahandi (R&B) Divison
Bhawanipatna

CHECK LIST FOR PREPARATION OF DETAILED PROJECT REPORT TO BE


SUBMITTED FOR LOANS UNDER R.I.D.F. ROAD/BRIDGE PROJECT.
i

Name of the Project


#REF!

ii

Districts covered

iii

Project
outlay(Rs.Crore)

Sl.No.
1
i
ii
iii
2
i
ii
iii
iv
v
3
i
a
b
c

d
e
f
ii
a

b
c

Kalahandi

#REF! Recast Estimated cost


Item

GENERAL
Whether the project is priorityzed by the State Govt.
Whether the project submitted through the Nodal Deptt.
Whether the project included in the State plan
Clearances from (Wherever applicable)
Ministry of Environment & Forests
Ministry of Railways
Administrative Approval
Technical Sanction
Land Acquisition-Extent,status and time-frame.
Technical Aspects
GENERAL
Whether Master Plan prepared by state Govt and proposed
projects are as per Master Plan
Whether proposed projects are new or strengthening of
existing roads.
Whether proposed projects have been designed as per IRC
standards.Reasons or deviation ,if any should be spelt out.
Type of road project- village Roads , Other District
Roads,Major Rural Roads
Whether fair weather connectivity is proposed.
Reasons for same to be elucidated
Road Projects
Details of roadway, carriage way , pavement thickness
(Formation, sub-base,base courses,black topping),culverts
and small bridges in existing and proposed conditions to be
furnished in relevant Annexure
Extent of cement concrete sections, wherever provided to
be detailed.
Justifications for widening/strengthening should be
supported by relevant data along with year of construction.

Furnished(
yes/No)

Remarks
Yes
Yes
Yes
Not Applicable
Not Applicable
Submitted
approval
Not Sanctioned
Not required

yes

Yes
ODR
Not required
Not required

L.S. & C.S.,Crust


design etc attached
NA

Yes

for

iii

4
i
ii
iii

Bridge Projects
Hydraulic data, geo-technical details of foundation,design
details and drawing to be furnished.
Financial Aspects.
Schedules of rate adopted ( whether uptdated to current
costs)
If,not whether cost proposed will be sufficient to create the
assets.
Cost Estimate.
a)Item - wise cost of project.
b)Item - wise expenditure incurred.
c)Item - wise cost of balance works.
d)Item - wise cost RIDF Loan.

e)Item wise state Government contribution

Not required

year-2013
Does not arise
Physical NA
NA
already
No.
and YES

Total
quantity,
completed
balance

to

be

completed

for

each

item of development
should be detailed in
unit cost analysis.

Attached

f) Year wise phasing of RIDF ioan and state and


Government contribution ( 2 year phasing allowed, reasos
for 3 years hasing, whether required )
g) Bar chart for project execution .

NA
yes

h) Specific justification for high cost of development


5

Yes

Benefit and justification


Overal impact of the
project need to assessed
and detailed

Potential:

Population

benefited/

accesss

to

marketing/

tourist/

pilgrims

centers.

(furnished) PCU, Data


likely saving in VOC
etc. Non recurring and
and

recurring

employment generation
- yes incom without with
project

and

statement

to

cash
be

furnished. yes
6

PWD, Works
Operation and maintenance

Department,
Odisha

7
i

Infrastructure facilities
PWD, Works
Organizational structure of the Implementing Deptt.

Department,
Odisha

ii

PWD, Works
Capacity and preparedness of the Implementing Deptt. And
status of Implemention of earlier sanctioned.

iii
iv
v
a
b
c
i
ii
iii
iv
v

Project quality control


Infrastructure and mechanisms
Availability of labour
Budget provision
For contribution to state share
For subsequent O&M
For repayment of loans - principal and interest.
Project Risks
Land Acquisition
Forest clearance
Railway /Road crossings
Construction hazards
Any other risk

Junior Engineer
Dharamagada (R&B) Section -II

Department,
Odisha
yes
yes
yes

Not required
Not required
Not required
NIL
No risk involves

Assistant Engineer
Dharamagada (R&B) Sub-Division

Executive Engineer
Kalahandi (R&B) Division

Page 7

QUANTITY FOR THE WORK:-

#REF!
Sl.
No.
1

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

Clearing and grubbing road land including sqm


uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier
and disposal of unserviceable materials and
stacking of serviceable material to be used
or auctioned, up to a lead of 1000 metres
including removal and disposal of top
organic soil not exceeding 150 mm in
thickness etc complete as per technical
specifications as per Clause 201 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)

#REF!

Scarifying the existing bituminous road sqm


surface to a depth of 50 mm and
disposal of scarified material with in all
lifts and lead etc. complete.

#REF!

Reworking the scarified bituminous sqm


surface after supplementing the base
materials with sand and compacting
finished surface etc. complete.

#REF!

Earth work in excavation of roadway cum


cutting in all kinds of soil or gavelly soil
including dressing and levelling the bed
within initial leads and lifts as per
direction of Engineer-in-charge.

#REF!

Loosening, leveling and Compacting cum


original
ground
supporting
embankment as per Clause 305 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Page 8
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

Providing coarse graded granular cum


Sub-base with Grading II stone
aggregate & screening materials as per
approved
drawing
and
technical
specifications as per Clause 401 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)

#REF!

Providing close graded granular Sub- cum


base with Grading II stone screening
materials as per approved drawing and
technical specifications as per Clause
401 of
MoSRT&H Specifications for
Road & Bridge works (Latest Revision)

#REF!

Providing,
laying,
spreading
and cum
compacting graded stone aggregate to
WMM specification as per Clause 406 of
MoSRT&H Specifications for Road &
Bridge works (4th Revision)

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Providing and applying primer coat with sqm


bitumen emulsion on prepared surface of
granular Base including clearing of road
surface and spraying primer at the rate of
0.60 kg/sqm using mechanical means.

#REF!

#REF!

#REF!

#REF!

10

Providing and laying surface dressing as sqm


wearing course using crushed stone
aggregates of 13mm nominal size on a layer
of bituminous binder of 60/70 penetration
grade of bitumen as per clause 510 of
MoSRT&H specification for road & bridge
works (4th revision)

#REF!

#REF!

#REF!

#REF!

11

Providing and applying tack coat with sqm


bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg
per
sqm
on
the
prepared
bituminous/granular surface cleaned with
mechanical broom.

#REF!

#REF!

#REF!

#REF!

#REF!

Page 9
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

12

Providing
and
laying
bituminous cum
macadam with hot mix plant using
crushed aggregates of Grading-II and
60/70 penetration grade of bitumen as
per
Clause 504 of MoSRT&H
Specifications for Road & Bridge works
(4th Revision)

#REF!

#REF!

#REF!

#REF!

13

Providing and laying SDBC using cum


crushed aggregates of Grading-II and
60/70 penetration grade of bitumen as
per
Clause 508 of MoSRT&H
Specifications for Road & Bridge works
(4th Revision)
Using 13.2mm to
0.09mm
(Type-B)
nominal
size
aggregates

#REF!

#REF!

#REF!

#REF!

14

Earthwork in embankment obtained cum


from borrow areas by mechanical
means as per approved drawing and
technical specifications as per Clause
305 of
MoSRT&H Specifications for
Road & Bridge works (Latest Revision)

#REF!

#REF!

#REF!

#REF!

15

Earthwork in embankment obtained cum


from borrow areas by mannual means
as per approved drawing and technical
specifications as per Clause 305 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)

#REF!

#REF!

#REF!

#REF!

16

Construction of embankment with cum


approved materials depsoted at site from
roadway cutting and excavation from
road drain and foundation of other
structures graded and compacted to
meet requirement of Table 300-02 as per
Clause
No.305.3.17
of
MoRT&H
specification for road and bridge works.

#REF!

#REF!

#REF!

#REF!

Page 10
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

17

Providing
compacted
granular cum
materials in shoulder by using
moorum having required P.I value with
sand admixture if required as per
approved
drawing
and
technical
specifications as per Clause 407 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)

#REF!

#REF!

#REF!

#REF!

18

Providing and laying of hot sqm


applied
thermoplastic
compound
2.5
mm
thick
including reflectorizing glass beads
@ 250 gms per sqm area, thickness
of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35
.The finished surface to be level,
uniform and free from streaks and
holes as per approved drawing and
technical specifications as per
Clause 803 of
MoSRT&H
Specifications for Road & Bridge
works (Latest Revision)
Gravel backing to revetments as cum
per approved drawing and technical
specifications as per Section 2500
of MoSRT&H Specifications for Road
& Bridge works (Latest Revision)

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

20

Rough stone dry packing in aprons cum


and revetments as per approved
drawing and technical specifications as
per Section 2500 of MoSRT&H
Specifications for Road & Bridge works
(Latest Revision).

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

21

Backfilling
behind wall with cum
excavated materials with cost of all
labour T&P etc.complete as per
specification and direction of the
Engineer-in-charge

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

19

Page 11
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

22 Grouting aprons and revetments sqm


23cm. deep with cement concrete
(1:4:8) using 25mm size hard granite
crusher broken coarse aggregatesas per
approved
drawing
and
technical
specifications as per Section 2500 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)

#REF!

#REF!

#REF!

#REF!

23

Turfing the slopes of embankment with sqm


compact turf grass as per approved
drawing and technical specifications as
per Clause 307 of
MoSRT&H
Specifications for Road & Bridge works
(Latest Revision)

#REF!

#REF!

#REF!

#REF!

24

Reinforced cement concrete M15 grade


kilometre stone of standard design as per
IRC:8-1980, fixing in position including
painting and printing etc as per Clause 804
of MoRT&H Specifications for Road &
Bridge works(4th Revision)
A) 5th Kilometer Stone

#REF!

#REF!

#REF!

#REF!

B) Ordinary Kilometer Stone

#REF!

#REF!

#REF!

#REF!

c) 200 mtr Stone

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

25 Construction of dry lean cement concrete cum


Sub- base over a prepared sub-grade
with coarse and fine aggregate
conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm,
aggregate cement ratio not to exceed
15:1, aggregate gradation after blending
to be as per table 600-1, cement content
not to be less than 150 kg/ cum,
optimum moisture content to be
determined
during
trial
length
construction, concrete strength not to be
less than 10 Mpa at 7 days, mixed in a
batching plant, transported to site, laid
with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory
roller, finishing and curing.

#REF!

Page 12
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

26 Construction

of un-reinforced, dowel cum


jointed, plain cement concrete pavement
over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25
mm, mixed in a batching and mixing plant as
per approved mix design, transported to
site, laid with a fixed form or slip form
paver, spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound,
finishing to lines and grades as per drawing

#REF!

Cement Concrete (1:2:4) using 12mm cum


size hard granite metal including hoisting
laying using concrete mixture and
vibrators including cost of all materials
labour T.&P. etc complete and as
directed by Engineer - in - charge.

#REF!

28 Providing and filling sand in road Cum


sub-base and watering with cost of
all etc. complete
29 Sand Filling in foundation of Cum
structures
as
per
approved
drawing and technical specifications
as per Section 1200 & 2100 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision).

#REF!

27

30

Cement Concrete (1:3:6) using 40mm


size hard granite metal including hoisting
laying using concrete mixture and
vibrators including cost of all materials
labour T.&P. etc complete and as
directed by Engineer - in - charge.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

Page 13
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

31

Dismantling of Granular courses of


flexible pavements and disposal of
dismantled materials up to a lead of
1000 metres, stacking serviceable and
unserviceable materials separately

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

32 Dismantling of existing structures like


culverts, bridges, retaining walls and
other structures, comprising of masonry,
cement concrete, wood work, steel work
including T&P and scaffolding wherever
necessary sorting the dismantling
materials disposal of unserviceable
materials and stacking the serviceable
materials with all leads and lifts of 1000m
as per clause no. 202 of MoRT&H
specification and direction of the
Engineer-in-charge
a) PCC M 15 & above
b) RCC M 20 above
c) RR stone masonry
in
excavation
for
33 Earthwork
foundation of structures, road works
and drain works in hard soil as per
approved
drawing
and
technical
specifications as per Clause 304 of
MoSRT&H Specifications for Road &
Bridge works (Latest Revision)
34

cum

#REF!

#REF!

#REF!

#REF!

#REF!

cum

#REF!

#REF!

#REF!

#REF!

#REF!

cum
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

P.C.C. M15 grade in foundation up to


bed level as per approved drawing and
technical specifications as per Section
1500, 1700 & 2200 of MoSRT&H
Specifications for Road & Bridge works
(Latest Revision)

In Foundation (Without dewatering)

cum

In Foundation (With dewatering)

cum

35

#REF!

cum

P.C.C. M15 grade in sub-structure as cum


per approved drawing and technical
specifications as per Section 1500, 1700
& 2200 of MoSRT&H Specifications for
Road & Bridge works (Latest Revision)

#REF!

Page 14
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

36

Reinforced cement concrete M-25 cum


nominal mix with crushed stone
aggregates to 20mm nominal size
mechanically mixed placed in foundation
and compacted by vibration including
curing for 14 daysas per
Section
No.1000 and 2100 of MORT&H
specifcation and direction of the
Engineer-in-charge

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

37

Reinforced cement concrete M-20 cum


nominal mix in Super-structure with
crushed stone aggregates to 40mm
nominal size mechanically mixed placed
in foundation and compacted by vibration
including curing for 14 daysas per
Section No.1000 and 2100 of MORT&H
specifcation and direction of the
Engineer-in-charge

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

38

Reinforced cement concrete M-30 cum


wearing coat and compacted by vibration
including curing for 14 daysas per
Section No.1000 and 2100 of MORT&H
specifcation and direction of the
Engineer-in-charge

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

39

Providing and laying flooring complete as cum


per drawing and technical specification
laid over cement concrete bedding
(150mm thick Flat Stone aprons
embaded 300mm thick concrete in M-15
with crushed stone aggregates

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

40 Supplying fitting and fixing HYSD bars Qntl


reinforcement in foundation, substructure
and superstructures as per drawing and
technical specifications as per section
1600 of MORT&H specifcation and
direction of the Engineer-in-charge

#REF!

Page 15
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

43 Providing and fixing in position of 20mm sqm


thick Salitex board in expansion joint for
fixed ends of simply supported spans not
exceeding 10m to cater for a horizontal
movement upto 20mm covered with
sealant complete as per drawing and
technical specification as per clause
no.2605 of MoRT&H specification and
direction of the EIC

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

44

Providing 40mm to 90mm size hard stone


metal as filter media including filling the
interstices with sand and rolling with hand
road roller or ramming with rammer.

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

45

Random Rubble Stone masonry work in CM cum


1:3
in
foundation/Substructure
and
superstructure including curing for 14 days
provision of weep holes scaffolding farm
work etc.complete as per drawing and
technical specification (1400)
12.7 of
MoRT&H (1st.revision

#REF!

#REF!

#REF!

#REF!

46 20mm thick cement plaster sqm


(1:4) over stone masonry as per
Section 1300 & 2200 of MoRT&H
specifications for Road & Bridge
works (4th Revision)

#REF!

#REF!

#REF!

#REF!

41 Providing & fixing drainage Each


spout with GI pipe-100mm dia up
to 600mm length including grating
and fixing of all arrangements
complete in deck slab as per
approved drawing and technical
specifications in deck slabs as per
Section
2700
of
MoSRT&H
Specifications for Road & Bridge
works (Latest Revision).
42 Providing weep holes as per approved mtr
drawing and technical specifications as
per Section 2700 of MoSRT&H
Specifications for Road & Bridge works
(Latest Revision)

cum

Page 16
Sl.
No.

Items

Unit

Road proper

CC Road

Retaining
Wall

Toe wall

CD works

CD works

CD works

Total
Quantity

Rate

Amount

10

11

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

47 Painting on Cement concrete sqm


surface providing and applying two
coats of Water based Cement paint
to un-plastered concrete surface
after cleaning the surface of dirt,
dust, oil, grease, efflorescence and
applying paint @ 1.00 ltr for 2.00
sqm. as per the direction of the
Engineer-in charge
48 Providing and fixing of R.C.C M15 Each
guard posts of 1.0m height and of size
15cm External diameter Meter at top and
25cm External diameter Meter at bottom
with base of 30cm x 30cm x 10 cm thick
as per IRC specifications for finished
item of work as per Section 1500, 1600
& 1700 of MoSRT&H Specifications for
Road & Bridge works (Latest Revision).

#REF!

49 Providing and fixing of retro- reflectorised


cautionary, mandatory and informatory
sign as per IRC :67 made of high
intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle
iron post 75 mm x 75 mm x 6 mm firmly
fixed to the ground by means of properly
designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm,
60 cm below ground level as per
approved drawing

a). Cautionery sign board Circular


b). Mandatory sign equilateral
c). Informatory sign board 600 x 450
d). Informatory sign board 120 x 80cm

each

#REF!

#REF!

#REF!

#REF!

Each

#REF!

#REF!

#REF!

#REF!

each

#REF!

#REF!

#REF!

#REF!

each

#REF!

#REF!

#REF!

#REF!
#REF!

Volume Calculation sheet of Earth work


SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

0.00

20

20.00

40

20.00

60

20.00

80

20.00

100

20.00

120

20.00

140

20.00

160

20.00

10

180

20.00

11

200

20.00

12

220

20.00

13

240

20.00

14

260

20.00

15

280

20.00

16

300

20.00

17

320

20.00

18

340

20.00

19

360

20.00

20

380

20.00

21

400

20.00

22

420

20.00

23

440

20.00

24

460

20.00

25

480

20.00

26

500

20.00

27

520

20.00

28

540

20.00

29

560

20.00

30

580

20.00

31

600

20.00

32

620

20.00

33

640

20.00

34

660

20.00

35

680

20.00

36

700

20.00

20.00

4.345

37

720

20.00

20.00

3.767

Mean Area

Filling volume
in cum

concrete road

concrete
road

4.056

81.120

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

38

740

20.00

20.00

4.157

3.962

79.240

39

760

20.00

20.00

4.460

4.309

86.170

40

780

20.00

20.00

5.326

4.893

97.860

41

800

20.00

20.00

5.597

5.462

109.230

42

820

20.00

20.00

4.865

5.231

104.620

43

840

20.00

20.00

4.762

4.814

96.270

44

860

20.00

20.00

4.868

4.815

96.300

45

880

20.00

20.00

4.596

4.732

94.640

46

900

20.00

20.00

4.284

4.440

88.800

47

920

20.00

20.00

3.968

4.126

82.520

48

940

20.00

20.00

4.462

4.215

84.300

49

960

20.00

20.00

4.914

4.688

93.760

50

980

20.00

20.00

4.914

4.914

98.280

51

1000

20.00

20.00

5.101

5.008

100.150

52

1020

20.00

20.00

4.797

4.949

98.980

53

1040

20.00

20.00

5.177

4.987

99.740

54

1060

20.00

20.00

5.039

5.108

102.160

55

1080

20.00

20.00

5.362

5.201

104.010

56

1100

20.00

20.00

5.509

5.436

108.710

57

1120

20.00

20.00

1.571

3.540

70.800

58

1140

20.00

20.00

5.079

3.325

66.500

59

1160

20.00

20.00

5.116

5.098

101.950

60

1180

20.00

20.00

5.538

5.327

106.540

61

1200

20.00

20.00

5.068

5.303

106.060

62

1220

20.00

20.00

5.317

5.193

103.850

63

1240

20.00

20.00

3.901

4.609

92.180

64

1260

20.00

20.00

3.953

3.927

78.540

65

1280

20.00

20.00

4.223

4.088

81.760

66

1300

20.00

20.00

4.966

4.595

91.890

67

1320

20.00

20.00

4.701

4.834

96.670

68

1340

20.00

20.00

4.783

4.742

94.840

69

1360

20.00

20.00

4.036

4.410

88.190

70

1380

20.00

20.00

4.627

4.332

86.630

71

1400

20.00

20.00

4.336

4.482

89.630

72

1420

20.00

20.00

4.621

4.479

89.570

73

1440

20.00

20.00

5.008

4.815

96.290

74

1460

20.00

20.00

4.469

4.739

94.770

75

1480

20.00

20.00

3.761

4.115

82.300

concrete
road

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

76

1500

20.00

20.00

4.322

4.042

80.830

77

1520

20.00

20.00

4.984

4.653

93.060

78

1540

20.00

20.00

4.163

4.574

91.470

79

1560

20.00

20.00

4.642

4.403

88.050

80

1580

20.00

20.00

5.068

4.855

97.100

81

1600

20.00

20.00

4.748

4.908

98.160

82

1620

20.00

20.00

2.982

3.865

77.300

83

1640

20.00

20.00

4.253

3.618

72.350

84

1660

20.00

20.00

3.768

4.011

80.210

85

1680

20.00

20.00

4.686

4.227

84.540

86

1700

20.00

20.00

5.439

5.063

101.250

87

1720

20.00

20.00

4.823

5.131

102.620

88

1740

20.00

20.00

4.665

4.744

94.880

89

1760

20.00

20.00

3.976

4.321

86.410

90

1780

20.00

20.00

3.288

3.632

72.640

91

1800

20.00

20.00

9.910

6.599

131.980

92

1820

20.00

20.00

4.391

7.151

143.010

93

1840

20.00

20.00

4.497

4.444

88.880

94

1860

20.00

20.00

4.387

4.442

88.840

95

1880

20.00

20.00

3.619

4.003

80.060

96

1900

20.00

20.00

4.004

3.812

76.230

97

1920

20.00

20.00

4.287

4.146

82.910

98

1940

20.00

20.00

4.130

4.209

84.170

99

1960

20.00

20.00

5.136

4.633

92.660

100

1980

20.00

20.00

4.695

4.916

98.310

101

2000

20.00

20.00

4.240

4.468

89.350

20.00

7.518

102
103
104
105

14340

106

14360

107

14380

108

14400

109

14420

110

14440

111

14460

112

14480

113

14500

concrete road

20.00

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

114

14520

20.00

20.00

8.464

7.991

159.820

115

14540

20.00

20.00

9.726

9.095

181.900

116

14560

20.00

20.00

7.836

8.781

175.620

117

14580

20.00

20.00

10.229

9.033

180.650

118

14600

20.00

20.00

10.379

10.304

206.080

119

14620

20.00

20.00

9.358

9.869

197.370

120

14640

20.00

20.00

9.216

9.287

185.740

121

14660

20.00

20.00

8.879

9.048

180.950

122

14680

20.00

20.00

8.624

8.752

175.030

123

14700

20.00

20.00

7.296

7.960

159.200

124

14720

20.00

20.00

6.801

7.049

140.970

125

14740

20.00

20.00

7.971

7.386

147.720

126

14760

20.00

20.00

10.469

9.220

184.400

127

14780

20.00

20.00

5.143

7.806

156.120

128

14800

20.00

20.00

9.283

7.213

144.260

129

14820

20.00

20.00

3.009

6.146

122.920

130

14840

20.00

20.00

9.115

6.062

121.240

131

14860

20.00

20.00

8.458

8.787

175.730

132

14880

20.00

20.00

6.986

7.722

154.440

133

14900

20.00

20.00

8.503

7.745

154.890

134

14920

20.00

20.00

8.111

8.307

166.140

135

14940

20.00

20.00

9.505

8.808

176.160

136

14960

20.00

20.00

8.965

9.235

184.700

137

14980

20.00

20.00

9.324

9.145

182.890

138

15000

20.00

20.00

8.096

8.710

174.200

139

15020

20.00

20.00

11.594

9.845

196.900

140

15040

20.00

20.00

9.695

10.645

212.890

141

15060

20.00

20.00

10.029

9.862

197.240

142

15080

20.00

20.00

12.811

11.420

228.400

143

15100

20.00

20.00

10.576

11.694

233.870

144

15120

20.00

20.00

9.879

10.228

204.550

145

15140

20.00

20.00

11.112

10.496

209.910

146

15160

20.00

20.00

10.242

10.677

213.540

147

15180

20.00

20.00

9.679

9.961

199.210

148

15200

20.00

20.00

8.680

9.180

183.590

149

15220

20.00

20.00

9.483

9.082

181.630

150

15240

20.00

20.00

9.651

9.567

191.340

151

15260

20.00

20.00

9.101

9.376

187.520

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

152

15280

20.00

20.00

9.654

9.378

187.550

153

15300

20.00

20.00

10.453

10.054

201.070

154

15320

20.00

20.00

10.820

10.637

212.730

155

15340

20.00

20.00

10.797

10.809

216.170

156

15360

20.00

20.00

11.404

11.101

222.010

157

15380

20.00

20.00

11.074

11.239

224.780

158

15400

20.00

20.00

9.166

10.120

202.400

159

15420

20.00

20.00

10.128

9.647

192.940

160

15440

20.00

20.00

8.517

9.323

186.450

161

15460

20.00

20.00

6.059

7.288

145.760

162

15480

20.00

20.00

14.512

10.286

205.710

163

15500

20.00

20.00

11.195

12.854

257.070

164

15520

20.00

20.00

8.969

10.082

201.640

165

15540

20.00

20.00

11.155

10.062

201.240

166

15560

20.00

20.00

12.368

11.762

235.230

167

15580

20.00

20.00

11.790

12.079

241.580

168

15600

20.00

20.00

11.658

11.724

234.480

169

15620

20.00

20.00

10.577

11.118

222.350

170

15640

20.00

20.00

11.574

11.076

221.510

171

15660

20.00

20.00

9.773

10.674

213.470

172

15680

20.00

20.00

9.934

9.854

197.070

173

15700

20.00

20.00

11.478

10.706

214.120

174

15720

20.00

20.00

13.355

12.417

248.330

175

15740

20.00

20.00

9.715

11.535

230.700

176

15760

20.00

20.00

8.891

9.303

186.060

177

15780

20.00

20.00

11.452

10.172

203.430

178

15800

20.00

20.00

13.026

12.239

244.780

179

15820

20.00

20.00

8.715

10.871

217.410

180

15840

20.00

20.00

11.232

9.974

199.470

181

15860

20.00

20.00

12.976

12.104

242.080

182

15880

20.00

20.00

13.339

13.158

263.150

183

15900

20.00

20.00

13.263

13.301

266.020

184

15920

20.00

20.00

14.209

13.736

274.720

185

15940

20.00

20.00

12.718

13.464

269.270

186

15960

20.00

20.00

11.104

11.911

238.220

187

15980

20.00

20.00

10.770

10.937

218.740

188

16000

20.00

20.00

11.844

11.307

226.140

189

16020

20.00

20.00

12.178

12.011

240.220

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

190

16040

20.00

20.00

12.103

12.141

242.810

191

16060

20.00

20.00

12.825

12.464

249.280

192

16080

20.00

20.00

12.376

12.601

252.010

193

16100

20.00

20.00

12.556

12.466

249.320

194

16120

20.00

20.00

12.963

12.760

255.190

195

16140

20.00

20.00

12.595

12.779

255.580

196

16160

20.00

20.00

13.584

13.090

261.790

197

16180

20.00

20.00

13.667

13.626

272.510

198

16200

20.00

20.00

13.334

13.501

270.010

199

16220

20.00

20.00

17.893

15.614

312.270

200

16240

20.00

20.00

17.654

17.774

355.470

201

16260

20.00

20.00

14.510

16.082

321.640

202

16280

20.00

20.00

14.369

14.440

288.790

203

16300

20.00

20.00

16.75

15.561

311.220

204

16320

20.00

20.00

16.238

16.496

329.910

205

16340

20.00

20.00

11.729

234.580

206

16360

20.00

20.00

6.962

7.091

141.820

207

16380

20.00

20.00

14.169

10.566

211.310

208

16400

20.00

20.00

14.863

14.516

290.320

209

16420

20.00

20.00

17.387

16.125

322.500

210

16440

20.00

20.00

15.617

16.502

330.040

211

16460

20.00

20.00

15.581

15.599

311.980

212

16480

20.00

20.00

15.897

15.739

314.780

213

16500

20.00

20.00

15.415

15.656

313.120

214

16520

20.00

20.00

15.447

15.431

308.620

215

16540

20.00

20.00

16.801

16.124

322.480

216

16560

20.00

20.00

16.76

16.781

335.610

217

16580

20.00

20.00

16.152

16.456

329.120

218

16600

20.00

20.00

16.503

16.328

326.550

219

16620

20.00

20.00

12.467

14.485

289.700

220

16640

20.00

20.00

12.214

12.341

246.810

221

16660

20.00

20.00

17.645

14.930

298.590

222

16680

20.00

20.00

18.801

18.223

364.460

223

16700

20.00

20.00

17.832

18.317

366.330

224

16720

20.00

20.00

14.739

16.286

325.710

225

16740

20.00

20.00

17.135

15.937

318.740

226

16760

20.00

20.00

17.796

17.466

349.310

227

16780

20.00

20.00

17.791

17.794

355.870

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

228

16800

20.00

20.00

14.505

16.148

322.960

229

16820

20.00

20.00

19.189

16.847

336.940

230

16840

20.00

20.00

21.802

20.496

409.910

231

16860

20.00

20.00

21.202

21.502

430.040

232

16880

20.00

20.00

19.857

20.530

410.590

233

16900

20.00

20.00

19.824

19.841

396.810

234

16920

20.00

20.00

17.499

18.662

373.230

235

16940

20.00

20.00

19.855

18.677

373.540

236

16960

20.00

20.00

18.767

19.311

386.220

237

16980

20.00

20.00

19.664

19.216

384.310

238

17000

20.00

20.00

17.411

18.538

370.750

239

17020

20.00

20.00

17.056

17.234

344.670

240

17040

20.00

20.00

17.656

17.356

347.120

241

17060

20.00

20.00

18.528

18.092

361.840

242

17080

20.00

20.00

19.973

19.251

385.010

243

17100

20.00

20.00

18.08

19.027

380.530

244

17120

20.00

20.00

18.179

18.130

362.590

245

17140

20.00

20.00

17.609

17.894

357.880

246

17160

20.00

20.00

17.47

17.540

350.790

247

17180

20.00

20.00

15.611

16.541

330.810

248

17200

20.00

20.00

15.402

15.507

310.130

249

17220

20.00

20.00

17.561

16.482

329.630

250

17240

20.00

20.00

22.216

19.889

397.770

251

17260

20.00

20.00

17.071

19.644

392.870

252

17280

20.00

20.00

13.765

15.418

308.360

253

17300

20.00

20.00

19.884

16.825

336.490

254

17320

20.00

20.00

20.197

20.041

400.810

255

17340

20.00

20.00

19.975

20.086

401.720

256

17360

20.00

20.00

20.407

20.191

403.820

257

17380

20.00

20.00

19.844

20.126

402.510

258

17400

20.00

20.00

17.63

18.737

374.740

259

17420

20.00

20.00

18.181

17.906

358.110

260

17440

20.00

20.00

13.244

15.713

314.250

261

17460

20.00

20.00

13.929

13.587

271.730

262

17480

20.00

20.00

13.991

13.960

279.200

263

17500

20.00

20.00

14.49

14.241

284.810

264

17520

20.00

20.00

16.86

15.675

313.500

265

17540

20.00

20.00

18.539

17.700

353.990

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

266

17560

20.00

20.00

15.728

17.134

342.670

267

17580

20.00

20.00

17.874

16.801

336.020

268

17600

20.00

20.00

19.439

18.657

373.130

269

17620

20.00

20.00

21.975

20.707

414.140

270

17640

20.00

20.00

19.302

20.639

412.770

271

17660

20.00

20.00

17.418

18.360

367.200

272

17680

20.00

20.00

16.059

16.739

334.770

273

17700

20.00

20.00

16.692

16.376

327.510

274

17720

20.00

20.00

16.058

16.375

327.500

275

17740

20.00

20.00

18.448

17.253

345.060

276

17760

20.00

20.00

17.361

17.905

358.090

277

17780

20.00

20.00

16.656

17.009

340.170

278

17800

20.00

20.00

17.602

17.129

342.580

279

17820

20.00

20.00

16.499

17.051

341.010

280

17840

20.00

20.00

15.285

15.892

317.840

281

17860

20.00

20.00

17.124

16.205

324.090

282

17880

20.00

20.00

15.164

16.144

322.880

283

17900

20.00

20.00

16.669

15.917

318.330

284

17920

20.00

20.00

15.835

16.252

325.040

285

17940

20.00

20.00

14.915

15.375

307.500

286

17960

20.00

20.00

18.149

16.532

330.640

287

17980

20.00

20.00

17.601

17.875

357.500

288

18000

20.00

20.00

21.066

19.334

386.670

289

18020

20.00

20.00

17.541

19.304

386.070

290

18040

20.00

20.00

19.081

18.311

366.220

291

18060

20.00

20.00

14.211

16.646

332.920

292

18080

20.00

20.00

11.796

13.004

260.070

293

18100

20.00

20.00

17.644

14.720

294.400

294

18120

20.00

20.00

16.663

17.154

343.070

295

18140

20.00

20.00

15.178

15.921

318.410

296

18160

20.00

20.00

14.713

14.946

298.910

297

18180

20.00

20.00

15.006

14.860

297.190

298

18200

20.00

20.00

16.776

15.891

317.820

299

18220

20.00

20.00

16.401

16.589

331.770

300

18240

20.00

20.00

16.729

16.565

331.300

301

18260

20.00

20.00

21.143

18.936

378.720

302

18280

20.00

20.00

18.846

19.995

399.890

303

18300

20.00

20.00

22.009

20.428

408.550

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

304

18320

20.00

20.00

15.852

18.931

378.610

305

18340

20.00

20.00

18.396

17.124

342.480

306

18360

20.00

20.00

16.793

17.595

351.890

307

18380

20.00

20.00

14.301

15.547

310.940

308

18400

20.00

20.00

14.683

14.492

289.840

309

18420

20.00

20.00

14.939

14.811

296.220

310

18440

20.00

20.00

13.656

14.298

285.950

311

18460

20.00

20.00

14.293

13.975

279.490

312

18480

20.00

20.00

18.171

16.232

324.640

313

18500

20.00

20.00

17.383

17.777

355.540

314

18520

20.00

20.00

17.112

17.248

344.950

315

18540

20.00

20.00

16.923

17.018

340.350

316

18560

20.00

20.00

16.656

16.790

335.790

317

18580

20.00

20.00

15.291

15.974

319.470

318

18600

20.00

20.00

19.363

17.327

346.540

319

18620

20.00

20.00

17.996

18.680

373.590

320

18640

20.00

20.00

16.023

17.010

340.190

321

18660

20.00

20.00

28.798

22.411

448.210

322

18680

20.00

20.00

18.917

23.858

477.150

323

18700

20.00

20.00

17.541

18.229

364.580

324

18720

20.00

20.00

19.42

18.481

369.610

325

18740

20.00

20.00

22.969

21.195

423.890

326

18760

20.00

20.00

11.654

17.312

346.230

327

18780

20.00

20.00

30.832

21.243

424.860

328

18800

20.00

20.00

24.243

27.538

550.750

329

18820

20.00

20.00

13.632

18.938

378.750

330

18840

20.00

20.00

14.101

13.867

277.330

331

18860

20.00

20.00

21.104

17.603

352.050

332

18880

20.00

20.00

20.885

20.995

419.890

333

18900

20.00

20.00

15.873

18.379

367.580

334

18920

20.00

20.00

20.926

18.400

367.990

335

18940

20.00

20.00

18.277

19.602

392.030

336

18960

20.00

20.00

18.657

18.467

369.340

337

18980

20.00

20.00

16.749

17.703

354.060

338

19000

20.00

20.00

18.707

17.728

354.560

339

19020

20.00

20.00

16.394

17.551

351.010

340

19040

20.00

20.00

21.562

18.978

379.560

341

19060

20.00

20.00

19.64

20.601

412.020

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

342

19080

20.00

20.00

20.485

20.063

401.250

343

19100

20.00

20.00

16.308

18.397

367.930

344

19120

20.00

20.00

17.309

16.809

336.170

345

19140

20.00

20.00

19.831

18.570

371.400

346

19160

20.00

20.00

15.373

17.602

352.040

347

19180

20.00

20.00

21.677

18.525

370.500

348

19200

20.00

20.00

21.606

21.642

432.830

349

19220

20.00

20.00

19.163

20.385

407.690

350

19240

20.00

20.00

21.472

20.318

406.350

351

19260

20.00

20.00

22.158

21.815

436.300

352

19280

20.00

20.00

23.623

22.891

457.810

353

19300

20.00

20.00

19.726

21.675

433.490

354

19320

20.00

20.00

10.468

15.097

301.940

355

19340

20.00

20.00

9.69

10.079

201.580

356

19360

20.00

20.00

10.577

10.134

202.670

357

19380

20.00

20.00

27.955

19.266

385.320

358

19400

20.00

20.00

28.088

28.022

560.430

359

19420

20.00

20.00

30.099

29.094

581.870

360

19440

20.00

20.00

21.187

25.643

512.860

361

19460

20.00

20.00

12.804

16.996

339.910

362

19480

20.00

20.00

20.006

16.405

328.100

363

19500

20.00

20.00

20.02

20.013

400.260

364

19520

20.00

20.00

10.759

15.390

307.790

365

19540

20.00

20.00

15.152

12.956

259.110

366

19560

20.00

20.00

16.301

15.727

314.530

367

19580

20.00

20.00

10.708

13.505

270.090

368

19600

20.00

20.00

7.798

9.253

185.060

369

19620

20.00

20.00

13.296

10.547

210.940

370

19640

20.00

20.00

11.068

12.182

243.640

371

19660

20.00

20.00

15.621

13.345

266.890

372

19680

20.00

20.00

18.945

17.283

345.660

373

19700

20.00

20.00

23.901

21.423

428.460

374

19720

20.00

20.00

20.466

22.184

443.670

375

19740

20.00

20.00

17.286

18.876

377.520

376

19760

20.00

20.00

17.256

17.271

345.420

377

19780

20.00

20.00

16.018

16.637

332.740

378

19800

20.00

20.00

16.003

16.011

320.210

379

19820

20.00

20.00

14.796

15.400

307.990

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

380

19840

20.00

20.00

13.099

13.948

278.950

381

19860

20.00

20.00

11.794

12.447

248.930

382

19880

20.00

20.00

7.531

9.663

193.250

383

19900

20.00

20.00

8.191

7.861

157.220

384

19920

20.00

20.00

11.397

9.794

195.880

385

19940

20.00

20.00

8.361

9.879

197.580

386

19960

20.00

20.00

7.212

7.787

155.730

387

19980

20.00

20.00

9.529

8.371

167.410

388

20000

20.00

20.00

16.204

12.867

257.330

389

20020

20.00

20.00

13.671

14.938

298.750

390

20040

20.00

20.00

4.233

8.952

179.040

391

20060

20.00

20.00

6.321

5.277

105.540

392

20080

20.00

20.00

16.497

11.409

228.180

393

20100

20.00

20.00

15.381

15.939

318.780

394

20120

20.00

20.00

15.553

15.467

309.340

395

20140

20.00

20.00

15.754

15.654

313.070

396

20160

20.00

20.00

18.257

17.006

340.110

397

20180

20.00

20.00

16.178

17.218

344.350

398

20200

20.00

20.00

18.276

17.227

344.540

399

20220

20.00

20.00

21.523

19.900

397.990

400

20240

20.00

20.00

18.362

19.943

398.850

401

20260

20.00

20.00

16.093

17.228

344.550

402

20280

20.00

20.00

15.492

15.793

315.850

403

20300

20.00

20.00

16.09

15.791

315.820

404

20320

20.00

20.00

17.01

16.550

331.000

405

20340

20.00

20.00

12.769

14.890

297.790

406

20360

20.00

20.00

17.896

15.333

306.650

407

20380

20.00

20.00

17.438

17.667

353.340

408

20400

20.00

20.00

14.525

15.982

319.630

409

20420

20.00

20.00

16.9

15.713

314.250

410

20440

20.00

20.00

18.396

17.648

352.960

411

20460

20.00

20.00

13.142

15.769

315.380

412

20480

20.00

20.00

13.445

13.294

265.870

413

20500

20.00

20.00

13.702

13.574

271.470

414

20520

20.00

20.00

16.265

14.984

299.670

415

20540

20.00

20.00

14.059

15.162

303.240

416

20560

20.00

20.00

13.658

13.859

277.170

417

20580

20.00

20.00

13.124

13.391

267.820

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

418

20600

20.00

20.00

15.828

14.476

289.520

419

20620

20.00

20.00

14.014

14.921

298.420

420

20640

20.00

20.00

13.133

13.574

271.470

421

20660

20.00

20.00

17.329

15.231

304.620

422

20680

20.00

20.00

21.787

19.558

391.160

423

20700

20.00

20.00

16.479

19.133

382.660

424

20720

20.00

20.00

16.897

16.688

333.760

425

20740

20.00

20.00

16.687

16.792

335.840

426

20760

20.00

20.00

15.895

16.291

325.820

427

20780

20.00

20.00

17.212

16.554

331.070

428

20800

20.00

20.00

16.122

16.667

333.340

429

20820

20.00

20.00

12.965

14.544

290.870

430

20840

20.00

20.00

17.827

15.396

307.920

431

20860

20.00

20.00

16.637

17.232

344.640

432

20880

20.00

20.00

18.503

17.570

351.400

433

20900

20.00

20.00

17.327

17.915

358.300

434

20920

20.00

20.00

15.743

16.535

330.700

435

20940

20.00

20.00

20.218

17.981

359.610

436

20960

20.00

20.00

15.273

17.746

354.910

437

20980

20.00

20.00

14.258

14.766

295.310

438

21000

20.00

20.00

16.514

15.386

307.720

439

21020

20.00

20.00

16.919

16.717

334.330

440

21040

20.00

20.00

16.352

16.636

332.710

441

21060

20.00

20.00

17.49

16.921

338.420

442

21080

20.00

20.00

17.682

17.586

351.720

443

21100

20.00

20.00

17.084

17.383

347.660

444

21120

20.00

20.00

15.977

16.531

330.610

445

21140

20.00

20.00

17.243

16.610

332.200

446

21160

20.00

20.00

17.867

17.555

351.100

447

21180

20.00

20.00

15.045

16.456

329.120

448

21200

20.00

20.00

15.839

15.442

308.840

449

21220

20.00

20.00

17.302

16.571

331.410

450

21240

20.00

20.00

11.893

14.598

291.950

451

21260

20.00

20.00

18.085

14.989

299.780

452

21280

20.00

20.00

17.208

17.647

352.930

453

21300

20.00

20.00

20.894

19.051

381.020

454

21320

20.00

20.00

16.728

18.811

376.220

455

21340

20.00

20.00

20.577

18.653

373.050

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

456

21360

20.00

20.00

32.021

26.299

525.980

457

21380

20.00

20.00

14.948

23.485

469.690

458

21400

20.00

20.00

15.695

15.322

306.430

459

21420

20.00

20.00

17.378

16.537

330.730

460

21440

20.00

20.00

17.365

17.372

347.430

461

21460

20.00

20.00

24.401

20.883

417.660

462

21480

20.00

20.00

17.039

20.720

414.400

463

21500

20.00

20.00

13.963

15.501

310.020

464

21520

20.00

20.00

15.955

14.959

299.180

465

21540

20.00

20.00

16.768

16.362

327.230

466

21560

20.00

20.00

15.833

16.301

326.010

467

21580

20.00

20.00

17.487

16.660

333.200

468

21600

20.00

20.00

13.493

15.490

309.800

469

21620

20.00

20.00

18.195

15.844

316.880

470

21640

20.00

20.00

16.648

17.422

348.430

471

21660

20.00

20.00

17.036

16.842

336.840

472

21680

20.00

20.00

15.511

16.274

325.470

473

21700

20.00

20.00

17.524

16.518

330.350

474

21720

20.00

20.00

11.48

14.502

290.040

475

21740

20.00

20.00

17.642

14.561

291.220

476

21760

20.00

20.00

17.531

17.587

351.730

477

21780

20.00

20.00

22.614

20.073

401.450

478

21800

20.00

20.00

18.123

20.369

407.370

479

21820

20.00

20.00

18.473

18.298

365.960

480

21840

20.00

20.00

16.917

17.695

353.900

481

21860

20.00

20.00

12.829

14.873

297.460

482

21880

20.00

20.00

15.929

14.379

287.580

483

21900

20.00

20.00

16.613

16.271

325.420

484

21920

20.00

20.00

14.629

15.621

312.420

485

21940

20.00

20.00

16.512

15.571

311.410

486

21960

20.00

20.00

14.079

15.296

305.910

487

21980

20.00

20.00

14.699

14.389

287.780

488

22000

20.00

20.00

15.777

15.238

304.760

489

22020

20.00

20.00

20.267

18.022

360.440

490

22040

20.00

20.00

13.096

16.682

333.630

491

22060

20.00

20.00

14.452

13.774

275.480

492

22080

20.00

20.00

14.855

14.654

293.070

493

22100

20.00

20.00

17.22

16.038

320.750

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

494

22120

20.00

20.00

16.122

16.671

333.420

495

22140

20.00

20.00

16.424

16.273

325.460

496

22160

20.00

20.00

15.873

16.149

322.970

497

22180

20.00

20.00

14.136

15.005

300.090

498

22200

20.00

20.00

18.321

16.229

324.570

499

22220

20.00

20.00

23.422

20.872

417.430

500

22240

20.00

20.00

22.029

22.726

454.510

501

22260

20.00

20.00

21.945

21.987

439.740

502

22280

20.00

20.00

21.534

21.740

434.790

503

22300

20.00

20.00

19.012

20.273

405.460

504

22320

20.00

20.00

20.76

19.886

397.720

505

22340

20.00

20.00

10.042

15.401

308.020

506

22360

20.00

20.00

6.241

8.142

162.830

507

22380

20.00

20.00

10.969

8.605

172.100

508

22400

20.00

20.00

16.655

13.812

276.240

509

22420

20.00

20.00

13.632

15.144

302.870

510

22440

20.00

20.00

11.57

12.601

252.020

511

22460

20.00

20.00

14.712

13.141

262.820

512

22480

20.00

20.00

17

15.856

317.120

513

22500

20.00

20.00

20.032

18.516

370.320

514

22520

20.00

20.00

13.5

16.766

335.320

515

22540

20.00

20.00

19.808

16.654

333.080

516

22560

20.00

20.00

16.352

18.080

361.600

517

22580

20.00

20.00

19.157

17.755

355.090

518

22600

20.00

20.00

19.516

19.337

386.730

519

22620

20.00

20.00

15.933

17.725

354.490

520

22640

20.00

20.00

15.832

15.883

317.650

521

22660

20.00

20.00

16.224

16.028

320.560

522

22680

20.00

20.00

14.816

15.520

310.400

523

22700

20.00

20.00

19.183

17.000

339.990

524

22720

20.00

20.00

22.452

20.818

416.350

525

22740

20.00

20.00

18.215

20.334

406.670

526

22760

20.00

20.00

19.478

18.847

376.930

527

22780

20.00

20.00

18.305

18.892

377.830

528

22800

20.00

20.00

20.321

19.313

386.260

529

22820

20.00

20.00

18.317

19.319

386.380

530

22840

20.00

20.00

7.672

12.995

259.890

531

22860

20.00

20.00

12.915

10.294

205.870

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

532

22880

20.00

20.00

13.389

13.152

263.040

533

22900

20.00

20.00

20.162

16.776

335.510

534

22920

20.00

20.00

20.238

20.200

404.000

535

22940

20.00

20.00

19.605

19.922

398.430

536

22960

20.00

20.00

12.138

15.872

317.430

537

22980

20.00

20.00

14.884

13.511

270.220

538

23000

20.00

20.00

21.32

18.102

362.040

539

23020

20.00

20.00

19.189

20.255

405.090

540

23040

20.00

20.00

16.959

18.074

361.480

541

23060

20.00

20.00

16.152

16.556

331.110

542

23080

20.00

20.00

13.936

15.044

300.880

543

23100

20.00

20.00

10.803

12.370

247.390

544

23120

20.00

20.00

16.032

13.418

268.350

545

23140

20.00

20.00

16.901

16.467

329.330

546

23160

20.00

20.00

16.767

16.834

336.680

547

23180

20.00

20.00

11.779

14.273

285.460

548

23200

20.00

20.00

13.973

12.876

257.520

549

23220

20.00

20.00

12.36

13.167

263.330

550

23240

20.00

20.00

12.357

12.359

247.170

551

23260

20.00

20.00

16.625

14.491

289.820

552

23280

20.00

20.00

17.063

16.844

336.880

553

23300

20.00

20.00

15.404

16.234

324.670

554

23320

20.00

20.00

15.824

15.614

312.280

555

23340

20.00

20.00

4.709

10.267

205.330

556

23360

20.00

20.00

9.763

7.236

144.720

557

23380

20.00

20.00

12.254

11.009

220.170

558

23400

20.00

20.00

9.577

10.916

218.310

559

23420

20.00

20.00

13.85

11.714

234.270

560

23440

20.00

20.00

21.221

17.536

350.710

561

23460

20.00

20.00

19.992

20.607

412.130

562

23480

20.00

20.00

17.913

18.953

379.050

563

23500

20.00

20.00

20.3

19.107

382.130

564

23520

20.00

20.00

15.552

17.926

358.520

565

23540

20.00

20.00

17.667

16.610

332.190

566

23560

20.00

20.00

8.01

12.839

256.770

567

23580

20.00

20.00

3.291

5.651

113.010

568

23600

20.00

20.00

7.929

5.610

112.200

569

23620

20.00

20.00

14.144

11.037

220.730

SL No Chainage

Length in
mtr

Less CD
Length

Net length

Filling Area

Mean Area

Filling volume
in cum

570

23640

20.00

20.00

14.832

14.488

289.760

571

23660

20.00

20.00

18.087

16.460

329.190

572

23680

20.00

20.00

17.562

17.825

356.490

573

23700

20.00

20.00

16.392

16.977

339.540

574

23720

20.00

20.00

12.882

14.637

292.740

575

23740

20.00

20.00

15.657

14.270

285.390

576

23760

20.00

20.00

10.122

12.890

257.790

577

23780

20.00

20.00

13.34

11.731

234.620

578

23800

20.00

20.00

12.569

12.955

259.090

579

23820

20.00

20.00

12.801

12.685

253.700

580

23840

20.00

20.00

13.092

12.947

258.930

581

23860

20.00

20.00

16.077

14.585

291.690

582

23880

20.00

20.00

4.898

10.488

209.750

583

23900

20.00

20.00

4.355

4.627

92.530

584

23920

20.00

20.00

10.836

7.596

151.910

585

23940

20.00

20.00

17.901

14.369

287.370

586

23960

20.00

20.00

4.495

11.198

223.960

587

23980

20.00

20.00

4.536

4.516

90.310

588

24000

20.00

20.00

4.345

4.441

88.810

TOTAL

151,283.22 CUM

Chainage

FillingArea

#REF!
$18,000.00

$4.95

$18,020.00

$3.92

88.728

$18,040.00

$5.40

93.194

$18,060.00

$6.12

115.131

$18,080.00

$7.45

135.7

$18,100.00

$8.02

154.75

$18,120.00

$8.02

160.375

$18,140.00

$6.41

144.288

$18,160.00

$10.18

165.963

$18,180.00

$15.38

255.598

$18,200.00

$9.19

245.69

$18,220.00

$9.25

184.435

$18,240.00

$9.64

188.924

$18,260.00

$10.16

197.999

$18,280.00

$7.84

179.98

$18,300.00

$9.36

171.955

$18,320.00

$11.46

208.135

$18,340.00

$10.71

221.635

$18,360.00

$7.81

185.185

$18,380.00

$9.04

168.535

$18,400.00

$11.94

209.77

$18,420.00

$11.39

233.23

$18,440.00

$11.89

232.78

$18,460.00

$10.89

227.755

$18,480.00

$10.32

212.005

$18,500.00

$12.91

232.255

$18,520.00

$14.99

278.98

$18,540.00

$10.89

258.805

$18,560.00

165.79

$18,580.00

110.815

$18,600.00

125.02

$18,620.00

140.71

$18,640.00

136.574

$18,660.00

129.17

$18,680.00

126.016

$18,700.00

129.58

$18,720.00

151.42

#REF!
$18,740.00

161.32

$18,760.00

151.48

$18,780.00

149.305

$18,800.00

153.985

$18,820.00

155.86

$18,840.00

144.355

$18,860.00

138.805

$18,880.00

$10.60

175.804

$18,900.00

$6.77

173.689

$18,920.00

$10.32

170.965

$18,940.00

$9.75

200.77

$18,960.00

$6.91

166.645

$18,980.00

$8.43

153.445

$19,000.00

$8.03

164.68

$19,020.00

$6.90

149.35

$19,040.00

$7.32

142.255

$19,060.00

$6.24

135.67

$19,080.00

$7.70

139.405

$19,100.00

$8.94

166.33

$19,120.00

$10.43

193.645

$19,140.00

$15.83

262.593

$19,160.00

$14.10

299.253

$19,180.00

$17.98

320.755

$19,200.00

$16.29

342.655

$19,220.00

$14.52

308.005

$19,240.00

$14.31

288.28

$19,260.00

$14.00

283.105

$19,280.00

$17.42

314.155

$19,300.00

$16.88

342.94

$19,320.00

$14.14

310.18

$19,340.00

$16.18

303.209

$19,360.00

$15.53

317.069

$19,380.00

$18.71

342.415

$19,400.00

$15.57

342.79

$19,420.00

$14.89

304.555

$19,440.00

$12.95

278.38

$19,460.00

$13.04

259.855

$19,480.00

$14.42

274.555

#REF!
$19,500.00

$13.02

274.405

$19,520.00

$13.29

263.155

$19,540.00

$14.43

277.195

$19,560.00

$11.94

263.71

$19,580.00

$10.77

227.125

$19,600.00

$12.71

234.76

$19,620.00

$11.90

246.055

$19,640.00

$8.46

203.62

$19,660.00

$8.31

167.695

$19,680.00

$7.60

$19,700.00

$9.66

$19,720.00

$13.17

228.28

$19,740.00

$10.38

235.428

$19,760.00

$11.63

220.053

$19,780.00

$8.84

204.655

$19,800.00

$13.29

221.305

$19,820.00

$15.45

287.38

$19,840.00

$20.96

364.045

$19,860.00

$16.65

376.045

$19,880.00

$15.83

324.73

$19,900.00

$15.58

314.08

$19,920.00

$18.40

339.805

$19,940.00

$15.06

334.555

$19,960.00

$8.70

237.58

$19,980.00

$18.99

276.9

$20,000.00

$13.21

321.932

$20,020.00

$41.85

550.53

$20,040.00

$50.21

920.52

$20,060.00

$55.29

1054.939

#REF!

$56.03

$1,100.82

#REF!

$46.31

$1,023.39

#REF!

$49.35

$956.61

#REF!

$46.14

$954.93

#REF!

$54.69

$1,008.26

#REF!

$54.16

$1,088.41

#REF!

$55.55

$1,097.07

#REF!

$56.16

$1,117.12

#REF!

$51.46

$1,076.18

#REF!
#REF!

$52.30

$1,037.61

#REF!

$52.62

$1,049.21

#REF!

$52.29

$1,049.11

#REF!

$51.85

$1,041.43

#REF!

$56.83

$1,086.82

#REF!

$55.63

$1,124.63

#REF!

$55.05

$1,106.78

#REF!

$56.86

$1,119.12

#REF!

$46.68

$1,035.46

#REF!

$35.92

$826.01

#REF!

$35.49

$714.09

#REF!

$29.07

$645.57

#REF!

$20.52

$495.83

#REF!

$12.04

$325.53

#REF!

$2.39

$144.24

#REF!

$7.61

$99.92

#REF!

$7.07

$146.70

#REF!

$7.76

$148.27

#REF!

$7.88

$156.45

#REF!

$6.62

$145.05

#REF!

$8.02

$146.40

#REF!

$7.64

$156.52

#REF!

$6.25

$138.84

#REF!

$8.09

$143.41

#REF!

$7.52

$156.13

#REF!

$6.88

$143.98

#REF!

$4.74

$116.21

#REF!

$5.98

$107.25

#REF!

$7.10

$130.78

#REF!

$5.60

$126.99

#REF!

$5.50

$110.99

#REF!

$5.16

$106.57

#REF!

$6.26

$114.21

#REF!

$7.54

$138.00

#REF!

$6.90

$144.39

#REF!

$5.91

$128.05

#REF!

$5.92

$118.21

#REF!

$6.83

$127.44

#REF!
#REF!

$6.32

$131.43

#REF!

$6.86

$131.79

#REF!

$6.17

$130.33

#REF!

$6.57

$127.42

#REF!

$7.18

$137.50

#REF!

$6.17

$133.48

#REF!

$5.88

$120.49

#REF!

$7.00

$128.82

#REF!

$6.93

$139.38

#REF!

$9.09

$160.24

#REF!

$8.57

$176.56

#REF!

$8.78

$173.47

#REF!

$5.13

$139.11

#REF!

$7.31

$124.38

#REF!

$9.13

$164.36

#REF!

$10.62

$197.43

#REF!

$8.57

$191.88

#REF!

$12.44

$210.09

#REF!

$7.64

$200.73

#REF!

$9.31

$169.42

#REF!

$8.07

$173.80

#REF!

$8.63

$167.01

#REF!

$5.68

$143.05

#REF!

$10.12

$157.96

#REF!

$10.71

$208.27

#REF!

$12.41

$231.16

#REF!

$15.98

$283.87

#REF!

$15.33

$313.06

#REF!

$12.08

$274.08

#REF!

$11.59

$236.70

#REF!

$7.73

$193.20

#REF!

$7.14

$148.72

#REF!

$12.35

$194.91

#REF!

$10.93

$232.83

#REF!

$10.74

$216.67

#REF!

$9.36

$200.97

#REF!

$11.15

$205.11

#REF!

$8.72

$198.72

#REF!
#REF!

$8.87

$175.92

#REF!

$9.18

$180.51

#REF!

$8.91

$180.93

#REF!

$8.37

$172.76

#REF!

$8.35

$167.18

#REF!

$10.71

$190.58

#REF!

$7.97

$186.75

#REF!

$12.35

$203.22

#REF!

$11.35

$237.04

#REF!

$11.21

$225.64

#REF!

$9.16

$203.67

#REF!

$7.69

$168.49

#REF!

$8.19

$79.40

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

PART-E
Detailed estimate for " Construction of Concrete Drain

from Km 0/00 to 1/00

0/00 to 1/00 (both)


1

2000 mtr
Earth work in excavation for foundation of structures as per
drawing and technical specifications, including setting out
construction of shoring and bracing, removal of stumps and
other deleterious materials dressing of sides and bottom and
backfilling with approved materials all kinds of soil as per
clause no.304 of MoRT&H specification and direction of the
EIC
1 x 2000.0 x 1.00 x 0.9 =
1800.00 cum
Net quantity
Filling foundation and plinth with coarsed river sand as per
direction of department including cost, conveyance, royalty
and taxes of all materials as per clause 304.2 as per clause
no.304 3.7 of MORT&H specifcation and direction of the
Engineer-in-charge

@R

#REF! /cum

#REF!

1 x 2000.00 x 1.00 x 0.100


=
200.00 cum
Plain cement concrete 1:3:6 Nominal mix in foundation with
crushed stone aggregates 40mm nominal size mechanically
mixed placed in foundation and compacted by vibration
including curring for 14 days

@R

#REF!

/cum

#REF!

1 x 2000.00 x 1.00 x 0.100


=
200.00 cum
Plain cement concrete M-15 nominal mix in Foundation with
crushed stone aggregates to 40mm nominal size mechanically
mixed placed in Sub-structure and compacted by vibration
including curing for 14 daysas per Section No.1000 and 2100
of MORT&H specifcation and direction of the Engineer-incharge

@R

#REF!

/cum

#REF!

@R

#REF!

/cum

#REF!

#REF!

#REF!

Bed concrete
1 x 2000.00
Side wall

x 1.00 x 0.100

2 x

x 0.15 x 0.60

200.00 cum

=
360.00 cum
=
560.00 cum
Providing weep holes in masonry/ Plain reinforced cement
concrete abutment, wing wall/ return wall with 100mm dia AC
pipe extending through the full width at the structure with
slope of IV:20 H towards drainage face complete as per
drawing and technical specification as per clause no.2706 of
MoRT&H specification and direction of the EIC
1 x

2000.00

2000.00

2 side x 0.20 m =

800.0 mtr

@R

#REF! /Mtr

Plain cement concrete M-20 nominal mix in cover slab with


crushed stone aggregates to 12mm nominal size mechanically
mixed placed in foundation and compacted by vibration
including curing for 14 days a s per MoRT&H Data Book with
specification as section 1000 and 2100 of MoRT&H
specification and direction of the EIC
2 x
1 x

450.0 x
1100.0 x

0.85 x 0.15
0.85 x 0.15 x

30%

=
=
=

114.75
42.08
156.83

cum

@R

#REF! /cum

Supplying fitting and fixing HYSD bars reinforcement in


foundation, substructure and superstructures as per drawing
and technical specifications as per section 1600 of MORT&H
specifcation and direction of the Engineer-in-charge

slab

156.83 cum@.0.80Qnt/cum

125.460 qnt

Skin

2000 x2.00 @ 5kg/sqm

200.000 Qnt
325.460 qnt

or Say

325.46 Qntl

Junior Engineer

@R

Assistant Engineer

#REF! /Qntl

Executive Engineer
NH Division, Deogarh

#REF!

#REF!

Construction of 600mm dia single row Hume Pipe culvert at ch.


1 Earth work in excavation of foundation of
structures as per drawing and technical
specification, including setting out construction of
shoring and bracing removal of stumps and other
deleterious materials, dressing of sides and
bottoms backfilling the excavation earth to the
extent required and utilising the remaining earth
locally for road work as per claue no.304 of
MoRT&H specification and direction of the
Engineer-in-charge

Head Wall
Below HP

2 x
1 x

4.76
12.55

x
x

1.325
1.360

x
x

1.11
1.16

=
=

14.00 cum
19.80 cum
33.80 cum

@R #REF! /cum

#REF!

#REF!

#REF!

2 Filling foundation and plinth trenches with sand as


per drawing and technical specification of
MoRT&H including cost, conveyance taxes of all
materials as per clause no. 304.3.7 MORT&H
specifcation and direction of the Engineer-incharge
Head Wall
2 x
Below Pipe
1 x
1/3rd of item 3 above

4.76
13.19

x
x

1.325
1.360

@R

x
x

#REF!

0.15
0.15

=
=
=
=

cum
cum
cum
cum

/cum

Plain cement concrete M-15 nominal mix in


foundation with crushed stone aggregates to
40mm nominal size mechanically mixed placed in
foundation and compacted by vibration including
curing for 14 daysas per Section No.1000 and
2100 of MORT&H specifcation and direction of the
Engineer-in-charge Below bed level
Head Wall

4.76 x 1.325 x 0.15


=
0.805 + 1.125
=
2 x 4.76 x
x 0.65
2
Below Pipe
1 x 13.39 x 1.36 x 0.15
=
=

2 x

@R

1.89
2.69
11.27
15.85

#REF!

Plain cement concrete M-15 nominal mix in


foundation with crushed stone aggregates to
40mm nominal size mechanically mixed placed in
foundation and compacted by vibration including
curing for 14 daysas per Section No.1000 and
2100 of MORT&H specifcation and direction of the
Engineer-in-charge Above bed level

/cum

1.89 cum
5.97 cum
2.73 cum
10.59 cum

2100 of MORT&H specifcation and direction of the


Engineer-in-charge Above bed level
Head Wall
+ 0.805
x 1.21
2
1 x 13.65 x 0.96 x
2 x 4.76 x 0.40 x
1 x 15.00 x 0.785 x 0.76 x 0.76

2 x 4.76 x
Around HP
Parapet
Deduct Pipe

0.40

@R

0.86
0.40

/cum

=
=
=
=

6.94 cum
11.27
1.52
-6.80
12.93

cum
cum
cum
cum
R

#REF!

#REF!

#REF!

#REF!

Providing and laying 600mm dia NP3 single row HP


with cost and carriage of all materials etc. complete.
Hume Pipe

6 x 2.50
@R

#REF!

=
#REF!

15.00 Mtr
/mtr

Providing weep holes in brick masonry / plain or RCC


abutment, wing wall and return wall with 100mm dia
AC pipe extending through the full width of structure
with slope of 1V : 20H towards draining face complete
as per drawing and technical specification as per
clause no.2706 of MoRT&H specification and
direction of the EIC
2 x 2 X 2 NOS

Junior Engineer

8.00 NOS

@R

Assistant Engineer

#REF! /Mtr

Executive Engineer

Part-B
Construction of One Row 1000mm dia NP-4 H.P. Culvert at Km 0/400, 16/00 & 23/600
1 Earth work in excavation of foundation of structures
as per drawing and Technical specification including
setting out, construction of shoringand bracing
removal of stumps and other deleterious matter
dressing of sides andbottom and back filling with
approved materials.
Face wall

6.40

Bed

10.86

U/S appron

3.30

U/S Toe

D/S appron.

D/S appron.

D/S Toe

286/960, 287/140, 287/360 Estimate


for=

1.40

1.60

1.500

1.50

4.10

6.40

2.30

3Nos

1.35

24.19 cum

1.72

29.89 cum

0.60

2.97 cum

0.600

0.60

1.08 cum

2.30

0.60

5.66 cum

0.70

0.60

2.69 cum

0.60

0.60

1.66 cum

68.14 cum

2.69 cum

29.04 cum

#REF!

#REF!

2 Plain cement concrete (1:2:4) M-15 in foundation with


crushed stone aggregates 20mm size technically
mixed, placed in foundation and compacted including
cost of all materials, labour, T&P etc. complete.
Face wall base

6.40

1.40

0.15

Face wall

6.40

1.25

+
2

0.40

Pipe bed

10.860 x

1.60

0.520

9.04 cum

Parapet

6.400

0.40

0.400

2.05 cum

42.82 cum

-1.94 cum

-1.99 cum

x 2.75

Deduction.
H.P. in face wall

2 x II/4x(1.23)2 x 1/2(1.027+0.606)

H.P. Base

1x 4/3 xh x
1x 4/3 x0.26x

a +2/5(h) x10.86m.
2

(0.502)2+2/5(0.26 )2 x10.86m.= 0.183 x 9.70

Total =

38.89 cum

#REF!

#REF!

12.50 Mtr.

#REF!

#REF!

#REF!

#REF!

3 Laying R.C.C pipe NP4 /Prestressed Concrete pipe for


culverts on first class bedding of granular material in
single row including fixing collar with Cement
mortar(1:2) but excluding excavation, protection work
back filling concrete and masonry works in head walls
and parapets.
1

12.50

4 Filling foundation & Plinth with sand well watered and


rammed including cost of all materials, royalty and
taxes, labour, T&P etc. complete.
Face wall

6.40

x 1.40

x 0.15

2.69 cum

Bed of H.P

10.860

x 1.60

x 0.15

2.61 cum

Inner face of face wall


upto Bed level.

6.40

x 0.150

+ 0.350

3.36 cum

Outer face

6.40

0.15

1.05

2.02 cum

Above pipe

11.70

1.60

0.60

11.23 cum

21.91 cum

x 1.05

5 Providing and laying Filter material underneath


pitching in slopes complete as per drawing and
Technical specification 15.5 2504
Revetment.

1.32

1.88

0.15

1.49 cum

1.49 cum

1.49 cum

#REF!

#REF!

6 Rough stone dry packing in approns and revetments


with cost of all materials, labour, T&P etc. complete.
U/S appron.

3.30

1.50

0.30

U/S Toe

1.50

0.60

0.60

1.08 cum

D/S appron.

4.10

2.30

0.30

2.83 cum

D/S appron.

6.40

0.70

0.30

1.34 cum

D/S Toe

2.30

0.60

0.60

1.66 cum

Revetment

1.32

1.88

0.30

2.98 cum

11.38 cum

#REF!

#REF!

54.57 sqm

#REF!

#REF!

6 Painting concrete surface Providing and applying 2


coats of water based cement paint to unplastered
concrete surface over a coat of cement wash after
cleaning the surface of dirt dust, oil grease
efflorescence and applying paint @ 1 Ltr for 2 sqm
Main wall

6.40

2.75

Top

6.40

0.40

35.20 sqm
5.12

sqm

Side

0.83

2.75

9.13

sqm

Road side

6.40

0.40

5.12

sqm

For 3 No culvert

#REF!
#REF!

PART-A
WIDENING OF EXISTING 3.00 X 1.50M. SPAN R.C.C. SLAB CULVERT AT KM 0.923,
1.250, 18.800, 19.300, 19.500 & 20.600KM OF DHARMAGADA- GOLAMUNDASINAPALI ROAD (MDR-111) UNDER CRF SCHEME
1

Dismantling of existing structures like culverts, bridges,


retaining walls and other structures, comprising of
masonry, cement concrete, wood work, steel work
including T&P and scaffolding wherever necessary sorting
the dismantling materials disposal of unserviceable
materials and stacking the serviceable materials with all
leads and lifts of 1000m as per clause no. 202 of
MoRT&H specification and direction of the Engineer-incharge

PCC Parapet
2 x 4.60 x 0.50
Qnty for 1no
Quantity for 6 nos

x 0.400 M

1.84 cum
1.84 cum
11.04 cum

0.41
0.12
0.12
0.65
3.90

cum
cum
cum
cum
cum

1 x 5.5 x 4.60
=
25.30 Sqm
Qnty for 1no
25.30 cum
Quantity for 6 nos
151.80 cum
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out
construction of shoring and bracing removal of stumps and
other deleterious materials, dressing of sides and bottoms
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work as per claue
no.304 of MoRT&H specification and direction of the
Engineer-in-charge
Abutment

4 x

2.50

2.85

Wingwall

4 x

3.60

3.13

Curtain US
U/S cross
Curtain DS
DS cross
Curtain wal
Embankment

1
1
1
1

1
2
1
2

3.30
0.72
3.30
2.20

+ 5.13 x 2.05
2 4.13
0.90 x 1.70
0.90 x 1.70
0.90 x 1.70
0.90 x 1.70

#REF!

@R.

#REF! /cum

#REF!

@R.

#REF! /sqm

#REF!

#REF!

Removal of existing cement concrete wearing coat


including its disposal complete as per Technical
Specification without causing any detrimental effect to
any part of the bridge structure and removal of dismantled
material with all lifts and lead upto 1000m

d
e

#REF! /cum

RCC M 20 side of Deck slab & Dirt


wall
2 x 4.600 x 0.30 x 0.150 M
4 x 0.650 x 0.30 x 0.150 M
4 x 0.515 x 0.383 x 0.150 M
Qnty for 1no
Quantity for 6 nos

@R.

x
x
x
x

4 x

x
x
x
x

5.50

x
x
x
x

2.00

+
2

1.85

3.95
2.98

52.730 cum

1.30

Qnty for 1no


Quantity for 6 nos
@R.

121.920 cum
5.049
2.203
5.049
6.732

cum
cum
cum
cum

85.090 cum
278.77 cum
1672.64 cum
#REF! /cum

Filling foundation and plinth trenches with sand as per


drawing and technical specification of MoRT&H including
cost, conveyance taxes of all materials as per clause no.
304.3.7 MORT&H specifcation and direction of the Engineerin-charge

(I)

Below PCC
Abutment
Wing wall
(II) Below GL
Wing Inner

1 x 4 x
2 x 2 x

2.50
3.60

x
x

2.85
3.13

x
x

2
2
2
4

x 2 x 3.60 x 0.60 x
x 2 x 3.60 x 0.80 x
Wing end
x 2 x 3.13 x 0.10 x
Wing outer
x 3.70 x 0.80 + 1.10
US Rigid Apron
2 0.95
Inner
0.800 + 0.970
0.100
1 x 2 x
x
2 0.89
1.500 + 2.040
0.100
1 x 1 x
x
2 1.77
Outer
1 x 1 x 7.00 x 0.10 x
DS Rigid Apron
Inner
3.000 + 3.170
0.100
1 x 2 x
x
2 3.09
2.200 + 2.740
0.100
1 x 1 x
x
2 2.47
Outer
1 x 1 x 9.30 x 0.10 x
Belo BD
10.10 + 9.700
0.800
1 x 2 x
x
2 9.9
Above
2.70 + 2.400
9.200
1 x 2 x
x
BD
2 2.55

0.20
0.20

5.700 cum
9.014 cum

0.40
0.80
1.85
x 1.85

3.456
9.216
2.316
26.010

+ 0.300
x
2 0.2
+ 0.300
x
2 0.2
1.05
+ 0.300
2 0.2
+ 0.300
2 0.2
1.05
+ 0.500
2 0.65
+ 8.300
2 8.75

0.60
0.60

cum
cum
cum
cum

0.214 cum
0.212 cum
0.735 cum

0.60

0.60

1.20

1.35

0.742 cum
0.296 cum
0.977 cum
15.444 cum
60.244 cum
134.58 cum

5
(I)

Qnty for 1no


134.58 cum
Quantity for 6 nos
807.46 cum
@R.
Cement concrete (1:3:6) using 4cm size hard granite metal
including cost of all materials, labour T&P etc. complete
Below PCC
Abutment
Wing wall
Curtain wall US

Cross
Curtain wall DS

Cross

1
2
1
1
1
1

x
x
x
x
x
x

4
2
1
2
1
2

2.50
3.25
3.80
0.70
3.80
2.20

x
x
x
x
x
x

2.85
2.13
0.90
0.90
0.90
0.90

x
x
x
x
x
x

0.15
0.15
0.15
0.15
0.15
0.15

Qnty for 1no


10.24 cum
Quantity for 6 nos
61.43 cum
@R.
Plain cement concrete M-15 nominal mix in foundation with
crushed stone aggregates to 40mm nominal size mechanically
mixed placed in foundation and compacted by vibration
including curing for 14 daysas per Section No.1000 and 2100
of MORT&H specifcation and direction of the Engineer-incharge

A Below Bed level


a Abutment
1st.Footing
2nd.Footing
3rd.Footing

4 x
4 x
4 x
4 x

x
x
x
x
x
x

Wing wall
1st.footing
2nd footing

2.50 x 2.65 x 0.20


=
2.50 x 2.25 x 0.20
=
2.50 x 1.85 x 0.40
=
1.85 + 1.45
2.50
x 0.40
2 1.65

2 x 2 x
2 x 2 x
2 x 2 x

3.10
3.30
3.50

x
x
x

1.93
1.93
1.53

x
x
x

0.20
0.20
0.40

#REF! /cum

4.275
4.154
0.513
0.189
0.513
0.594
10.24

#REF!

#REF!

cum
cum
cum
cum
cum
cum
cum

#REF! /cum

5.300
4.500
7.400
6.600

cum
cum
cum
cum

4.786 cum
5.095 cum
8.568 cum

3rd footing
c

2 x 2 x

Curtain wall
DS Curtain wall
Cross wall

1 x
2 x

US Curtain wall
Cross wall
d

Rigid Apron
US Apron
DS appron

3.80

1.100 +
2

1 x
2 x

3.50

3.80

2.600 +
2

0.972 +
2
2.472 +
1 x
2
1 x

1.53

+ 1.13
2

0.700 + 0.400
2 0.55
0.800
0.700 +
x
0.95
2
0.700 + 0.400
x
2 0.55
2.300
0.700 +
x
2.45
2
x

2.195 cum

1.05

0.400
x
0.55
x

18.620 cum

0.40

1.05

2.195 cum

1.05

0.400
x
0.55

1.015
2.129 + 2.043
x
x
0.99
2 2.09
2.515
2.129 + 2.043
x
x
2.49
2 2.09

1.097 cum

1.05

0.15
0.15

2.830 cum

0.310 cum
0.781 cum
70.277 cum

Qnty for 1no


Quantity for 6 nos

70.28 cum
421.66 cum

4
Dirtwall
b

Wing wall

Rigid Apron
Cross wall

1
4
1
1

+ 1.39
2 1.42
1.39 + 0.97
x 2.50 x
2 1.18
x 4 x 2.50
0.467 +
x
2
4.00 + 3.50
1.130
x
x
2 3.75
x 2 x 1.50 x 0.40 x
x 2 x 3.70 x 0.40 x
2.50

1.45

Qnty for 1no


Quantity for 6 nos
7

0.30

1.30

0.30

1
1
1
1

#REF!

#REF!

#REF! /cum R

#REF!

15.340 cum

x 0.515

+ 0.500
x 2.025
2 0.82
0.60
=
0.60
=

1.975 cum
24.908 cum
0.720 cum
1.776 cum
48.979 cum

48.98 cum
293.87 cum

x
x
x
x

4
2
2
2

x
x
x
x

Qnty for 1no


Quantity for 6 nos

#REF! /cum

2.80
2.80
4.60
4.60

x
x
x
x

0.550
4.000
0.550
0.400

x 0.20
x 0.350
x 0.32
x 0.50

=
=
=
=

1.232
7.840
1.594
1.840
12.506

cum
cum
cum
cum
cum

12.51 cum
75.04 cum
@R.

#REF!

4.260 cum

@R.
Plain /Reinforcement cement concrete M-25 nominal mix in
Superstructure with crushed stone aggregates to 40mm
nominal size mechanically mixed placed in foundation and
compacted by vibration including curing for 14 days as per
section 1000 and 2300 of MORT&H specifcation and
direction of the Engineer-in-charge
Bed Block
Deck slab
Kerbs
Parapets

#REF! /cum

@R.
B Above Bed level M-15
a Abutment
4 x

#REF! /cum

RCC Grade M-30 in RCC wearing coat including dewatering


farm work and mixing Cement mortar with concrete Mixer
and complete as per MORT&H specification
Over deck
1 x
Qnty for 1no
Quantity for 6 nos

4.60

x 10.90 x 0.075 =
3.76 cum
22.56 cum

3.76 cum
@R.

Drainage spouts complete as per drawing and technical


specification of MORT&H specifcation and direction of the
Engineer-in-charge

Over deck
2 x 2.00 =
4.00 nos
Qnty for 1no
4.00 nos
Quantity for 6 nos
24.00 nos
10 Supplying fitting and fixing HYSD bars reinforcement in
foundation, substructure and superstructures as per drawing
and technical specifications as per section 1600 of MORT&H
specifcation and direction of the Engineer-in-charge
A Skin reinforcement
0.15+0.4+0.4+0.8+0.3+1.5+0.55+0.3
Abt Outer
0.15+0.4+0.4+0.8+1.5+0.50+0.515
Abt Inner
Abt Outer
1 x 4 x 2.80 x 4.400
Abt Inner
1 x 4 x 2.80 x 4.265
Abt Face
4 x 2.65 x 0.550
4 x 2.50 x 0.200
4 x 2.10 x 0.200
4 x 1.85 x 0.400
4 x 1.85 + 1.45 x 0.400
2 1.65
4 x 1.45 + 0.97 x 1.500
2 1.21
4 x 0.47 + 0.30 x 0.515
2 0.38
Wing Out/ Inn
4 x 2 x 3.10 x 0.400
4 x 2 x 3.30 x 0.600
4 x 2 x 3.50 x 0.800
4 x 2 x 3.50 + 4.00 x 2.160
2 3.75
Wing End
2 x 2 x 1.93 x 0.400
2 x 2 x 1.53 x 0.400
2 x 2 x 1.53 + 1.13 x 0.400
2 1.33
2 x 2 x 1.13 + 0.50 x 2.025
2 0.82

=
=
=
=
=
=
=

@R.

49.28
47.77
5.83
2.00
1.68
2.96
2.64

7.26 sqm

0.78 sqm
9.92
15.84
22.40
64.80

#REF!

#REF!

#REF!

sqm
sqm
sqm
sqm
sqm
sqm
sqm

=
=
=
=

#REF! /nos

sqm
sqm
sqm
sqm

=
=
=

3.09 sqm
2.45 sqm
2.13 sqm

6.64 sqm
247.47 sqm

247.47 sqm @ 5.00 Kg/sqm


B Dirt wall, RCC slab, Kerb & Parapet
Vide item- 6
12.506 cum @ 120 Kg/cum
C Wearing coat
Vide item- 7
3.760
cum @ 75 Kg/cum

1237.35 Kg
1500.72 Kg
282.00 Kg
3020.07 kg

302.0100 Qntl
Qnty for 1no
302.01 Qnt
Quantity for 6 nos
1812.06 Qnt
@R.
11 Providing weep holes in brick masonry / plain or RCC
abutment, wing wall and return wall with 100mm dia AC pipe
extending through the full width of structure with slope of
1V : 20H towards draining face complete as per drawing and
technical specification as per clause no.2706 of MoRT&H
specification and direction of the EIC
a
b

Abutment
Wing wall

1 x 2 x
1 x 4 x

Qnty for 1no


Quantity for 6 nos

1.5
4.0

#REF! /Qnt

3.00 nos
16.00 nos
19.00 nos
19.00 nos
114.00 nos

@R.

#REF! /Ech

12 Metal Spall backing in the rear of well steining or weep holes


of abutment and deep drains including cost of all materials etc
complete
Abt

1 x 4 x

2.50 +
2
Wing 2 x 2 x 3.30 +
wall
2
Volume
37.290 x
Qnty for 1no
Quantity for 6 nos

1.90
2.20
4.00
3.65
0.60

x 1.500 =

13.20 sqm

x 1.650 =

24.09 sqm
37.290 sqm
22.370 cum

22.37 cum
134.22 cum

#REF!

#REF!

1380.00

#REF! /sqm

#REF!

#REF! /sqm

#REF!

#REF!

@R.

#REF! /cum

13 Providing and laying flooring complete as per drawing and


technical specification laid over cement concrete bedding
(150mm thick Flat Stone aprons embaded 300mm thick
concrete in M-15 with crushed stone aggregates
a

US Appron

DS Apron

1 x
1 x

1.10
2.60

+
2
+
2

0.950
5.100 + 4.800
x
x
1.03
2 4.95
2.45
5.100 + 4.800
x
x
2.53
2 4.95

0.30
0.30

1.530 cum
3.757 cum
5.287 cum

Qnty for 1no


Quantity for 6 nos

5.29 cum
31.72 cum

@R.
14 Providing Tar paper as bearing between cap and deck slab as
per drawing and technical specification of Road and Bridge
works (4th Revision) of Ministry and direction of the
Engineer-in-charge
1
x 4 x 2.50
Qnty for 1no
Quantity for 6 nos

x 0.575

5.75 sqm
5.75 sqm
34.50 sqm

@R.

#REF! /cum

40.00 /sqm

Ls

15 Providing and fixing in position of 20mm thick Salitex board


in expansion joint for fixed ends of simply supported spans
not exceeding 10m to cater for a horizontal movement upto
20mm covered with sealant complete as per drawing and
technical specification as per clause no.2605 of MoRT&H
specification and direction of the EIC
1
x 4 x 2.8 x 0.300 =
3.36 sqm
Qnty for 1no
3.36 sqm
Quantity for 6 nos
20.16 sqm
@R.
16 Painting concrete surface Providing and applying 2 coats of
water based cement paint to unplastered concrete surface over
a coat of cement wash after cleaning the surface of dirt dust,
oil grease efflorescence and applying paint @ 1 Ltr for 2 sqm

Parapet
Kerb

2 x
2 x

4.60
4.60

Qnty for 1no


Quantity for 6 nos

x 1.300
x 0.300

11.96
2.76
14.72
14.72
88.32

sqm
sqm
sqm
sqm
sqm

@R.

CROSS SECTION OF CONCRETE DRAIN

150

150

RCC COVER SLAB

WEEP HOLES
PCC M-15

600
###

###

550

100MM PCC M-15


100MM CC 1:3:6
100MM SAND

1000

Assistant Engineer,

Executive Engineer,

Construction of Box Cell of 2000mm x 2000mm at chainage 1/900 & 18/00 Km


Qnty. Unit

Rate
@Rs.

Amount.(in
Rs.)

1 Earth work in excavation of foundation in all kinds


of soil
Road embankment.

x 16.00

+ 8.00
2

x 1.50

x 3.00

Bed of Box cell

x 3.34

x 12.00

x 0.85

For key at base

x 0.95

x 2.60

x 0.85

Floor Appron DS &US

x 2.77

+ 0.30
2
x 7.358

+ 2.00

x 0.75

Flexible appron.U/S

x 3.00

x 7.358

x 0.75

Flexible appron.D/S

x 6.00

x 7.358

x 0.75

Wing wall

x 4.779

+ 1.894

x 3.399

Return wall

x 0.944

1.20

108.00 cum

34.000 cum

2.760 cum

25.270 cum

21.520 cum

43.040 cum

77.600 cum

22.800 cum

18.760 cum

2
+ 1.20
2
+ 1.20
2

2
+ 1.694

+ 2.010 x 2.150
2

x 2.01

x 2.15

2
Certain Wall
U/S Type-II

x 7.358

x 1.50

x 1.70

D/S Type-II

x 7.358

x 1.85

x 2.20

29.950 cum

383.700 cum

Quantity for 2 Nos

767.400 cum

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

2 Providing P.C.C M-15 grade concrete in foundation


and plinth.
Bed of Box cell

x 3.340

x 12.00

x 0.15

For key at Base

x 3.340

x 1.35

x 0.15

Floor Appron DS &US

x 2.77

x 7.358

+ 2.00

6.010 cum

1.350 cum

x 0.15

3.890 cum

+ 2.010 x 0.150

5.410 cum

1.710 cum

2
Wing wall

x 4.779

+ 1.894

x 3.399

2
Return wall

x 1.04

+ 1.79

2
x 2.01

x 0.15

2
Certain Wall
U/S Type-II Base

x 7.358

x 1.50

x 0.15

1.660 cum

1st footing

x 7.358

x 1.30

x 0.80

7.650 cum

2nd footing.

x 7.358

x 0.45

x 0.75

2.480 cum

3rd footing .

x 7.358

x 0.20

x 0.45

0.660 cum

D/S Type-I Base

x 7.358

x 1.85

x 0.15

2.040 cum

1st footing

x 7.358

x 1.65

x 0.55

6.680 cum

2nd footing.

x 7.358

x 0.75

x 0.75

4.140 cum

3rd footing .

x 7.358

x 0.45

x 0.75

2.480 cum

4th footing.

x 7.358

x 0.20

x 0.45

0.660 cum

Below approach slab

x 3.500

x 12.00

x 0.15

12.600 cum

Above appron.

x 2.77

x 7.358

+ 2.00
2

x 0.30

7.780 cum

67.200 cum

Quantity for 2 Nos

134.400 cum

3 Providing R.C.C M-20


A) Box Cell.
Total quantity vide standard drawing for box cell
culverts SD-108 of 1/22/0 P-11
Quantity for 2 Nos

54.00 Cum
108.000 cum

4 Providing P.C.C M-20 grade concrete


Wing wall.

Qnty. As per standard drawing for box cell culvert


Quantity for 2 Nos

47.10 Cum
94.200 cum

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

5 Filling foundation with sand .


Below bed slab.

x 3.340

x 12.00

x 0.15

6.010 cum

x 1.894

x 0.10

x 0.50

4x1.894x1/2[{(0.455x0.70)+(0.35x0.85)}+{(0.467x0.70)+(0.55x0.85)}]

=
=

0.380 cum
13.460 cum

Inner side.

0.960 cum

10.274 cum

Wing wall up to Bed Level.


Back of wing wall

x 4.779

x 0.10

x 0.50

4x4.779x1/2[{(0.455x0.70)+(0.35x0.70)}+1/2{(0.703x0.70)+1/2(0.70+0.46)x0.46 }]

Certain Wall
U/S Type-I Base

D/S Type-II Base

Back filling

x 7.358

x 1.85

x 0.15

2.040 cum

x 7.358

x 0.10

x 0.55

0.810 cum

x 7.358

x 0.55

x 0.75

6.070 cum

x 7.358

x 0.70

x 0.75

7.730 cum

x 7.358

x 1.50

x 0.15

1.660 cum

x 7.358

x 0.10

x 0.80

1.180 cum

x 7.358

x 0.525

x 0.75

5.790 cum

x 7.358

x 0.65

x 0.45

4.300 cum

x 12.000 x 3.50

+ 1.00

x 2.50

135.000 cum

195.664 cum
391.330 cum

Quantity for 2 Nos


6 Providing HYSD bar reinforcement including
straightening, cutting,bending and binding placing
in position etc. complete.
Wing wall.
A) For Box Cell.

As per standard drawings of Box cell culvert vide


SD/108 of 1/22/0 P-11
b Wearing coat qnty

2.130

@ 75 Kg/cum

3.458 M.T
0.160 M.T

=
Quantity for 2 Nos

3.618 M.T
7.240 MT

7 Providing R.C.C railing as per SD-115


Qnty. = 2x2.60m. = 5.20 R.Mtr.

Quantity for 2 Nos

5.20 R.Mtr
10.400 RM

8 Rough stone dry pitching in approns & revetments.


Revetment.

x 3.029

+ 0.75

U/S & D/S

x 10.535 + 2.00

x 4.50

x 0.30

10.200 cum

x 4.267

x 0.15

8.020 cum

23.700 cum

2
2
Flexible appron
U/S

x 10.535 x 3.00

x 0.75

D/S

x 10.535 x 6.00

x 0.75

Quantity for 2 Nos

47.410 cum

89.330 cum
178.660 cum

9 Providing 75mm thick RCC M-30 grade concrete


for wearing coat
1

x 10.900 x 2.60

x 0.075

Quantity for 2 Nos

2.130 cum

4.260 cum

#REF!

#REF!

2 Nos.
4.000 nos

#REF!

#REF!

32 Nos.
64.000 nos

#REF!

#REF!

10.40
5.20
15.60
31.200

#REF!

#REF!

#REF!

#REF!

10 Providing drain spout. 100mm dia.


1

x 2

Quantity for 2 Nos


11 Providing Weep holes 100mm dia PVC pipe.
4

x 8

Quantity for 2 Nos


12 Painting concrete surface Providing and applying 2
coats of water based cement paint to unplastered
concrete surface over a coat of cement wash after
cleaning the surface of dirt dust, oil grease
efflorescence and applying paint @ 1 Ltr for 2 sqm

Railing

x 2.60

Kerbs

x 2.60

=
=

Quantity for 2 Nos

sqm
sqm
sqm
sqm

13 Metal Spall backing in the rear of well steining or


weep holes of abutment and deep drains including
cost of all materials etc complete
Back of wing wall

x 5.317

x 0.60

x 1.676

+ 1.35

19.31 cum

2
Quantity for 2 Nos

38.620 cum

#REF!

Constn. Of 5 Rows 1000mm dia HPC for Diversion road.


1 Earth work in excavation of foundation in hard soil within initial lead and lifts
with rough dressing and breaking clods to maximum 5cm to 7cm and laying in
layers not exceeding 0.3m in depth including all labour, T&P etc. complete as
per direction of the Engineer-in-charge.
For Head Wall
Bed of Pipe

1 x
1 x

2 x
1 x

13.07
10.45

x
x

1.40
8.40

x
x

2.00
1.275

=
=
=

73.19 cum
111.92 cum
185.11 cum

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

2 Cement concrete (1:3:6) with 25mm size hard granite metal including
cost,conveyance, royalty of all materials, labour, T&P articles required for the
work etc. complete.
For Head Wall
1 x
Bed of Pipe
1 x
Deduct Pipe
1 x 5 x 10.45 x

2 x
1 x

13.07
10.45

x
x

1.40
x
0.15
=
8.40
x
0.375
=
2
0.49 2
4 x 0.30 x
1.4
+ 2 x
0.300
0
3
20.9
1 ### 0.725
5
0.4
=
3 R.R.stone masonry with cement mortar(1:3) with watering, curing including
cost,conveyance, royalty of all materials, labour, T&P etc. complete as per
direction of the Engineer-in-charge.
For Head Wall

1 x

2 x

13.07

1.25

Parapet
Deduct Pipe

1 x

2 x

13.07

0.40

22
28

x 1.200

1 x 5 x 2 x

2
1

1.024 +
0.786

+
2
x

0.40 x
0.825
0.50

0.698
2 0.861

2.45

5.49 cum
32.92 cum
-15.16 cum
23.25 cum

52.835 cum

5.228 cum

-9.745 cum

48.318 cum

#REF!

4 Laying R.C.C pipe NP4 /Prestressed Concrete pipe for culverts on first class
bedding of granular material in single row including fixing collar with Cement
mortar(1:2) but excluding excavation, protection work back filling concrete and
masonry works in head walls and parapets.
1 x 5 x 2.50 x 5.00
=
62.500 mtr
Filling
foundation
with
sand
well
watered
and rammed including cost of all
5
materials, royalty and taxes, labour, T&P etc. complete.

#REF!

Bed
1 x
8.40 x 10.45 +
11.28 x
0.90
Deduct Pipe
2 10.865
1x 5x {22/28 x (1.2)2- 4/3 x 0.30 x (1.04)2 - 2/5 x (0.3)2 }x (10.45+11.28)

82.139 cum

-50.94 cum

Over Pipe
1 x
11.28 x
8.40 x
0.30
Foundation
2 x
13.07 x 0.075 +
0.301 x 0.575
Deduct Pipe
2 0.188
6 20mm thick cement plaster in cement mortar(1:3) over stone work, watering
&curing with cost ofall materials, labour,T&P articles required for the work
etc.complete as per direction of Engineer-in-charge.

=
=
=

28.426 cum
2.826 cum
62.451 cum

#REF!

#REF!

=
=
=
=
=

47.052
36.596
0.800
-11.314
73.134

sqm
sqm
sqm
sqm
sqm

#REF!

#REF!

73.134 sqm

#REF!

#REF!

#REF!

Head wall
Parapet

1 x
1 x
1 x

13.07 x
1.80
13.07 x
1.40
2x
0.40 x
0.50
2
Deduct Pipe
22
1 x 5 x 2 x
x
1.200
28
1
7 Painting concrete surface Providing and applying 2 coats of water based
cement paint to unplastered concrete surface after cleaning the surface of dirt
dust, oil grease efflorescence and applying paint @ 1 Ltr for 2 sqm
Area of Plastered surface

2 x
2 x
2 x

Construction of H.L. Bridge over River Ret (Span 4 x 35 Mtr) at 4th Km on


Dadapur Rupra Road (ODR) in the district of Kalahandi under RIDF-XVIII.
ANALYSIS OF RATE (with current SR-2012 & enhanced labour rate)
Sl. No

Description

Scarifying the existing bituminous road surface to a


depth of 50 mm and disposal of scarified material
with in all lifts and lead upto 1000 metres as per
Clause 501.8.3.2 of MoSRT&H Specifications for
Road & Bridge works (4th Revision).

Unit

Qnty

Rate

Amount

Unit = Sqm
Taking output = 100 Sqm
a)

b)

c)
d)

Labour
Mate

Each

0.01

170.00

1.70

Mulia unskilled

Each

0.25

150.00

37.50

Tractor with ripper attachment


@ 60 cum per hour

Hour

0.08

#REF!

#REF!

Front end loader 1 cum bucket capacity

Hour

0.20

#REF!

#REF!

Tipper 5.5 cum capacity,


4 trips per hour.

Hour

0.23

#REF!

#REF!

Machinery

Overhead charges @ 7.5% on (a+b)


Contractor's Profit @ 7.5% on (a+b)

7.5%
7.5%

#REF!
#REF!

Cost for 100 Sqm = a+b+c

#REF!

Rate per Sqm = (a+b+c)/100

#REF!

Add Labour Welfare Cess @ 1%


Or Say
2

#REF!
#REF!

Reworking the scarified bituminous surface suitably


after supplementing the base materials with sand
and compacting finished surface as per Clause
501.8.3.2 of MoSRT&H Specifications for Road &
Bridge works (4th Revision).
Unit = Sqm
Taking output = 100 Sqm
a) Labour
Man Mulia considering 0.30nos per 93sqm of 6mm
thick {(0.3x50x100x0.30)/(6x93)}

Each

0.81

150.00

121.50

b) Materials
Sand (100sqm x 0.05mx0.30 = 1.50cum)

Cum

1.50

#REF!

#REF!

KL

0.09

#REF!

#REF!

Hire and running charges of PRR for 1.50cum,


considering output of PRR as 30cum in 1 hour

Hour

0.05

#REF!

#REF!

Water tanker for 0.09KL considering 6KL in 1hour

Hour

0.015

#REF!

#REF!

Cost of water for 1.50cum considering 6KL for


100cum
c) Machineries

#REF!
Overhead charges @ 7.5% on (a+b+c)

7.5%

#REF!

Contractor's Profit @ 7.5% on (a+b+c)

7.5%

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

e) carriage and Royalty of materials


Sand (100sqm x 0.05mx0.30 = 1.50cum)

Cum

1.50

#REF!

Cost per 100 Sqm = a+b+c+d+e

#REF!

Rate per Sqm = (a+b+c+d+e)/100

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
3

#REF!
#REF!

Clearing and grubbing road land including uprooting


rank vegetation, bushes, shrubs, saplings and trees
girth up to 300 mm as per Clause 201 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision).
Unit = Sqm
Taking output = 1 Hectare
In area of light jungle
a)

b)

Labour
Mate

Each

6.00

170.00

1020.00

Mulia unskilled

Each

150.00

150.00

22500.00

Hour

1.00

#REF!

Machinery
Tractor-trolley

#REF!
#REF!

Overhead charges @ 7.5% on (a+b+c)


Contractor's Profit @ 7.5% on (a+b+c)

7.5%
7.5%

#REF!
#REF!

Rate per Hectare = a+b+c

#REF!

Rate per Sqm = (a+b+c)/10000

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
4

Earth work in excavation in hard soil or gravelly soil


as per Clause 301 & 304 of
MoSRT&H
Specifications for Road & Bridge works (4th
Revision).
Unit = Cum
Taking output = 100 Cum
a)

Labour
Man Mulia unskilled

Each

21.50

150.00

3225.00

Woman Mulia unskilled

Each

21.50

150.00

3225.00

(A)

6450.00

Overhead charges @ 7.5% on (a+b+c)

7.5%

483.75

Contractor's Profit @ 7.5% on (a+b+c)


Cost per 100 Cum = a+b+c+d

7.5%

483.75
7417.50
74.18

Rate per Cum = (a+b+c+d)/100


d)

Add 20% for ecavation of foundation

0.20

74.18

Add Labour Welfare Cess @ 1%


Or Say

14.84
89.02
0.89
89.90

Sl. No

Description

Loosening, leveling and Compacting original ground


supporting embankment
as per Clause 305 of
MoSRT&H Specifications for Road & Bridge works
(4th Revision)

Unit

Qnty

Rate

Amount

Unit = Cum
Taking output = 600 Cum

a)

Labour
Mate

Each

0.08

170.00

13.60

Mulia unskilled

Each

2.00

150.00

300.00
313.60

b)

Machinery
Tractor with ripper attachment

Hour

6.00

249.00

1494.00

Vibratory road roller 8-10 tonne capacity

Hour

7.50

994.00

7455.00

Water tanker 6 KL capacity

Hour

4.00

#REF!

#REF!
#REF!

c)

Material
Cost of water

KL

24.00

#REF!

#REF!
#REF!

Overhead charges @ 7.5% on (a+b+c)


Contractor's Profit @ 7.5% on (a+b+c)

7.5%
7.5%

#REF!
#REF!

Cost for 600 Cum = (a+b+c+d)

#REF!

Rate per Cum = (a+b+c+d) / 600

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
6

Turfing the slope of the embankment slope with


compact turf grass as per Clause 307 of MoSRT & H
Specifications for Road & Bridge works (4th
Revision).
Unit = Sqm
Taking output = 100 Sqm
a)

Labour
Man Mulia unskilled

Each

Overhead charges @ 7.5% on (a+b+c)


Contractor's Profit @ 7.5% on (a+b+c)
d)
Conveyance of turf 6cm thick (mechanical
means of 5 km)

2.54

150.00

7.5%
Cum

7.5%
6.00

381.00
28.58

#REF!

28.58
#REF!

Cost per 100 Sqm = a+b+c

#REF!

Rate per Sqm = (a+b+c)/100

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say

Sl. No

Description

Construction of embankment with approved material


obtained from borrow pits by mechanical means
within a lead of 5kms as per Clause 305 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision)

Unit

Qnty

Rate

Amount

Unit = Cum
Taking output = 100 Cum
a)

Labour
Mate

Each

0.04

170.00

Mulia unskilled

Each

1.00

150.00

6.80
150.00
156.80

b)

Machinery
Hydraulic Excavator1 cum bucket capacity
Tipper (160 X L =5) = 800

Hour
Tonne.k
m

10% of carriage to cover cost of loading and


unloading

1.67

#REF!

#REF!

800.00

#REF!

#REF!

0.10

#REF!

#REF!

Dozer 80 HP for spreading @ 200 cum per hour

Hour

0.50

#REF!

#REF!

Motor grader for grading @ 100 cum per hour

Hour

1.00

#REF!

#REF!

Water tanker 6 KL capacity

Hour

4.00

#REF!

#REF!

Vibratory roller 8 -10 tonnes@100cum per hour

Hour

1.00

#REF!

#REF!
#REF!

c)

Material
Cost of water

KL

24.00

#REF!

#REF!
#REF!

Total cost a+b+c

#REF!

Overhead charges @ 7.5% on (a+b+c)


Contractor's Profit @ 7.5% on (a+b+c)
Cost for 100 Cum = a+b+c+d

7.5%
7.5%

#REF!
#REF!
#REF!

Rate per Cum = (a+b+c+d)/100


Add royalty

#REF!
cum

1.000

27.44

27.44
#REF!

Add Labour Welfare Cess @ 1%


Or Say
8

#REF!
#REF!

Construction of embankment with hard soil of


approved material obtained from excavated earth by
mechanical means as per Clause 305 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision)
Unit = Cum
Taking output = 100 Cum
a)

Labour
Mate

Each

0.02

170.00

Mazdoor

Each

0.50

150.00

3.40
75.00
78.40

Description

Unit

Drozer 80 HP for spreading @200 cum per hr

Hour

0.500

#REF!

#REF!

Motor Grader for grading @100 cum per hr

Hour

1.000

#REF!

#REF!

Water tanker 6 KL capacity

Hour

4.00

#REF!

#REF!

Vibratory roller 8 -10 tonnes @ 100 cum per


hour

Hour

1.00

#REF!

#REF!

Sl. No

b)

Qnty

Rate

Amount

Machinery

#REF!
c)

Material
Cost of water

KL

24.00

#REF!

#REF!
#REF!

Total cost a+b+c

#REF!

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%

7.5%
7.5%

#REF!
#REF!

Cost for 100 Cum = a+b+c+d

#REF!

Rate per Cum = (a+b+c+d)/100

#REF!

Add Labour Welfare Cess @ 1%


Or Say
9

#REF!
#REF!

Excavation in soil using Hydraulic Excavator CK 90


and Tippers with Disposal upto 1000 mtr.
Excavation for road work in soil with hydraulic
excavator of 0.9 cum bucket capacity including
cutting and loading I tippers, trimming bottom and
side slopes in accordance with requirements of lines,
grades and cross sections.
Unit = Cum
Taking output = 360 Cum
a)

Labour
Mate

day

0.08

170.00

Mazdoor

day

2.00

150.00

13.60
300.00
313.60

b)

Machinery
Hydraulic excavator 0.9 cum bucket capacity
@60 cum per hour

Hour

6.00

#REF!

Tipper 5.5 cum capacity, 4 trips per hour

Hour

16.00

#REF!

#REF!
#REF!
#REF!
#REF!

Overhead charges @ 7.5% on (a+b+c)

7.5%

#REF!

Contractor's Profit @ 7.5% on (a+b+c)


Cost for 360 Cum = a+b+c

7.5%

#REF!
#REF!

Rate per Cum = (a+b+c)/360

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say

Sl. No

Description

11

Providing and laying sand in sub-base, watering and


compacting with VRR as per Clause 401 of
MoSRT&H Specifications for Road & Bridge works
(4th Revision).

Unit

Qnty

Rate

Amount

Unit = Cum
Taking output = 100 Cum
a)
b)

c)

Labour
Man Mulia

Each

12.36

150.00

1854.00

Vibratory roller 8-10 tonne capacity

Hour

1.00

#REF!

#REF!

Water tanker 6KL capacity

Hour

1.00

#REF!

#REF!

cum

120.00

#REF!

#REF!

6.00

#REF!

#REF!

Machinery

Material
Sand
Cost of water

KL

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
e)
Carriage and Royalty of materials
Sand

7.5%
7.5%
cum

120.00

#REF!
#REF!
#REF!

Cost per 100 Cum = a+b+c+d+e

#REF!
#REF!

Rate per Cum = (a+b+c+d+e)/100

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
12

Providing and laying moorum in shoulders and


compacting with PRR as per Clause 407 of
MoSRT&H Specifications for Road & Bridge works
(4th Revision)
Unit = Cum
Taking output = 2.83 Cum
a)

b)

Labour
Man Mulia unskilled

Each

1.00

150.00

150.00

Mulia unskilled

Each

1.50

150.00

225.00

Hour

0.05327

#REF!

#REF!

Machinery
Hire & Running charges of PRR

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Cost per 2.83 Cum = a+b+c+d

7.5%

#REF!
#REF!

Rate per Cum = (a+b+c+d)/2.83


Cost, carriage & royalty of moorum

#REF!
Cum

1.28

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
13a

Construction of granular sub-base by providing


Coarse graded Grading-II material with motor
grader on prepared surface, mixing by mix in place
method as per Clause 401 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision)

#REF!
#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Unit = Cum
Taking output = 300 Cum
a)

b)

c)

Labour
Mate

Each

0.48

170.00

81.60

Mulia skilled

Each

2.00

190.00

380.00

Mulia unskilled

Each

8.00

150.00

1200.00

Motor Grader 110 HP @ 50 cum per hour

Hour

6.00

#REF!

#REF!

Vibratory roller 8 -10 tonne capacity

Hour

6.00

#REF!

#REF!

Tractor - Rotavator

Hour

12.00

#REF!

#REF!

Water tanker 6 KL capacity

Hour

3.00

#REF!

#REF!

26.5mm to 4.75mm 75%

Cum

288.00

#REF!

#REF!

2.36mm bellow 25%

Cum

96.00

#REF!

#REF!

KL

18.00

#REF!

#REF!

Machinery

Material

Cost of water
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%

7.5%
7.5%

#REF!
#REF!

e) Carriage & Royalty


26.5mm to 4.75mm 75%

Cum

288.00

#REF!

#REF!

2.36mm bellow 25%

Cum

96.00

#REF!

#REF!

Cost for 300 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/300

#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

0.48

170.00

81.60

13 b Construction of granular sub-base by providing Close


graded Grading-II material as per Clause 401 of
MoSRT&H Specif. for Road & Bridge works (4th
Revision)
Unit = Cum
Taking output = 300 Cum
a)

b)

c)

Labour
Mate

Each

Mulia skilled

Each

2.00

190.00

380.00

Mulia unskilled

Each

10.00

150.00

1500.00

Motor Grader 110 HP @ 50 cum per hour

Hour

6.00

#REF!

#REF!

Vibratory roller 8 -10 tonne capacity

Hour

6.00

#REF!

#REF!

Tractor - Rotavator

Hour

12.00

#REF!

#REF!

Water tanker 6 KL capacity

Hour

3.00

#REF!

#REF!

26.5 mm to 9.5 mm @ 35 per cent

Cum

134.40

#REF!

#REF!

9.5 mm to 2.36 mm @ 25 per cent

Cum

96.00

#REF!

#REF!

2.36 mm below @ 40% (Dust)

Cum

153.60

#REF!

#REF!

KL

18.00

#REF!

#REF!

Machinery

Material

Cost of water
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%

7.5%

#REF!

Description

Sl. No

e)

Unit

Qnty

Rate

Royalty
26.5 mm to 9.5 mm @ 35 per cent

Cum

134.40

#REF!

#REF!

9.5 mm to 2.36 mm @ 25 per cent

Cum

96.00

#REF!

#REF!

2.36 mm below @ 40% (Dust)

Cum

153.60

#REF!

#REF!

Cost for 300 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/300

#REF!

Add Labour Welfare Cess @ 1%


Or Say
14

Amount

#REF!
#REF!

Providing, laying, spreading and compacting graded


stone aggregate to WMM specification as per Clause
406 of MoSRT&H Specifications for Road & Bridge
works (4th Revision)
Unit = Cum
Taking output = 225 Cum (495 tonnes)
a)

b)

Labour
Mate

Each

0.48

170.00

81.60

Mulia skilled

Each

2.00

190.00

380.00

Mulia unskilled

Each

10.00

150.00

1500.00

Wet mix plant of 75 tonne hourly capacity

Hour

6.60

#REF!

#REF!

Electric generating set 125 KVA

Hour

6.00

#REF!

#REF!

Front end loader 1 cum capacity

Hour

6.00

#REF!

#REF!

Paver finisher Mechanical 100TPH

Hour

6.00

#REF!

#REF!

Vibratory roller 8 - 10 tonne (6.00 x 0.65*)

Hour

3.90

#REF!

#REF!

Water tanker 6 KL capacity

Hour

3.00

#REF!

#REF!

Tipper (495 X L =21) =2475

Tonne.k
m

Machinery

495.00

#REF!

Add 10% carriage to cover cost of loading &


unloading
c)

#REF!
#REF!

Material ( Table 400-11)


45 mm to 22.4 mm@ 30 per cent (26.5mm)

Cum

89.10

#REF!

#REF!

22.4 mm to 2.36 mm @ 40 per cent


(13.2mm+6.7mm)/2

Cum

118.80

#REF!

#REF!

2.36 mm to 75 micron@ 30 per cent

Cum

89.10

#REF!

#REF!

KL

18.00

#REF!

#REF!

Cost of water
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e)
Carriage and Royalty

7.5%

#REF!

45 mm to 22.4 mm@ 30 per cent

Cum

89.10

#REF!

#REF!

22.4 mm to 2.36 mm @ 40 per cent

Cum

118.80

#REF!

#REF!

2.36 mm to 75 micron@ 30 per cent

Cum

89.10

#REF!

#REF!

Cost for 225 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/225

#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Dry Lean Cement Concrete Sub- base


Construction of dry lean cement concrete Sub- base
over a prepared sub-grade with coarse and fine
aggregate conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm, aggregate cement
ratio not to exceed 15:1, aggregate gradation after
blending to be as per table 600-1, cement content
not to be less than 150 kg/ cum, optimum moisture
content to be determined during trial length
construction, concrete strength not to be less than
10 Mpa at 7 days, mixed in a batching plant,
transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller,
finishing and curing. vide ARP 188 item no.55 Data
for 450cum

Unit = cum
Taking output = 450 cum (990 tonne)
a)

Labour

Mate

day

1.120

170.00

190.40

Mazdoor skilled
Mazdoor
b)
Machinery

day
day

6.000
22.000

190.00
150.00

1140.00
3300.00

Front end loader 1 cum bucket capacity


Cement concrete batch mix plant @ 75 cum per hour

hour
hour

6.000
6.000

#REF!
#REF!

#REF!
#REF!

Electric generator 100 KVA


Paver with electronic sensor

hour
hour

6.000
6.000

#REF!
#REF!

#REF!
#REF!

Vibratory roller 8-10 t capacity


Water tanker6 KL capacity

hour
hour

8.000
8.000

#REF!
#REF!

#REF!
#REF!

Tipper
tonne.km
Add 10 per cent of cost of carriage to cover cost
of loading and unloading

990 x L

c)

#REF!

#REF!
#REF!

Material

Crushed stone coarse aggregate of 25 mm and 12.5


mm nominal sizes graded as per table 600-1 @ 0.90
cum/cum of concrete conforming to clause 602.2.4.

cum

405.000

#REF!

#REF!

Coarse Sand as per IS: 383 @ 0.45 cum/cum of


concrete

cum

203.000

#REF!

#REF!

tonne

67.500

#REF!

#REF!

KL

48.000

10.00

Cement @ 150 kg/cum of concrete


Cost of water
Overhead charges @ 7.5%

7.5%

480.00
#REF!
#REF!

Contractor's Profit @ 7.5%


e)
Carriage and Royalty

7.5%

#REF!

25 mm to 12.5 mm size CBHG chips

Cum

405.00

#REF!

#REF!

Coarse Sand as per IS: 383 @ 0.45 cum/cum of


concrete

Cum

203.00

#REF!

#REF!

Cement

MT

67.50

#REF!

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Cost for 450 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/450

#REF!
#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

Cement Concrete Pavement


Construction of un-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base
with 43 grade cement @ 400 kg per cum, coarse and
fine aggregate conforming to IS 383, maximum size
of coarse aggregate not exceeding 25 mm, mixed in a
batching and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip
form paver, spread, compacted and finished in a
continuous
operation
including
provision
of
contraction, expansion, construction and longitudinal
joints, joint filler, separation membrane, sealant
primer, joint sealant, debonding strip, dowel bar, tie
rod, admixtures as approved, curing compound,
finishing to lines and grades as per drawing as per
ARP 190 item no.56

Unit = cum
Taking output = 1050 cum (2415 tonne)
a)

Labour

Mate

day

2.000

170.00

340.00

Mazdoor skilled
Mazdoor

day
day

15.000
35.000

190.00
150.00

2850.00
5250.00

Road Sweeper @ 1250 sqm per hour


Front end loader 1 cum bucket capacity

hour
hour

2.800
18.000

230.00
#REF!

644.00
#REF!

Cement concrete batch mix plant @ 175 cum per


hour (effective output)

hour

6.000

#REF!

#REF!

Electric generator 250 KVA


Slip form paver with electronic sensor

hour
hour

6.000
6.000

#REF!
16188.00

#REF!
97128.00

Water tanker6 KL capacity


Transit truck agitator 5 cum capacity.

hour
tonne.km

36.000
2415 x L

#REF!
#REF!

#REF!
#REF!

b)

Machinery

Add 10 per cent of cost of carriage to cover cost


of loading and unloading
Concrete joint cutting machine .
Texturing machine .

#REF!
hour
hour

12.000
12.000

300.00
250.00

Crushed stone coarse aggregates of 25mm and


12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .

cum

945.000

#REF!

#REF!

Sand as per IS: 383 and conforming to clause


602.2.4 @ 0.45 cum/cum of concrete

cum

473.000

#REF!

#REF!

Cement 43 grade @ 400 kg/cum of concrete

tonne

414.000

#REF!

#REF!

32 mm mild steel dowel bars of grade S 240

tonne

9.450

#REF!

#REF!

c)

3600.00
3000.00

Material

Description

Sl. No

16 mm deformed steel tie bars of grade S 415


Separation Membrane of impermeable plastic
sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.

Unit

Qnty

tonne
1.170
sqm 3675.000

Rate

Amount

#REF!
3.00

sqm

16.330

1200.00

19596.00

kg
kg

875.000
116.670

50.00
30.00

43750.00
3500.10

sqm
46.670
liter 1850.000

200.00
42.00

9334.00
77700.00

Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement

kg 2070.000

40.00

82800.00

Cost of water

KL

10.00

2160.00

Joint sealant
Sealant primer
Plastic sheath,1.25 mm thick for dowel bars
Curing compound

216.000

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap,
cotton / compressible sponge and cradle for dowel
bars, work bridges for men to approach concrete
surface without walking over it, cutting blades and
bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen
items.

#REF!

Cost for 1050cum = a+b+c+d+e

#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e)
Carriage and Royalty

7.5%

#REF!

Crushed stone coarse aggregates of 25mm and


12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .

cum

945.000

#REF!

#REF!

Sand as per IS: 383 and conforming to clause


602.2.4 @ 0.45 cum/cum of concrete

cum

473.000

#REF!

#REF!

Cement 43 grade @ 400 kg/cum of concrete

tonne

414.000

#REF!

#REF!

32 mm mild steel dowel bars of grade S 240


16 mm deformed steel tie bars of grade S 415
Grand Total for 1050cum

tonne
tonne

9.450
1.170

#REF!
#REF!

#REF!
#REF!
#REF!

Rate per cum = (a+b+c+d+e)/1050

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say
15

#REF!
11025.00

#REF!

Providing and applying tack coat with bitumen @


0.20 kg per sqm as per Clause 503 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision)
Unit = Sqm
Taking output = 3500 Sqm
a)

b)

Labour
Mate

Each

0.08

170.00

13.60

Mulia unskilled

Each

2.00

150.00

300.00

Mechanical broom @ 1250 sqm per hour

Hour

2.80

#REF!

#REF!

Air compressor 250 cfm

Hour

2.80

#REF!

#REF!

Bitumen pressure distributor @ 1750 sqm/hour

Hour

2.00

#REF!

#REF!

Machinery

Description

Sl. No

c)

Unit

Qnty

Rate

Material
Bitumen @ 0.2 kg/sqm

Tonne

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
e)

0.70

#REF!

7.5%
7.5%

#REF!
#REF!
#REF!

Carriage & Royalty


Bitumen @ 0.2 kg/sqm

Tonne

0.70

#REF!

#REF!

Cost for 3500 Sqm = a+b+c+d+e

#REF!

Rate per Sqm = (a+b+c+d+e)/3500

#REF!

Add Labour Welfare Cess @ 1%


Or Say
16

Amount

#REF!
#REF!

Providing and laying surface dressing using crushed


stone aggregates of 13mm nominal size stone
chipping and 60/70 penetration grade of bitumen as
per Clause 510 of MoSRT&H Specifications for Road
& Bridge works (4th Revision)
Unit = Sqm
Taking output = 9000 Sqm
a)

b)

c)

Labour
Mate

Each

0.44

170.00

74.80

Mulia unskilled

Each

9.00

150.00

1350.00

Mulia skilled

Each

2.00

190.00

380.00

Mechanical broom @ 1250 sqm per hour

Hour

7.20

#REF!

#REF!

Machinery
Air compressor 250 cfm

Hour

7.20

#REF!

#REF!

Hydraulic self propelled chip spreader


@ 1500 sqm per hour

Hour

6.00

#REF!

#REF!

Tipper 10 tonne capacity for carriage of stone


chips from stockpile on road side to chip
spreader

Hour

6.00

#REF!

#REF!

Front end loader 1 cum bucket capacity

Hour

6.00

#REF!

#REF!

Bitumen pressure distributor

Hour

6.00

#REF!

#REF!

Smooth wheeled roller 8-10 tonne weight

Hour

6.00

#REF!

#REF!

60/70 penetration grade of bulk Bitumen


@ 1.00 kg per sqm

Tonne

9.00

#REF!

#REF!

Crushed stone chipping,13 mm nominal size


@ 0.01 cum per sqm

Cum

90.00

#REF!

#REF!

Material:13 mm nominal size chipping

#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%
e)

7.5%
7.5%

#REF!
#REF!

Carriage & Royalty


60/70 penetration grade of bulk Bitumen

Tonne

Crushed stone chipping,13 mm nominal size

Cum

9.00

#REF!

#REF!

90.00

#REF!

#REF!
#REF!

Cost for 9000 Sqm = a+b+c+d+e

#REF!

Description

Sl. No

Unit

Qnty

Rate

Rate per Sqm = (a+b+c+d+e)/9000

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
17

Amount

Providing and laying bituminous macadam with hot


mix plant using crushed aggregates of Grading-II
and 60/70 penetration grade of bitumen as per
Clause 504 of MoSRT&H Specifications for Road &
Bridge works (4th Revision)
Unit = Cum
Taking output = 205 Cum (450 tonnes)
a)

Labour
Mate

Each

0.76

170.00

129.20

Mulia unskilled

Each

14.00

150.00

2100.00

Mulia Skilled

Each

5.00

190.00

950.00
3179.20

b)

Machinery
Batch mix HMP 60-90TPH @ 75 tonne per hour

Hour

6.00

#REF!

#REF!

Paver finisher hydrostatic with sensor control

Hour

6.00

#REF!

#REF!

Generator 250 KVA

Hour

6.00

#REF!

#REF!

Front end loader 1 cum bucket capacity

Hour

6.00

#REF!

#REF!

Tipper 10 tonne capacity (450 X L=21) =

Tonne.k
m

450.00

#REF!

Add 10% carriage to cover cost of loading and


unloading

#REF!
#REF!

Smooth wheeled roller 8-10 tonnes

Hour

3.90

#REF!

#REF!

Vibratory roller 8 tonnes

Hour

3.90

#REF!

#REF!

6-8 tonnes smooth wheeled tandem roller

Hour

3.90

#REF!

#REF!
#REF!

c)

Material:Grading II (19 mm nominal size)


60/70 penetration grade of Bitumen

Tonne

14.85

#REF!

#REF!

25 - 10 mm @ 40 per cent

Cum

116.04

#REF!

#REF!

10 - 5 mm @ 40 per cent

Cum

116.04

#REF!

#REF!

5 mm and below @ 20 per cent

Cum

58.02

#REF!

#REF!
#REF!
#REF!

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
e)

7.5%
7.5%

#REF!
#REF!

Carriage & Royalty


60/70 penetration grade of Bitumen

Tonne

14.85

#REF!

#REF!

25 - 10 mm @ 40 per cent

Cum

116.04

#REF!

#REF!

10 - 5 mm @ 40 per cent

Cum

116.04

#REF!

#REF!

5 mm and below @ 20 per cent

Cum

58.02

#REF!

#REF!
#REF!

Cost for 205 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/205

#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Sl. No

Description

18

Providing and laying SDBC using crushed aggregates


of Grading-II and 60/70 penetration grade of
bitumen as per
Clause 508 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision)

Unit

Qnty

Rate

Amount

Unit = Cum
Taking output = 195 Cum (450 tonnes)
a)

Labour
Mate

Each

0.76

170.00

129.20

Mulia unskilled

Each

14.00

150.00

2100.00

Mulia Skilled

Each

5.00

190.00

950.00
3179.20

b)

Machinery
Batch mix HMP 60-90TPH @ 75 tonne per hour

Hour

6.00

#REF!

#REF!

Paver finisher hydrostatic with sensor control

Hour

6.00

#REF!

#REF!

Generator 250 KVA

Hour

6.00

#REF!

#REF!

Front end loader 1 cum bucket capacity

Hour

6.00

#REF!

#REF!

Tipper 10 tonne capacity (450 X L=21)

Tonne.k
m

450.00

#REF!

Add 10% carriage to cover cost of loading and


unloading

#REF!
#REF!

Smooth wheeled roller 8-10 tonnes

Hour

3.90

#REF!

#REF!

Vibratory roller 8 tonnes

Hour

3.90

#REF!

#REF!

6-8 tonnes smooth wheeled tandem roller

Hour

3.90

#REF!

#REF!
#REF!

c)

Material:Grading II: 10 mm (Nominal Size)


60/70 penetration grade of Bitumen

Tonne

22.50

#REF!

#REF!

9.5 - 4.75 mm @ 57 per cent (10mm+4.7mm)

Cum

162.45

#REF!

4.75 and below @ 41 per cent (4.75mm+dust)

Cum

116.85

372.00

43468.20

Filler @ 2 per cent of weight of aggregates.

Cum

5.70

88.00

501.60

#REF!

#REF!
#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%
e)

7.5%
7.5%

#REF!
#REF!

Carriage & Royalty


60/70 penetration grade of Bitumen

Tonne

22.50

#REF!

9.5 - 4.75 mm @ 57 per cent

Cum

162.45

#REF!

4.75 and below @ 41 per cent

Cum

116.85

199.11

Filler @ 2 per cent of weight of aggregates.

Cum

5.70

#REF!

#REF!
#REF!
23266.00
#REF!
#REF!

Cost for 195 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/195

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say

Description

Sl. No

Unit

Qnty

Rate

Amount

Reinforced Cement Concrete Crash Barrier


Provision of an Reinforced cement concrete crash
barrier at the edges of the road, approaches to
bridge structures and medians, constructed with M20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450
mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which
it is built and installed as per design given in the
enclosure to MOST circular No. RW/NH 33022/1/94-DO III dated 24 June 1994 as per
dimensions in the approved drawing and at locations
directed by the Engineer, all as specified

Unit = Linear metre


Taking output = 10 m
(i)

a)

M 20 grade concrete
cum

3.000

#REF!

#REF!

tonne

0.280

#REF!

#REF!

sqm

0.320

1200.00

384.00

Mate

day

0.040

170.00

6.80

Mazdoor

day

1.000

150.00

150.00

M 20 grade concrete
c)

Material

HYSD steel reinforcement including dowel bars


Pre-moulded asphalt filler board
b)

Labour

Overhead charges @ 7.5%

7.5%

40.56

Contractor's Profit @ 7.5%

7.5%

40.56

Cost for 10 metre = a+b+c+d+e

#REF!

Rate per metre = (a+b+c+d+e)/10

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say
Note

i) Excavation and backfilling are incidental to work


and not to be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on
super structure.
Metal Beam Crash Barrier

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Type - A, "W" : Metal Beam Crash Barrier


Providing and erecting a "W" metal beam crash
barrier comprising of 3 mm thick corrugated sheet
metal beam rail, 70 cm above road/ground level,
fixed on ISMC series channel vertical post, 150 x 75
x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m
below ground/road level, all steel parts and fitments
to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of
channel section 150 x 75 x 5 mm, 330 mm long
complete as per clause 810

Unit = Running metre


Taking output = 4.5 metre length
a)

Labour

Mate

day

0.060

170.00

10.20

Blacksmith

day

0.500

129.00

64.50

Mazdoor

day

1.000

150.00

150.00

hour

0.100

#REF!

#REF!

Corrugated sheet,3 mm thick, "W" beam section


railing,4.5 m in length

kg

41.210

Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @


16.4 kg per metre

kg

88.560

Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @


16.4 kg per metre

kg

16.240

Nuts and bolts

kg

20.000

b)

Machinery

Tractor-trolley
c)

Material
85.00

3502.85

72.00

6376.32

72.00

1169.28

70.00

1400.00

Add 25 per cent of the cost of material for


fabrication, nuts, bolts and washers etc.)
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%

3112.11
7.5%
7.5%

#REF!
#REF!

Cost for 4.5 metre = a+b+c+d+e

#REF!

Rate per metre = (a+b+c+d+e)/4.5

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Type - B, "THRIE" : Metal Beam Crash Barrier


Providing and erecting a "Thrie" metal beam crash
barrier comprising of 3 mm thick corrugated sheet
metal beam rail, 85 cm above road/ground level,
fixed on ISMC series channel vertical post, 150 x 75
x 5 mm spaced 2 m centre to centre, 2 m high with
1.15 m below ground level, all steel parts and
fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal
beam rail to be fixed on the vertical post with a
space of channel section 150 x 75 x 5 mm, 546 mm
long complete as per clause 810

Unit = Running metre


Taking output = 4.5 metre length
a)

Labour

Mate

day

0.060

170.00

10.20

Blacksmith

day

0.500

205.00

102.50

Mazdoor

day

1.000

150.00

150.00

hour

0.100

#REF!

#REF!

85.00

6199.90

72.00

7084.80

72.00

1933.92

70.00

2100.00

b)

Machinery

Tractor-trolley
c)

Material

Corrugated sheet,3 mm thick, "Thrie" beam section


railing,4.5 m in length

kg

72.940

Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4


kg per metre

kg

98.400

Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos

kg

26.860

Nuts and bolts

kg

30.000

Add 15 per cent of the cost of material for


fabrication, nuts, bolts and washers etc.)
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%

2597.79
7.5%
7.5%

#REF!
#REF!

Cost for 4.5 metre = a+b+c+d+e

#REF!

Rate per metre= (a+b+c+d+e)/4.5

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say
19

Rigid and smooth centering and shuttering for R.C.C.


works including false works and dismantling them
after casting including cost of materials complete
Approach slab and wearing coat
Unit = Sqm
Taking Output = 10 Sqm

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

a) Materials
25mm thick non sal planks

Cum

0.267

#REF!

#REF!

Non-sal bullah 80mm dia for strutting

Mtr.

12.60

#REF!

#REF!

Cum

0.3284

#REF!

Carriage of wood
Total

#REF!
#REF!

Considering 10times use of the materials, for use


once
b) Labour

#REF!

Carpenter (second class)

Each

0.50

190.00

95.00

Semiskilled mulia

Each

0.50

170.00

85.00
180.00
#REF!

Overhead charges @ 7.5% (on a+b)


Contractor's Profit @ 7.5%
Cost per 10 sqm = a+b+c

7.5%
7.5%

#REF!
#REF!
#REF!

Rate for 1sqm =(a+b+c)/10=

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
20

Rigid and smooth Steel centering and shuttering at


all heights of bridge work such as well curb, well
steining, well cap, pier and abutment shaft, pier and
abutment cap, wing wall, tie beam, road kerb and dirt
wall using required nos of vertical and horizontal
supports of scaffolding with joists, N.G. rails and
channels and steel shutering plates including
welding, bolting,cost, conveyance , royalty and all
other taxes of all materials and cost of scaffolding
gangway etc. including cost of conveyance of
dismantling and disposing debris clear of work site
complete to receive reinforcement grills and
concrete as per requirement as directed by
Engineer-in-Charge
Unit = Sqm
a) Materials
Cost of Steel shuttering plate
1.524m x 0.914m = 1.393sqm
M.S Angle of size 50mm x 50mm x6mm
3 x 1.524m = 4.572m
5 x 0.914m = 4.570m
Total =

9.142m

Weight of Angle = 9.142m @ 4.5kg/mtr = 41.139kg


M.S Plate 4mm thick = 1.524m x 0.914m = 1.393sqm
Weight of
=43.740kg

Plate

1.393sqm

31.40kg/sqm

Total weight of 1 plate = 41.139kg + 43.740kg =


84.879kg

Kg

84.879

#REF!

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Cost of fabrication
Labour for fabrication
Cost of welding rod for fabrication

Kg
Packet

84.879

2.708

229.85

1.00

300.00

300.00
#REF!

#REF!

#REF!

#REF!

#REF!

Cost of nut and bolt


@2kg/sqm for 1sqm @ Rs.70.00/kg
ii) Considering 4times use of materials, rate of nut
and bolt for use once = 2 x Rs.70.00/4

35.00

Cost of sal bullah 150mm to 200mm dia up to 5.50m


long
#REF!

#REF!

#REF!

#REF!
#REF!

b) Labour
Data for 4.20sqm
Carpenter 2nd class

Each

2.75

190.00

522.50

Semiskilled mulia

Each

2.75

170.00

467.50
990.00

Rate per sqm =(b)/4.2

235.71

Total of a+b

#REF!

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
Rate per sqm = a+b+c

7.5%
7.5%

#REF!
#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
21

#REF!
#REF!

Supplying,
fitting
and
placing
HYSD
bar
reinforcement for R.C.C works complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a)

Material
HYSD bars including 5% for laps and wastage

MT

1.05

#REF!

#REF!

Binding wire

Kg

8.00

72.00

576.00
#REF!

Each

0.44

170.00

74.80

3.00

205.00

615.00

8.00

150.00

1200.00
1889.80

#REF!

#REF!

b) Labour for cutting, bending, tying and placing in


position
Mate
Blacksmith Special
Mulia unskilled

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%

Each
Each

7.5%
7.5%

#REF!
#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

d) Carriage
HYSD bars

MT

1.05

#REF!

Rate per MT = a+b+c+d

#REF!
#REF!

Rate per Quintal = (a+b+c+d)/10

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
22

Plain cement
foundation

concrete

(1:3:6)

nominal

mix

in

Unit = cum
Taking output = 1 cum
a)

Materials
40mm size H.G.C.B metal

Cum

0.96

#REF!

#REF!

Sand (screened & washed)

Cum

0.48

#REF!

#REF!

Cement

Qntl

2.29

#REF!

#REF!
#REF!

b)

Labour
Mason 2nd class

Each

0.18

190.00

34.20

Man Mulia

Each

2.50

150.00

375.00

Woman Mulia

Each

1.40

150.00

210.00
619.20
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


d)
Carriage & Royalty

7.5%

#REF!

Cum

0.96

#REF!

#REF!

Sand (screened & washed)

Cum

0.48

#REF!

#REF!

Cement

Qntl

2.29

#REF!

40mm size H.G.C.B metal

#REF!
#REF!

Rate per Cum = a+b+c+d

#REF!

Add Labour Welfare Cess @ 1%


Or Say

23

#REF!
#REF!

P.C.C Grade M15


Unit = Cum
Taking output = 15 Cum
a)

Material
Cement

MT

4.13

#REF!

#REF!

Coarse sand

Cum

6.75

#REF!

#REF!

40 mm Aggregate

Cum

8.10

#REF!

#REF!

20 mm Aggregate

Cum

4.05

#REF!

#REF!

10 mm Aggregate

Cum

1.35

#REF!

#REF!
#REF!

Description

Sl. No

b)

c)

Unit

Qnty

Rate

Amount

Labour
Mate

Each

0.86

170.00

146.20

Mason 2nd Class

Each

1.50

190.00

285.00

Mulia unskilled

Each

20.00

150.00

3000.00
3431.20

Concrete mixer (cap. 0.40/0.28 cum)

Hour

6.00

#REF!

#REF!

Generator 33 KVA

Hour

6.00

#REF!

#REF!
#REF!

Machinery

#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%
e)

7.5%
7.5%

#REF!
#REF!

Carriage & Royalty


Cement

MT

4.13

#REF!

#REF!

Coarse sand

Cum

6.75

#REF!

#REF!

40 mm Aggregate

Cum

8.10

#REF!

#REF!

4.05

#REF!

#REF!

1.35

#REF!

#REF!
#REF!

20 mm Aggregate
10 mm Aggregate

Cum
Cum

Cost for 15 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/15

#REF!

Add Labour Welfare Cess @ 1%


Or Say
A) With frame work
Rate as above

#REF!
#REF!
#REF!

Add frame work in substructure (S/R 2006 Item 11, Sqm


pg.12) 106.20

3.00

106.20

318.60
#REF!

Add Labour Welfare Cess @ 1%


Or Say
B)

Wing wall & Abutment, Abutment Cap, Dirt Wall


Parapet
Basic cost as above
Add for centreing & shuttering work

#REF!
Sqm

3.00

361.13

1083.39

Rate per cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

C)

#REF!
#REF!

#REF!

RCC Drain Wall


Basic cost as above
Add frame work in substructure (S/R 2006 Item 11,
pg.12) 106.20

#REF!
Sqm

8.00

106.20

849.60

Rate per cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

#REF!

Description

Sl. No

24

Unit

Qnty

Rate

Amount

R.C.C Grade M20


Unit = Cum
Taking output = 15 Cum
a)

Material
Cement

MT

5.21

#REF!

#REF!

Coarse sand

Cum

6.75

#REF!

#REF!

20 mm Aggregate

Cum

8.10

#REF!

#REF!

10 mm Aggregate

Cum

5.40

#REF!

#REF!
#REF!

b)

Labour
Mate

Each

0.86

170.00

Mason 2nd Class


Mulia unskilled

146.20

Each

1.50

190.00

285.00

Each

20.00

150.00

3000.00
3431.20

c)

Machinery
Concrete mixer (cap. 0.40/0.28 cum)

Hour

6.00

#REF!

Generator 33 KVA

Hour

6.00

#REF!

#REF!
#REF!
#REF!
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e)
Carriage & Royalty

7.5%

#REF!

Cement

MT

5.21

#REF!

#REF!

Coarse sand

Cum

6.75

#REF!

#REF!

8.10

#REF!

#REF!

5.40

#REF!

20 mm Aggregate
10 mm Aggregate

Cum
Cum

Cost for 15 Cum = a+b+c+d+e


Rate per Cum = (a+b+c+d+e)/15
Or Say
(A)

#REF!
#REF!
#REF!
#REF!
#REF!

Cap and Dirt Wall


Rate as per Item No.24
Add for centering and shuttering

#REF!
Sqm

1.50

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
(B)

#REF!
#REF!

Deck slab
Rate as per Item No.24
Add for centering and shuttering

#REF!
Sqm

3.00

361.13

1083.39
#REF!

Add Labour Welfare Cess @ 1%


Or Say
C)

#REF!
#REF!

For Wing walls


#REF!

Basic Rate
Add for centering & shuttering 3.00 sqm

Sqm

3.00

361.13

Add Labour Welfare Cess @ 1%


or say

1083.39
#REF!
#REF!
#REF!

Description

Sl. No

D)

Unit

Qnty

Rate

Amount

For Raft
#REF!

Basic Rate
Add for centering & shuttering 2.00 sqm @Rs. 67.28

sqm

2.00

67.28

183.49
#REF!

Add Labour Welfare Cess @ 1%


or say
(E)

#REF!
#REF!

Cover Slab
Rate as per Item No.24
Add for centering and shuttering

#REF!
Sqm

6.70

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
25

#REF!
#REF!

R.C.C Grade M30


Unit = Cum
Taking output = 15 Cum
a)

Material
Cement

MT

6.10

#REF!

#REF!

Coarse sand

Cum

6.75

#REF!

#REF!

20 mm Aggregate

Cum

8.10

#REF!

#REF!

10 mm Aggregate

Cum

5.40

#REF!

#REF!
#REF!

b)

Labour
Mate

Each

0.86

170.00

146.20

Mason 2nd Class

Each

1.50

190.00

285.00

Mulia unskilled

Each

20.00

150.00

3000.00
3431.20

c)

Machinery
Concrete mixer (cap. 0.40/0.28 cum)

Hour

6.00

#REF!

#REF!

Generator 33 KVA

Hour

6.00

#REF!

#REF!
#REF!
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e)
Carriage & Royalty

7.5%

#REF!

Cement

MT

6.10

#REF!

#REF!

Coarse sand

Cum

6.75

#REF!

#REF!

20 mm Aggregate

Cum

8.10

#REF!

#REF!

5.40

#REF!

10 mm Aggregate

Cum

#REF!

Cost for 15 Cum = a+b+c+d+e

#REF!
#REF!

Rate per Cum = (a+b+c+d+e)/15

#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Description

Sl. No

(A)

Unit

Qnty

Rate

Wearing coat & Approach slab


Rate as above
Add towards centering and shuttering

#REF!
Sqm

0.50

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!
#REF!
#REF!

Or Say
26

Amount

Cement mortar 1:3 (1 cement : 3 sand)


Unit = Cum
Taking output = 1 Cum
a)

Material
Cement

MT

0.51

#REF!

#REF!

Sand

Cum

1.05

#REF!

#REF!
#REF!

b)

Labour
Mate

Each

0.040

170.00

6.80

Mulia unskilled

Each

0.90

150.00

135.00
141.80

Total Mateial, Labour & carriage = (a+b)

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
27

Providing weep holes


Unit = Mtr.
Taking output = 30 Mtr
a)

Materials

A.C pipe 100mm dia including wastage 5%

Metre

31.50

60.00

1890.00

M.S clamp

Each

30.00

10.00

300.00

Collar for A.C pipe (average) taking 10% of above


pipe rate

Each

10.00

6.00

60.00

Cement mortar (1:3) as above

Cum

0.05

#REF!

#REF!
#REF!

b)

Labour
Mate

Each

0.03

170.00

5.10

Mason 2nd class

Each

0.50

190.00

95.00

Mulia unskilled

Each

0.25

150.00

37.50
137.60
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


d)Carriage & Royalty

7.5%

#REF!

Cement (0.05 X 0.51 Qntl)

MT

0.02550

#REF!

Sand (0.05 X 1.05 Cum)

Cum

0.05250

#REF!

#REF!
#REF!
#REF!

Cost per 30 Mtrs = a+b+c+d

#REF!

Rate per Mtr = (a+b+c+d)/30

#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Sl. No

Description

28

Rough stones dry packing in approns and revetment


with hard granite stone 30cm and above size

Unit

Qnty

Rate

Amount

Unit = Cum
Taking output = 1 cum
a)

Material
Rough stone granite

Cum

1.00

#REF!

#REF!
#REF!

b)

Labour
Mason special

Each

0.17

205.00

34.85

Stone packer

Each

0.35

170.00

59.50

Woman Mulia

Each

0.52

150.00

78.00

Man Mulia

Each

0.87

150.00

130.50
302.85

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
d)

#REF!
#REF!

7.5%
7.5%

Royalty

Rough stone granite

Cum

1.00

#REF!

#REF!
#REF!

Rate per Cum= (a+b+c+d)

#REF!

Add Labour Welfare Cess @ 1%


Or Say
29

#REF!
#REF!

Gravel backing to revetments


Unit = Cum
Taking output = 1 Cum
a)

Material
Gravel or moorum

Cum

1.00

#REF!

#REF!
#REF!

b)

Labour
Man Mulia

Each

0.71

150.00

106.50

Woman Mulia

Each

0.35

150.00

52.50
159.00
#REF!

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
d)

Carriage & Royalty


Gravel or moorum

7.5%
7.5%
Cum

1.00

#REF!
#REF!
#REF!

Rate per cum= (a+b+c+d)

#REF!

Add Labour Welfare Cess @ 1%


Or Say
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding
in Single Row .
Laying
Reinforced
cement
concrete
pipe
NP4/prestressed concrete pipe for culverts on first
class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and
parapets .

#REF!
#REF!
#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m
length each )
A

1000 mm dia
a)

b)

Labour
Mate

day

0.180

170.00

30.60

Mason
Mazdoor

day
day

0.500
4.000

205.00
150.00

102.50
600.00

Sand at site
Cement at site

cum
tonne

0.070
0.050

#REF!
#REF!

#REF!
#REF!

RCC pipe NP-4 /prestressed concrete pipe


including collar at site

metre

12.500

#REF!

#REF!

Granular material passing 5.6 mm sieve for


bedding

cum

4.500

#REF!

#REF!

Material

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
d)
Carriage & Royalty
Sand at site

7.5%
7.5%

#REF!
#REF!

cum

0.070

#REF!

#REF!

Cement at site

tonne

0.050

#REF!

#REF!

RCC pipe NP-4 /prestressed concrete pipe


including collar at site

metre

12.500

#REF!

#REF!

Granular material passing 5.6 mm sieve for


bedding

cum

4.500

#REF!

#REF!
#REF!

Rate per metre = (a+b+c+d)/12.5

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say
30

#REF!

Laying of NP3 hume pipe of 600MM diameter for


pipe culverts as per approved drawing and Section
2900 of MoRT&H specifications for Road & Bridge
works (4th Revision).
Unit = Mtr
Taking output = 1 Mtr
600MM dia
Labour for fitting and fixing as per S/R 28.10

Mtr

SR-2013

Cost & Carriage of hume pipe 600mm dia

Mtr

1.00

76.64
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Rate per 1 Mtr

7.5%

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
31

#REF!

#REF!
#REF!

R.C.C Grade M15


Unit = Cum
Taking output = 1 Cum
a)

Material
Cement

Qntl

2.80

#REF!

#REF!

Coarse sand

Cum

0.45

#REF!

20 mm Aggregate

Cum

0.54

#REF!
#REF!

10 mm Aggregate

Cum

0.36

#REF!

#REF!
#REF!

#REF!

Description

Sl. No

b)

Unit

Qnty

Rate

Amount

Labour
Mate

Each

0.06

170.00

10.20

Mason 2nd Class

Each

0.10

190.00

19.00

Each

1.33

150.00

199.50
228.70

Hour

0.40

#REF!

#REF!

0.40

#REF!

#REF!
#REF!

Mulia unskilled
c)

Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA

Hour

#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%
e)

7.5%
7.5%

#REF!
#REF!

Carriage & Royalty


Cement

Qntl

2.80

#REF!

#REF!

Coarse sand

Cum

0.45

#REF!

#REF!

20 mm Aggregate

Cum

0.54

#REF!

#REF!

0.36

#REF!

#REF!
#REF!

10 mm Aggregate

Cum

#REF!

Cost per Cum = a+b+c+d+e


Add Labour Welfare Cess @ 1%
Or Say
72

#REF!
#REF!

Dismentling brick/stone masonry in cement mortar


including T&P & scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material & stacking the serviceable
material within all lifts & 1 km lead
Data per 1.25 cum (RR Stone masonry)
a) Labour
Mulia

Each

0.750

150.00

112.50

Mate

Each

0.0300

170.00

5.10
117.60

Machinery
Tractor-Trolley

Hour

0.270

#REF!

Total (a+b)
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Cost per 1.25 cum

7.5%

#REF!
#REF!

Cost per 1 cum

#REF!

Add Labour Welfare Cess @ 1%


or say
32

#REF!
#REF!

#REF!
#REF!

Painting two coats in new concrete surface


(as per MoRT&H Data Book, Page-220)
Unit = Sqm
Taking output = 40 Sqm
a)

Labour
Mate

each

0.12

170.00

20.40

Painter 2nd class

each

2.00

190.00

380.00

Mulia unskilled

each

1.000

150.00

150.00
550.40

Description

Sl. No

b)

Unit

Qnty

Ltr

6.000

Rate

Amount

Material
Enamel Paint

176.00

1056.00
1056.00
1606.40

Overhead charges @ 7.5%

7.5%

120.48

Contractor's Profit @ 7.5%


Cost for 40 Sqm = a+b+c

7.5%

120.48
1847.36

Rate per Sqm = (a+b+c)/40

46.18

Add Labour Welfare Cess @ 1%

0.46
46.60

Or Say
49

Cement washing 2 coats wirh cost of all labour, T&P


etc. complete. A.R. page-113, item No.-41
Taking output =93 sqm
Materials
Cement

Qntl

1.5015

#REF!

#REF!

Painter 2nd class

Nos.

1.00

190.00

190.00

Mulia

Nos.

1.63

150.00

244.50

Labour

#REF!
Overhead charges @ 7.5%
d

Contractor's Profit @ 7.5%


Add conveyance of cement

7.5%

Rate per 93 sqm

#REF!
#REF!
#REF!

Rate for 1.00sqm

#REF!

Add Labour Welfare Cess @ 1%

#REF!

Rate per sqm

#REF!

Qntl

7.5%
1.5015

#REF!
#REF!

Rate of Cement painting over a coat of Cement


washing
Rate Cement painting

46.60

Rate of cement wash

#REF!
#REF!

33

Reinforced cement concrete M15 grade kilometre


stone of standard design as per IRC:8-1980, fixing in
position including painting and printing etc as per
Clause 804 of MoRT&H Specifications for Road &
Bridge works(4th Revision)

(i ) 5th kilometre stone (precast)


Unit = Nos.
Taking output = 6 Nos.
Cum

2.35

#REF!

b)Steel reinforcement @ 5 kg per sqm


c)Excavation in soil for foundation

Kg

22.08

#REF!

#REF!

Cum

1.68

89.02

149.55

d)Painting two coats on concrete surface

Sqm

9.85

46.18

454.87

Per cm
per
letter

1800

0.10

180.00

a)M-15 grade of concrete

e)Lettering on km post (average 30 letters of 10 cm


height each)
Transportation and fixing

#REF!

#REF!

Description

Unit

Qnty

Mate

each

0.26

170.00

44.20

Mason 2nd class

each

0.60

190.00

114.00

Mazdoor including loading and unloading

each

6.00

150.00

900.00
1058.20

6.00

#REF!

#REF!
#REF!

Sl. No

Rate

Amount

f)Labour

g)Machinery
hour

Tractor - trolley

#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%

7.5%
7.5%

Cost per 6 Nos.5th KM stone = a+b+c+d+e+f+g+h

#REF!
#REF!
#REF!

Rate per 1 No.5th KM stone =(a+b+c+d+e+f+g+h)/6

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
ii )

Ordinary kilometre stone (precast)


Unit = Nos.
Taking output = 14 Nos.
a)M-15 grade of concrete

Cum

3.77

#REF!

#REF!

b)Steel reinforcement @ 5 kg per sqm


c)Excavation in soil for foundation

Kg

26.32

#REF!

#REF!

Cum

2.77

89.02

246.59

d)Painting two coats on concrete surface

Sqm

11.41

46.18

526.91

Per cm
per
letter

1680

0.10

168.00

e)Lettering on km post (average 30 letters of 10 cm


height each)
Transportation and fixing

#REF!

f)Labour
Mate

each

0.32

170.00

54.40

Mason 2nd class

each

1.00

190.00

190.00

Mazdoor including loading and unloading

each

7.00

150.00

1050.00
1294.40

hour

6.00

#REF!

#REF!
#REF!

g)Machinery
Tractor - trolley

#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%

7.5%
7.5%

#REF!
#REF!

Cost per 14Nos.ordinary KM stone=a+b+c+d+e+f+g+h


Rate
per
1No.
(a+b+c+d+e+f+g+h)/14

ordinary

KM

stone

#REF!
=

#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Description

Sl. No

(iii)

Unit

Qnty

Rate

Amount

Hectometer stone (precast)


Unit = Nos.
Taking output = 33 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

cum
kg

1.580

#REF!

#REF!

66.000

#REF!

#REF!
123.74

c)

Excavation in soil for foundation

cum

1.390

89.02

d)

Painting two coats on concrete surface

sqm

6.270

46.18

289.55

330.000

0.16

52.80

e)
Lettering on km post (average 1 letter of 10 cm
height each)

per cm
per
letter

#REF!
f)Labour
Mate

each

0.34

170.00

Mason 2nd class

each

1.50

190.00

285.00

Mazdoor including loading and unloading

each

7.00

150.00

1050.00
1392.80

hour

6.00

#REF!

#REF!
#REF!

57.80

g)Machinery
Tractor - trolley

#REF!
Overhead charges @7.50%
Contractor's Profit @7.50%
Cost per 33Nos.hectometer stone=a+b+c+d+e+f+g+h

#REF!
#REF!
#REF!

Rate per 1No. 1No. hectometer stone = (a+b+c+d+


e+f+g+h)/33
Add
Labour Welfare Cess @ 1%

#REF!
Or Say

#REF!
#REF!

Printing New Letter and Figures of any Shade


Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved
colour to give an even shade
(i)

Hindi ( Matras commas and the like not to be


measured and paid for Half letter shall be counted
as half )

Details for 100 letters of 16 cm height i.e. 1600


cm
Unit = per cm height per letter
a)

Labour

Mate

day

0.120

170.00

20.40

Painter

day

2.000

205.00

410.00

Mazdoor

day

1.000

150.00

150.00

Litre

0.700

172.00

120.40

b)

Material

Paint
Overhead charges @7.50%

52.56

Contractor's Profit @7.50%

52.56

Cost for 1600 cm = a+b+c+d

805.92

Description

Sl. No

Unit

Qnty

Rate

Amount

Rate per cm height per letter = (a+b+c+ d)/1600

(ii)

0.50

say

0.50

English and Roman


Hyphens and the like not to be measured and paid
for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a)

Labour

Mate

day

0.070

170.00

11.90

Painter Ist class

day

1.250

205.00

256.25

Mazdoor

day

0.500

150.00

75.00

Litre

0.500

172.00

86.00

b)

Material

Paint
Overhead charges @7.50%

32.19

Contractor's Profit @7.50%

32.19

Cost for 1600 cm = a+b+c+d

493.53

Rate per cm height per letter = (a+b+c +d)/1600

0.31

say

0.30

Painting on Steel Surfaces


(ii)

Providing and applying two coats of ready mix paint


of approved brand on steel surface after through
cleaning of surface to give an even shade

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate

day

0.03

170.00

5.10

Painter

day

0.45

205.00

92.25

Mazdoor

day

0.25

150.00

37.50

Litre

1.25

172

215.00

b) Material
Paint ready mixed approved brand.
Add @ 1% on cost of material for scaffolding

2.15

Overhead charges @7.50%

26.40

Contractor's Profit @7.50%

26.40

Cost for 10 sqm = a+b+c+d

404.80

Rate per sqm = (a+b+c+d)/10

40.48

say

40.50

Description

Sl. No

Unit

Qnty

Rate

Amount

Retro-Reflectorised Traffic Signs


Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per
IRC :67 made of high intensity grade sheeting vide
clause 801.3, fixed over aluminium sheeting, 1.5 mm
thick supported on a mild steel angle iron post 75 mm
x 75 mm x 6 mm firmly fixed to the ground by means
of properly designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing

Unit = Each
Taking output = one traffic sign
i)

Excavation for foundation

cum

0.216

89.02

19.23

ii)

Cement concrete M15 grade

cum

0.120

#REF!

#REF!

iii)

Painting angle iron post two coats

sqm

0.430

40.48

17.41

Mate

day

0.010

170.00

1.70

Mazdoor

day

0.250

150.00

37.50

kg

19.000

#REF!

#REF!

sqm

0.350

7000.00

2450.00

sqm

0.156

7000.00

1092.00

sqm

0.283

7000.00

1981.00

sqm

0.480

7000.00

3360.00

sqm

0.270

7000.00

1890.00

sqm

0.360

7000.00

2520.00

sqm

0.672

7000.00

4704.00

hour

0.010

231.00

2.31

a)

b)

Labour (For fixing at site)

Material

Mild steel angle iron 75 x 75 x 6 mm


Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and
signs as applicable
Add 2 per cent of cost of angle iron towards cost
of drilling holes, nuts, bolts etc.
( i ) 90 cm equilateral triangle
or
( ii ) 60 cm equilateral triangle
or
( iii ) 60 cm circular
or
( iv ) 80 mm x 60 mm rectangular
or
( v ) 60 cm x 45 cm rectangular
or
(vi ) 60 cm x 60 cm square
or
( vii ) 90 cm high octagon
c)

Machinery

Tractor-trolley

Description

Sl. No

Unit

Qnty

Rate

Amount

( i ) 90 cm equilateral triangle
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%


( ii ) 60 cm equilateral triangle

say

#REF!
#REF!

Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%


( iii ) 60 cm circular

say

#REF!
#REF!

Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

( iv ) 80 mm x 60 mm rectangular
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

( v ) 60 cm x 45 cm rectangular
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

(vi ) 60 cm x 60 cm square
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

( vii ) 90 cm high octagon


Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Direction and Place Identification Signs upto 0.9


sqm Size Board.
Providing and erecting direction and place
identification retro-reflectorised sign as per IRC:67
made of high intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 2 mm thick
with area not exceeding 0.9 sqm supported on a mild
steel single angle iron post 75 x 75 x 6 mm firmly
fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45
x 60 cm, 60 cm below ground level as per approved
drawing

Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation

cum

0.216

89.02

19.23

ii) Cement concrete M15 grade

cum

0.120

#REF!

#REF!

iii) Painting angle iron post two coats

sqm

0.430

40.48

17.41

Mate

day

0.010

170.00

1.70

Mazdoor

day

0.200

150.00

30.00

kg

19.000

#REF!

#REF!

sqm

0.900

hour

0.020

a)

b)

Labour (For fixing at site)

Material

Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85


metres long
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size 0.9 sqm

7000.00

6300.00

231.00

4.62

Add 2 per cent of cost of materials for drilling


holes, nuts, bolts, fabrication etc.
c)

Machinery

Tractor-trolley
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e

#REF!

Rate per sqm (for sign having area upto 0.9 sqm)
= (I+ii+iii+a+b+c+d+e)/0.90

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say
Direction and Place Identification Signs with size
more than 0.9 sqm size Board.
Providing and erecting direction and place
identification retro- reflectorised sign as per IRC :
67 made of high intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 2 mm thick
with area exceeding 0.9 sqm supported on a mild
steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos.
firmly fixed to the ground by means of properly
designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground
level as per approved drawing

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

Unit = sqm
Taking output = 1.50 sqm
i)

Excavation for foundation

cum

0.430

89.02

38.28

ii)

Cement concrete M15 grade

cum

0.240

#REF!

#REF!

iii)

Painting angle iron post 2 coats

sqm

0.860

40.48

34.81

Mate

day

0.010

170.00

1.70

Mazdoor

day

0.300

150.00

45.00

kg

38.000

#REF!

#REF!

a)

b)

Labour (For fixing at site)

Material

Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85


metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting

sqm

1.500

hour

0.020

7000.00

10500.00

231.00

4.62

Add 2 per cent of cost of materials for drilling


holes, nuts, bolts, fabrication etc.
c)

Machinery

Tractor-trolley
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e

#REF!

Rate per sqm ( for sign having area more than 0.9
sqm) = ( i+ii+iii+a+b+c+d+e)/1.50

#REF!

Add Labour Welfare Cess @ 1%

#REF!

say

36

#REF!

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam
specification as per Clause 404 of MoSRT&H
Specifications for Road & Bridge works (4th
Revision)
Unit = Cum
Taking output = 360 Cum
a)

Labour
Mate

Each

10.08

170.00

1713.60

Mulia skilled

Each

2.00

190.00

380.00

Mulia unskilled

Each

250.00

150.00

37500.00
39593.60

b)

Machinery
Smooth 3 wheeled steel roller @ 30cum/hour

Hour

12.000

#REF!

#REF!

Water tanker 6 KL capacity

Hour

24.000

#REF!

#REF!
#REF!

c)Material

Description

Sl. No

(i)

Unit

Qnty

Rate

Amount

IRC Grading-II-40mm to 90mm size hard stone metal Using moorum or gravel
40mm to 90 mm size hard stone metal@ 1.21cum
per 10 sqm for compacted thickness of 100 mm

Cum

435.60

#REF!

#REF!

Moorum or Gravel @ 0.30 cum per 10 sqm

Cum

108.00

#REF!

#REF!

KL

144.00

#REF!

Cost of water

#REF!
#REF!
#REF!

Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%


e)
Carriage & Royalty

#REF!

40mm to 90 mm size hard stone metal

Cum

435.60

#REF!

#REF!

Crushable type such as Moorum or Gravel

Cum

108.00

#REF!

#REF!

Cost for 360 Cum = a+b+c+d+e

#REF!
#REF!

Rate per Cum = (a+b+c+d+e)/360

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
(ii)

IRC Grading-II Using Type-B 11.2mm Stone Screening


Grading-II 63 mm to 45 mm @0.91cum per
10sqm

Cum

435.60

#REF!

#REF!

Type B 11.2 mm for grading-II @0.20cum per


10sqm

Cum

96.01

#REF!

#REF!

Binding Material @ 0.06 cum per 10 sqm

Cum

28.80

#REF!

#REF!

KL

144.00

#REF!

#REF!
#REF!

Cost of water

#REF!
Overhead charges @7.50%
Contractor's Profit @7.50%
e)
Royalty

#REF!
#REF!

Grading-II 63 mm to 45 mm @0.91cum per


10sqm

Cum

435.60

#REF!

#REF!

Type B 11.2 mm for grading-II @0.20cum per


10sqm

Cum

96.01

#REF!

#REF!

Binding Material @ 0.06 cum per 10 sqm

Cum

28.80

#REF!

#REF!
#REF!

Cost for 360 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/360

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
(iii)

IRC Grading-III Using Gravel


Grading-III 53 mm to 22.4 mm @0.91cum per
10sqm

Cum

435.60

#REF!

#REF!

Gravel as filler materials

Cum

105.59

#REF!

#REF!

KL

144.00

#REF!

#REF!
#REF!

Cost of water
Overhead charges @7.50%
Contractor's Profit @7.50%

#REF!
#REF!

Description

Unit

Qnty

Grading-III 53 mm to 22.4 mm @0.91cum per


10sqm

Cum

435.60

#REF!

#REF!

Gravel as filler materials

Cum

105.59

#REF!

#REF!

Sl. No

e)

Rate

Amount

Carriage & Royalty

#REF!
Cost for 360 Cum = a+b+c+d+e

#REF!

Rate per Cum = (a+b+c+d+e)/360

#REF!

Add Labour Welfare Cess @ 1%


Or Say
37

#REF!
#REF!

Providing 63mm size C.B.H.G metal as filter media


including filling the interstices with sand and rolling
with hand road roller or ramming with rammer
Unit = Cum
Taking output = 2.83 cum
a) Labour
Stone packer

Each

0.500

170.00

85.00

Man mulia

Each

0.500

150.00

75.00

Woman Mulia

Each

2.500

150.00

375.00
535.00

63mm size C.B.H.G metal = 2.83 cum

2.83

#REF!

Overhead charges @7.50%


Contractor's Profit @7.50%

#REF!
#REF!

Cost per 2.83 Cum = a+b+c

#REF!

Rate per Cum = (a+b+c) / 2.83

#REF!

d) Cost, Carriage & Royalty


40mm to 90mm size hard stone metal

Cum

1.00

#REF!

#REF!

Sand

Cum

0.25

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
38

#REF!
#REF!

#REF!
#REF!

Random Rubble hard granite stone masonry in cement


mortar (1:4) as per approved drawing and Section
1400 & 2200 of MoRT&H Specifications for Road &
Bridge works (4th Revision)
In foundation and plinth
a) Materials
HBG Stone

Cum

1.00

#REF!

#REF!

0.34
1.2156

#REF!
#REF!

#REF!

Cement

Cum
Qntl

b) Labour
Mason 1st Class.

Each

0.35

205.00

71.75

Mason 2nd class.

Each

1.41

190.00

267.90

Mulia

Each

3.17

150.00

475.50
815.15

Sand

#REF!
#REF!

#REF!

Description

Sl. No

Unit

Qnty

Rate

Overhead charges @7.50%


Contractor's Profit @7.50%
d) Carriage & Royalty
HBG Stone
Sand
Cement

#REF!
#REF!
Cum

1.00

#REF!

#REF!

Cum
Qntl

0.34

#REF!

#REF!

1.2156

#REF!

#REF!
#REF!
#REF!

Rate per sqm= (a+b+c+d)


Add Labour Welfare Cess @ 1%
Or Say
39

#REF!
#REF!

20mm thick cement plaster (1:4) over stone masonry


as per Section 1300 & 2200 of MoRT&H
specifications for Road & Bridge works (4th
Revision)
a) Materials
Sand

Cum

0.021

Qntl

0.0744

#REF!
#REF!

#REF!

Cement
b) Labour
Mason 2nd class

Each

0.16

190.00

30.40

Mulia

Each

0.24

150.00

36.00
#REF!

#REF!

Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%


d) Carriage & Royalty
Sand

#REF!
Cum

0.021

#REF!

#REF!

Cement

Qntl

0.0744

#REF!

#REF!
#REF!

Rate per sqm= (a+b+c+d)


Add Labour Welfare Cess @ 1%
Or Say
40

Amount

#REF!
#REF!

Grouting approns and revetment 23cm deep with


cement concrete (1:3:6) with 25mm size crusher
broken granite metal
Unit = sqm
Taking output = 1 sqm
a) Materials
25mm size metal (0,03x0,96cum=0,0288cum)

Cum

0.0288

#REF!

#REF!

Coarse sand (0,03x0,48=0,0144cum)

Cum

0.0144

#REF!

#REF!

Cement (0,03x1.72 qntl=0.0516qntl)

Qntl

0.0516

#REF!

#REF!

Mason 2nd class(0,03x0,18 no.=0,0054 no,)

Each

0.0054

190.00

1.03

Man Mulia (0,03 x 2.5no. = 0,075no.)

Each

0.075

150.00

11.25

Woman Mulia (0,03 x 1,4no. = 0,042no.)

Each

0.042

6.30

Mason special

Each

0.050

150.00
205.00

10.25

Man Mulia

Each

0.110

150.00

16.50

Woman Mulia

Each

0.110

150.00

b) Labour

16.50
#REF!

Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount

d) Carriage & Royalty


25mm size metal (0,03x0,96cum=0,0288cum)

Cum

0.0288

#REF!

#REF!

Coarse sand (0,03x0,48=0,0144cum)

Cum

0.0144

#REF!

#REF!

Cement (0,03x2.29qntl=0,0687qntl)

Qntl

0.0516

#REF!

#REF!

Rate per sqm= (a+b+c+d)

#REF!

Add Labour Welfare Cess @ 1%


41

Or Say

#REF!
#REF!

Laying of NP3 hume pipe of 1000MM dia.r for pipe


culverts as per approved drawing & Section 2900 of
MoRT&H specifications for Road & Bridge works
(4th Revision).
Unit = Mtr
Taking output = 1 Mtr
600MM dia
Labour for fitting and fixing as per S/R 42.20

Mtr

1.00

42.20

42.20

Cost & Carriage of hume pipe 1000mm dia

Mtr

1.00

#REF!

#REF!

Rate per 1 Mtr

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

or say
41

Laying of NP3 hume pipe of 600MM dia.r for pipe


culverts as per approved drawing & Section 2900 of
MoRT&H specifications for Road & Bridge works
(4th Revision).
Unit = Mtr
Taking output = 1 Mtr
600MM dia
Labour for fitting and fixing as per S/R 28.10

Mtr

1.00

76.64

76.64

Cost & Carriage of hume pipe 1000mm dia

Mtr

1.00

#REF!

#REF!

Rate per 1 Mtr

#REF!

Add Labour Welfare Cess @ 1%


or say
41

#REF!
#REF!

Laying of NP3 hume pipe of 900MM dia.r for pipe


culverts as per approved drawing & Section 2900 of
MoRT&H specifications for Road & Bridge works
(4th Revision).
Unit = Mtr
Taking output = 1 Mtr
600MM dia
Labour for fitting and fixing as per S/R 42.20

Mtr

1.00

115.09

115.09

Cost & Carriage of hume pipe 1000mm dia

Mtr

1.00

#REF!

#REF!

Rate per 1 Mtr

#REF!

Add Labour Welfare Cess @ 1%


or say
Earth work in hard soil by mechanical means with
compaction in O.M.C. rolling earth P.R.R. with cost of
etc.
complete
A) (i) all
Hire
and
running charges of PRR Rs. 339.00 / Hour
including rolling well compaced 425 cum/day=
Rs. 339.00 x 8 x 100/425

#REF!
#REF!

42

639.62

Description

Sl. No

Unit

(ii)

Cost of water with in 5 km by truck


for 1 cum earth = 5x100/390=1.28 trip

Trip

(iii)

Labour charges
for 100 cum=50x100/390=12.82 Nos.

Nos

Qnty

Rate

1.28

910.00

12.82

150.00

Amount
1166.67
1923.08
3729.36

d)
Overhead charges @ 7.5% on (a+b+c)
Contractor's Profit @ 7.5%

7.5%
7.5%

279.70
279.70
4288.76
42.89

Rate for 1 cum


B)

Labour
Man mulia unskilled

Each

21.500

150.00

3225.00

Women mulia unskilled

Each

21.500

150.00

3225.00
6450.00

C)

Overhead charges @7.50%

483.75

Contractor's Profit @7.50%


Rate for 1 cum

483.75
7417.50
74.18

Add carriage cost upto 5 km

136.00

Total Rate per cum (A+B+C)

253.06
or say

By Local Means

253.06

136.00

Add Labour Welfare Cess @ 1%


or say
43

253.10
117.06
1.17
118.20

Providing, laying and spreading Quarry rubbish in


sub-base in layers not excedding 225mm, watering
and compaction to the required density in OMC with
VRR etc. upto thickness 150mm and including cost,
conveyance of sub base materials, labour, T&P etc.
complete.
Rate as A.R.-2006 P-154, item No.-31

i)

Taking output = 300.0 cum


Labour
Mate

Nos.

0.48

170.00

81.60

Skilled Mulia

Nos.

2.00

190.00

380.00

Man & Women Mulia

Nos.

10.00

150.00

1500.00
1961.60

ii)

Machinery
Motor grader 110 HP @ 50 cum per hour

Hour

6.00

1545.00

9270.00

Tractor Rotovator

Hour

12.00

249.00

2988.00

Vibratory Roller 8-10 tonne capacity

Hour

6.00

994.00

5964.00

3.00

582.00

1746.00

Water Tanker 6 KL capacity

Hour

19968.00
iii)

Cost of water

KL

18.000

#REF!

180.00
22109.60

Overhead charges @7.50%

1658.22

Contractor's Profit @7.50%


Cost for 300 cum

1658.22
25426.04
84.75

Rate per cum


Add cost, lead & royality of quarry rubbish
Add Labour Welfare Cess @ 1%
Rate per cum

Cum

1.200

#REF!

#REF!
#REF!
#REF!

Sl. No

Description

44

Labour for admixing sand and moorum etc. complete


including cost of all labour and hire charges of T&P
materials required for work as per specification and
direction of Engineer-in-charge but excluding cost
and conveyance of sand and moorum

Unit

Qnty

Rate

Amount

Unit=Cum
a

Taking output = 1 cum


Labour
Man mulia for mixing sand and moorum

Nos.

0.25

150.00

37.50
37.50

Overhead charges @7.50%

2.81

Contractor's Profit @7.50%


Add Labour Welfare Cess @ 1%

2.81
0.43
43.55

Rate per cum (a+b+c)


45

Providing and laying moorum and sand admixture in


shouldera as per clause 407 of MoRT&H
specifications for road & bridge works
Unit = cum

i)

ii)

Taking output = 2.83 cum


Labour
Man Mulia

Nos.

1.00

150.00

150.00

Man & Women Mulia

Nos.

1.50

150.00

225.00

#REF!

#REF!

Machinery
Add hire & running charges of PRR for consolidation
considering 425 cum of out turn with PRR per day (8
hours)=2.83 x 8 x 320.00 / 425

Hour

0.0533

#REF!
Overhead charges @7.50%
Contractor's Profit @7.50%

#REF!
#REF!

Rate per cum

#REF!
#REF!

Add cost, lead & royality of Sand

Cum

0.51

#REF!

#REF!

Add cost, lead & royality of Moorum=1.28 x 0.7

Cum

0.770

#REF!

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Rate per cum

51

Construction of embankment with approved materials


depsoted at site from roadway cutting and
excavation from road drain and foundation od toher
structures graded and compacted to meet
requirement of table 300 as per clause No.305.3.17
of MoRTH specification for road and bridge works
Unit=Cum

a)

Taking output = 100 cum


Labour
Labour 2/3 of Item No. 4

b)

4300.00

Machinery
Water tanker 6 KL capacity

Hour

4.00

#REF!

2328.00

Description

Sl. No

Vibrator roller 8-10 tonnes @ 100 cum per hour

Unit
Hour

Qnty
1.00

Rate
994.00

Amount
994.00
3322.00

c)

Material
Cost of Water

KL

24.00

#REF!

240.00
7862.00

Overhead charges @7.50%

589.65

Contractor's Profit @7.50%

589.65
9041.30

Rate per 100 cum


Rate per cum

90.41

Add Labour Welfare Cess @ 1%

0.90
or say

52

91.30

Centering, shuttering for R.C.C. works with cost of


all labour etc. complete in slab for culverts and
bridges upto 8.00 mtr. Span and above 4 mtr. And
upto 8 mtr. Height
A.R. page -53, item No.-10
Taking output = 9.00 sqm
Nonsal wood scantling

Cum

0.452

18260.00

8253.52

120mm dia bullah

Rmt

56.00

94.00

5264.00

Carriage of Wood

CUm

1.142

117.60

134.30
13651.82

Considering 10 times use of materials for once use

1365.18

Labour
Carpenter 2nd class

Nos.

2.75

190.00

Semiskilled mulia

Nos.

2.75

170.00

522.50
467.50
2355.18

Overhead charges @7.50%

176.64

Contractor's Profit @7.50%


For 9 sqm

176.64
2708.46
300.94

For 1 sqm
A)

Upto 4.00 mtr. Height


300.94

Basic Rate

60.19

Add 20% extra for strong posts and brassing

361.13

Rate per sqm


53

R.C.C. M-25 with 20mm down graded chips with cost,


conveyance, labour and T&P etc. complete A.R. page50, item no-5
Unit=Cum

a)

b)

c)

Taking output = 15 cum


Labour
Mate

day

0.86

170.00

146.20

mason 2nd class

day

1.50

190.00

285.00

Mulia

day

20.00

150.00

3000.00

Machinery
Hire charges of concrete mixture

Hour

6.00

177.00

1062.00

Hire charges of Generator 33 KVA

Hour

6.00

240.00

1440.00

Cost of 20mm chips

Cum

8.10

#REF!

#REF!

Cost of 10mm chips

Cum

5.40

#REF!

#REF!

Cost of sand

Cum

6.75

#REF!

#REF!

Materials

Description

Sl. No

Cost of Cement

Unit
MT

Qnty
6.05

Rate
#REF!

Amount
#REF!
#REF!

Overhead charges @7.50%


Contractor's Profit @7.50%
e)

A)

#REF!
#REF!

Add Royality and conveyance


Aggregates

Cum

13.500

#REF!

#REF!

Sand

Cum

6.750

#REF!

#REF!

Cement

MT

6.050

#REF!

#REF!

Rate per 15 cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!

Rate per cum

#REF!

Raft
Basic cost as above
Add for centreing & shuttering work

#REF!
Sqm

2.000

67.28

Rate per cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

B)

Add for centreing & shuttering work

#REF!
Sqm

3.000

361.13

Rate per cum

#REF!
or say

#REF!

Deck slab
Basic cost as above
Add for centreing & shuttering work

#REF!
Sqm

3.000

361.13

1083.39

Rate per cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

#REF!

Kerb
Basic cost as above
Add for centreing & shuttering 4 sqm

#REF!
Sqm

4.000

361.13

Rate per cum

1444.52
#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

A)

1083.39
#REF!

Add Labour Welfare Cess @ 1%

D)

#REF!

Wing wall & Abutment, Abutment Cap, Dirt Wall


Basic cost as above

C)

134.56

#REF!

Box culvert
Basic cost as above
Add for centreing & shuttering work (Box culvert)

#REF!
Sqm

8.000

361.13

2889.04

Rate per cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

#REF!

Description

Sl. No

54

Backfilling
No.-8

b)

Qnty

Rate

Amount

behind wall as per A.R. Page-265, item

Taking output = 10 cum


Granular materials (Gravel)
a)

Unit

Cum

12.00

#REF!

#REF!

Mate

day

0.28

170.00

47.60

Mulia

day

7.00

150.00

1050.00

Water tanker

Hour

0.05

582.00

29.10

Power Rammer

Hour

2.50

13.00

Labour

Machinery
32.50
#REF!
Overhead charges @7.50%
Contractor's Profit @7.50%

#REF!
#REF!
#REF!

Rate per 10 cum


Rate per cum
Conveyance and Royality of Granular materials

53

Cum

1.200

#REF!

#REF!
#REF!

Total cost

#REF!

Add Labour Welfare Cess @ 1%

#REF!

Rate per cum

#REF!

R.C.C. M-20 with 20mm down graded chips with cost,


conveyance, labour and T&P etc. complete A.R. page50, item no-5
Unit=Cum

a)

b)

c)

Taking output = 15 cum


Labour
Mate

day

0.86

170.00

146.20

mason 2nd class

day

1.50

190.00

285.00

Mulia

day

20.00

150.00

3000.00

Machinery
Hire charges of concrete mixture

Hour

6.00

177.00

1062.00

Hire charges of Generator 33 KVA

Hour

6.00

240.00

1440.00

Cost of 20mm chips

Cum

8.10

#REF!

#REF!

Cost of 10mm chips

Cum

5.40

#REF!

#REF!

Cost of sand

Cum

6.75

#REF!

#REF!

Cost of Cement

MT

5.21

#REF!

#REF!

Materials

#REF!

e)

A)

Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%


Add Royality and conveyance

#REF!

Aggregates

Cum

13.500

#REF!

#REF!

Sand

Cum

6.750

#REF!

#REF!

Cement

MT

5.210

#REF!

#REF!

Rate per 15 cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!

Rate per cum

#REF!

Box culvert Parapets


Basic cost as above

#REF!

Description

Sl. No

Add for centreing & shuttering work (Box culvert)

Unit
Sqm

Qnty
6.000

Rate
361.13

2166.78

Rate per cum

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

55

Amount

#REF!

Road marking with hot applied thermoplastic


compound with reflectorising glass beads on
bituminous surface. Providing and laying of hot
applied thermoplastic compound 2.5mm thick
including reflectorising glass beads @ 250 gms per
sqm area thickness of 2.5mm is exclusive of surface
to be level and free from streaks and holes
Unit-Sqm

a)

b)

c)

Taking output = 640 sqm


Labour
Mate

day

0.50

170.00

85.00

Mazdoor

day

2.00

150.00

300.00

Road Marking Machine @ 80 sqm

Hour

8.00

60.00

480.00

Tractor Trolley

Hour

8.00

#REF!

#REF!

Hot applied thermo plastic compound

Ltr.

2000.00

130.00

260000.00

Reflectorising glass beads

Kg.

200.00

50.00

10000.00

Machinery

Materials

#REF!
Overhead charges @7.50%
Contractor's Profit @7.50%
Rate per 640 sqm

#REF!
#REF!
#REF!

Rate per sqm

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

56

#REF!

Providing moorum bedding as per approved drawing


and Clause 2904 of MoRT&H Specifications for Road
& Bridge works (4th Revision).
Unit = Cum
Taking output = 2.83 Cum
a) Labour
Mulia

Each

3.00

150.00

450.00
450.00

Overhead charges @7.50%

33.75

Contractor's Profit @7.50%


Cost per 2.83cum = a+b

33.75
517.50

Rate per cum = (a+b)/2.83


c) Cost, carriage & royalty of moorum

(B)

182.86
Cum

1.00

Say

182.90

#REF!

#REF!

Add Labour Welfare Cess @ 1%

#REF!

Rate per cum = (a+b+c)

#REF!

RCC M-30 Grade Railing and Post of Box Culvert


Rate as above
Add towards centering and shuttering

4591.80
Sqm

15.00

#REF!

#REF!
#REF!

Sl. No

Description

57

Plain cement concrete (1:2:4) with 12 mm size hard


broken granite chips including cost of all materials,
labour, T&P etc. complete.

Unit

Qnty

Rate

Amount

Unit = cum
Taking output = 1 cum
a)

b)

Materials
12mm size H.G.C.B chips

Cum

0.90

#REF!

#REF!

Sand (screened & washed)

Cum

0.45

#REF!

#REF!

Cement

Qntl

3.23

#REF!

#REF!

Mason 2nd class

Each

0.68

190.00

129.20

Man Mulia

Each

3.20

150.00

480.00

Woman Mulia

Each

1.40

150.00

210.00

Labour

#REF!
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%


d)
Carriage & Royalty

#REF!

12mm size H.G.C.B chips

Cum

0.90

#REF!

#REF!

Sand (screened & washed)

Cum

0.45

#REF!

#REF!

Qntl

3.23

#REF!

#REF!

Cement
Rate per Cum = a+b+c+d

#REF!

Add Labour Welfare Cess @ 1%


Or Say
58

#REF!
#REF!

Rigid and smooth centering and shuttering for R.C.C.


works including false works and dismantling them
after casting including cost of materials complete
Column base & footing
Unit = Sqm
Taking Output = 10 Sqm
a) Materials
25mm thick non sal planks for shutters

Cum

0.267

18260.00

4875.42

Non-sal bullah 80mm dia for strutting

Mtr.

12.60

46.00

579.60

Carriage of wood
Total

Cum

0.3284

117.60

38.62
5493.64

Considering 10times use of the materials, for use


once
b) Labour

549.36

Carpenter (second class)

Each

0.50

190.00

95.00

Semiskilled mulia

Each

0.50

170.00

85.00
729.36

Overhead charges @7.50%


Contractor's Profit @7.50%
Cost per 10 sqm = a+b+c

54.70
54.70
838.76

Rate for 1sqm =(a+b+c)/10=

83.88

Add Labour Welfare Cess @ 1%


Or Say
60

0.84
84.70

Random rubble hard granite stone masonry in sand


grouted in foundation and plinth
Unit = 1 cum
a) Materials
Rough stone granite inlcuding bond stone

Cum

1.00

#REF!

#REF!

Description

Unit

Sand grouted including watering

Cum

Sl. No

Qnty
0.24

Rate
#REF!

Amount
#REF!
#REF!

b) Labour
Mason 2nd class

Each

1.41

190.00

267.90

Man & Women Mulia

Each

2.470

150.00

370.50
638.40

Total a+b

#REF!

Overhead charges @7.50%


Contractor's Profit @7.50%

#REF!
#REF!

d) Carriage & Royalty


Rough stone granite inlcuding bond stone

Cum

1.00

#REF!

#REF!

Sand grouted including watering

Cum

0.24

#REF!

#REF!
#REF!

Rate per cum= (a+b+c+d)

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Or Say
62

P.C.C Grade M 20
Unit = cum
Taking output = 15 cum
Materials
40mm HBG Metal (CB)
HG chips 20 mm size (CB)

5.40

cum

#REF!

#REF!

5.40

cum

#REF!

#REF!

HG chips 10 mm size (CB)

2.70

cum

#REF!

#REF!

Sand

6.75

cum

#REF!

#REF!

cement

5.16

MT

#REF!

#REF!

Labour
Mate

0.86

nos

170.00

146.20

Mason 2nd class

1.50

nos

190.00

285.00

20.00

nos

150.00

3,000.00

6.00
6.00

hour
hour

#REF!
#REF!

#REF!

Mulia unskilled
Machinary
Hire and running charges of concrete mixer
Generator 33 KVA

#REF!
#REF!

Overhead charges @7.50%


Contractor's Profit @7.50%

#REF!
#REF!

Conveyance & Royalty charges


40mm HBG Metal (CB)
HG chips 20 mm size (CB)

5.40

cum

#REF!

cum

#REF!
#REF!

5.40

HG chips 10 mm size (CB)

2.70

cum

#REF!

#REF!

Sand

6.75

cum

#REF!

#REF!

cement

5.16

MT

#REF!

#REF!

Total per 15 cum=


Rate per Cum

#REF!
#REF!

15
or say

With frame work

#REF!
#REF!
106.20

Add Labour Welfare Cess @ 1%


Total per Cum
a

#REF!

#REF!
#REF!

Rate for Box cell Wing walls


Basic Rate of PCC M 20
Add centering and shuttering

#REF!
sqm

6.00

#REF!

#REF!

Description

Sl. No

Unit

Qnty

Rate

Add Labour Welfare Cess @ 1%


Total per Cum
63

Amount
#REF!
#REF!

Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying
primer at the rate of 0.60 kg/sqm using mechanical
means.

Unit = sqm
Taking output = 3500 sqm
a)

Labour

Mate

day

0.080

170.00

13.60

Mazdoor

day

2.000

150.00

300.00

Mechanical broom @ 1250 sqm per hour

hour

2.800

230.00

644.00

Air compressor 250 cfm

hour

2.800

206.00

576.80

Bitumen pressure distributor @ 1750 sqm per hour

hour

2.000

516.00

1032.00

Water tanker 6 KL capacity @ 1 trip per hour

hour

1.000

582.00

582.00

Bitumen emulsion @ 0.6 kg per sqm

tonne

2.100

#REF!

#REF!

Cost of water

KL

6.000

10.00

60.00

b)

c)

Machinery

Material

#REF!
Overhead charges @7.50%

#REF!

Contractor's Profit @7.50%


Lead of Materials

#REF!

Bitumen emulsion

tonne

2.100

#REF!

Cost for 3500 sqm = a+b+c+d+e

#REF!

Rate per sqm = (a+b+c+d+e)/3500

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

or say
65

#REF!

Cement concrete (1:2:4) with 12 mm size hand broken


granite chips

Data for 1 cum


a) Materials
12 mm size CB chips

0.90

cum

#REF!

#REF!

Sand

0.45

cum

#REF!

#REF!

Cement

3.23

Qtl

#REF!

#REF!

Mason 2nd class

0.68

Nos.

190.00

129.20

Male & Fememal mulia

4.60

Nos.

150.00

690.00

b) Labour

#REF!
Overhead charges @7.50%
Contractor's Profit @7.50%

#REF!
#REF!

d) Carriage & Royalty of materials


12 mm size CB chips

0.90

cum

#REF!

#REF!

Sand

0.45

cum

#REF!

#REF!

Cement
Rate per cum

3.23

Qtl

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%


or say
66

Cost of Tar paper (Vide S/R 2013, item no-117)

sqm

#REF!
#REF!
15.00

Description

Sl. No

67

Bitumen expansion joint 25 mm thick


2013, item No. 159(c))

Unit
(Vide S/R

Qnty

Rate

sqm

1200.00

Add labour

10.00

Add Labour Welfare Cess @ 1%

69

Amount

12.10
1,237.10

RCC M-20 grade in railing of culvert as per approved


drawing & technical specification and as per section 1500, 1700 & 2200 of MoRT&H specification for
road & bridge
Taking
output works
2 x 24(Latest
m span Revision).
= 48 m
No. of vertical post = (12+2) x 2 = 28 Nos. External
area of
a) Basic cost of M-20 concrete (without OHC) item
no.

cum

3.342

#REF!

b) Add 5% of (a) for form work for casting in yard


c) HYSD bars including 5% for Laps & Wastage

647.32
Mt

0.660

#REF!

#REF!

d) Add 5% of (a+b+c) for handeling & fixing precast


panels in position

#REF!

Overhead charges @7.5% on (a+b+c)


Add contractor's Profit @ 7.5%
f) Carriage & royalty of M-30 concrete

cum

3.342

#REF!

#REF!
#REF!

g) Carriage of HYSD bars

Mt

0.660

#REF!

Total cost for 48 mtr

#REF!
#REF!
#REF!

Rate per mtr

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

or say
70

#REF!

Painting two coats with enamel paints over a coat of


primer in road kerb & post of approved shade for
finished item of work as per the direction of the
Engineer-in-Charge.
a) Enamel Painting two coats (Data per 9.30 sqm)
Painter special class

Each

1.250

205.00

256.25

Mulia

Each

1.100

150.00

165.00
421.25

Overhead charges @7.50%


Contractor's Profit @7.50%
Total for 9.36 sqm

31.59
31.59
484.43

Rate per sqm


Cost of enamel paint

52.09
Lit

0.125

176.00

22.00
74.09

b) Primer One Coat (Data per 9.30 sqm)


Cost of Labour
Painter special class

Each

0.500

205.00

102.50

Mulia

Each

0.500

150.00

75.00
177.50

Overhead charges @7.50%


Contractor's Profit @7.50%
Total per 9.30 sqm

13.31
13.31
204.12

Description

Sl. No

Unit

Qnty

Rate

Rate per sqm


Cost of Primer

Amount
21.95

Lit

0.084

140.00

Rate per sqm

11.76
33.71
107.80

Add Labour Welfare Cess @ 1%

1.08
108.90

Total Cost per 1 Sqm (a+b)


71

Rigid and smooth centering & shuttering of RCC walls


RCC wall
Data per 23.9 sqm
Non-sal plants / scanting

cum

1.223

18260.00

22331.98

Non-sal bullah 120 mm dia

Mtr

100.800

94.00

9475.20

Carriage of wood

cum

2.4610

#REF!

#REF!
#REF!

Considering 10 times use for once

#REF!

Carpenter 2nd Class

No.

13.50

190.00

2565.00

Semi-skilled mulia

No.

13.50

170.00

2295.00
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%

7.5%

#REF!
#REF!

Rate per 1 sqm

#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

or say
74

Earthwork in ordinary soil with 50 mtr initial lead &


1.5 mtr initial lift including rough dressing and
breaking the clods to 5 to 7 cm and laying in layers
not exceeding 0.3 mtr in depth
Data per 100 cum
a) Labour
Male mulia
Female Mulia

Each
Each

16.000
16.000

150.00
150.00

2400.00
2400.00
4800.00

Overhead charges @ 7.5%

7.5%

360.00

Contractor's Profit @ 7.5%

7.5%

360.00
5520.00

Add Labour Welfare Cess @ 1%

55.20
5575.20

Rate per 100 cum


75

Earthwork in hard or gravelly soil with 50 mtr initial


lead & 1.5 mtr initial lift including rough dressing and
breaking the clods to 5 to 7 cm and laying in layers
not exceeding 0.3 mtr in depth
Data per 100 cum
a) Labour
Male mulia
Female Mulia

Each
Each

21.500
21.500

Overhead charges @ 7.5%

7.5%

Contractor's Profit @ 7.5%

7.5%

Add Labour Welfare Cess @ 1%

150.00
150.00

3225.00
3225.00
6450.00
483.75
483.75
7417.50
74.18

Description

Sl. No

Unit

Qnty

Rate

7491.70

Rate per 100 cum


76

Amount

Earthwork in stoney earth and gravels mixed with


stone boulders not exceeding 0.014 cum in volume
with 50 mtr initial lead & 1.5 mtr initial lift including
rough dressing and breaking the clods to 5 to 7 cm
and laying in layers not exceeding 0.3 mtr in depth
Data per 100 cum
a) Labour
Male mulia

Each

33.530

150.00

5029.50

Female Mulia

Each

33.530

150.00

5029.50
10059.00

Overhead charges @ 7.5%

7.5%

754.43

Contractor's Profit @ 7.5%

7.5%

754.43
11567.86

Add Labour Welfare Cess @ 1%

115.68
11683.50

Rate per 100 cum


77

Earthwork in cutting embankroads etc in all kinds of


soil with initial lead & 1.5 mtr initial lift including
rough dressing and breaking the clods to 5 to 7 cm
and laying in layers not exceeding 0.3 mtr in depth
8250.13

Rate per cum = Average rate of above


Rate per 100 cum
78

or say

8250.10

Excavation of foundation in ordinary soil soil with 50


mtr initial lead & 1.5 mtr initial lift including rough
dressing and breaking the clods to 5 to 7 cm and
laying in layers not exceeding 0.3 mtr in depth
Data per 100 cum
a) Labour
Male mulia

Each

16.000

150.00

2400.00

Female Mulia

Each

16.000

150.00

2400.00
4800.00

Overhead charges @ 7.5%

7.5%

360.00

Contractor's Profit @ 7.5%


Rate per 100 cum
Add extra 20% for excavation of foundation

7.5%

360.00
5520.00
1104.00
6624.00

Add Labour Welfare Cess @ 1%

66.24
6690.20

Rate per 100 cum


79

Excavation of foundation in hard or gravelly soil with


50 mtr initial lead & 1.5 mtr initial lift including
rough dressing and breaking the clods to 5 to 7 cm
and laying in layers not exceeding 0.3 mtr in depth
Data per 100 cum
a) Labour
Male mulia

Each

21.500

150.00

3225.00

Female Mulia

Each

21.500

150.00

3225.00
6450.00

Overhead charges @ 7.5%

7.5%

483.75

Contractor's Profit @ 7.5%


Rate per 100 cum

7.5%

483.75
7417.50
1483.50

Add extra 20% for excavation of foundation

Description

Sl. No

Unit

Qnty

Rate

Amount
8901.00

Add Labour Welfare Cess @ 1%

89.01
8990.00

Rate per 100 cum


80

Excavation of foundation in stoney earth and gravels


mixed with stone boulders not exceeding 0.014 cum
in volume with 50 mtr initial lead & 1.5 mtr initial lift
including rough dressing and breaking the clods to 5
to 7 cm and laying in layers not exceeding 0.3 mtr in
depth
Data per 100 cum
a) Labour
Male mulia
Female Mulia

Each
Each

33.530
33.530

150.00
150.00

Overhead charges @ 7.5%

7.5%

10059.00
754.43

Contractor's Profit @ 7.5%

7.5%

754.43

Rate per 100 cum


Add extra 20% for excavation of foundation

11567.86
2313.57
13881.43

Add Labour Welfare Cess @ 1%

138.81
14020.20

Rate per 100 cum


81

Earthwork in cutting embankroads etc in all kinds of


soil with initial lead & 1.5 mtr initial lift including
rough dressing and breaking the clods to 5 to 7 cm
and laying in layers not exceeding 0.3 mtr in depth
9900.13

Rate per cum = Average rate of above


Rate per 100 cum
82

or say

9900.10

or say

6600.10

Filling foundation & plinth with excavated mterials /


earth including watering & ramming etc complete

6600.07

2/3 rate of above item


50

5029.50
5029.50

C.C. (1:4:8) with 40 mm hard granite metal with cost,


conveyance, labour and T&P etc. complete. A.R. Page43, item No.-4
Materials
H.G. Broken stone metal 4 cm size

Cum

0.96

#REF!

#REF!

Sand

Cum

0.48

#REF!

#REF!

Cement

Qtl

1.72

#REF!

#REF!

Mulia

Nos.

3.90

150.00

585.00

Mason 2 nd class

Nos.

0.18

190.00

34.20

Labour

#REF!
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%
Add conveyance & Royalty of metal

7.5%

#REF!

Cum

7.5%
0.960

#REF!

#REF!
#REF!

Add conveyance & Royality of sand

Cum

0.480

#REF!

#REF!

Add conveyance of cement

Qtl

1.7200

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%

#REF!

Rate per cum

#REF!

Description

Sl. No

83

Unit

Qnty

Rate

Amount

Grouting approns and revetment 23cm deep with


cement concrete (1:4:8) with 25mm size crusher
broken granite metal
Unit = sqm
Taking output = 1 sqm
a) CC (1:4:8) as per item no 50 with OHC

Cum

0.03

#REF!

#REF!

Mason special

Each

0.050

205.00

10.25

Man Mulia

Each

0.110

150.00

16.50

Woman Mulia

Each

0.110

150.00

16.50

b) Extra Labour

Overhead charges @ 7.5%

7.5%

3.24

Contractor's Profit @ 7.5%


Rate per sqm= (a+b+c+d)

7.5%

3.24
#REF!

Add Labour Welfare Cess @ 1%


Or Say
84

Metal Spall backing in the rear of well steining or


weep holes of abutment and deep drains including
cost of all materials etc complete
Ref A/R 2006 page 82 item 26 Unit -1 cum
a) Materials
Hand broken granite metal 5 cm size
b) Labour
Man mulia for lowering the metal

1.00

cum

#REF!

#REF!

0.88

Nos.

150.00

132.00
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


d) Carriage & Royalty of materials

7.5%

#REF!

5 mm size CB chips
Rate per sqm= (a+b+c+d)

1.00

cum

#REF!

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say
85

#REF!
#REF!

#REF!
#REF!

Supplying and fixing 15 cm dia 1.0 mtr long guard


post of RCC (1;2:4) using 75 kg of steel per cum for
each guard post with 12 mm size HGCB chips
including cost of reinforcement & materials,
centering, shuttering & watering & curing etc.
complete
Unit = No
Data for 1 No.
For one guard post
Cost of RCC (1:2:4) with 12mm size chips (as per A/R item no. 1 or RCC = 3459.1994)
Cost of RCC (1:2:4) with 12mm HGCB Chips as per
A/R item no. 1 Rs. 2473.557 per cum
Qnty = (22/7)/4 x (0.15) 2 x 1.00 = 0.018 cum

cum

0.020

#REF!

#REF!

Cost of steel required 3.50kg or 0.035 qtl


reinforcement per each post as per item no-23 of
RCC Item 6719.991615 (As per A/R Item no. 8a of
RCC)

qntl

0.040

#REF!

#REF!

Centering and shuttering required.

qntl

0.020

#REF!

#REF!

Total
Add Labour Welfare Cess @ 1%

#REF!
#REF!

Description

Sl. No

Unit

Qnty

Rate per 1 No.


87

R.C..C Work of M-30 grade with 20mm & down grade


size black hard granite (crusher broken) chips
including hoisting, laying, watering, curing, centering,
shuttering and finished the exposed surface, cost of
all materials and labour etc. complete.

a.

RCC M-30 in well curb

Rate
Or say

cum

1.00

#REF!

#REF!

Add cost of shuttering 3.2 sqm.

sqm

3.20

#REF!

#REF!
#REF!

RCC M-25 in well steining


Basic Rate of RCC M-25

cum

1.00

#REF!

#REF!

Add cost of shuttering 6.0 sqm.

sqm

6.00

#REF!

#REF!

Rate per 1 cum.


c.

#REF!

RCC M-30 in well cap


Basic Rate of RCC M-30
Add cost of shuttering 6.0 sqm.

cum
sqm

1.00

#REF!

#REF!

6.00

#REF!

#REF!

Rate per 1 cum.


d.

#REF!

RCC M-30 in abutment and pier shaft


Basic Rate of RCC M-30

cum

1.00

#REF!

#REF!

Add cost of shuttering 8.0 sqm.

sqm

8.00

#REF!

#REF!

Rate per 1 cum.


e.

#REF!

RCC M-30 in pier and abutment cap


Basic Rate of RCC M-30

cum

1.00

#REF!

#REF!

Add cost of shuttering 8.0 sqm.

sqm

8.00

#REF!

#REF!

Rate per 1 cum.


f.

#REF!

RCC M-30 in column, cantilever wing wall, tie


beam
Basic Rate of RCC M-30
Add cost of shuttering 8.0 sqm.

cum
sqm

1.00

#REF!

#REF!

8.00

#REF!

#REF!

Rate per 1 cum.


g.

#REF!

RCC M-30 Dirt wall


Basic Rate of RCC M-30
Add cost of shuttering 6.0 sqm.

cum
sqm

1.00

#REF!

#REF!

8.00

#REF!

#REF!

Rate per 1 cum.


h.

#REF!

RCC M-30 in Deck Slab


Basic Rate of RCC M-30

cum

1.00

#REF!

#REF!

Add cost of shuttering 6.0 sqm.

sqm

6.00

#REF!

#REF!

Rate per 1 cum.


i.

#REF!

Basic Rate of RCC M-30

Rate per 1 cum.


b.

Amount

#REF!

RCC M-30 in Wearing coat


Basic Rate of RCC M-30

cum

1.00

#REF!

#REF!

Add cost of shuttering 0.5 sqm.

sqm

0.50

#REF!

#REF!

Description

Sl. No

Unit

Qnty

Rate

Rate per 1 cum.


j.

#REF!

PCC M-25 in Approach Slab


Basic Rate of PCC M-25
Add cost of shuttering 0.5 sqm.

cum
sqm

1.00

#REF!

0.50

#REF!

Rate per 1 cum.


k.

#REF!
#REF!
#REF!

RCC M-25 in Kerb


Basic Rate of RCC M-25
Add cost of shuttering 0.5 sqm.

cum
sqm

1.00

#REF!

1.00

#REF!

Rate per 1 cum.


88

Amount

#REF!
#REF!
#REF!

Providing, laying and rolling of open - graded premix


surfacing of 20 mm thickness composed of 13.2 mm
to 5.6 mm aggregates with batch type hot mix plant
and using 60/70 penetration grade of bitumen to
required line, grade & level to serve as wearing
course on a previously prepared base including mixing
in a suitable plant, laying & rolling with a smooth
wheeled roller 8-10 tonne capacity, finished to
required level and grades as per Clause 511 of
MoSRT&H Spef for Road & Bridge works (4th
Unit = sqm
Revision)
Taking output = 10250 sqm
(205 cum = 450tonne)
a)

b)

Labour
each
each

0.760
14.000

Mulia Skilled for checking line & levels

each

5.000

150.00
190.00

129.20
2100.00

i) Batch type HMP 60-90 TPH


@ 75 tonne per hour

hour

6.000

#REF!

#REF!

ii) Electric Generator Set 250 KVA


iii) Front end loader 1 cum bucket capacity

hour
hour

6.000
6.000

#REF!
#REF!

#REF!
#REF!

#REF!

#REF!
#REF!

950.00

Machinery

iv) Tipper 10 tonne capacity


tonne.km
Add 10 per cent of cost of carriage to cover cost
of loading and unloading

c)

170.00

Mate
Mulia unskilled working with HMP, road sweeper,
paver and roller

450.00

v) Paver finisher Mechanical 100TPH

hour

6.000

#REF!

#REF!

iv) Smooth wheeled roller 8-10 tonnes weight


Material

hour

6.000

#REF!

#REF!

60/70 penetration grade of bitumen Bitumen @


14.60 kg per 10 sqm

tonne

14.965

#REF!

#REF!

13.2mm nominal size


@ 0.18 cum per 10 sqm

cum

184.500

#REF!

#REF!

11.2mm nominal size


@ 0.09 cum per 10 sqm

cum

92.250

#REF!

#REF!

Crushed stone chipping,13.2 mm to 5.6 mm @


0.27 cum per 10 sqm

#REF!
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e) Carriage & Royalty

7.5%

#REF!

60/70 penetration grade of bitumen Bitumen @


14.60 kg per 10 sqm

tonne

14.965

#REF!

#REF!

Description

Unit

Qnty

13.2mm nominal size


@ 0.18 cum per 10 sqm

cum

184.500

#REF!

#REF!

11.2mm nominal size


@ 0.09 cum per 10 sqm

cum

92.250

#REF!

#REF!

Sl. No

Rate

Amount

Crushed stone chipping,13.2 mm to 5.6 mm @


0.27 cum per 10 sqm

#REF!

89

Cost for 10250 sqm = a+b+c+d+e


Rate per sqm = (a+b+c+d)/10250

#REF!
#REF!

Add Labour Welfare Cess @ 1%

#REF!
Say

#REF!

170.00

40.80

Providing and laying seal coat sealing the voids in a


bituminous surface laid to the specified levels, grade
and cross fall using Type-A seal coat with 0.09cum of
6.7mm size chips and 9.80kg. of 60/70 penetration
grade of bitumen for 10sqm as per Clause No. 513 of
MoSRT&H specifications for Road & Bridge works
(4th Revision)
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
a)

b)

c)

Labour
Mate

each

0.240

Mulia unskilled
Machinery

each

6.000

Hydraulic self propelled chip spreader

hour

6.000

#REF!

#REF!

Tipper 5.5 cum capacity


Front end loader 1 cum bucket capacity
Bitumen pressure distributor
@ 1750 sqm per hour

hour
hour

6.000
6.000

#REF!
#REF!

#REF!
#REF!

hour

6.000

#REF!

#REF!

Smooth wheeled roller 8 -10 tonne weight


Material

hour

6.000

#REF!

#REF!

60/70 penetration grade of Bitumen


@ 9.80 kg per 10 sqm

tonne

10.045

#REF!

#REF!

cum

92.250

#REF!

#REF!

Crushed stone chipping of 6.7 mm size defined


as 100 per cent passing 11.2 mm sieve and
retained on 2.36 mm sieve applied @ 0.09 cum
per 10 sqm

150.00

900.00

#REF!
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e) Carriage & Royalty

7.5%

#REF!

60/70 penetration grade of Bitumen


@ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined
as 100 per cent passing 11.2 mm sieve and
retained on 2.36 mm sieve applied @ 0.09 cum
per 10 sqm

tonne

10.045

#REF!

#REF!

cum

92.250

#REF!

#REF!

Cost for 10250 sqm = a+b+c+d+e

#REF!

Rate per sqm = (a+b+c+d+e)/10250

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

#REF!

Sl. No

Description

Unit

Qnty

90

Providing and laying 6mm thick precoated seal coat


Type-B using 0.06cum of 6.7mm size chips and
6.80kg.of 60/70 penetration grade of bitumen for
10sqm with 100-120 TPH HMP by transporting the
Hot Mix to work site laying with a Mechanical Paver
Finisher to the required grade, level and alignment as
per Clause No. 513 of MoSRT&H specifications for
Road & Bridge works (4th Revision)

Rate

Amount

Mate
Mulia unskilled
Machinery

each
each

0.160
4.000

Batch type HMP 100-120 TPH


@ 75 tonne per hour

hour

2.000

#REF!

#REF!

hour
hour
tonne.km

2.000
2.000
104.00

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

Unit = sqm
Taking output = 7858 sqm
(47.16 cum = 104tonne)
a)

b)

Labour

Electric Generator Set 250 KVA


Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity

170.00
150.00

Add 10 per cent of cost of carriage to cover cost


of loading and unloading
Paver finisher Mechanical 100TPH
Smooth wheeled 8-10 tonnes capacity
c)

27.20
600.00

#REF!
hour
hour

2.000
2.000

#REF!
#REF!

#REF!
#REF!

tonne

5.343

#REF!

#REF!

cum

47.150

#REF!

#REF!

Material
60/70 penetration grade of Bitumen
@ 6.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined
as passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.06 cum per 10 sqm

#REF!
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e) Carriage & Royalty

7.5%

#REF!

60/70 penetration grade of Bitumen


@ 6.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined
as passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.06 cum per 10 sqm

tonne

5.343

#REF!

#REF!

cum

47.150

#REF!

#REF!

Cost for 7858 sqm = a+b+c+d+e

#REF!

Rate per sqm = (a+b+c+d)/7858

#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

91

#REF!

Binding road surface with sand 6mm thick (labour


only)
Unit = 100 Sqm
Taking output = 93 sqm
a) Labour
Man Mulia
b) Materials
Sand (93 x0.006 = 0.558 cum)

each

0.300

150.00

45.00

cum

0.558

#REF!

#REF!

Description

Sl. No

Unit

Qnty

Rate

Amount
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


d) carriage & Royalty

7.5%

#REF!

Sand

cum

0.558

#REF!

Cost per 93 Sqm = a+b+c+d+e


Rate per 1 Sqm = (a+b+c+d+e) x 100 / 93

#REF!
#REF!

Add Labour Welfare Cess @ 1%

#REF!
or say

92

#REF!

#REF!

Drainage Spouts complete as per drawing and


Technical specification
Unit = 1 No.
Taking output = 1 No.

a.

Material
Corrosion resistant Structural steel including 5
percent wastage

b.

kg

4.00

#REF!

#REF!

GI Pipe 100 mm dia

mtr

6.00

400.00

2400.00

GI Pipe 10 mm dia

Nos

6.00

10.00

60.00

Galvanised MS flat clamp

Nos

2.00

20.00

40.00

Mate

Nos

0.02

170.00

3.40

Skilled (Blacksmith, welder etc.)

Nos

0.02

190.00

3.80

Mazdoor

Nos

0.02

150.00

3.00

Mate

Nos

0.01

170.00

1.70

Mason

Nos

0.01

190.00

1.90

Mazdoor

Nos

0.20

150.00

30.00

Labour for fabrication

For fixing in position

c.

Add @ 5percent of cost of material and labour for


electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.

#REF!
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Rate per 6 mtr (a+b+c+d)

7.5%

#REF!
#REF!
#REF!

Rate per 1 mtr (a+b+c+d)


Add Labour Welfare Cess @ 1%

#REF!
#REF!

For each number of length - 0.60 m


105 Cutting of trees, including cutting of trunks,
branches and removal of stumps, roots, stacking of
serviceable material with all lifts and upto a lead of
1000 mtrs and sand filling in the depression / pit as
per Clause 201 MoRT & H Specifications for Road &
Bridge works (Latest Revision).
Unit = Each
a.

b.

Labour
Mate

Each

0.08

170.00

13.60

Mulia unskilled

Each

2.00

150.00

300.00

Hour

0.40

#REF!

#REF!

Machinaries
Tractor- trolley

#REF!

Description

Sl. No

Unit

Qnty

Rate

Overhead charges @ 7.5%

7.5%

Contractor's Profit @ 7.5%

7.5%

#REF!
#REF!

Add Labour Welfare Cess @ 1%

#REF!
#REF!

Rate per each (a+b+c)


111

Amount

Conveying from stack and laying sub-base in layers


watering and compacting to the required density in
O.M.C with PRR.
Unit = Cum
Taking output = 2.83 cum
a) Labour
Man Mulia for removing from stacks spreading and
rolling.

each

1.000

Women Mulia for watering & conveyance, etc.


b) Machinery

each

1.500

Add hire and running charges of PRR for


consolidation considering 425Cum of out turn with
PRR per day (8 hours) =
2.83 x 8 x 269.00 /425

hour

0.05327

150.00
150.00
150.00
#REF!

225.00
#REF!

#REF!
Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Cost per 2.83 Cum = a+b+c+d
Rate per Cum = (a+b+c+d) / 2.83

7.5%

#REF!
#REF!

Say

#REF!
#REF!
#REF!

Add Labour Welfare Cess @ 1%


a

GSB with Gravel Moorum


Cost of gravel

Cum

1.28

#REF!

#REF!

Labour charges for compaction


OH charges @ 7.5% on Gravel
Contractor profit @ 7.5% on Gravel

Cum

1.00

#REF!

#REF!
#REF!

Carriage & Royalty of Gravel


Rate per cum

Cum

#REF!
Or Say

112

PCC M-15 in pier & Abutment foundation


Basic rate of PCC M-15
Cum
Add cost of dewatering S/R 2006 P-121 Item-11 57.60

#REF!

PCC M-15 in pier & Abutment upto bed level


Basic rate of PCC M-15
Cum
Add cost of dewatering S/R 2006 P-121 Item-11 57.60 sqm

1.00
1.00

#REF!
57.60

Add for shuttering S/R 2006 P-121 Item 12 106.20

3.00

106.20

sqm

PCC M-15 in pier & Abutment Above bed level


Basic rate of PCC M-15
Add for shuttering as above

#REF!
57.60
#REF!
#REF!

Add Labour Welfare Cess @ 1%


Rate per cum
c

#REF!
#REF!
#REF!

PCC works M-15 grade using 40 mm down graded


hard granite crusher aggregates including watering,
curing, centering, shuttering & finishing the exposed
surface, cost of all materials & labour etc. complete.

Add Labour Welfare Cess @ 1%


Rate per cum
b

#REF!

#REF!
57.60
289.64
#REF!
#REF!

Cum
sqm

1.00
3.00

#REF!
361.13

#REF!
289.64

Description

Sl. No

Unit

Qnty

Rate

Add Labour Welfare Cess @ 1%


Rate per cum

Amount
#REF!
#REF!

114 Filling in foundatin and plinth with sand watered and


rammed
i)

Labour
Man Mulia
cost of sand

Each
cum

12.36
120

150.00
#REF!

1854.00
#REF!
#REF!

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
Royalty & Lead of Sand

10

7.5%

Per One Cum

#REF!
#REF!
#REF!

Add Labour Welfare Cess @ 1%


Rate for 1 cum

Or Say

#REF!
#REF!

cum

7.5%
120

#REF!
#REF!

Dismantling of Cement Concrete Grade M-15 & M- 20


including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres Unit =
cum Taking output = 1.25 cum ARP.197 item no.5
a)

Labour
Mate

Each

0.05

170.00

8.50

Mulia unskilled for dismantling and loading

Each

1.25

150.00

187.50
196.00

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
Cost per 1.25Cum

7.5%
7.5%

14.70
14.70
225.40

Rate per Cum = (a+b+c)/1.25

180.32

Add Labour Welfare Cess @ 1%


Or Say
10

1.80
182.12

Dismantling of Prestressed / Reinforced cement


concrete grade M-20 & above including T&P and
scaffolding wherever necessary, sorting the
dismantled material, disposal of unserviceable
material and stacking the serviceable material with
all lifts and lead of 1000 metres Unit = cum Taking
output = 1.25 cum ARP.197 item no.5
a)

Labour
Mate

Each

0.15

Black smith 2nd class

Each

0.25

Mulia unskilled for dismantling and loading

Each

3.5

Tractor / trolley

hr

0.27

170.00
190.00

25.50

150.00
231.00

525.00

47.50
62.37

Description

Sl. No

Unit

Qnty

Rate

Amount
660.37

Overhead charges @ 7.5%


Contractor's Profit @ 7.5%
Cost per 1.25Cum

7.5%
7.5%

49.53
49.53
759.43

Rate per Cum = (a+b+c)/1.25

607.54

Add Labour Welfare Cess @ 1%


Or Say
10

6.08
613.62

Removal of existing cement concrete wearing coat


including its disposal complete as per Technical
Specification without causing any detrimental effect
to any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000
m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a)

Labour
Mate

Each

0.06

170.00

10.20

Mulia unskilled for dismantling and loading

Each

1.00

150.00

150.00

hr

1.00

#REF!

hr

0.50

#REF!

Air Compressor 250 cfm with pneumatic


breaker/jack hammer along with accessories.
Tractor / trolley

#REF!
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Cost for 10 sqm

7.5%

#REF!
#REF!

Rate per Sqm = (a+b+c)/10

#REF!

Add Labour Welfare Cess @ 1%


Or Say
10

#REF!

#REF!
#REF!

Dismantling of Granular courses of flexible


pavements and disposal of dismantled materials up to
a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum Taking output = 1 cum
a)

Labour
Mate

Each

0.04

170.00

6.80

Mulia unskilled for dismantling and loading

Each

150.00

Tractor

hour

0.33

150.00
#REF!

#REF!
#REF!

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


Rate per Cum = (a+b+c)

7.5%

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Providing and laying Flooring complete as per


drawing and Technical specifications laid over
cement concert bedding.
Rubble stone laid in cement mortar 1:3

Unit = cum
Taking output = 1 cum
a)
Cement mortor 1:3 (Rate as in Item 12.6 subanalysis)

cum

0.33

#REF!

#REF!

Description

Sl. No

b)
Add for cement concrete bedding (M15
Nominal mix) vide Item 12.8 (A) excluding OH &
CP . Quantity shall be adopted as per design
( Assume Rubble stone Flooring thickness 300mm
and cement concrete bedding thickness 100mm)

Unit
cum

Qnty
0.33

Rate
#REF!

Add 1 per cent of cost to account for


excavation for preparation of bed.
c)

Amount
#REF!

#REF!

Material

d)

Stone
Stone Spalls
Labour

cum
cum

1.00
0.20

#REF!
#REF!

#REF!
#REF!

Mate
Mason
Mazdoor (for laying stones, filling of quarry
spalls)

day
day
day

0.08
0.50
1.50

170.00
205.00

13.60
102.50
225.00

150.00

Overhead charges @ 7.5%

7.5%

#REF!

Contractor's Profit @ 7.5%


e)
Carriage & Royalty

7.5%

#REF!

Stone & Spalls

cum

1.20

#REF!

Rate per cum = (a+b+c+d+e+f)

#REF!
#REF!

Add Labour Welfare Cess @ 1%


Or Say

#REF!
#REF!

Providing & fixing 20 mm thick compressible fibre


board in expansion joint complete as per drawing &
Technical Specification.

Unit = Running meter


Taking output = 12 m
a)

Labour

For carrying, placing & fixing.


Mate

day

0.008

170.00

1.36

Mazdoor
Mazdoor (Skilled)

day
day

0.10
0.10

150.00
205.00

15.00
20.50

sqm

3.00

1200.00

3600.00

b)

Material

20 mm thick compressible fibre board 12 m long x 25


cm deep.
Area = 12 x 0.25 = 3 sqm
Overhead charges @ 7.5%
Contractor's Profit @ 7.5%

7.5%
7.5%

272.76
272.76

Cost for 12 m = (a+b+c+d)


Rate per m = (a+b+c+d)/12

4182.38
348.53

Add Labour Welfare Cess @ 1%


Or Say

3.49
352.02

Sl. No

Description

Junior Engineer
East (R&B) Section No-I,
Bhawanipatna

Assistant Engineer
Kalahandi East(R&B) SubDivn
Bhawanipatna

Unit

Qnty

Rate

Executive Engineer
Kalahandi (R&B) Division,
Bhawanipatna

Amount

LEAD STATEMENT
Serial
no

Description of materials

Unit

Lead in KM

Name of Quarry

Conveyance mode Lead cost in Rs

Royalty

Carriage +
Royalty

Granite stone product

Cum

26

Bhabandha

By Truck

304.00

98.78

402.78

Crusher product

Cum

26

Bhabandha

By Truck

304.00

98.78

402.78

Sand for Mortar work

Cum

Purushottampur

By Truck

136.00

27.44

163.44

Sand for other work

Cum

Purushottampur

By Truck

136.00

27.44

163.44

Cement

Qtl

39

Berhampur

By Truck

40.20

0.00

40.20

Steel, iron grills

Qtl

448

Bhubaneswar

By Truck

303.17

0.00

303.17

Moorum

Cum

10

Bhabandha

By Truck

27.44

203.44

Bitumen

Mt

415

Vizag

By Truck

2820.50

0.00

2820.50

Hume pipe & bulky materials

Trip

17

Berhampur

By Truck

219.20

0.00

219.20

176.00

Certified that the leads provided in this estimate are correct and minimum to the best of my knowledge.

You might also like