5. Proof of Property
Contract of Lease
Contract of Sale
Those are the usual application forms you need gather and prepare.
4. Present the Order of Payment at the Treasurers Office and pay the fees. Fees range from
P6,000 and above depending on the your construction size, municipality location and the
assessment plan. Fees in the provinces are usually cheaper than in the cities.
5. Photocopy the OR (Official Receipt) and bring a copy to the Office of the Building Official
releasing section.
6. After 5 working days, go back to the releasing section of the Office of the Building Official
and claim your building permit.
Source: http://philpad.com/building-permit-requirements-fees-application-forms-andprocedure/How to get building permit in the Philippines?