Im sharing you here the requirements, fees, and application procedure for the

issuance of building permit in the country

Why do you need a building permit?


It is simply in compliance with the proper construction of a house or a building following the
requirements set by law or the National Building Code. Of course you want to make sure all the
proper technical, mechanical, electrical, and structural plans for the construction of the building
are met.
In addition, if you build a house or a building without a permit from your
municipality, construction will be stopped until a permit has been issued or
released. Youll receive a strict notice to apply for a permit.

Building Permit Requirements in the Philippines


1. Properly filled-up application forms duly signed and sealed by engineers
concerned:

Building Permit Forms (5 copies)

Electrical Permit Forms (3 copies)

Sanitary Permit Forms (3 copies)

2. Five (5) complete sets of Detailed Plans


3. For construction of two-storey building:

Structural Design Analysis signed and sealed by Civil Engineer at every


page

4. For construction of more than two-storey building:

Boring and Plate Load Test

Seismic Analysis

5. Proof of Property

Photocopy of Transfer Certificate if Title (TCT)

Photocopy of tax Declaration of Property-lot (Certified True Copy) 5 copies

Photocopy of Current Tax Receipt (5 copies)

6. If property is not registered under the name of the applicant:

Submit 5 copies of any of the following:

Contract of Lease

Contract of Sale

Affidavit of Consent of the Lot Owner for the construction of building/house

Deed of Absolute Sale

7. Permit Billboard (0.60 X 0.90 Plywood with the following contents):


8. Bill of Materials and Specification (5 copies) signed and sealed by an
engineer or an architect at every page
9. Locational Clearance
10.Photocopy of PTR # and PRC license of all concerned engineers and architects
11.Clearance from the DPWH if the construction is located along National
Highway
12.DOLE Clearance

Those are the usual application forms you need gather and prepare.

How to get Building Permit in the Philippines Procedures


1. Get a Requirements-Checklist and application forms from your municipals office (Office of
the Building Official). Your architect mostly knows them but you need to get the documents
from your municipals office since every form bears the municipals seal. Your architect and
engineers then will be the ones who will fill them up.
2. Go to the Office of the Building Official and submit the papers. They will tell you then where
to go next, in this case Assessors Office. If youre in the city hall, they usually have windows
where you have to submit each folder of each set of forms. But in the provinces, each section are
usually close to each other if not on the same unit.
3. You will be issued Acknowledgement Slip which bears the date of the status of your
application. Its usually around 10 working days.
If your application is approved and in compliant with the National Building Code, youll be
given an Order of Payment to pay the necessary building permit fees.

4. Present the Order of Payment at the Treasurers Office and pay the fees. Fees range from
P6,000 and above depending on the your construction size, municipality location and the
assessment plan. Fees in the provinces are usually cheaper than in the cities.
5. Photocopy the OR (Official Receipt) and bring a copy to the Office of the Building Official
releasing section.
6. After 5 working days, go back to the releasing section of the Office of the Building Official
and claim your building permit.