ENERGY If youre considering building a small This fact sheet will help you determine
hydropower system on water flowing whether a small hydropower system will
through your property, you have a long work for your power needs and whether
tradition from which to draw your inspi- your location is right for hydropower tech-
ration. Two thousand years ago, the nology. It will also explain the basic system
Greeks learned to harness the power of components, the need for permits and
running water to turn the massive wheels water rights, and how you might be able to
that rotated the shafts of their wheat flour sell the excess electricity you generate.
grinders. And in the hydropower heyday
of the 18th century, thousands of towns Uses of Hydropower
and cities worldwide were located around
In the United States today, hydropower
small hydropower sites.
projects provide 81 percent of the nations
renewable electricity generation and
Today, small hydropower projects offer
about 10 percent of the nations total elec-
emissions-free power solutions for many
tricity. Thats enough to power 37.8 mil-
remote communities throughout the
worldsuch as those in Nepal, India, lion homes, according to the National
China, and Peruas well as for highly Hydropower Association.
industrialized countries, like the United
States.

Duane Hippe, NREL/PIX 04410

This small-scale hydropower system is helping an Alaskan community save money on their
electricity.

NT OF
ME EN
RT
This document was produced for the U.S. Department of Energy (DOE) by the National Renewable Energy Laboratory (NREL), a DOE national laboratory. The
A

ER
DEP

GY

document was produced by the Information and Outreach Program at NREL for the DOE Office of Energy Efficiency and Renewable Energy. The Energy Efficiency
I CA
U N IT

and Renewable Energy Clearinghouse (EREC) is operated by NCI Information Systems, Inc., for NREL / DOE. The statements contained herein are based on
information known to EREC and NREL at the time of printing. No recommendation or endorsement of any product or service is implied if mentioned by EREC.
ER
ED

ST A
AT E S OF
Printed with a renewable-source ink on paper containing at least 50% wastepaper, including 20% postconsumer waste
The vast majority of the hydropower pro- or turbine. The moving water rotates the
duced in the United States comes from wheel or turbine, which spins a shaft. The
large-scale projects that generate more motion of the shaft can be used for
than 30 megawatts (MW)enough elec- mechanical processes, such as pumping
tricity to power nearly 30,000 households. water, or it can be used to power an alter-
Small-scale hydropower systems are those nator or generator to generate electricity.
that generate between .01 to 30 MW of This fact sheet will focus on how to
electricity. Hydropower systems that gen- develop a run-of-the-river project.
erate up to 100 kilowatts (kW) of electricity
are often called microhydro systems. Most of Is Hydropower Right for You?
A 10 kW system can the systems used by home and small busi-
Of course to build a small hydropower
ness owners would qualify as microhydro
system, you need access to flowing water.
provide enough power systems. In fact, a 10 kW system generally
A sufficient quantity of falling water must
can provide enough power for a large
be available, which usually, but not
for a large home, a home, a small resort, or a hobby farm.
always, means that hilly or mountainous
sites are best.
small resort, or a How Hydropower Works
Hydropower systems use the energy in Next youll want to determine the amount
hobby farm. flowing water to produce electricity or of power that you can obtain from the
mechanical energy. Although there are flowing water on your site. The power
several ways to harness the moving water available at any instant is the product of
to produce energy, run-of-the-river systems, what is called flow volume and what is
which do not require large storage reser- called head.
voirs, are often used for microhydro, and
sometimes for small-scale hydro, projects. Determining head
For run-of-the-river hydro projects, a por- Head is the vertical distance that water
tion of a rivers water is diverted to a falls. Its usually measured in feet, meters,
channel, pipeline, or pressurized pipeline or units of pressure. Head also is a func-
(penstock) that delivers it to a waterwheel tion of the characteristics of the channel or
pipe through which it flows.

Most small hydropower sites are catego-


rized as low or high head. The higher the
head the better because youll need less
water to produce a given amount of
Intake power, and you can use smaller, less
expensive equipment. Low head refers to
Canal
a change in elevation of less than 10 feet (3
meters). A vertical drop of less than 2 feet
Forebay (0.6 meters) will probably make a small-
scale hydroelectric system unfeasible.
However, for extremely small power gen-
eration amounts, a flowing stream with as
little as 13 inches of water can support a
submersible turbine, like the type used
Penstock originally to power scientific instruments
towed behind oil exploration ships.

When determining head, you need to con-


sider both gross head and net head. Gross
Powerhouse head is the vertical distance between the
top of the penstock that conveys the water
under pressure and the point where the
water discharges from the turbine. Net
head equals gross head minus losses due
In this microhydropower system, water is diverted into the penstock. Some to friction and turbulence in the piping.
generators can be placed directly into the stream.

2
hose, water may continue to move
Forebay through the hose after both ends of the
hose are actually level. You may wish to
subtract an inch or two (2 to 5 centimeters)
from each measurement to account for
this. It is best to be conservative in these
preliminary head measurements.
Head
Powerhouse
If your preliminary estimates look favor-
able, you will want to acquire more accu-
rate measurements. The most accurate way
to determine head is to have a professional
survey your site. But if you know you
have an elevation drop on your site of sev-
eral hundred feet, you can use an aircraft
Turbine
altimeter. You may be able to buy, borrow,
or rent an altimeter from a small airport or
Head is the vertical distance the water falls. Higher heads require less water to flying club. A word of caution, however:
produce a given amount of power. while using an altimeter might be less
expensive than hiring a professional sur-
To get a rough estimate of the vertical dis- veyor, your measurement will be less accu-
tance, you can use U.S. Geological Survey rate. In addition, you will have to account
maps of your area or the hose-tube method. for the effects of barometric pressure and
The hose-tube method involves taking calibrate the altimeter as necessary.
stream-depth measurements across the
width of the stream you intend to use for Determining flow
your systemfrom the point at which you The quantity of water falling is called
want to place the penstock to the point at flow. Its measured in gallons per minute,
which you want to place the turbine. You cubic feet per second, or liters per second.
will need an assistant; a 20 to 30 foot (6 to The easiest way to determine your
9 meters) length of small-diameter garden streams flow is to obtain data from local
hose or other flexible tubing; a funnel; and offices of the U.S. Geological Survey, the
a yardstick or measuring tape. U.S. Army Corps of Engineers, the U.S.
The quantity of water Department of Agriculture, your countys
Stretch the hose or tubing down the engineer, or local water supply or flood
falling is called flow. stream channel from the point that is the control authorities. If you cant obtain
most practical elevation for the penstock existing data, youll need to conduct your
intake. Have your assistant hold the own flow measurements.
upstream end of the hose, with the funnel
in it, underwater as near the surface as You can measure flow using the bucket
possible. Meanwhile, lift the downstream method, which involves damming your
end until water stops flowing from it. stream with logs or boards to divert its
Measure the vertical distance between flow into a bucket or container. The rate at
your end of the tube and the surface of the which the container fills is the flow rate.
water. This is the gross head for that sec- For example, a 5-gallon bucket that fills in
tion of stream. Have your assistant move 1 minute means that your streams water
to where you are and place the funnel at is flowing at 5 gallons per minute.
the same point where you took your mea-
surement. Then walk downstream and Another way to measure flow involves
repeat the procedure. Continue taking measuring stream depths across the width
measurements until you reach the point of the stream and releasing a weighted-
where you plan to site the turbine. float upstream from your measurements.
You will need an assistant; a tape measure;
The sum of these measurements will give a yardstick or measuring rod; a weighted-
you a rough approximation of the gross
head for your site. Note: due to the
waters force into the upstream end of the

3
float, such as a plastic bottle filled halfway restricted on the amount of water you
with water; a stopwatch; and some graph can divert from your stream at certain
paper. With this equipment you can calcu- times of the year, use the average flow
late flow for a cross section of the during the period of the highest expected
streambed at its lowest water level. electricity demand.

First, select a stretch of stream with the Estimating power output


straightest channel and the most uniform There is a simple equation you can use to
depth and width possible. At the narrow- estimate the power output for a system
est point, measure the width of the stream. with 53 percent efficiency, which is repre-
Then, holding the yardstick vertically, sentative of most small hydropower sys-
walk across the stream and measure the tems. Simply multiply net head (the
water depth at one-foot increments. To vertical distance available after subtract-
help with the process, stretch a string or ing losses from pipe friction) by flow (use
Whatever the upfront rope upon which the increments are U.S. gallons per minute) divided by 10.
marked across the stream width. Plot the That will give you the systems output in
costs, a hydroelectric depths on graph paper to give yourself a watts (W). The equation looks this: net
cross-sectional profile of the stream. Then head [(feet) x flow (gpm)]/10 = W.
system will typically determine the area of each section by
calculating the areas of the rectangles Economics of a small system
last a long time and (area = length x width) and right triangles
If you determine that your site is feasible
(area = 12 base x height) in each section.
is relatively mainte- for a small hydropower system, the next
obvious step is to determine whether it
Next, from the same point where you
nance free. measured the streams width, mark a
makes sense economically to undertake
building a system.
point at least 20 feet upstream. Release the
weighted-float in the middle of the stream
Add up all the estimated costs of develop-
and record the time it takes for the float to
ing and maintaining the site over the
travel to your original point downstream.
expected life of your equipment, and
Dont let the float drag along the bottom of
divide the amount by the systems capac-
the streambed. If it does, use a smaller float.
ity in watts. This will tell you how much
the system will cost in dollars per watt.
Divide the distance between the two
Then you can compare that to the cost of
points by the float time in seconds to get
utility-provided power or other alterna-
flow velocity in feet per second. The more
tive power sources. Whatever the upfront
times you repeat this procedure, the more
costs, a hydroelectric system will typically
accurate your flow velocity measurement
last a long time and, in many cases, main-
will be.
tenance is not expensive.
Finally, multiply the average velocity by
In addition, there are a variety of financial
the cross-sectional area of the stream.
incentives available on the state, utility,
Then multiply your result by a factor that
and federal level for investments in
accounts for the roughness of the stream
renewable energy systems. They include
channel (0.8 for a sandy streambed, 0.7 for
income tax credits, property tax exemp-
a bed with small to medium sized stones,
tions, state sales tax exemption, loan pro-
and 0.6 for a bed with many large stones).
grams, and special grant programs,
The result will give you the flow rate in
among others. Contact your state energy
cubic feet or meters per second.
office to see if your project may qualify for
any incentives (see NASEO and DSIRE in
Stream flows can be quite variable over a
Resources).
year, so the season during which you take
flow measurements is important. Unless
youre considering building a storage
reservoir, you can use the lowest average
flow of the year as the basis for your sys-
tems design. However, if youre legally

4
headrace, forebay, and water conveyance
Environmental Issues (channel, pipeline, or penstock).
Large-scale dam hydropower projects are
often criticized for their impacts on The headrace is a waterway running paral-
wildlife habitat, fish migration, and water lel to the water source. A headrace is
flow and quality. However, small, run-of- sometimes necessary for hydropower sys-
the-river projects are free from many of
tems when insufficient head is provided.
the environmental problems associated
with their large-scale relatives because They often are constructed of cement
they use the natural flow of the river, and or masonry. The headrace leads to the fore-
thus produce relatively little change in the bay, which also is made of concrete or
stream channel and flow. The dams built masonry. It functions as a settling pond for
for some run-of-the-river projects are very
large debris which would otherwise flow
small and impound little waterand
many projects do not require a dam at all. into the system and damage the turbine.
Thus, effects such as oxygen depletion, Water from the forebay is fed through the
increased temperature, decreased flow, trashrack, a grill that removes additional
and rejection of upstream migration aids debris. The filtered water then enters
like fish ladders are not problems for
through the controlled gates of the spill-
many run-of-the-river projects.
way into the water conveyance, which
funnels water directly to the turbine or
waterwheel. These channels, pipelines, or
System Components penstocks can be constructed from plastic
Small run-of-the-river hydropower sys- pipe, cement, steel and even wood. They
tems consist of these basic components: often are held in place above-ground by
support piers and anchors.
Water conveyancechannel, pipeline,
or pressurized pipeline (penstock) that Dams or diversion structures are rarely
delivers the water used in microhydro projects. They are an
Turbine or waterwheeltransforms the added expense and require professional
energy of flowing water into rotational assistance from a civil engineer. In addi-
Dams or diversion energy tion, dams increase the potential for envi-
Alternator or generatortransforms the ronmental and maintenance problems.
structures are rarely rotational energy into electricity
Regulatorcontrols the generator Turbines and waterwheels
used in microhydro Wiringdelivers the electricity. The waterwheel is the oldest hydropower
system component. Waterwheels are still
projects. Many systems also use an inverter to con- available, but they arent very practical for
vert the low-voltage direct current (DC) generating electricity because of their slow
electricity produced by the system into speed and bulky structure.
120 or 240 volts of alternating current
(AC) electricity (alternatively you can buy Turbines are more commonly used today
household appliances that run on DC elec- to power small hydropower systems. The
tricity). Some systems also use batteries to moving water strikes the turbine blades,
store the electricity generated by the sys- much like a waterwheel, to spin a shaft. But
tem, although because hydro resources turbines are more compact in relation to
tend to be more seasonal in nature than their energy output than waterwheels. They
wind or solar resources, batteries may not also have fewer gears and require less mate-
always be practical for hydropower sys- rial for construction. There are two general
tems. If you do use batteries, they should classes of turbines: impulse and reaction.
be located as close to the turbine as possi-
ble, because it is difficult to transmit low- Impulse
voltage power over long distances.
Impulse turbines, which have the least com-
plex design, are most commonly used for
Channels, storage, and filters
high head microhydro systems. They rely
Before water enters the turbine or water- on the velocity of water to move the turbine
wheel, it is first funneled through a series
of components that control its flow and fil-
ter out debris. These components are the

5
wheel, which is called the runner. The most
common types of impulse turbines include
the Pelton wheel and the Turgo wheel.

The Pelton wheel uses the concept of jet

Jack Rabbit Marine, NREL/PIX 09976


force to create energy. Water is funneled
into a pressurized pipeline with a narrow
nozzle at one end. The water sprays out of
the nozzle in a jet, striking the double-
cupped buckets attached to the wheel. The
impact of the jet spray on the curved
buckets creates a force that rotates the
wheel at high efficiency rates of 70 to 90
percent. Pelton wheel turbines are avail- The submersible Jack Rabbit turbine was
able in various sizes and operate best originally designed to power scientific
instruments during marine oil exploration
under low-flow and high-head conditions.
expeditions.

The Turgo impulse wheel is an upgraded


Another turbine option is called the Jack
version of the Pelton. It uses the same jet
Rabbit (sometimes referred to as the
spray concept, but the Turgo jet, which is
Aquair UW Submersible Hydro Genera-
half the size of the Pelton, is angled so that
tor). The Jack Rabbit is the drop-in-the-
the spray hits three buckets at once. As a
creek turbine, mentioned earlier, that can
result, the Turgo wheel moves twice as
generate power from a stream with as lit-
fast. Its also less bulky, needs few or no
tle as 13 inches of water and no head. Out-
gears, and has a good reputation for trou-
put from the Jack Rabbit is a maximum of
ble-free operations. The Turgo can operate
100 W, so daily output averages 1.5 to 2.4
under low-flow conditions but requires a
kilowatt-hours, depending on your site.
medium or high head.
Reaction
Reaction turbines, which are highly effi-
cient, depend on pressure rather than
velocity to produce energy. All blades of
the reaction turbine maintain constant
contact with the water. These turbines are
often used in large-scale hydropower sites.
Because of their complexity and high cost,
they arent usually used for microhydro
projects. An exception is the propeller tur-
bine, which comes in many different
designs and works much like a boats pro-
peller. Propeller turbines have three to six
usually fixed blades set at different angles
aligned on the runner. The bulb, tubular,
and Kaplan tubular are variations of the
propeller turbine. The Kaplan turbine,
which is a highly adaptable propeller sys-
tem, can be used for microhydro sites.

Pumps as substitutes for turbines


Conventional pumps can be used as sub-
stitutes for hydraulic turbines. When the
Pelton wheels, like this one, can be purchased with one or more nozzles. Multi- action of a pump is reversed, it operates
nozzle systems allow a greater amount of water to impact the runner, which can like a turbine. Since pumps are mass pro-
increase wheel output. duced, youll find them more readily
available and less expensive than turbines.

6
However, for adequate pump performance, Utilities in many states now offer a special
your microhydro site must have fairly incentive to small power providers called
constant head and flow. Pumps are also net metering. Net metering is a billing
less efficient and more prone to damage. method that allows you, as a small power
provider, to be billed only for the net
Obtaining a Permit and amount of electricity you consume over a
Water Rights billing cycle. You effectively get the same
You can usually sell value for the output of your system as you
If your hydropower system will have min- pay for electricity from the utility, up to
imal impact on the environment, and you the point where excess power is produced.
any excess power arent planning to sell power to a utility, Any excess power from your system is
theres a good chance that the process you then bought by the utility, generally at
you produce to your must go through to obtain a permit wont the wholesale rate. For detailed informa-
be too complex. Locally, your first point tion on net metering, contact your states
local utility. of contact should be the county engineer. utility regulatory agency, typically the
Your state energy office may be able to public utility commission or public service
provide you with advice and assistance commission.
as well (see NASEO in Resources). In
addition, youll need to contact the Fed- Aside from the advantages associated
eral Energy Regulatory Commission and with selling power back to your utility,
the U.S. Army Corps of Engineers (see grid-connected systems also render addi-
Resources). tional electricity storage capacity, such as a
battery bank, unnecessary. The grid will
Youll also need to determine how much supply power when your hydropower
water you can divert from your stream system cant meet all your power require-
channel. Each state controls water rights ments. However, if you live in an area
and you may need a separate water right where you can obtain higher rates for pro-
to produce power, even if you already duction during peak demand periods or
have a water right for another use. for so-called green power, it might be
Grid-connected
economical to include energy storage
Selling the Power You Produce capacity to dispatch power to your utility
systems render
The great thing about producing your on demand.
additional electricity own power is that you can usually sell any
excess power to your local utility. If you A Clean Energy Future
storage capacity, decide to sell, youll need to contact the By investing in a small hydropower system,
utility to find out application procedures, you can reduce your exposure to future fuel
such as a battery metering and rates, and the equipment the shortages and price increases, and help
utility requires to connect your system to reduce air pollution. There are many fac-
bank, unnecessary. the electricity grid (it is generally best to tors to consider when buying a system, but
do this before you purchase your hydro with the right site and equipment, careful
system). If your utility does not have an planning, and attention to regulatory and
individual assigned to deal with grid-con- permit requirements, small hydropower
nection requests, try contacting your pub- systems can provide you a clean, reliable
lic utilities commission, state utility source of power for years to come.
consumer advocate group, state consumer
representation office, or state energy
office. In general, utilities require a grid-
interactive inverter listed by a safety-test-
ing and certification organization such as
Underwriters Laboratories, and the ability
to disconnect your system from the util-
itys grid in the event of a power outage.
The latter is necessary to prevent utility
personnel working on the outage from
accidentally being electrocuted.

7
Resources
The following are sources of additional information on U.S. Army Corps of Engineers
small hydropower systems and related topics. The list is 441 G. St., N.W.
not exhaustive, nor does the mention of any resource Washington, DC 20426
constitute a recommendation or endorsement. Phone: (202) 761-0008
Web site: www.usace.army.mil
Energy Efficiency and Renewable Energy Can provide you with contact information for your local dis-
Clearinghouse (EREC) trict office.
P.O. Box 3048
Merrifield, VA 22116 Volunteers in Technical Assistance (VITA)
Phone: 1-800-DOE-EREC (1-800-363-3732) 1600 Wilson Blvd., Suite 710
Fax: (703) 893-0400 Arlington, VA 22209
E-mail: doe.erec@nciinc.com Phone: (703) 276-1800
Web site: www.eren.doe.gov/consumerinfo/ Fax: (703) 243-1865
E-mail: vita@vita.org
Energy experts and information specialists at EREC provide
Web site: www.vita.org
free general and technical information to the public on many
topics and technologies pertaining to energy efficiency and Provides publications on hydropower systems, including
renewable energy. design guides for low-cost turbines and waterwheels.

Organizations Web Sites


Federal Energy Regulatory Commission (FERC) Database of State Incentives for Renewable Energy
Public Reference Room (DSIRE)
888 1st St., N.E. Web site: www.dsireusa.org
Washington, DC 20426 Features information on state, utility, and local government
Phone: (202) 208-1371 financial and regulatory incentives, programs, and policies
Fax: (202) 208-2320 designed to promote renewable energy technologies.
Web site: www.ferc.gov U.S. Department of Energy Hydropower Program
Licenses and inspects private, municipal, and state hydro Web site: hydropower.inel.gov
projects. Provides information on current research and development of
hydropower technologies, as well as environmental issues.
National Association of State Energy Officials
(NASEO) Energy Efficiency and Renewable Energy Network
1414 Prince St., Suite 200 (EREN)
Alexandria, VA 22314 U.S. Department of Energy
Phone: (703) 299-8800 Web site: www.eren.doe.gov
Fax: (703) 299-6208 A comprehensive online resource for DOEs energy efficiency
E-mail: info@naseo.org and renewable energy information.
Web site: www.naseo.org
Home Power
Provides current contact information for state energy offices, Web site: www.homepower.com
including links to their Web sites.
An online journal providing information on renewable energy
National Hydropower Association (NHA) power systems for the home.
One Massachusetts Ave., N.W., Suite 850
Washington, DC 20001 Microhydro
Web site: www.geocities.com/wim_klunne/hydro/
Phone: (202) 682-1700
index.html
Fax: (202) 682-9478
E-mail: info@hydro.org Features a discussion group and literature on small
Web site: www.hydro.org hydropower.

Seeks to secure hydropowers place as an emissions-free, Books, Pamphlets, and Reports


renewable, and reliable energy source. Micro-Hydro Design Manual: A Guide to Small-Scale
Solar Energy International (SEI) Hydropower Schemes, A. Harvey et. al, Intermediate
P.O. Box 715 Technology, 1993.
Carbondale, CO 81623 Mini-Hydropower, ed. J. Tong, John Wiley and Son, Ltd.,
Phone: (970) 963-8855 1997.
Fax: (970) 963-8866
E-mail: sei@solarenergy.org Motors as Generators for Micro Hydropower, N. Smith,
Web site: www.solarenergy.org Intermediate Technology Development Group, London,
1995. Available from Stylus Publishing, Inc., P.O. Box
Offers workshops on how to design fully functional microhy-
605, Herndon, VA 20172-0605, (703) 661-1581, or
dro systems.