Professional Documents
Culture Documents
J.C. Becket
Project Civil Engineer For SGI consulting.
and
A.O. Ilori
Civil Engineer, Federal Airports of Nigeria. Civil Engineering Department,
Calabar Airport, Calabar. Nigeria
e-mail bidemiini@yahoo.com
ABSRACT
A maintained load test was carried out on randomly selected grouted small
diameter steel end piles at a water treatment plant site in Calabar, southeastern
Nigeria. At a load of 75tons, which is about one and half times the design
working load of the pile, settlement value obtained was 3.75mm and 2.95mm for
the filter and clarifier respectively. The maximum estimated settlement for the
pile group based on Skemptons relation is 37.8mm thus satisfying the designed
permissible settlement of 60mm allowed for the structure. Settlement of the
structures monitored over eight months indicates values between 6mm to 21mm.
INTRODUCTION
Every piling works should normally include a load test carried out to estimate
limiting values for safe working load and settlement on piles proposed to be
installed. Although
Piling works is not very common within the area being reported upon especially
for building structures except for long bridges across some of the major rivers in
the locality. The record of a load test programme is therefore thought to be a
valuable asset for practicing engineers within the locality; serving as reference as
there is not much in published works; also a comparison of similar load test
within the Coastal Plain Sands from other parts of the world is welcome.
Zone
Size of zone
(m x m)
Pile length
(m)
A
B
C
D
E
F
10.58 x 19.35
5.95 x 67.50
14.0 x 67.00
2.60 x 2.40
7.05 x 19.75
0.40 x 12.60
9
11
13
11
11
6
All piles were founded in first depth range, and pile lengths ranges from 10.013.0m
The average cone resistance qc, for this gravel layer from cone penetration
campaign around the site is 12MPa.
Borehole diameter
150mm
Length of boring
6-9-11-13m
Pile- steel grade
55
Steel pile external diameter/thickness 88.9mm/8.0mm
Minimum volume of grout
60 liters
Cement type
Type1 (100kg)
Plasticizer agent
1kg
The piles were then lowered into drilled holes. The hole drilling and installation
of piles were carried out in different zones. After the piles have been lowered,
bentonite slurry with a setting retarder-Rheobuild 501 was poured down each
hole around the piles to hold the pile in position until grouting. The retarder
prevents the bentonite slurry from setting until grouting material, which displaces
the slurry, is forced into place.
A packer device placed inside the piles was systematically used to break the
rubber seal enclosing the perforated holes starting from the bottom part of the
pile upward. The packer device ensures that only one rubber is broken at a time,
thereafter grouting of that length of the pile is carried out under pressure into the
pile hole, the hole surrounding the pile, and the surrounding soil at that level.
Grouting at each of the hole was carried out at pressures between five to six Bars.
When grouting reaches ten Bars or 6oliters of grouting materials was used at a
level, the grout is considered to have filled and fully penetrate the available
spaces around the pile and voids in the surrounding soil at that horizon. Further
grouting could lead to a blow out .The pressure of 10 Bars or 60 liters of grout
volume is therefore considered as refusal.
A total numbers of 253 steel piles were install for the filter using the procedure
describe above.
The pile heads were at about 400 mm above ground level. Near the top were
welded brackets, which serves to carry the top reinforcement for the structures.
Table 3. Representative readings for pile load test for a pile in zone c of filter
Load (Tons)
(1)
(2)
(3)
(4)
8:55
9:15
9:35
9:55
10:15
10:35
11:55
13:55
14:55
16:05
16:15
16:25
16:35
16:55
15.
25
35
45
55
65
75
75
75
65
55
45
35
15
0.84
1.54
2.11
2.70
3.23
3.23
4.41
4.47
4.50
4.40
4.18
3.85
3.45
1.94
0.76
1.40
1.94
2.53
3.04
3.04
4.20
4.28
4.30
4.15
3.87
3.61
3.23
1.80
0.43
0.80
1.17
1.53
1.87
1.87
2.77
2.82
2.85
2.76
2.57
2.40
2.18
1.18
0.39
0.83
1.23
1.62
1.98
1.98
2.95
3.01
3.06
3.01
2.83
2.60
2.35
1.25
0.605
1.142
1.612
2.095
2.530
2.530
3.582
3.645
3.677
3.580
3.262
3.115
2.802
1.542
10:20
10:40
11:00
11:20
11:40
12:00
12:20
14:00
16:00
17:10
17:20
17:30
17:40
17:50
15
25
35
45
55
65
75
75
75
65
55
45
35
25
(1)
(2)
(3)
(4)
0.73
1.04
1.30
1.60
1.90
2.16
2.89
2.24
3.30
3.21
2.99
2.73
2.42
2.05
0.41
0.65
0.86
1.19
1.38
1.72
2.34
2.67
2.74
2.66
2.48
2.25
1.99
1.62
0.28
0.61
0.86
1.16
1.42
1.76
2.39
2.70
2.74
2.63
2.42
2.19
1.86
1.48
0.62
0.93
1.17
1.45
1.71
2.07
2.59
2.92
3.01
2.96
2.76
2.51
2.30
1.88
0.51
0.808
1.050
1.333
1.603
1.928
2.553
2.895
2.950
2.865
2.663
2.420
2.143
1.756
Table 5. Monitored settlement values for different parts of the filter and clarifier
Structures
Filter
Settlement
Positio
(mm)
n
Clarifier A
Clarifier B
Clarifier C
Clarifier
Clarifier
Clarifier
A
Settlement(mm)
B
Settlement(mm)
C
Settlement(mm)
Position
Position
Position
T1
T2
T3
FN1
FN2
FN3
FN4
FN5
FN6
FN7
FN8
6
3
4
1
5
0
2
2
5
6
1
A1
A2
A3
A4
18
16
16
7
B1
B2
B3
B4
Top
13
13
18
16
22
C1
C2
C3
C4
Top
21
20
19
13
9
Figures 1 and 2 show the load -settlement curve for the load tests. The 75 tons
load represents one and half times the expected working load of each piles. For
the pile group, Tomlinson (1980) stated that for most engineering structures the
load to be applied to the group is usually determined by settlement consideration
rather than from ultimate carrying capacity of the group divided by an arbitrary
factor of safety. Fellenius (2001), in a similar vein argued that settlement should
form the basis of determining pile capacity. The pile load test gives such
information on settlement. Estimating settlement reliably from pile load tests is
somewhat difficult due to time effects and group action. However, empirical
relationships for example Skempton et al (1953), gives an expression from which
settlement of pile group (driven or bored) in cohesionless soil can be estimated. It
predicts a settlement value of 2-16 times the settlement of a single pile.
The Skempton relationship as reported by Broms (2001), can be written as
(1)
Settlement Monitoring
Settlements of the filter were monitored over a period of eight months
(November, 2000 to June, 2001). Table 5 presents the observed settlement values
for the different parts of the structures. The maximum settlement obtained for the
filter over this period was 6 mm at location T (Figure 3) while the clarifier
records the maximum of all the settlement values over this period at 21 mm at
point C1 on clarifier C.
Table 5. Monitored settlement values for different parts of the filter and clarifier
Structures
Filter Settlement
Position
(mm)
Clarifier A
Clarifier B
Clarifier C
Clarifier
Clarifier
Clarifier
A
Settlement(mm)
B
Settlement(mm)
C
Settlement(mm)
Position
Position
Position
T1
A1
18
B1
13
C1
21
T2
T3
FN1
FN2
FN3
FN4
FN5
FN6
FN7
FN8
3
4
1
5
0
2
2
5
6
1
A2
A3
A4
16
16
7
B2
B3
B4
Top
13
18
16
22
C2
C3
C4
Top
REFERENCES
20
19
13
9
ACKNOWLEGEMENT
The lead author wishes to express his appreciation to the Cross River state water
board and SGI consulting (Nigeria) for the opportunity given to him to
participate in the project as one the site engineers.