Professional Documents
Culture Documents
CONTENT
1.Basis of Compilation
2.Project Overview
3.Types of Karst
1.Basis of Compilation
1).Contract signed with the owner.
2).Tender documents signed with the owner.
3).Design drawings provided by the owner.
4).Geological Report provided by owner.
5).Relevant Malaysian construction regulations, foundation construction
specifications.
2.Project Overview
Cadangan pembangunan 1 blok pangsapuri servis 51 tingkat (437 unit)
termasuk 1 tingkat basemen dan kemudahan penduduk serta podium dan
1 unit pondok pengawal
di atas Lot 11599, 1524, 1525 dan 1526, Jalan Ampang Kiri, Mukim
Ampang, KL
-1-
3.Types of Karst
Karst can generally be divided into three types: completely void,
half-filled, and fully-filled. Karst that are taller than 3 meters are
classified as large karst.
12-30
Static
pressure
chemical
grouting
Static
pressure
chemical
grouting
Backfill G20
concrete
Static
pressure
chemical
grouting
Below
30
Static
pressure
chemical
grouting
Static
pressure
chemical
grouting
Static
pressure
chemical
grouting
Static
pressure
chemical
grouting
Description of
work method
Embed pile casing
8-12 according to
geological
condition.
Backfilling
concrete produces
better results for
large karst of such
depth.
Static pressure
chemical grouting
produces better
results.
Item 1:
Pile casting covering method: Based on the predrilling result,
determine the depth to embed the pile casing. For piling location with
detected karst, pile casing embed to the weathered rock layer, on surface
of strong weathered rock layer, so that can penetrate soil caves. The
bottom of the pile casing shall be the rock layer or top of the karst. For
karst free piles, pile casing to be embedded underneath mucky clay,
gravel layer, placed at least 2 meter deep in the gritty clay.
Item 2:
Backfill method (crushed rocks or concrete) for completely void or
-4-
shearing resistance of the earth form in the karst creates retaining wall
that will prevent the hole from collapsing.
Static Pressure Chemical Grouting Method:
Drill hole
Material
Method
Main
equipment &
facility
To prevent high pressure inside the hole from deterring the grouting
works, apply other holes to relieve the pressure.
Grouting Pressures
The following pressures should be used for grouting cavities located
at the corresponding depths below the existing ground surface.
Depth(m)
20.1-30
87
30.1-40
116
40.1-50
145
50.1-60
174
60.1-70
203
70.1-80
232
80.1-90
261
90.1-100
290
-6-
QUANTITY
80m
120m
10 tonnes
200 sheets
1 unit
1 unit
Type
Project manager
Safety officer
Technical manager
Site engineer
Site supervisor
-7-
Quantity
1
1
1
2
4
Remark
Chinese
Malay
Malay Chinese
Chinese
Chinese