Submitted to
NATIONAL HIGHWAY AUTHORITY OF INDIA
Submitted by
INDIAN INSTITUTE OF TECHNOLOGY DELHI
September 2010
TABLEOFCONTENTS
TABLE OF CONTENTS ..................................................................................................... i
LIST OF TABLES .............................................................................................................. vi
LIST OF FIGURES ........................................................................................................... vii
Unit 1 ..................................................................................................................................... 1
1.1 Introduction and Guidance to Users ............................................................................ 1
1.1.1
1.1.4
1.1.5
1.2
Legislation ................................................................................................................... 4
1.2.1
1.3
Laws and Rules related to Health, Safety and Welfare of construction workers 4
1.3.1
Training Facility................................................................................................. 30
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.10.1 Signs...................................................................................................................... 47
3.10.1.1 Sign Placement ........................................................................................... 53
3.10.1.2 Regulatory Signs ............................................................................................ 54
3.10.1.3 Warning Signs................................................................................................ 55
3.10.2
Delineators ..................................................................................................... 57
Drums ............................................................................................................. 58
3.10.5
Barricades ....................................................................................................... 61
3.10.6
Flagmen .......................................................................................................... 65
3.11.
3.11.1
Introduction ....................................................................................................... 69
3.11.2
3.13
3.14
3.16
3.17
3.17.1
3.17.2
3.18
3.19
3.20
3.21
Alternatives for Different work zone Situations for Traffic Management ......... 116
4.2.2.1
4.2.3
5.2
5.3 Guidelines for the preparation of Formwork Schemes (Plans) .................................... 182
5.3.1
5.3.2
5.4
5.4.1
5.4.2
5.4.3
5.4.4
5.4.5
5.4.6
5.5
5.6
5.6.1
5.7
5.8
LISTOFTABLES
Table 1 Examples of commonly used indicators of the road traffic injury problem ............... 14
Table 2 Recommended Lengths of Traffic Control Zones ...................................................... 44
Table 3 Minimum Sightline Distances and The Minimum Size of The Signs ........................ 57
Table 4: Barricade Characteristics ........................................................................................... 63
Table 5: Buffer Zone Safety Clearences .................................................................................. 71
Table 6: Maximum Traffic Flows For Length of Site ............................................................. 79
vi
LISTOFFIGURES
viii
Unit1
1.1 IntroductionandGuidancetoUsers
1.1.1 Whythismanual?
According to official statistics (National Crime Records Bureau), 118 239 people were
killed in road traffic crashes in India in 2008. The situation in India has worsened in recent
years. Traffic fatalities increased by about 5% per year from 1980 to 2000, and since then
have increased by about 8% per year in recent years. This is attributable partly to an increase
in the number of vehicles on the road, and partly to the absence of a coordinated official
policy to control the problem. The fatality rate has increased from 36 fatalities per million
persons in 1980 to 103 fatalities per million persons in 2008. Many of these traffic injuries
and deaths take place in constructions zones on all roads and highways. In addition, a
significant number of workers associated with construction and maintenance of roads also
get injured and killed every year. This increasing trend in injuries and fatalities has been
recognised as a public health problem of significance by the authorities and public at large.
There is an urgent need to train practitioners and policy-makers in the scientific
approach to injury prevention. There needs to be a cadre of professionals working from a
shared understanding of the magnitude of the problem of road traffic and work injuries, risk
factors and the value of implementing evidence-based strategies. This underscores the need
for persons working at all levels in road construction and maintenance to be equipped with
appropriate knowledge and skills derived from empirical evidence and professional wisdom.
Intervention programmes seeking to prevent injuries need to address the problem of capacity
in different sectors. This manual attempts to address the problem of capacity for injury
prevention by providing guidance to professionals managing road construction activity
1.1.2 Howwasthismanualdeveloped?
This manual was developed jointly by Prof Geetam Tiwari, Asst Prof Kalaga
Ramachandra R and Asst Prof K N Jha. NHAI had engaged Indian Institute of Technology
Delhi (IITD) for undertaking safety audit of contract packages under the Lucknow
Muzaffarpur National Highway Project (LMNHP), World Bank funded 4-laning of NH-28
between Lucknow and Muzaffarpur. The IITD team consisted of experts from the following
disciplines:
Contract specialist
Construction safety,
1
Structural safety,
OSHA Specialist
The team visited all construction zones, conducted safety audits, and had discussions
with all stake holders. The technical, legal and social issues were discussed in detail with
NHAI and World Bank authorities and at workshops organised for this purpose. All the
relevant information was gathered and a draft of the manual was prepared, peer reviewed, and
revised, ultimately being published in the present form. It is envisaged that the manual will be
further refined in the light of experience in its use.
1.1.3 Whoaretheintendedusers?
This manual is designed for a broad inter-disciplinary audience consisting of people
involved in preventing work and road traffic injuries at work zones on roads and highways.
This group includes policy-makers, administrators, road engineers, medical doctors, law
enforcers, contractors. Since effective implementation of safety policies requires an
interdisciplinary approach, this manual provides guidance to workers in a wide range of
disciplines, who are involved in different aspects of road construction activity in different
settings.
1.1.4 Structureandcontent
This manual includes two introductory chapters:
Legislation
This structure gives managers and trainers flexibility to customize the content for
different audiences. The units provide users with information enabling them to respond to key
safety questions:
2
What are the appropriate methods and approaches for preventing accidents and
injuries in different settings?
What can road construction and maintenance professionals do to initiate and sustain
viable programmes to improve safety?
Laws and Rules related to Safety, Health and Welfare of construction workers
SHE Policy
This manual provides principles and information to meet training needs in different
settings. It can be used in facilitator-guided training, as well as for self-learning. Professionals
managing safety have different levels of prior knowledge. Some may have had formal
training, while others may not. Also, these professionals are likely to be working on different
aspects of safety. Trainers are advised to consider the needs of different audiences, especially
their pre-existing knowledge and practical needs in their work. The modular structure of this
manual allows for flexibility in customizing the content to meet different training needs
1.1.5 Adaptingthecontenttoalocalcontext
This manual provides key principles and discusses problems encountered in the Indian
context, but these principles and problems need to be made relevant to the local context.
While the importance of adapting the content to local situations cannot be underestimated,
trainers who are overseeing the local adaptation of the training materials must ensure that the
fundamental principles are not radically changed or misrepresented. It is also important to
ensure that the material, when adapted to a specific local setting, remains accurate. There are
a number of ways of adapting this manual to a local context. Trainers can do this by:
Modifying the style and level of content in view of the pre-existing knowledge base of
the training audience.
Introducing local experiences into the training materials to make the course
meaningful to the audience, for instance by considering the local implications of road
traffic collisions, risk factors and policy development.
Asking trainees to look for examples in advance and make presentations on them
during the training sessions.
1.2
Legislation
Laws and Rules related to Safety, Health and welfare of construction workers:
The law provides a set of limits or minimum standards of protection for workers health
and safety. It establishes the boundaries as to what may be negotiated between unions and
employers, and what may be imposed on workers by employers acting under economic
pressure. It also mandates and regulates the conditions of work so that workers are not
subjected to unsafe environments and may take recourse to the courts to enforce the
provisions. The following laws are of relevance to the issues of workplace hazards and safety
and some of the provisions of the main ones are mentioned below. However, it is incumbent
on safety officers to keep copies of all the laws and become familiar with the provisions
therein.
1.2.1 Laws and Rules related to Health, Safety and Welfare of construction
workers
The Contractor shall develop a thorough understanding of the Building and Other
Construction Workers (Regulation of Employment and Conditions of Service) Act 1996, the
Factories Act, 1948, Central Rules 1998, Building and Other Construction Workers Welfare
Cess Act, 1996, to not only satisfy the Inspectors but also to develop a perspective on the use
of these legislations as the main tool for safety of workers at construction worksites. The
Contractor is strongly advised to practice the principle of voluntary self-regulation rather than
merely adopt a compliance attitude.
In addition to this, the construction works shall be undertaken in accordance with all
applicable Legislations and Indian statutory requirements listed below for better health and
safety management at construction worksites.
4
1.3
Safety,HealthandEnvironmentManagement
1.3.1 Safety,HealthandEnvironment(SHE)Policy
The contractor as per Section 39 of the BOCW Act shall formulate a SHE policy and get
it approved by DG/CIIBC respectively and display it at conspicuous places at work sites in
Hindi and a local language understood by the majority of construction workers.
Within 4 weeks of the notification of acceptance of the tender, the Contractor shall
submit a detailed and comprehensive Contract specific SHE Plan. The SHE Plan shall include
detailed policies, procedures and regulations which, when implemented, will ensure
compliance of the contract provisions. The SHE Plan shall include the following but not be
restricted to:
19) A statement of the Contractors policy and procedures for ensuring that
subcontractors comply with the Contractor's safety plan;
20) A statement of the Contractors disciplinary procedures with respect to SHE
21) related matters, and
22) A statement of the Contractors procedure for reporting and investigating
23) accidents, dangerous occurrences or occupational illnesses
The Contractor shall, from time to time and as necessary are required by the Employer to
produce supplements to the SHE Plan such that it is at all times a detailed, comprehensive
and contemporaneous statement by the Contractor of his site safety, industrial health and
environment obligations, responsibilities, policies and procedures relating to work on Site.
Any and all submissions of supplements to the SHE Plan shall be made to the Employer in
accordance with the agreed procedures.
If at any time the SHE plan is, in the Employers opinion, insufficient or requires
revision or modification to ensure the security of the Works and the safety of all workmen
upon and visitors to the Site, the Employer may instruct the Contractor to revise the SHE plan
and the Contractor shall within 7 days submit the revised plan to the Employer for review.
Any omissions, inconsistencies and errors in the SHE Plan or the Employers acceptance
or rejection of the SHE Plan and/or supplements thereto shall be without prejudice to the
Contractor's obligations with respect to site safety, industrial health and environment and
shall not excuse any failure by the contractor to adopt proper and recognised safety practices
throughout the execution of the Work.
The Contractor shall adhere to the SHE Plan and shall ensure, as far as practically
possible, that all sub-contractors of all tiers require that contracting parties each have a copy
of the Site SHE Plan and comply with its provisions.
The details of contents to be covered in the site SHE plan are given in Appendix No.:3.
B.
In the following sections the responsibilities and scope of work of the major stakeholders
are briefly described.
1.3.2OrganizationStructure
Corporate level
1.3.3 ScopeofWorkforConsultants
1.3.3.1
The consultant shall ensure safety of workers and road users at construction
sites. For this, the consultant shall refer to the requirements specified in Section 100
of MORTH Specifications particularly Clause 101, 105 and 112 and IRC:SP55
(Guidelines on Safety in Road Construction Zones), IRC: 67 and IRC: 35, Work Zone
8
Road Safety Manual, Good Industry Practice and provisions of Building and Other
Construction Workers Acts/Rules.
1.3.3.2
The consultant shall carry out close inspection of the project alignment in
various stretches and provide for the following in the DPR:
i.
Stretches with chainages specified, where it would not be possible to use the existing
carriageway or part width thereof and therefore, it would become necessary to provide
separate temporary diversions and temporary cross-drainage structures for movement
of traffic. These requirements should, thereafter, form part of the BOQ.
ii.
Prepare illustrative plans for safety at construction sites keeping in view the
requirements laid down in IRC: SP: 55 for the following situations:
For each of the situations (a), (b), (c) and (d) of (ii) above, the quantity (number,
length, area, etc.) of the following items shall be estimated and provided in the BOQ:
a)
Cones
b)
Drums
c)
Crash cushions
d)
Lanterns/bulbs
e)
f)
g)
h)
Temporary fencing/guardrail
i)
Pavement markings
j)
Barricades Type I
k)
Barricades Type II
l)
m)
Barricades type IV
n)
1.3.3.3
The consultant shall propose supplementary technical specifications, which in
his considered view, would further enhance the safety of workers and road users at
construction sites which is not currently covered by the existing MORTH
specifications
It can be noticed that the scope of work in respect of Design Consultants and
Supervision Consultants has been elaborated to improve the outcomes in respect of safety
and better traffic arrangements at construction sites. The intention is to make the TOR for
these consultants more precise and specific. These are indicated in Annexure 4 for design
consultants and Annexure 5 for supervision consultants. These suggestions can be
incorporated in future consultancy assignments to be entrusted by NHAI. The Contract
Management Cell of NHAI may, after approval of the Competent Authority, issue
necessary guidelines.
1.3.4ResponsibilitiesofProjectDirectors
1.3.4.1
The Project Directors have an important role in overseeing and ensuring
adherence to the norms/guidelines and contractual provisions from the consultants and
the contractors. A listing of the duties has been proposed in Annexure.
1.3.4.2
The Project Director shall designate one of the Technical Managers to be
responsible for safety besides environment and social aspects on the NHDP projects.
Other duties proposed are already on the lines indicated in the previous circulars of
the NHAI.
1.3.4.3
Administration Division may reiterate the same by a suitable policy circular
after approval.
C.
D.
10
Unit2
SafetyManagementIssues
2.1 Investigation,Reporting,AnalysisandRecordKeepingofIncidents
Introduction
Any incident and resulting injury results from a combination of factors related to the
components of the environment-equipment/machine/vehicle-user system and to the way they
interact. Some factors contribute to the occurrence of an incident and are therefore part of
incident causation. Other factors aggravate the effects of the incident and thus contribute to
trauma severity. Some factors may not appear as if they are directly related to the incident
causing injuries. Some causes are immediate, but they may be underpinned by medium- and
long-term structural causes. Identifying the risk factors that contribute to injuries is important
in identifying interventions that can reduce the risks associated with those factors. We
approach the problem in four steps (Figure 2)
11
The first step is to determine the magnitude, scope and characteristics of the
problem. Defining the problem goes beyond simply counting cases: it includes
delineating mortality, morbidity, and risk taking behaviours. This step includes
obtaining information on the demographic characteristics of the person involved,
the temporal and geographical features of the incident, the circumstances under
which it occurred, and the severity and cost of the injuries.
The second step is to identify the factors that increase the risk of injury or
disability, and to determine which factors are potentially modifiable. Whereas the
first step looks at "who, when, where, what and how", the second step looks at
"why". It may also be used to define populations at high-risk for violence or
accidental injuries and to suggest specific interventions.
The third step is to assess what measures can be taken to prevent the problem by
using the information about causes and risk factors to design, pilot test and
evaluate interventions.
The final step is the implementation of interventions that have been proven or are
highly likely to be effective on a broad scale. In both instances it is important that
data be collected to evaluate the programme's effectiveness.
effective or have very limited impact. Work zone safety policies and programmes should
therefore be based on reliable and valid research-derived evidence. This is not just about
simply collecting data on incidents and injuries but utilizing the best and validated evidence
possible on intervention measures. In fact, there is need to ensure reliability of not only the
data collected but also the methods and instruments used to collect and analyse information to
generate evidence.
Reliable data and sound evidence are essential for:
Establishing priorities and allocating resources for prevention of work zone injuries.
Raising awareness.
What are the most common causes and types of injuries in different age groups?
What are the characteristics of persons who are most likely to be injured?
What are the circumstances under which injuries are most likely to occur?
What policies and programmes can reduce the likelihood and severity of injuries in a
community?
Analysing data, producing regular outputs and disseminating information on work zone
injuries are all vital activities. It is necessary to share and disseminate data and evidence on
injuries with colleagues, other researchers, policy makers, victims and the community at the
local, and national levels. Though writing reports is central to this activity, this should not be
an end in itself. The design of databases should therefore take account of the principal needs
of their users, providing quality data without overburdening those collecting the data.
There are a number of issues and concerns on road traffic injury data. These are
summarized below. Indicators are important not just for measuring the magnitude of a
problem but also for setting targets and assessing performance. The most frequently used
absolute and relative indicators for measuring the magnitude of the work zone and road
traffic injury problem are presented in Table 1.
Index
Description
Number of
injuries
Number of
deaths
Index
Description
equipment
locations.
Fatalities /
injuries per 100
workers
Road traffic
fatalities per km
of road length
Road traffic
fatalities per
vehicle
kilometre
travelled
Indicators
Two very common indicators are the number of injuries/deaths per worker/person, and
the number of injuries/deaths per vehicle/equipment. Both of these indicators, though, have
limitations regarding their reliability and validity that place restrictions on how they can be
used and interpreted. The number of deaths per person is widely used with reasonable
confidence to monitor changes over time in personal risk levels and to make comparisons
15
a failure on the part of the injured to report owing to specific policies followed by
employers;
hospitals not reporting cases presenting to them as injuries due to work or traffic
crashes;
some victims cannot afford to attend hospital, unless they are assured of
reimbursement.
5. Establish a procedure for collecting injury details for those who get admitted to hospitals
or receive outpatient treatment.
6. Data collection officers should be trained in the use of the forms designated for road
traffic and work injuries.
7. The data so collected should be entered on a computer at a central location soon after the
forms are filled so that the current situation can be monitored by the management on a
regular basis.
Forms for recording events
Two different forms should be used for recording injury and fatality producing events:
one for road traffic crashes and one for all other injuries. These two forms are attached
(Annexure 2.1 and 2.2). The minimum data to be collected is indicated in these forms. Each
contractor can modify the form to include any other items that may be considered important
based on local requirements. However, the basic format should be retained so that these data
can be consolidated centrally to enable regional and national assessments.
17
A work place injury or a road traffic crash is the result of a series of events in which
many components of the system are involved and have been interacting: individuals with
specific characteristics, some features of the infrastructure at the injury location or on the
routes leading to it, some equipment or vehicles used by those involved, some other factors
in the surrounding environment. The injury therefore results from a combination of these
factors related to the components of the equipment-vehicle-worker-road user system and to
the way they interact. Some factors contribute to the occurrence of an injury and are thus part
of causation; other factors aggravate the effects of the event and thus contribute to trauma
severity.
Making a work zone or road traffic system less hazardous requires a systems approach
understanding the system as a whole and the interaction between its elements, and
identifying where there is potential for intervention. In particular, it requires recognition that
the human body is highly vulnerable to injury and that humans make mistakes. A safe system
is one that accommodates and compensates for human vulnerability and fallibility.
The data included in the forms provide objective information and measurements (for
example description of site, vehicles, road-users involved, and weather conditions) as well as
personal accounts of the event provided by the those involved or by witnesses. These must be
obtained and registered without any bias related to assumptions on how the injury occurred
18
and without searching for one particular culprit. Analysis of a crash generating process
therefore implies the building up of a "tree" of causes, focusing on the interactions and links
between factors. Preventive action may then control one key factor through another one, less
obvious but more manageable. The essence of using a systems approach is to consider, not
only the underlying factors, but also the role of different agencies and actors in prevention
efforts.
Data analysis for worker injuries
The data collected may be organised in the following statistics and tables:
Total injuries per year:
Treatment
Number
First Aid
OPD
Hospital admission
Fatality
Total
19
ANNEXURE 2.1
Form No:
Filled by:
Date filled:
Yes/ No
1. Time of accident:
(24hr)
3. Day:
4. Holiday:
2. Date
(DD)
(MM)
6. Accident severity:
7. Number of fatalities:
8. No. injured:
9. Number vehicles:
13. Divider:
14. Location:
16.Road
Category
(YY)
17. Chainage
20
Vehicle 1 data :
18. Type:
19. Manoeuvre:
20. Loading:
21.Disposition
Vehicle 2 data :
25. Type:
26 Manoeuvre:
27. Loading:
28.Disposition
31 Make/Model
Vehicle 3 data :
32. Type:
33 Manoeuvre:
34. Loading:
35.Disposition
38 Make/Model
Victim 1 data
Victim 2 data
43. Sex
46 Impact with
Victim 3 data
Victim 4 data
44. Injury
55. Sex
56. Injury
Victim 5 data
49. Sex
21
1. Form No: __ __ __ __ __ __ __ __ __
Case Number in serial order
Chainage
0=No
1=Yes
1= Monday
2=Tuesday
3= Wednesday
4=Thursday
5=Friday
6=Saturday
7= Sunday
9=Unknown.
4. Holiday:
0 = No
1 = Yes
9=Unknown
1 = Yes
0 = No
9=Unknown
2= Injury
3=Fatal
9= Unknown
2 = Vehicles head on
5 = Overturn
8= Others
9 = Unknown
1 = On straight road
2 = Road junction
3 = Other
9 = Unknown
0= Unmetalled
2=Others
9=Unknown
In case of more than one type reported in a series of events the first collision/event will
be considered.
22
13. Divider
14. Location:
1=Yes
1=Urban
9= Unknown
2= State Highway
4= Other
9=Unknown
3=National Highway
9= Unknown
VEHICLE
4 =Bus
5 = Car/van/jeep/taxi
9 = Tractor
13= Bicycle
14 = Pedestrian
88 = Other
99 = Unknown
1 = Proceeding straight
2 = Turning
3 = Reversing
4 = Overtaking
5=Parked/Stopped
6 = Other
9 = Unknown
20. Loading:
1=Normal
2= Overloaded
3= Others
9= Unknown
1=Yes
0=No
9= Unknown
23. Striking-Vehicle/Object:
If this vehicle hit another vehicle or pedestrian enter appropriate code 1-99
from section 18 above,
Otherwise use following codes:
15=Tree
VICTIM
39. Road user: The vehicle number from above (1, 2, or 3) the victim was occupant of ,
OR
7 = Pedestrian
9 = Unknown
7 = Pedestrian,
8 = Other
2: Passenger
In years, 99 if unknown
43. Sex :
1 = Male
44. Injury :
0 = No injury
2 = Female
9 = Unknown
9 = Unknown
4 = Fatal
9 = Unknown
24
ANNEXURE 2.2
NHAI FORM FOR RECORDING WORKER INJURIES
25
ANNEXURE 2.2
NHAI FORM FOR RECORDING WORKER INJURIES
26
2.2EmergencyResponsePlan
The Contractor shall prepare as required under Rule 36 of BOCWR, an Emergency
Response Plan for all work sites as a part of the Contractor SHE Plan. The plan shall integrate
the emergency response plans of the Contractor and all other subcontractors. The Emergency
Response Plan shall detail the Contractors procedures, including detailed communications
arrangements, for dealing with all emergencies that could affect the Site. This include where
applicable, injury, sickness, evacuation, fire, chemical spillage, severe weather and rescue.
The contractor shall ensure that an Emergency Response Plan is prepared to deal with
emergencies arising out of:
i) Fire and explosion
ii) Collapse of lifting appliances and transport equipment
iii) Collapse of building, sheds or structure etc.
iv) Gas leakage or spillage of dangerous goods or chemicals
v) Bomb threatening, Criminal or Terrorist attack
vi) Drowning of workers
vii) Landslides getting workers buried floods, Earthquake, storms and other natural
calamities.
Arrangements shall be made for emergency medical treatment and evacuation of the
victim in the event of an accident or dangerous incident occurring, the chain of command and
the responsible persons of the contractor with their telephone numbers and addresses for
quick communication shall be adequately publicized and conspicuously displayed in the
workplace.
Contractors shall require to tie-up with the hospitals and fire stations located in the
neighbourhood for attending to the casualties promptly and emergency vehicle kept on
standby duty during the working hours for the purpose.
Contractor shall conduct an onsite emergency mock drill once in every month for all his
workers and his subcontractors workers.
It shall be the responsibility of the contractor to keep the Local Law & Order Authorities
informed and seek urgent help, as the case may be, so as to mitigate the consequences of an
emergency. Prompt communication to NHAI, telephonically initially and followed by a
written report, shall be made by the contractor.
27
2.3HealthofWorkers
2.3.1a)Preemploymenthealthcheckup
General:
A pre-employment health check up is the medical examination conducted when a
potential employee applies for a job. It should be designed to assess general fitness as well as
the susceptibility of the worker to any particular hazard he/she may encounter on the job.
I
The Contractor shall ensure that the following examinations are carried out:
A. Complete physical check-up of the worker
B. The doctor will record the medical history of the employee, including
previous sickness or present conditions, medications, and therapies
C. The usual tests like blood tests, x-rays, urine, and stool exams
2.3.2b)Records:
The following records shall be maintained by the Contractor:
I.
Records containing details of employees, work done, hours worked, rest, wages,
receipts in the prescribed form should be maintained.
II.
III.
IV.
V.
VI.
Notice of accidents for death and injury and enquiry status for every month.
Documents containing certain dangerous occurrences of bodily injury or disability or
not and notices that are sent by the Contractor and Manager to the authorities as per
prescribed form and time.
VII.
VIII.
2.3.3c)Provisionoffacilities
The facilities that are to be provided by the Contractor are:
28
I.
II.
Overcrowding
A. No room shall be overcrowded that can cause injury to the health of
workers.
B. At least 14.2m2 area has to be provided for each worker.
III.
Drinking water
A. Effective arrangement and maintenance at suitable points for sufficient
marked supply of wholesome drinking water.
B. All such points shall be legibly marked as Drinking Water and such
point shall be situated at more than 6m from any source of contamination.
C. Cool drinking water during summer for sites employing more than 250
workers.
IV.
2.3.4d)Provisionofmedicalstaff:
The Contractor shall give special attention to the provision of medical staff as follows:
I.
For more than 500 workers, an ambulance room in the charge of such medical and
nursing staff as prescribed by the State government shall be provided and maintained.
II.
A qualified Doctor, Nurse and Assistant Nurse shall be in attendance at the first aid
base during all times when work is being undertaken on the site.
29
2.4 Training
The Contractor shall organize regular safety training courses to acquaint Managers,
Supervisors, workers and other personnel in the principles of work safety, implementation of
mandatory safety provisions, and how to audit and improve safety performance.
2.4.1 TrainingFacility
I.
The Contractor shall determine the training requirements for all the employees and
initiate a training programme to demonstrate that all persons employed, including
subcontractors, are suitably qualified, competent, and fit to implement safety
provisions. This will include:
A. Detailed job descriptions for all personnel to include their specific safety
responsibilities.
B. Specification of qualifications, competency and training requirements for all
personnel.
C. Assessment and recording of training needs for all personnel, including
subcontractors employees in the workforce, vendor representatives, and site
visitors.
D. A system for assessing the competence and training requirements of newly
hired persons.
E. A safety protocol for evaluating and confirming that the system is effective.
F. A matrix and schedule of training requirements covering general, task
specific, and SHE-related training, showing the training frequency and the
interval between refresher courses.
G. Timely, competent delivery of training courses by certified instructors.
II.
The Contractor shall arrange training programmes for all executives in how to
identify, recognise, and eliminate unsafe acts and unsafe conditions.
III.
2.4.2.ToolBoxMeeting
The Contractor shall ensure that:
A. Toolbox meetings and trainings are conducted on site on a daily basis by safety
managers and supervisors.
30
B. On-the spot practical skill development training on safety including scaffold safety,
crane safety, welding safety, electrical safety, and traffic safety for marshals shall also
be conducted for all foremen/ workmen associated with the concerned jobs.
C. Daily Safety Oath is to be administered to every employee including all workmen to
remind them about their responsibilities to themselves and fellow workers.
D. All vehicle drivers including Hydra operators shall be trained on defensive driving at
training centres. All vehicle drivers shall also undergo refresher training on defensive
driving provided by the same institute once in 6 months.
2.5
SafetyPromotion
2.6Auditing
I.
II.
Audit Procedure
A. The Contractor has to ensure that the audit team briefs the work package
team regarding the purpose of the audit, methodology of audit, and the
terms of reference of the audit team
B. After the briefing by the audit team, the leader of the work team makes a
presentation before the audit team. The presentation should cover the
topics mentioned below:
a. General:
31
Identification of work-zones
A. The audit team members are equipped with a check list covering different
aspects related to safety. Against each of the checklist items, the
32
2.7 HazardIdentification,RiskAssessmentandControlMeasures
I.
General: The purpose of hazard identification and risk assessment is to identify all
the significant hazards prior to the commencement of any potential high-risk
operations, which may occur during the operations, and to rank them according to
their severity. Having ranked the risks the Contractor shall then take measures to
mitigate the effects of that risk by recording his findings on appropriate worksheets
that show what measures the Contractor is going to take to remove or reduce the level
of risk to acceptable levels.
II.
Safety principles: The basic principles that govern the identification of and
protection from hazards, in order of priority, are:
A. Remove
B. Reduce
C. Protect
Thus the Contractor, having identified the risk and ranked it according to severity, has to first
take steps to remove the risk itself. If this step leaves behind some residual hazards, then the
attempt has to be to reduce it to acceptable levels. Only in the last resort is the worker to be
33
issued with personal protective equipment (PPE) so that he/she can function in an unsafe
environment.
III.
34
Unit3
TrafficSafety
Preamble
The two primary objective of temporary traffic control is to manage the traffic as
efficiently and safely as possible under all work conditions and second objective of
these guidelines is to lay down procedures to be adopted by field engineers to ensure the
safe and efficient movement of traffic and also to ensure the safety of workers at site
undertaking the construction.
Traffic control aims to give adequate warning and clear information to motorists
about the nature of works on site. This will translate into correct actions required in
order to pass the work site safely. Traffic control shall also include measures to
safeguard pedestrians when necessary. Proper traffic control also protects those who are
directly involved in carrying out the works. It is necessary that the existing work
procedure and contract conditions are standardized to provide for the proper
management of the construction site so that all road users (that is pedestrians, cyclists,
motor cyclists, animal traffic and vehicular traffic) are properly and safely
accommodated.
Process
35
PROCESS
During Execution
CSC checks
TMP as per the
check list once a
week
submits to CSC
More details /
modifications
(CSC informs client)
CSC approval
NO
Noncompliance if
found to be dealt
with as per the
provisions in
WZRSM
submits to CSC
More details /
modifications
(CSC informs client)
YES
Contractor implements the
TMP at site, Ask for RFI
CSC approval
More details /
modifications
(CSC informs client)
CSC approval
NO
YES
Contractor implements the
TMP at site, Ask for RFI
NO
More details /
modifications
(CSC informs client)
YES
CSC approval
NHAI checks randomly
NO
YES
Work starts
3.1GuidingPrinciples
The guiding principles for safety in road construction zones are to:
(i)
guiding
road
users;
(iv)
Provide adequate measures that control driver behavior through construction
zones.
b.
Roads with construction sites have higher accident rate, when compared with
similar sections of road without construction sites.
36
3.2
PhasesofTrafficControl
37
3.3
ComponentsofConstructionZone
(2001: Guidelines for Safety Construction, Indian Road Congress ,IRC :SP:55:2001 p
4)
The policy under these guidelines is to keep the closure of the roads to a minimum
and to ensure that traffic is delayed as little as possible by the construction operations.
Highest regard is to be given to traffic safety as well as to provide a safe working
environment to the workmen. Before starting the construction work, which will
influence traffic, the contractor has to get the legal permission of the road traffic
authority and local police about the means and extent of securing the construction zone.
The traffic management strategies to be used at construction zones should ensure that
traffic safety is an integral and high priority element of the project. This can be ensured
by avoiding inconvenience to traffic control elements and traffic operations must be
carried out so that care and attention to roadside safety is never slack during the
progress of project.
3.4
TrafficControlZone
1.
For the purpose of these guidelines, the construction zone describes that area of
the road which is affected by the works and which affects traffic flow and road
users. The main area of interest can be called in this context as the "Traffic
Control Zone ". It includes all those areas of carriageway in advance of the
actual work site which are required for advance warning of the hazard as well as
safety zones, the transition zones and the working zone itself. These elements
are shown in Fig 2.1 and defined in succeeding Para. (Draft revision IRC: SP:
55)
2.
3.
In urban areas where construction zones are likely to be even more constrained,
diversions may have to be taken over adjacent sections of the road network in
38
addition to the sharing of road space to road users (for example, shuttle working
under signal control). The effects of construction zones may therefore be felt
over a wide area.
4.
The Traffic Control Zone can be divided into three components, that is, the
Advance Warning Zone, the Transitions Zone and Working Zone. All
construction zones will have a working zone, which is flanked, by a transition
zone for each direction of approaching traffic and an advanced warning zone
will precede these in turn.
39
40
3.5
AdvanceWarningZone
a. The Advance Warning Zone, is the area to warn the road user of the
approaching hazard and to prepare them for the change in driving
conditions. It is essential for traffic control in the construction zone. It
should provide information on:
(i)
(ii)
(iii)
(iv)
3.6
ApproachTransitionZone
a) The transition zone is the area in which the traffic is guided into the altered
traffic flow pattern around the working zone. This is one of the most crucial
zones as far as safety aspects are concerned because most of the movements
involved are merging/turning movements. The transition zone has two
components: The Approach Transition Zone and Terminal Transition Zone.
b) The initial part of the transition zone called Approach Transition Zone should
further reduce the approach speed of vehicles and channel them into the
narrower and/or restricted number of lanes, if this is necessary.
41
c) At other construction zones, it may be necessary to divert traffic away from the
original carriageway and the design of the temporary road geometry through the
transition zone should take into account the following factors:
i.
the turning radius of the longest vehicle that generally uses the road
should be the ruling radius for curves;
ii.
iii.
the zone should have good drainage to avoid any ponding on the road
surface;
iv.
sources of dust should be minimized .This is not only essential for good
visibility but also for clearance maintenance of signs and barricades in
the zone.
d) The traffic is taken across the transition zone mostly with the help of signs,
barricades, channelisers and pavement marking. The various types of barricades
and channelisers are discussed in detail in later paragraphs. The guiding
principle for their design is that they should convey the message clarify and
unambiguously. The colour and shape of the signs should also be as the
standards noted in later paragraphs to eliminate the conclusion caused by use of
different signs for the same purpose.
e) All the signs/barricades are too maintained properly and kept clean of dust at all
times. Sufficient stock of these should be maintained at the site so as to replace
the damaged or vandalized signs/barricades. Proper lighting arrangements for
illuminating these signs must be made during the night hours. Most of the
accidents at nights involve collision between vehicles and objects rather than
vehicle to vehicle collision. Reflective paints/sheets must therefore be used for
the signs/barricaded so that these are visible at all times.
f) Very often the road width available through the transition and working zones is
quite insufficient for simultaneous passage of both the up and down traffic
signals. In both the cases a waiting area with a properly demarcated stop line has
to be provided for the vehicles.
3.7
WorkingZone
42
c) The path of the traffic must be very clearly delineated through the traffic
control zone to avoid vehicle intruding into the work area.Delineators and
channelisers discussed below must be used effectively for this purpose.
Where the work site uses machinery with revolving booms like cranes or
excavators the intrusion of moving parts must be taken into account when
determining the lateral clearances for the buffer or safety zone.
3.8
TerminalTransitionZone
a) The terminal Transition Zone (TTZ) provides a short distance to clear the
work area and to return to normal traffic lanes. It extends from the
downstream end of the work area to the sign indicating the end of works.
b) A downstream or closing taper may be placed in the TTZ. It may be useful
in smoothening the flow of traffic. However, it may not be advisable when
the trucks carrying material move into the work area by reversing from the
downstream end of working zone. The length of the down stream taper may
be 25-30m.
c) There may be occasions when TTZ could include a transition. For example,
as in fig 5.20 if a taper is used to shift traffic into opposing lanes around the
work area, then the TTZ should have a taper to shift back to its normal path.
This taper would then be in the TTZ for the opposing direction of traffic.
d) If the construction zone is situated on a divided-carriageway, there will
need to be a smaller length transition zone to return the traffic to the
original lanes.
43
3.9
OtherAspects
Following sections are from guidelines for Safety Construction, Indian Road
Congress, IRC:SP:55:2001 p 8.
The distance between two traffic control zones should be such that the flow of
traffic can return to normal stream between them.
The length of traffic control zone will vary and depend on the work being
undertaken. The lengths of the advanced warning and transition zones are governed by
the speed of approaching vehicles and the locations of the site. The recommended
lengths for each component of the zones for a well located site ( with a clearly visible
approach ) are given in Table 2. (Guidelines for Safety Construction, Indian Road
Congress ,IRC :SP:55:2001 p 8)
It may be necessary to extend the advance warning zone where approach visibility is
poor and this will vary on a site by site basis but should not be less than that specified.
On occasions additional signing to that discussed later may need to be provided to give
not only sufficient warning but additional reminders through the advance warning zone.
The longitudinal and lateral buffer zone clearances are shown in Table 3.
Length of Advance
Warning Zone (m)
Length of Approach
Transition Zone (m)
Length of Working
Zone (m)
50 or less
100
50
51-80
100-300
50-100
) Varies
81-100
300-500
100-200
Over 100
1000
200-300
44
There may be different situations in construction zone requiring full or partial, closure
of roads for example
(a) closure of berms only e.g. repairs to slopes, construction / maintenance of road
side durians, gravelling/paving of hard shoulders, maintenance of traffic signs, repairs
to parapets of cross drainage works, guard rails;
(b) closure of small areas of the carriageway only, e.g. repairs to potholes
,resurfacing, renewing road markings;
(c) closure of lane of the carriageway along with the closure of berms e.g.
widening of the carriageway, repairs to culverts, floods damage repairs. These types of
works can further be classified according to availability or non-availability of space for
operating the displaced traffic on the remaining portion of the carriageway and
shoulders.
(d) closure of the entire road width for undertaking repairs to pavement or culvert.
Gaps in the work area may be avoided as these may falsely give an impression to
the road users that they have passed the work area. The guide signs in this regard should
be installed at appropriate locations.
i.
The same basic rules and layouts will apply in urban areas but may be it
would be necessary to modify the layouts according to site requirements. At
all times the safety of all roads users as well the site operatives should be
taken into account.
ii.
In urban situations where road works are to be carried out, more attention
should be given to the problems of pedestrians and non-motorized vehicles
in heavy traffic volumes. As far as possible, then only day time repairs
should be carried out. Repairs during peak hours should also be avoided.
iii.
Road users channelised and routed and around area under repair with
minimum of delays .Driver behavior should be effectively influenced so
that the speeds are reduced to desired levels on approaches to construction
zones. The traffic control and construction activity should be coordinated in
such a manner as to provide for safe and efficient flow of traffic together
with safe, efficient and rapid progress of construction activity.
45
iv.
v.
3.10 TrafficControlDevices
This section is from Guidelines for Safety Construction, Indian Road Congress,
IRC:SP:55:2001 p 9.
General
Traffic control devices are the equipment and installations over and on the road,
which individually and collectively perform the following tasks;
(ii)
(iii)
(iv)
Allow adequate time for proper response from road users; and
46
(v)
The primary traffic control devices used in work zones are signs, delineators,
barricades, cones, pylons, pavements markings and flashing lights. The following
general rules should apply to all traffic control devices with the traffic control zone.
(i) Comprehension: All traffic control devices should be capable of being easily
understood. A particular device must convey one and only one meaning .Good and
clean condition of the device aids comprehension;
(ii) Visibility and Stability : Devices should be within the cone of vision of the
driver and be placed such that it allows adequate response time at the average speed or
the desired speed through the traffic control zone. All traffic control devices should be
clearly visible by day and night, at these speeds and under the usually prevailing
climatic conditions. They should be kept properly aligned and legible at all times.
Foliage or any other obstruction should not be allowed to impede the view of these
devices, nor should wind, road dirt or the like be allowed to obscure their face. The
traffic control devices must be able to resist the local wind pressure, rain and the
vibrations etc, of the passing traffic but these should not act as rigid obstacles in the
event of a collision.
3.10.1Signs
The road construction and maintenance signs fall into the same three major
category as do other traffic signs, that is Regulatory signs, Warning signs and Direction
(or Guidance ) signs..Where possible, the size, colors and placement of shall confirm to
Appendices .The main signs that would be utilized are shown in figure. This manual
also covers signs that are not included in IRC: 67 but are considered desirable to aid
drivers' comprehension of the route through the road works. Each sign should be well
located so that its message is seen and is clear, which will be assisted if the
surroundings are devoid of unnecessary" signs and other clutter. These signs should be
of retro-reflective Sheetings of high intensity grade or Prismatic grade depending upon
the importance of the road as directed by the Engineer.
47
48
49
50
51
52
3.10.1.1
SignPlacement
The correct positioning and size of signs will ensure that it can observed and
recognized, thereby providing the driver with more time to react and take action.
The following principles should govern the positioning of signs:
a) Their location should have clear visibility;
b) They should be so placed that driver would have adequate time for
responses.
c) As a general rule, signs should be placed on the left-hand side of the road.
Where special emphasis is required, duplicate signs should be installed on
the left and right side of roadway .In case of hill roads, the sign shall
generally be fixed on the valley side of the road unless traffic and road
conditions warrant these to be placed on the hill side ;
d) Roll up signs mounted on portable supports may be placed within the
roadway itself.
e) Roll up signs may also be mounted on or above the barricades
f) The signs should be covered or removed when they are not required.
On kerbed roads, the extreme edge of the sign adjacent to the road shall not be
less than 600 mm away from the edge of the Kerb. On un-kerbed roads, the extreme
edge of the sign adjacent to the road shall be a distance of two to three meter away from
the edge of the carriageway depending on local conditions but in no case, shall any part
of sign come in the way of vehicular traffic. Where signs are in position for some time
and pedestrians are expected, the lower edge of the lowest sign should not be less than
two meter above the surface on which it stands. Where pedestrians are not expected,
signs may be mounted on trestles (tripod) fig.3.6. but during wet conditions should be
mounted away from the traffic splash" zone so that they do not become obscured by
dirt. Trestle mounted signs are particularly for short term temporary works. These
should be so placed that pedestrians movements are not obstructed. In urban
conditions, it may not be possible to erect new sign poles in footways crowded with
public utilities and "A" frames may be the only alternative. Signs for longer term works
should follow normal rules for the mounting of permanent signs.
53
3.10.1.2RegulatorySigns
i.
ii.
Various other signs that are needed to regulate traffic may be required
which have not been standardized. They should confirm with the general
requirements of shape and colour, and their message should be brief and
clearly understandable. [Fig 3.1 (c)]. (2001: Guidelines for Safety
Construction, Indian Road Congress ,IRC :SP:55:2001 p 16-17)
Figure 3.6
54
3.10.1.3WarningSigns
i.
Warning Signs in the traffic control zone are utilized to warn the drivers of
specific hazards that may be encountered .drivers should be altered to
potential hazards in sufficient time to adjust their movement and speed. The
most common type of warning signs for the use in the traffic control zone
are: Men at work, Road Narrows, Right lane Diverted, Right Lane Closed,
55
Left lane closed, Right Lane Closed, Median Closed, Diversion to Other
Carriageway, Traffic Signal Ahead, Two traffic, Rough Road, Loose
chipping, Divided Road and divided Road Ends [ Fig 3.1 (d) and (e) ].
ii.
iii.
iv.
v.
56
Table 3 Minimum Sightline Distances and The Minimum Size of The Signs
Average
Speed
(km/h)
Minimum
number of signs
in advance of the
hazard
Distance E to
End of Road
Works Sign
Under 50
100
600
10-30
51-60
100-300
750
10-30
61-80
120-300
900
3 or 4
10-30
81-100
300-500
1200
30-45
Over 100
1000
1200 to 1500
30-45
3.10.2
two
(i)
(ii)
(m)
Delineators
The delineators are the elements of a total system of traffic control and have
distinct purposes:
To delineate and guide the driver to and along a safe path.
As a taper: to move traffic from one lane to another.
The channelising devices such as cones, traffic cylinders, tapes, drums are
placed in or adjacent to the roadway to control the flow of traffic. These should
normally
be retro-reflectorised. Some delineators or the roadway edge have been
discussed in IRC: 79.
57
3.10.3Trafficconesandcylinders
a) Traffic cones are 500mm, 750 mm and 1000mm high and 300mm to 500mm
in diameter or in square shape at base and are often made of plastic or rubber
and normally have retro-reflectorised red and white band. Their advantages
are that they:
i. cause minor impediments to traffic flow and capacity,
ii. are well recognized and understood, without damaging vehicle
when hit,
iii. can be easily stored and transported ,
iv. can be fastened to the pavement and self-restoring when hit.
b) Their disadvantages are that they have minimal respect of drivers , can be
equally penetrated displaced and knocked over and require special treatment
for night times.
c) Cones and cylinders are easily blown over or displaced unless their bases are
loaded with ballast or anchored. It may, therefore be sometimes necessary to
double the cones in order to provide added weight, use the cones with
special weighted bases, use heavier weighted cones or use weights such as
sand bag rings to provide increased stability but this weight should not
present a hazard. The cones should be placed close enough together to give
an impression of continuity. The spacing of cones should be 3 m (close) or
9m (normal) or 18m (wide).Where cones have to be used at between 45 and
90 to the line of traffic, their spacing should be 1.2. Larger size cones
should be used where speeds are relatively high or wherever more
conspicuous guidance is needed.
d) Concrete cones painted with retro reflective paints can be used as delineators
as shown in figure .
3.10.4
Drums
2) The drums are normally metal drums e.g. empty bitumen drums cut to the
required height. They can be made of plastic also. Plastic drums are lighter,
pose fewer hazards to vehicles and workers and can be needed for easy
transportation and shortage and generally have one or more flat sides to
preclude rolling. Drums may be filled up with earth or sand for stability.
They should be painted in circumferential stripes of alternate black and
white of 100 mm to 150 mm width. Drums should be reflectorised for use at
night and should never e placed in the roadway without advance warning
signs. Fig 2 shows some typical dimensions of cones, delineators and
drums.
59
60
3.10.5
Barricades
(i)
(ii)
(iii)
(iv)
61
62
II
III
Width of Rail
200 mm-300 mm
200 mm-300 mm
200 mm-300 mm
Length of Rail
2 m 2.5 m
1 m 1.2 m
Width of Strip
200 mm
200 mm
200 mm
Type of Frame
Heavy A Frame
Light A Frame
Fixed, Demountable
Flexibility
Essentially movable
Portable
Essentially Permanent
d. Type III barricades are the permanent type and can be made of wood, metal or
other suitable material like masonry. These are erected at the point of closure when a
road section is closed to traffic on construction projects. They may extend completely
across a roadway and its shoulders or from Kerb to Kerb. Fig shows some typical ex of
fixed and moveable barricades. Where provision must be made for the access of
construction and supervision vehicles, type III barricades must be provided with a gate
or moveable section That can be opened and/or closed as required .signs such as
ROAD Closed " and "DETOUR ARROWS" should be erected on the fixed barricade.
e. Where the works are to be undertaken which will continue for some time or where
the space is limited and there is a need for the protection of the work force, particularly
63
where the speed of passing traffic may be high, purpose designed concrete or plastic
barriers may be used. Their design is often similar to the cross section of a New Jersey
Barrier or rectangular and they are some 1.5 m to 2.0 m long with shaped ends that can
be interlocked and connected .Plastic barriers available in trapezoidal shape of about 80
cm to 100 cm length can also be tried. Their use should be carefully controlled until
more experience is gained with them but they offer advantages to the workforce in that
the speed of impact will be much reduced should there be an accident and the workforce
will feel more secure. They will enable narrower traffic lanes and buffer zones to be
employed where space is a premium and vehicle speed likely to be high.
Type IV Barriers: When the work area has deep excavation which must be barricaded
from moving traffic and other road users, Type IV barricades should be used as shown
in figure 4.
64
3.10.6
Flagmen
65
66
67
3.11.
Congress
,IRC
TrafficManagementPractices
Following section is from Guidelines for Safety Construction, Indian Road Congress,
IRC :SP:55:2001 p 24.
68
3.11.1
Introduction
During the past two decades, the traffic on roads has increased manifold and most
of the roads are expected to operate at their maximum capacity in the near future. Under
the circumstances, the existing methods of maintenance and construction which
compromise safety and cause delay are no longer acceptable and a change in work
procedures and method has become inevitable. Under the existing method of
maintenance and reconstruction, the traffic is invariably diverted over unprepared
shoulders or forced to use part of the existing roads under maintenance. This results in
the vehicle operating cost and reduction in safety besides causing environmental
pollution. Therefore, the existing work procedure and contract conditions are required
to be changed to provide for proper management strategies to be used at traffic control
zones must include the following fundamental principles:
(i)
Make traffic safety an integral and high priority element of every project,
3.11.2
SiteLayoutDefinitions
Work zone
Working space : the space around the works area that will need to store tools,
excavated material, equipment and plant. It is also the space to allow workmen to move
around to do the job. Enough working space must be left to make sure that the
movement and operation of the plant (e.g. swinging of jibs and excavator arms) is clear
of passing traffic and is not encroaching into the safety zone.
Safety Zone : The zone that is provided to protect workmen from traffic and to protect
the traffic from them. The safety zone must not be entered in the normal course of
work. Materials and equipment must not be placed in the zone either. Workmen will
69
only need to enter the zone to maintain cones and other road signs. The safety zone is
made up from
Approach Transition Zone : This will vary with the speed limit and the width of the
works as given in Table 5.
Longitudinal Buffer Zone: This is the length between the end of the lead-in taper of
cones(T) and the working space. It will vary with the speed limit as given in Table 5.
Lateral Buffer Zone : This is the width between the working space and moving traffic.
It will vary with the speed limit as given in Table 5. (2001: Guidelines for Safety
Construction, Indian Road Congress, IRC :SP:55:2001 p 27)
The lateral buffer zone safety clearance is measured from the outside edge of the
working space to the bottom of the conical sections of the cones on the side nearest to
the traffic .For roads with a speed restriction of 80 km /h or greater as additional traffic
barrier is required at the end of the lead-in taper.
70
Minimum longitudinal
buffer zone (L) (m)
50 or less
5.0
0.5
60
15
0.5
80
30
1.2
100
60
1.2
120
120
1.2
Where an advisory speed limit is in operation, use it (rather than the mandatory
speed limit) to determine the minimum longitudinal and lateral buffer zone safety
clearances. Whenever traffic speeds are to be reduced, the method must be agreed in
advance with the road authority. Site Engineer should consider advising emergency
services of the location and duration of the works.
Working space and safety zones must be provided when personnel are present, but
when a site becomes unoccupied it may be possible to make it smaller. This will make it
less of an obstruction to traffic. However, if pedestrians are diverted into the
carriageway, a safety zone must be provided at all times between the outer pedestrian
barrier and the traffic.
71
Where the road width is so restricted as to prohibit the provision of the appropriate
lateral buffer safety clearance detailed in Table 5, and diversion of traffic would be
impractical, traffic speeds must be reduced to less than 15 km/h and an agreed safe
method of working imposed on the site. This method of working should preclude
working in the safety zone wherever possible. It must be decided in advance of the
works. It is also advised that it should be recorded in writing.
3.11.2.1
BasicLayout
a.
Though each construction zone will pose unique problems there is a basic layout
that should be followed for all schemes but that will need to be amended within the
guidelines set out in these guidelines. These will be influenced by :
(i)
(ii) type of carriageway such as single lane ,two lane ,four lanes, multi lanes, divided
carriageway;
(iii) traffic volume and speed with and without work in progress on road;
(iv) type of traffic such as mixed or segregated;
(v)
(vi) mobility of work zone ,that is, for minor pot hole repairs, lane marking etc, the
workers and equipment may move along the road.
b. Figure 7 shows the basic layout that would permit two-way flow of traffic pass the
working zone. The road width must be at least 6.5 m for two way traffic to ensure that
problems for buses and Lorries are minimized . It should be noted that pedestrians are
retained on the existing footway. It should be noted that where the working zone is
long, cyclists can experience problems and this should also be taken into account.
Temporary markings and signages should be used as shown in figure 7.
c. On the roads with no buses or goods vehicles and low flows of vulnerable road users,
width of 5.5m could be acceptable but two-way working would not be possible. In this
case the cones should be used to reduce the carriageway to not more than 3.7 m and
traffic should be controlled by one of the methods given below.
d. The minimum width for one-way traffic is 3.25 m with an absolute minimum of 3 m.
As the basic layout should be used in all cases, including lightly used roads in housing
72
areas where there are only cars and other light vehicles, in these special circumstances,
the minimum width may be reduced to 2.75 m with an absolute minimum of 2.5 m.
e. In cases where a traffic control zone may affect an adjacent railway crossing and
there is a chance that traffic may block back across the railway line the railway
authorities should be informed .It may be necessary to put in place additional safe
guards through the use of additional staff to monitor traffic at the railway and to ensure
that at no time does traffic wait on the crossing itself.
f. Similarly, and more commonly, care needs to be taken if the shuttle working area
contains a road junction, the simpler layout may not be acceptable and it will be
necessary to use traffic signals to control all the arms. This is dealt with in a separate
section.
73
74
3.11.2.2VariationsontheBasicLayout
a. Give and take system: Figure 8 illustrates the Give and Take system of shuttle
working. This is intended for low flows and very low volumes of Lorries and no buses.
The following conditions must apply:
- total two -way traffic flow of less than 400 veh/ hour ;
- less than 20 lorries /hour;
- speed limit is 50 km / h or less and
- length of the working zone plus both transition zones is not more than 50 m ; and
- drivers approaching from either direction can see both ends of the site.
b. Priority signs: As flows and the difficulties of the site increase, enhanced systems
are more appreciable. Fig 9 illustrates the next stage; under traffic control by priority
signs the following condition apply:
- total two-way traffic flow of less than 850 veh/hour
- length of the working zone plus both transition zones is not more than 80 m ;
- drivers approaching from either direction can see through the site from a point 60 m
from their entry transition zone to a point 60 m beyond their exit transition zone ( coned
area ), for roads with a 50 km/h speed limit, on higher speed roads the appropriate clear
visibility distances are
- 70m on 60 km/h roads;
- Not applicable above this speed limit.
In Indian conditions, its use is not recommended on higher speed roads.
Priority must be given to either:
- The unobstructed vehicle lane; or
- Vehicles going up a steep gradient
75
30
Rumble Strips
at 80 m C/C
30
STOP/GO
Board
Diversion Sign
for 1-Lane traffic
( speed Limit )
76
30
STOP/GO
Board for
Priority Traffic
Rumble
Strips at 80
m C/C
30
Diversion Sign
for 1-Lane traffic
( speed Limit )
Priority Sign
STOP Line at
Non Priority
Traffic
Rumble Strips at 80 m C/C
77
c.
Stop/Go boards or flags: Figure 10 indicates the layout for the use of
STOP/GO boards or flagmen. Table 6 sets out the conditions for their use. (2001:
Guidelines for Safety Construction, Indian Road Congress, IRC :SP:55:2001 p 32)
30
STOP/GO
Board or
STOP Sign
30
Diversion Sign
for 1-Lane traffic
( speed Limit )
STOP/GO
Board
78
Vehicle/ hour
Vehicles/3minutes
100
1400
70
200
1250
63
300
1050
53
400
950
47
500
850
42
3.12 PortableTrafficSignals
a) Portable Traffic Signals for traffic Signals for traffic control can be used at most
sites that have a length of 300m or less. However, it should be ensured that the
exit from the restricted length of road is not blocked. Otherwise tailbacks will
occur which will stop traffic traveling in the opposite direction from the moving
when the lights change to green.
c) If it is considered that portable traffic signals used elsewhere may cause road
traffic to block back to a level crossing, railway management must be consulted
before work starts. The solution will probably be to move the traffic control to a
point on the side of the crossing opposite the works so that traffic can be stopped
before reaching the crossing. The portable traffic signals must be controlled
manually. The crossings own road traffic signals and advance warning and
informatory signs should remain clearly visible to approaching vehicle drivers.
79
d) The road authority and traffic police must be informed when Portable Traffic
Signals are going to be used .Authorization will be required if these signals are
to be used at road junctions.
e) The requirements for setting out the signs, cones and portable traffic signals are
given in Table 4.1. This gives dimension D, the site layout definitions and the
definition of working space and Table 4.2 gives the dimensions of the Buffer
Zone Safety Clearance. Fig 4.5 shows the layout of working zone and traffic
control by portable traffic signals.
f) The traffic signal timings must be correctly set up to correspond to the length of
the works and the speed of the traffic past the site. The detectors must be tested,
which are sometimes provided on the signals, to make sure that they are
working properly before they are used.
g) As back up, Stop/Go board should be available in case the Portable Traffic
Signals break down.
3.13 WorksonFootwaysAlternativewayforpedestrians
3. Exceptionally, the use of the other footway may be acceptable in some quiet
roads, but if this option is selected the alternative route must be safe to use, and
the needs of the children and of people with disabilities must be taken into
account.
80
3.14 PedestrianSafety
2. Kerb ramps or raised footways should be provided to help blind, poorly sighted,
elderly and disabled people and for those with prams or wheelchairs.
3.14.1PedestrianBarriers
a. Pedestrian barriers should be used to mark out any temporary footway. A rigid
barrier must always be used to protect pedestrians from traffic, excavations, plant or
materials. Place road danger lamps at the ends of the barriers at night. Portable
pedestrian barriers, which may include mesh, should be reasonably rigid and have:
- a hand rail fixed at between 1.0 m and 1.2m above ground level, which should be
reasonably smooth and rigid for pedestrians to hold to obtain guidance and some
measure of support;
- a visibility panel at least 150 mm deep which may be integral with the hand rail or if
separate must be fixed so that its upper edge is a minimum of 0.9 m above ground level.
81
Visibility panels of yellow, white or orange colours are best for detection by partially
sighted people, while the red and white rail gives a good contrast and provides
interchangeability with traffic barriers ; and
- a tapping rail ( for blind people with a white stick ) of min depth 150 mm with a lower
edge at ground level or up to a min height of 200 mm above the ground.
3.14.2VisuallyHandicapped
It should be ensured that the barriers can be detected easily by a visually handicapped
person using a cane stick.
2) Safety Zones: A safety zone is provided in the carriageway if the works are
closer to the Kerb than the width of the Lateral Buffer Safety Clearance as
given in Table 4.2. Use the basic layout in Fig.4.1 to help with the approach
signing and guarding of the safety zone.
3.14.3
WorksatJunctions
82
The two-way traffic should be kept flowing past the works if possible. If this is not
possible, a diversion route may be required and should be identified by the Road
Authority.
Men at Works signs with arrow plated will be required on the main route if the
workspace located on a side road. (Fig. 4.7)
Fig 11 shows on or near the far side of a junction. At works like these the taper of
cones should be taken up to the approach side of the junction but that any cones near the
junction mouth help drivers turn left smoothly. Table 4.1 gives the dimensions D and T
and the Site Layout Definitions of 'working space' and the Table 4.2 dimensions of the
safety zone.
83
84
b. The Central line of the road shifted (eccentric widening) : While constructing the
additional carriageway, the centre line of new road/highway gets shifted to a new
location. It would have two stages of construction:a) The new carriageway shall be constructed in the first stage, adjacent to the
existing one and the shoulder in between would become part of the central
median of the improved divided carriageway facility. The traffic would continue
to ply in both directions on the existing carriageway and an approached
diversion would be taken out of the works zone for the movement of
construction and supervision vehicles.
c.
No shift in central line of the road (co-centric widening): This activity would
be mostly required to be taken up in the stretches of the road/highway passing through
built up portions where there may be constraints of land availability. At such locations
service roads would also be necessarily constructed for the segregation of the local
traffic.
1. Stage I shall be construction of service roads or diversion road and the traffic
moving on the existing carriageway in both directions. The typical layout of
signs and control measures shall be, as shown in Fig. 12.
2. Stage II of the construction activity shall be strengthening of the existing
carriageway and the construction of the median. The traffic shall move in one
direction only on the service /diversion road constructed on both sides in stage I.
The layout for signs and traffic control devices for this stage should be as shown
in fig.13
3. In stage III, the work zone shall be shifted to take up the co-centric widening to
the adjacent stretch of the road/highway. Fig. 4.13 shows the layout for signs
and traffic control devices for this stage.
85
30
Work
Zone
Information with
Speed Limit
STOP/GO Board
STOP/GO Board
Diversion Sign
for 1-Lane traffic
( speed Limit )
30
30
Work
Zone
Information with
Speed Limit
86
30
Work
Zone
Information with
Speed Limit
STOP/GO Board
STOP/GO Board
Diversion Sign
for 1-Lane traffic
( speed Limit )
30
30
Work
Zone
Information with
Speed Limit
87
3.15 DividedCarriagewayRoads
(2001: Guidelines for Safety Construction, Indian Road Congress ,IRC :SP:55:2001
p 40)
a) Divided Carriageway Roads can be found in urban areas where the main
purpose is to cope with the expected traffic volumes besides providing fast
communications between urban centers. The section deals with divided
carriageways in general while expressways and high speed divided
carriageway roads are dealt with in a separate section.
b) Great care must be taken on main divided roads, as both traffic volumes and
speeds are likely to be high. If the work on these roads involves closing the
right hand lane, liaison with the police and road authority will be necessary.
c) Right Lane closure: Fig 14 shows a right hand lane closure. Care has to be
taken in this situation. The traffic should be led into the left lane in good
time to allow drivers time to merge into a single lane. The detailed
dimensions in the Tables 4.1 and 4.2.
d) Left Lane closure: If the left-hand lane is closed merging traffic to the left
by using a guide island is advisable before transferring into the right - hand
lane. If two or more lanes have to be transferred to the right, the
carriageway markings must be changed to make sure that the traffic lanes
are continuous. The length of the guide islands should be :
e) 50 m long for roads with an 80 km/h or less speed limit, and 100 m long for
roads with a 100 km/h or more speed limit (section on expressways and
high speed divided carriageway roads should also be referred.)
f) It may be necessary to merge traffic to the right at a left lane closure - for
example form lane 1 into lane 2. It can be done when:
g) lane 1 of a six lane divided carriageway is being closed ; or
h) there will be no more than about 60 vehicles per 3 minutes on each traffic
lane which is left open .
88
i) Signage Requirements: The signage requirements will vary with the speed
limit as follows. (2001: Guidelines for Safety Construction, Indian Road
Congress ,IRC :SP:55:2001 p 46)
Speed Limit
Signage Requirements
50 Km/h
60 Km/h
80 Km/h or
more
As shown in Figs. 14 and 15, but with an extra Lane closed to traffic
sign added on each side of the carriageway to give the sequence of
signs on the right of this page.
89
90
Rumble Strips at
80 m C/C
30
STOP/GO Board
30
Rumble Strips at
80 m C/C
Figure 15:
91
Rumble Strips at
80 m C/C
Rumble Strips at
80 m C/C
30
80 m
Rumble Strips
at 80 m C/C
Rumble Strips
at 80 m C/C
30
Figure 16:
92
Rumble Strips
at 80 m C/C
30
STOP/GO Board
Rumble Strips
at 80 m C/C
Rumble Strips
at 80 m C/C
STOP/GO Board
30
Rumble Strips
at 80 m C/C
Figure 17:
93
Rumble Strips
at 80 m C/C
30
STOP/GO Board
STOP/GO Board
Rumble Strips
at 80 m C/C
Rumble Strips
at 80 m C/C
30
Rumble Strips
at 80 m C/C
Figure 18:
(From New Recommended IRC)
94
Setting out : Table 4.1 gives dimension D and T and Sign Layout Definitions for
the definition of working space and the table 4.2 for the dimensions of the safety zone.
(i) Repairing the edges of the carriageway, shoulders, cleaning out drains, cutting
grass etc, where carriageway is basically not affected. Before starting the work, all
warning signs and traffic control devices should be placed as discussed above. These
should, however, be suitably modified duly keeping in view the size of construction
activities and whether it is rural or urban area. A flagman is probably sufficient and
should be present during the work duration;
(ii) Repairing small areas of the carriageway, the traffic is to be restricted only due
to repairs being carried out as major pothole and / or patch repairs , The work should
preferably be so organized that only half width of carriageway is closed at a time and
traffic is allowed on other half and traffic control devices as discussed above
( iii ) While working on the centre of the carriageway such as centre line, lane
marking necessitates the traffic to use restricted width on either side. This situation is
generally not acceptable and where possible, the work should be undertaken through the
closure of half of the carriageway .If this is not possible, the layout shown in Fig 4.16
should be used, with extreme caution.
3.16 ExpresswayandHighSpeedDividedCarriagewayRoads
95
Because of the high speed of the vehicles using these roads, extreme care has to be
taken when road works are carried out. Stopping distances increase considerably with
each 10 km/h increase in speed. Drivers therefore have to have very early warning of
restrictions on the road. If an accidents happens on this type of highway are discussed in
succeeding paras. The key to symbols used in these illustrations is shown in fig 19.
Many traffic management techniques are available for longer duration operation:
(i) Partial closure for work on the carriageway;
(ii) Partial closure for work on shoulders;
(iii) Detour on secondary network;
(iv) Detour on a temporary diversions; and
(v) Speed control
96
30
Diversion Sign
for 1-Lane traffic
( speed Limit )
Rumble Strips
at 80 m C/C
30
Figure 19:
97
STOP/GO
Board
30
Diversion Sign
for 1-Lane traffic
( speed Limit )
Rumble Strips at
80 m C/C
Figure 20:
(From New Recommended IRC)
98
3.17 CarriagewayRoads
3.17.1
Fourlanedividedcarriagewaysrightlaneclosure
The basic layout for a four lane divided high speed road is similar to those shown
in fig 4.14 and 4.18.Great care has to be taken in this situation. The traffic should be led
into the left lane in good time to allow drivers time to merge into a single lane. Location
of signs should be so given in fig 4.18 and details of 'B' and 'C' as per Fig 4.17.
3.17.2
Fourlanedividedcarriagewaysleftlaneclosure
If the left lane is closed normally traffic should be merged to the left by using a
guide before transferring into the right - hand lane. If two or more lanes have to be
transferred to the right, the carriageway markings must be changed to make sure that the
traffic lanes are continuous. The length of the guide islands should be :
- 50 m long for roads with a 80 km / h or less speed limit; and 100 m long for roads
with a 100 km/h or more speed limit. If merging traffic to the right at a left -hand lane
closure is required this can be done when :
- Lane 11 of a six lane divided carriageway is being closed; or
- there will be no more than about 60 vehicles per 3 min on each traffic lane which
is left open ( 1200 vehicle/h for each traffic lane open)
3.17.3
Four lane divided carriagewayscarriageway closure with
diversiontooppositecarriageway
On occasions it may be necessary to close-one carriageway completely over a
distance for major carriageway repairs or resurfacing. This can only be done by using (
or specially constructing) emergency crossing points through the median and diverting
all the traffic in both directions onto a single lane in opposite directions on one
carriageway. This does reduce capacity, and is likely to cause some delays for
motorists. The illustration shown in Fig 4.20 shows the procedure for this diversion.
Setting out: Table 4.1 gives the dimensions for D and T, site layout definitions and
the definition of working space (reference Fig 5.1) and the dimensions of the safety
zones are fixed in table 4.2
99
3.17.4
SixlaneDividedCarriagewaysandExpressways
These roads are often carrying very high traffic volumes. It therefore, become
important to avoid reducing the capacity of the road. As more road space is available
than on a four lane divided carriageway, the works can be carried out with only about
one third loss of capacity. This would be achieved by a contra flow arrangement.
Closing lanes without providing a contra flow should only be done during light traffic
flows.
Left and centre lane closed: This arrangement is shown in detail in the illustration
in fig 4.21.
Right and centre lane closed: This arrangement is shown in detail in the
illustration in fig 4.22.
100
Figure 21:
101
Figure 22:
(2001: Guidelines for Safety Construction, Indian Road Congress, IRC :SP:55:2001
p 51-55)
102
Rumble Strips at
80 m C/C
30
Rumble Strips at
80 m C/C
Figure 23:
103
30
Figure 24:
(From New Recommended IRC)
104
A. Segregated contra flow with buffer zones (Primary hard shoulders used):
This arrangement is shown in detail in the illustration in Fig 4.23.This is used on
roads with a full lane-width emergency hard shoulder .It requires the use of the
opposite carriageway for contra flow of one lane. Only two lane traffic is
provided for through the road works with the nearside lane being diverted onto
the hard shoulder. The offside lane is closed and the middle lane diverted onto
the opposite carriageway that also accommodates two lanes of traffic in the
opposite direction. It provides two working lanes plus a buffer lane for the
safety of the workforce. This arrangement can only be used if there is a hard
shoulder capable of taking heavy traffic, or if one is provided as part of the
works.
B. Segregated contra flow with buffer zones (Both hard shoulders used): This
arrangement is shown in detail in the illustration in fig 5.24 and is used on roads
with a full lane-width emergency hard shoulder. It requires the use of the
opposite carriageway for contra flow of one lane. Two lanes are provided for
traffic on the primary carriageway with three lanes provided in the opposite
direction by using the hard shoulder. It provides two working lanes plus a buffer
for the safety of the workforce. This arrangement can only be used if there is a
hard shoulder capable of taking heavy traffic, or if one is provided as part of the
works.
3.18 DetourviaSecondaryNetwork
(2001: Guidelines for Safety Construction, Indian Road Congress, IRC :SP:55:2001
p 56)
a. In the rural situations it may be possible to reduce traffic flows past the construction
zone by diverting traffic to an existing alternative route, thereby improving safety at the
site. However, it is likely that this will be a road of lower category and it is also likely
that the increase in traffic flows will bring about an increase of accidents on the
alternative route .Residential roads in cities should, if possible, be avoided. It is,
therefore, acceptable only with low traffic volumes. In such cases, it causes a lot of
inconvenience to the users. Before diverting the traffic to any alternative route it must
be ensured that traffic detours:
(i) are compatible with additional traffic in terms of geometric and structural length.
These should be improved to the extent possible to have safe and smooth flow of traffic;
(ii) have efficient driver information and
(iii) are clearly identifiable throughout.
105
b. The public in the area affected, and intending road users should be well informed
through press and other mass media about the closure/partial closure of the road and the
alternatives for through traffic.
c. Guidance regarding the diversion of traffic to the alternative route must be provided
at the appropriate road intersections on either side of the section with the construction
zone so that it is possible for the through traffic to divert. This must be done with
suitable warning, regulatory and guide signs at the intersection, for approaching traffic,
together with a supplementary plate stating " ROAD AHEAD CLOSED' and with the
distance to the hazards. There should also be a diversion sign, indicating the turn to be
taken. Again it must be emphasized that once traffic is diverted onto the alternative
route all junctions along the route must be provided with signages until the original
route is rejoined. If space to site new signs is limited, the use of a symbol is encouraged.
The signs at the diversion would state for diversion follow symbol ", which should
then be continued until the original route is rejoined. It is, of course, possible to use
different signed routes for the different irections of flow to reduce problems along the
alternative routes.
d. At the intersection where the diversion starts, and if the road is fully closed, the use
of the permanent type barricade (Type III) is recommended. Suitable 'Chevron' signs
and 'Diversion' sign should also be provided at this location for the guidance of the
approaching traffic. A watchman should invariably be present at these barricades. A
small opening should be provided, if need be at the extreme edge of the carriageway, at
this location. This should normally be kept closed with a double row of painted tar
drums. These drums should be removed only for permitting the vehicle for construction
and supervision, to pass each time and be put back in position immediately thereafter.
At night, lanterns with red light should be places at the drums for delineation. Suitable
direction and destination signs should also be provided at appropriate locations for the
guidance and smooth flow of traffic through the alternative route. The detour ' arrow'
signs should also be used at sharp turns on the diversion. Typical arrangements
according to the above plan are illustrated in Fig 4.25.
e. Alternative routes are more likely in urban areas and at confined sites it may be
necessary to utilize the technique to permit the work to be undertaken at all. However,
there is similar safety implication of diverting large volumes of traffic in choosing the
alternative routes and in providing signages.
106
30
Figure 25:
107
30
Figure 26:
108
30
30
30
30
30
Figure 27:
109
30
30
30
30
30
30
30
Figure 28:
(From New Recommended IRC)
110
3.19 TemporaryDiversions
Where the construction zone would close the road completely, the remaining
carriageway space would be insufficient for the traffic and create large delays, and there
is no suitable alternative route, it will be necessary to construct a temporary
carriageway for all or part of the traffic. This is most common situation in the cases of
any major or reconstruction of cross drainage works and of pavement failure due to, for
example, floods.
ii.
iii.
iv.
It should be dust free and shoulder ensure clear visibility at all times
of day and night;
v.
This requires that some of the existing work practices and procedures are changed
or abolished. For example, any separate area for stockpiling of construction material on
or very near carriageway will have to be discontinued. The present practice of exposing
the workman to traffic while carrying out works in the centre of the carriageway must
be discontinued.
Fig 26 shows the layout for sign and traffic control devices for temporary
diversions.
111
Figure 29: layout for sign and traffic control devices for temporary
diversion
112
3.20 SpeedControl
In most cases, work on the existing road encroaches on the running lanes and
shoulders and, therefore, cause a hindrance to the normal flow of traffic. In such
situations the closing of lanes is a normal practice. In any traffic management at road
works situation, traffic using lanes which are to be closed should have time and space
for merging with traffic in the next parallel lane as well as to transfer to provisional or
altered lanes or both. Normally this requires some reduction in speed, enough advance
information to enable safe merging. The critical information for approaching drivers is
as to which lane is blocked so that they can begin moving into the open lane at an early
stage.
It is preferable to close first the fastest lane and not the slowest, even if the work
zone occupies the latter. The reason for this is that slow moving commercial vehicles
are more reluctant to give way than the more maneuverable cars which use the fast lane.
In this method a reduction in speed is also more easily achieved. If the work zone
occupies a centre lane of a multi - lane road, it is recommended to close the adjacent
lane to avoid an 'island' situation.
Speed Control should often extend through the work site and will depend on the
volume of traffic and the width of the traffic lanes that it is feasible to permit. Traffic
lanes can be reduced to 3.0 m where space is restricted and, if used by cars and light
vehicles only may be reduced to 2.75m with caution. The maximum length of a lane
closure would depend upon the traffic volume and number of remaining lanes and
normally it should not exceed 5 km where speed control is in operation.
The co-operation of the local police should be sought to the introduction of a
temporary but mandatory speed limit, lower than the existing speed limit on the
approaches and through the working zone. This may be as low as 50 km/h even for high
speed roads, where only on lane is available for traffic.
Speed reducing measurement such as speed rumbles must be installed as explained
below
113
Figure 30:
114
Figure 31:
(2001: Guidelines for Safety Construction, Indian Road Congress ,IRC :SP:55:2001, fig
4.27 p 66)
115
In weekend
(iii)
116
117
AppendixISpecificationofReflectiveSheeting
1.1. Scope
The specification covers flexible, high intensity grade and micro-prismatic retro-reflective
sheeting designed for use on traffic control signs, delineators, barricades and other devices.
1.2. Description
1.2.1 High intensity grade sheeting: This sheeting shall be of encapsulated lens type
consisting of spherical glass lens, elements adhered to a synthetic resin and encapsulated by a
flexible, transparent, water proof plastic having a smooth surface. The retro reflective surface,
after cleaning with soap and water and in dry condition shall have the minimum co-efficient
of retro reflection (determined in accordance with ASTM E 810) as indicated in Table 1.
TABLE 1: Acceptable Minimum Coefficient Of Retro Reflection For High Intensity Grade
Sheeting (Candelas Per Lux Per Square Metre)
Observation
Angle (in deg)
Entrance
Angle (in deg)
White
Yellow
Green
Red
Blue
0.2
- 4
250
170
45
45
20
0.2
+ 30
150
100
25
25
11
0.5
- 4
95
62
15
15
7.5
0.5
+ 30
65
45
10
10
5.0
When totally wet, the sheeting shall not show less than 90 percent of the values of retroreflectance indicated in Table 1. At the end of 7 years, the sheeting shall retain at least 75
percent of its original retro-reflectance.
118
1.2.2. High intensity prismatic grade sheeting: The reflective sheeting shall be high
intensity retro reflective sheeting made of unmetallized microprismatic retro reflective
element material. The retro reflective surface, after cleaning with soap and water and in dry
condition shall have the minimum co-efficient of retro reflection (determined in accordance
with ASTM E 810) as indicated in Table 2.
Observation
Angle (in deg)
Entrance
Angle (in deg)
White
Yellow
Green
Red
Blue
0.2
- 4
360
270
50
65
30
0.2
+ 30
170
135
25
30
14
0.5
- 4
150
110
21
27
13
0.5
+ 30
72
54
10
13
When totally wet, the sheeting shall not show less than 90 percent of the values of retroreflectance indicated in Table 2. At the end of 7 years, the sheeting shall retain at least 75
percent of its original retro-reflectance. This retro-reflective sheeting shall confirm to type
IV sheeting classification specified in ASTM D-4956 standard specification for retroreflective sheeting for traffic control.
1.2.3. Super High-Intensity prismatic grade sheeting: The reflective sheeting shall be very
high intensity retro reflective sheeting made of unmetallized microprismatic retro reflective
element material. The retro reflective surface, after cleaning with soap and water and in dry
condition shall have the minimum co-efficient of retro reflection (determined in accordance
with ASTM E 810) as indicated in Table 3.
119
TABLE 3: Acceptable Minimum Coefficient Of Retro Reflection For Super High Intensity
Prismatic Grade Sheeting (Candelas Per Lux Per Square Metre)
Observation
Angle (in deg)
Entrance
White
Yellow
Orange
Red
Blue
0.2
- 4
700
525
265
105
42
0.2
+ 30
325
245
120
49
20
0.5
- 4
250
190
94
38
15
0.5
+ 30
115
86
43
17
When totally wet, the sheeting shall not show less than 90 percent of the values of retroreflectance indicated in Table 3. At the end of 7 years, the sheeting shall retain at least 75
percent of its original retro-reflectance. Typical application for super high intensity prismatic
grade sheeting shall be for cautionary, mandatory signs for State Highways, National
Highways and Major District Roads involving narrow observation angles.
Prohibitory signs
Compulsory Direction Control Signs
Cautionary / warning Signs
Informatory Signs
Supplementary Plates
1.2.4. Prismatic Retro reflective Sheeting for Roll up Signs: The sheeting shall be
flexible, white or fluorescent orange, wide angle prismatic retro reflective sheeting and
related processing materials designed to enhance the visibility of traffic control signs and
objects under all driving conditions, day and night. The sheeting shall consist of prismatic
lenses formed in a transparent clear or fluorescent orange synthetic resin, sealed, and backed
with a flexible coated fabric backing. The coefficients of Retroreflection shall not
120
be less than the minimum values specified in Table 4. Testing shall be in accordance with
ASTM E-810 and the values of 0 rotation and 90 rotation will be averaged to determine the
RA.
Table 4: Minimum Coefficient of Retroreflection RA (cd/lux/m2)
Observation
Angle (in deg)
Entrance
Angle (in deg)
White
Fluorescent
Orange
0.2
-4
300
200
0.2
+30
180
120
0.2
+45
100
60
0.5
-4
200
120
0.5
+30
75
50
0.5
+45
60
30
1.0
-4
100
10
1.0
+30
60
10
1.0
+45
15
10
At the end of 3 years the sheeting shall remain at least 50% of its original retro- reflectance.
A typical application for this material is urban areas with dense population and where signs
cannot be placed on roads.
121
AppendixIIColourSpecificationLimits
The colour of the material shall be located within the area defined by the chromaticity
coordinates in Table 5 and comply with the luminance factor as per ASTM D 4956.
Table 5
ColorSpecificationLimits(Daytime)
Daytime
Luminance
factor(Y%)
Color
Min
Max
White
0.303
0.300
0.368
0.366
0.340
0.393
0.274
0.329
15
Yellow
0.498
0.412
0.557
0.442
0.479
0.520
0.438
0.472
24
45
Green
0.026
0.399
0.166
0.364
0.286
0.446
0.207
0.771
2.5
11
Red
0.648
0.351
0.735
0.265
0.629
0.281
0.565
0.346
2.5
11
Blue
0.140
0.035
0.244
0.210
0.190
0.255
0.065
0.216
10
Orange
0.558
0.352
0.636
0.364
0.570
0.429
0.506
0.404
12
30
Brown
0.430
0.340
0.610
0.390
0.550
0.450
0.430
0.390
Fluoresc
ent
Yellow
0.479
0.520
0.446
0.483
0.512
0.421
0.557
0.442
45
Fluoresc
ent
Yellow
Green
0.387
0.610
0.369
0.546
0.428
0.496
0.460
0.540
60
Fluoresc
ent
Orange
0.583
0.416
0.535
0.400
0.595
0.351
0.645
0.355
25
The Colours shall be durable and uniform in acceptable hue when viewed in day light or
under normal headlights at night.
122
AppendixIII
TypesofSignsandColourUsed
Table 6
S.N
Type of Signs
Colour
Background
Stop
Legend/Arrow Border
Red
white
white
Give Way
White
Black
Red
Prohibitory Signs
Orange
Black
Black
Orange
Black
----
Informatory Signs
Orange
Black
Black
Cautionary signs
Orange
Black
Red
Supplementary Signs
Orange
Black
Black
123
AppendixIV
SpecificationsofAluminiumandAluminiumCompositematerial
Aluminium: Aluminium sheets used for sign boards shall be of smooth, hard and corrosion
resistant aluminium alloy conforming to IS: 736-Material designation 24345 or 1900.Signs
with a maximum side dimensions not exceeding 600 mm shall not be less than 1.5 mm thick.
All others shall be at least 2 mm thick. The thickness of the sheet shall be related to the size
of the sign and its support and shall be such that it does not bend or deform under the
prevailing wind and other loads.
124
TABLE 7
SpecificationforAluminumCompositeMaterial
S.N Description
Specification
Standardtest
Acceptablevalue/result
Standardtest
Acceptablevalue/result
MechanicalPropertiesOfACM
Morethan4N/mm
Tensilestrength
ASTME8
Morethan40N/mm2
0.2%ProofStress
ASTME8
Morethan34N/mm2
Elongation
ASTME8
6%
Flexuralstrength
ASTM393
Morethan130N/mm2
Flexuralmodulus
ASTM393
Morethan44,000N/mm2
ShearstrengthwithPunchsheartest
ASTM732
Morethan30N/mm2
PropertiesofAluminumSkin
Tensilestrength(Rm)
ASTME8
Min165N/mm2
Modulesofelasticity
ASTME8
Min70,000N/mm2
Elongation
ASTME8
A502%
0.2%proofstress
ASTME8
Min10N/mm2
125
AppendixV
SpecificationforTrafficCones
1.
2.
Definitions: All parts of the cones and cylinders except the retro-reflective portion.
Colour: The Colour of traffic cones and cylinder shall be red and comply to BS 873:
Part 8.
Min Luminance
0.690
0.575
0.521
0.610
Red
Factor
0.11
0.310
0.316
0.371
0.390
The traffic cone shall also confirm to the following specific requirements:
126
Body Material : PVC type or medium density polythlene (PE) type.The design of the
cones shall allow stacking within each other without binding and
without causing damage to the retro-reflective surfaces.
Sleeve
Logo
Test
127
Unit4
SafetyinRoadConstructionWorks
The contractor shall prepare the method statement for all the activities that he/she intends
to perform in order to fulfil his/her contractual obligations. Before starting any of the activity
the contractor shall make sure to get the approval of Construction Supervisory Consultant
(CSC)
4.1General
The Contractor shall take all precautions for safeguarding the environment during the
course of the construction of the works. He shall abide by all laws, rules and regulations in
force governing pollution and environmental protection that are applicable in the area where
the works are situated.
Quarry Operations
The Contractor shall obtain materials from quarries only after the consent of the Forest
Department or other concerned authorities is obtained. The quarry operations shall be
undertaken within the purview of the rules and regulations in force.
Control of Soil Erosion, Sedimentation and Water Pollution
The Contractor shall carry out the works in such a manner that soil erosion is fully
controlled, and sedimentation and pollution of natural water courses, ponds, tanks and
reservoirs is avoided.
etc. shall be located sufficiently away from habitation, agricultural operations or industrial
establishments. The Contractor shall take every precaution to reduce the levels of noise,
vibration, dust and emissions from his plants and shall be fully responsible for any claims
for damages caused to the owners of property, fields and residences in the vicinity and
violation of pollution control norms, if any.
Substances Hazardous to Health
The Contractor shall not use or generate any materials in the road construction works
which are hazardous to the health of persons, animals or vegetation. Where it is necessary to
use some substances which can cause injury to the health of workers, the Contractor shall
provide protective clothing or appliances to his workers.
Clearance shall be effected immediately by sweeping and removal of debris, and all dust,
mud and other debris shall be removed entirely from the road surface.
Additionally, if so directed by the Engineer, the road surface shall be hosed or watered
using suitable equipment.
Compliance with the foregoing will not relieve the Contractor of any responsibility for
complying with the requirements of any Highways Authority in respect of the roads used by
him.
129
4.1.2 MethodologyandSequenceOfWork
Prior to start of the construction activities at site, the Contractor shall, within 28 days
after the date of the Letter of Acceptance unless otherwise stipulated in the Contract, submit
to the Engineer for approval, the detailed method statement. The method statement shall be
submitted in two parts.
The general part of the method statement shall describe the Contractors proposals
regarding preliminary works, common facilities and other items that require consideration the
early stage of the contract. The general part shall include information on:
a) Source of materials like coarse aggregate and fine aggregate, quantity and quality of
materials available in different sources;
b) Source of manufactured materials like cement, steel reinforcement, pre-stressing
strands and bearings etc. He shall also submit samples/ test certificates of materials for
consideration of the Engineer;
c) Location of the site facilities such as batching plant, hot mix plant, aggregate
processing unit etc;
d) Details of facilities available for transportation of men/material and equipments;
e) Information on procedure to be adopted by the Contractor for prevention and
mitigation of negative environmental impact due to construction activities;
f) Safety arrangement during construction:
g) Any other information required by the Engineer.
4.2 EarthWork
4.2.1Excavationforroadwayanddrains
Scope
This work shall consist of excavation, removal and satisfactory disposal of materials
necessary for the construction of roadway, side drains and waterways in accordance with
requirements of these Specifications and the lines, grades and cross-sections shown in the
drawings or as indicated by the Engineer. It shall include the hauling and stacking of or
hauling to sites of embankment and subgrade construction, suitable cut materials from
reaches involving cutting as required, as also the disposal of unsuitable cut materials in
specified manner, trimming and finishing of the road to specified dimensions or as directed
by the Engineer.
130
4.2.2 ClassificationofExcavatedMaterial
4.2.2.1
Classification
All materials involved in excavation shall be classified by the Engineer in the following
manner:
a) Soil
This shall comprise topsoil, turf, sand, silt, loam, clay, mud, peat, black cotton soil, soft
shale or loose moorum, a mixture of these and similar material which yield to the ordinary
application of pick, spade and/or shovel, rake or other ordinary digging implement. Removal
of gravel or any other nodular material having dimension in any one direction not exceeding
75 mm shall be deemed to be covered under this category.
b) Marble:
c) Ordinary Rock (not requiring blasting) This shall include:
i) rock types such as laterites, shales and conglomerates, varieties of limestone and
sandstone etc., which may be quarried or split with crow bars, also including any rock which
in dry state may be hard, requiring blasting but which, when wet, becomes soft and
manageable by means other than blasting;
jj) macadam surfaces such as water bound and bitumen/tar bound; soling or roads, paths,
etc. and hard core; compact moorum or stabilized soil requiring grafting tool or pick or both
and shovel, closely applied; gravel and cobble stone
iii) lime concrete, stone masonry in lime mortar and brick work in lime/cement mortar
below ground level, reinforced cement concrete which may be broken up with crow bars or
picks and stone masonry in cement mortar below ground level; and
iv) boulders which do not require blasting found lying loose on the surface or embedded
in river bed, soil, talus, slope wash and terrace material or dissimilar origin.
d) Hard Rock (requiring blasting)
This shall comprise:
i) any rock or cement concrete for the excavation of which the use of mechanical plant
and/or blasting is required,
ii) reinforced cement concrete (reinforcement cut through but not separated from the
concrete) below ground level; and
iii) boulders requiring blasting.
e) Hard Rock (blasting prohibited)
131
Hard rock requiring blasting as described under (d) but where blasting is prohibited for
any reason and excavation has to be carried out by chiseling, wedging or any other agreed
method.
f) Marshy soil
This shall include soils like soft clays and peats excavated below the original ground
level of marshes and swamps and soils excavated from other areas requiring continuous
pumping or bailing out of water.
4.2.3 Authorityforclassification:
The classification of excavation shall be decided by the Engineer and his decision shall
be final and binding on the Contractor. Merely the use of explosives in excavation will not
be considered as a reason for higher classification unless blasting is clearly necessary in the
opinion of the Engineer.
Construction Operations
Setting out: After the site has been cleared as per Clause 200, the limits of excavation
shall be set out true to lines, curves, slopes, grades and sections as shown on the drawings or
as directed by the Engineer. The Contractor shall provide all labour, survey instruments and
materials such as strings, pegs, nails, bamboos, stones, lime, mortar, concrete, etc., required
in connection with the setting out of works and the establishment of bench marks. The
Contractor shall be responsible for the maintenance of bench marks and other marks and
stakes as long as in the opinion of the Engineer, they are required for the works.
good at the cost of the Contractor with suitable material of characteristics similar to that
removed and compacted to the requirements.
All debris and loose material on the slopes of cuttings shall be removed. No backfilling
shall be allowed to obtain required slopes excepting that when boulders or soft materials are
encountered in cut slopes, these shall be excavated to approved depth on instructions of the
Engineer and the resulting cavities filled with suitable material and thoroughly compacted in
an approved manner.
After excavation, the sides of excavated area shall be trimmed and the area contoured to
minimize erosion and ponding, allowing for natural drainage to take place.
Methods, tools and equipment : Only such methods, tools and equipment as approved
by the Engineer shall be adopted/used in the work. If so desired by the Engineer, the
Contractor shall demonstrate the efficacy of the type of equipment to be used before the
commencement of work. Recommended equipments for different materials are indicated in
Table 300-1.
Rock excavation: Rock, when encountered in road excavation, shall be removed upto
the formation level or as otherwise indicated on the drawings. Where, however, unstable
shales or other unsuitable materials are encountered at the formation level, these shall be
excavated to the extent of 500 mm below the formation level or as otherwise specified. In all
cases, the excavation operations shall be so carried out that at no point on cut formations the
rock protrudes above the specified levels. Rocks and large boulders which are likely to cause
differential settlement and also local drainage problems shall be removed to the extent of 500
mm below the formation level in the formation width including drains and cut through the
side drain. Where excavation is done to levels lower than those specified, the excess
excavation shall be made good as per Clauses 301.3.3 and 301.6 to the satisfaction of the
Engineer. Slopes in rock cutting shall be finished to uniform lines corresponding to slope
lines shown on the drawings or as directed by the Engineer. Notwithstanding the foregoing,
133
all loose pieces of rock on excavated slope surface which move when pierced by a crowbar
shall be removed. Where blasting is to be resorted to, the same shall be carried out as per
Clause 302 and all precautions indicated therein observed.
Where presplitting is prescribed to be done for the establishment of a specified slope in
rock excavation, the same shall be carried out as per Clause 303.
Marsh excavation : The excavation of soil from marshes/swamps shall be carried out as
per the programme approved by the Engineer.
Excavation of marshes shall begin at one end and proceed in one direction across the
entire marsh immediately ahead of backfilling with materials like boulders, sand moorum,
bricks bats, dismantled concrete as approved by the Engineer. The method and sequence of
excavating and backfilling shall be such as to ensure, to the extent practicable, the complete
removal or displacement of all muck from within the lateral limits called for on the drawings
or as staked by the Engineer.
conform to its condition at the time of removal and payment made accordingly regardless of
its condition earlier.
Dewatering : If water is met with in the excavations due to springs, seepage, rain or
other causes, it shall be removed by suitable diversions, pumping or bailing out and the
excavation kept dry whenever so required or directed by the Engineer. Care shall be taken to
discharge the drained water into suitable outlets as not to cause damage to the works, crops or
any other property. Due to any negligence on the part of the Contractor, if any such damage
is caused, it shall be the sole responsibility of the Contractor to repair/ restore to the original
condition at his own cost or compensate for the damage.
Disposal of excavated materials : All the excavated materials shall be the property of
the Employer. The material obtained from the excavation of roadway, shoulders, verges,
drains, cross-drainage works etc., shall be stacked neatly on specified land as directed by the
Engineer, of this, suitable material shall be used for filling-up of (i) roadway embankment,
(ii) the existing pits in the right-of-way and (iii) for landscaping of the road as directed by the
Engineer, including levelling and spreading with all lifts and leads and no extra payment shall
be made for the same.
Unsuitable and surplus material not intended for use shall be transported with all lifts and
lead beyond initial 1000 m, disposed of or used as directed by the Engineer.
Backfilling : Backfilling of masonry/concrete with all lifts and leads hume pipe drain
excavation shall be done with approved material after concrete/masonry/hume pipe is fully
set and carried out in such a way as not to cause undue thrust on any part of the structure
and/or not to cause differential settlement. All space between the drain walls and the side of
the excavation shall be refilled to the original surface making due allowance for settlement, in
layers generally not exceeding 150 mm compacted thickness to the required density, using
suitable compaction equipment such as trench compactor, mechanical tamper, rammer or
plate compactor as directed by the Engineer.
pipes, conduits and any other structures under or above ground, which may be affected by
construction operations and which, in the opinion of the Engineer, shall be continued in use
without any change. Safety measures taken by the Contractor in this respect, shall be got
approved from the Engineer. However, if any, of these objects is damaged by reason of the
Contractors negligence, it shall be replaced or restored to the original condition at his cost. If
the Contractor fails to do so, within the required time as directed by the Engineer or if, in the
opinion of the Engineer, the actions initiated by the Contractor to replace/restore the damaged
objects are not satisfactory, the Engineer shall arrange the replacement/restoration directly
through any other agency at the risk and cost of the Contractor after issuing prior notice to the
effect.
In rocky formations, the surface irregularities shall be corrected and the levels brought
up to the specified elevation with granular base material as directed by the Engineer, laid and
compacted in accordance with the respective Specifications for these materials. The
unsuitable material shall be disposed of in accordance with Clause 301.3.11. After satisfying
the density requirements, the cut formation shall be prepared to receive the sub-base/ base
course in accordance with Clauses 310 and 311 to receive the sub-base/base course.
Finishing Operations
Finishing operations shall include the work of properly shaping and dressing all
excavated surfaces. When completed, no point on the slopes shall vary from the designated
slopes by more than 150 mm measured at right angles to the slope, except where excavation
is in rock (hard or soft) where no point shall vary more than 300 mm from the designated
slope. In no case shall any portion of the slope encroach on the roadway.
The finished cut formation shall satisfy the surface tolerances described in Clause 902.
Where directed, the topsoil removed earlier and conserved (Clauses 301.3.2 and 305.3.3)
shall be spread over cut slopes, where feasible, berms and other disturbed areas. Slopes may
be roughened and moistened slightly, prior to the application of topsoil, in order to provide
136
satisfactory bond. The depth of topsoil shall be sufficient to sustain plant growth, the usual
thickness being from 75 mm to 100 mm. including all lifts and leads.
Construction Operations
Prior to starting drilling operations for presplitting, the Contractor shall furnish the
Engineer a plan outlining the position of all drill holes, depth of drilling, type of explosives to
be used, loading pattern and sequence of firing. The drilling and blasting plan is for record
purposes only and will not absolve the Contractor of his responsibility for using proper
drilling and blasting procedures. Controlled blasting shall begin with a short test section of a
length approved by the Engineer. The test section shall be presplit, production drilled and
blasted and sufficient material excavated whereby the Engineer can determine if the
Contractors method have produced an acceptable slope.
All overburden soil and weathered rock along the top of the excavation for a distance of
about 5 to 15 m beyond the drilling limits, or to the end of the excavation, as decided by the
Engineer shall be removed before drilling the presplitting holes. Particular care and attention
shall be directed to the beginning and end of excavations to ensure complete removal of all
overburden soil and weathered rock and to expose fresh rock to an elevation equal to the
bottom of the adjacent lift of the presplitting holes being drilled.
Slope holes for presplitting shall be drilled along the line of the planned slope within the
specified tolerances. The drill holes shall not be less than 60 mm nor more than 75 mm in
diameter. Drilling operations shall be controlled by the use of proper equipment and
technique to ensure that no hole shall deviate from the plane of the planned slope by more
than 300 mm nor shall any hole deviate from being parallel to an adjacent hole by more than
two-third of the planned horizontal spacing between holes.
1. The length of presplit holes for any individual lift shall not exceed 9 m.
2. The spacing of presplit holes shall not exceed 900 mm on centres and shall be
adjusted to result in a uniform shear face between holes.
3. Auxiliary drill holes along the presplit line, not loaded or stemmed, may be
ordered by the Engineer. Except for spacing, auxiliary drill holes shall conform to
the provisions for presplit holes.
137
4. The line of production holes shall be placed inside the presplit lines in such a
manner as to avoid damage to the presplit face.
5. If necessary, to reduce shatter and overbreak of the presplit surface, the first line
of the production holes shall be drilled parallel to the slope line at the top of the
cut and at each bench level thereafter.
6. Any blasting technique, which results in damage to the presplit surface, shall be
immediately discontinued.
7. No portion of any production holes shall be drilled within 2.5 m of a presplit
plane except as approved by the Engineer. The bottom of the production holes
shall not be lower than the bottom of the presplit holes.
8. A maximum offset of 600 mm will be permitted for a construction working bench
at the bottom of each lift for use in drilling the next lower presplitting pattern.
The drilling operations shall be adjusted to compensate for drift of previous
levels and for the offset at the start of new levels to maintain the specified slope
plane.
Borrow materials: No borrow area shall be made available by the Employer. The
arrangement for the source of supply of the material for embankment and sub-grade
complying with the guidelines as well as compliance to environmental requirements in
respect of excavation and borrow areas as stipulated, from time to time by the Ministry of
138
Environment and Forests, Government of India and the local bodies, as applicable shall be
the sole responsibility of the Contractor.
Area where pond ash is available for construction of embankment, borrowing of the
earth shall be avoided to the extent possible. Embankment constructed out of pond ash shall
be properly designed to ensure stability against uplifting etc. A suitable thick cover may
preferably be provided at intervening layers of pond ash for this purpose. A thick soil cover
shall be bound the edge of the embankment to protect it against erosion. Minimum thickness
of such soil cover shall be 500 mm. This work of providing soil cover shall be treated as
incidental to the work.
Borrow pits along the road shall be discouraged. If permitted by the Engineer, these shall
not be dug continuously. Ridges of not less than 8 m width should be left at intervals not
exceeding 300 m. Small drains shall be cut through the ridges to facilitate drainage. The
depth of the pits shall be so regulated that their bottom does not cut an imaginary line having
slope of 1 vertical to 4 horizontal projected from the edge of the final section of the bank, the
maximum depth in any case being limited to 1.5 m. Also, no pit shall be dug within the offset
width from the toe of the embankment required as per the consideration of stability with a
minimum width of 10 m.
Haulage of material to embankments or other areas of fill shall proceed only when
sufficient spreading and compaction plant is operating at the place of deposition.
No excavated acceptable material other than surplus to requirements of the Contract shall
be removed from the site. Should the Contractor be permitted to remove acceptable material
from the site to suit his operational procedure, then he shall make good any consequent
deficit of material arising therefrom.
Where the excavation reveals a combination of acceptable and unacceptable materials,
the Contractor shall, unless otherwise agreed by the Engineer, carry out the excavation in
such a manner that the acceptable materials are excavated separately for use in the permanent
works without contamination by the unacceptable materials. The acceptable materials shall be
stockpiled separately.
The Contractor shall ensure that he does not adversely affect the stability of excavation
or fills by the methods of stockpiling materials, use of plants or siting of temporary buildings
or structures.
The Contractor shall obtain representative samples from each of the identified borrow
areas and have these tested at the site laboratory following a testing programme approved by
the Engineer. It shall be ensured that the subgrade material when compacted to the density
requirements as in Table 300-3 shall yield the design CBR value of the sub-grade.
Table 300-3 Compaction Requirements for Embankment and Sub-grade
139
Construction Operations
Setting out : After the site has been cleared to Clause 201, the work shall be set out to
Clause 301.3.1 The limits of embankment/sub-grade shall be marked by fixing batter pegs on
both sides at regular intervals as guides before commencing the earthwork. The
embankment/sub-grade shall be built sufficiently wider than the design dimension so that
surplus material may be trimmed, ensuring that the remaining material is to the desired
density and in position specified and conforms to the specified side slopes.
Dewatering : If the foundation of the embankment is in an area with stagnant water, and
in the opinion of the Engineer it is feasible to remove it, the same shall be removed by bailing
out or pumping, as directed by the Engineer and the area of the embankment foundation shall
be kept dry. Care shall be taken to discharge the drained water so as not to cause damage to
the works, crops or any other property. Due to anynegligence on the part of the Contractor, if
any such damage is caused, it shall be the sole responsibility of the Contractor to
repair/restore it to original condition or compensate the damage at his own cost.
If the embankment is to be constructed under water, Clause 305.4.6 shall apply.
Finishing operations : Finishing operations shall include the work of shaping and
dressing the shoulders/verge/roadbed and side slopes to conform to the alignment, levels,
cross-sections and dimensions shown on the drawings or as directed by the Engineer subject
to the surface tolerance described in Clause 902. Both the upper and lower ends of the side
slopes shall be rounded off to improve appearance and to merge the embankment with the
adjacent terrain.
The topsoil, removed and conserved earlier (Clause 301.3.2 and 305.3.3) shall be spread
over the fill slopes as per directions of the Engineer to facilitate the growth of vegetation.
Slopes shall be roughened and moistened slightly prior to the application of the topsoil in
order to provide satisfactory bond. The depth of the topsoil shall be sufficient to sustain plant
growth, the usual thickness being from 75 mm to 150 mm.
Where directed, the slopes shall be turfed with sods in accordance with Clause 307. If
seeding and mulching of slopes is prescribed, this shall be done to the requirements of Clause
308.
141
When earthwork operations have been substantially completed, the road area shall be
cleared of all debris, and ugly scars in the construction area responsible for objectionable
appearance eliminated.
Engineer. The Contractor, if so desired by him, may also use suitable geosynthetic material to
increase the bearing capacity of the foundation. This exception to normal procedure will not
be permitted where, in the opinion of the Engineer, the embankments could be constructed in
the approved manner over such ground by the use of lighter or modified equipment after
proper ditching and drainage have been provided.
Where this exception is permitted, the selection of the material and the construction
procedure to obtain an acceptable layer shall be the responsibility of the Contractor. The cost
of providing suitable traffic conditions for construction equipment over any area of the
Contract will be the responsibility of the Contractor and no extra payment will be made to
him. The reminder of the embankment shall be constructed as specified in Clause 305.3.
Earthwork for high embankment : In the case of high embankments (more than 6 m),
the Contractor shall normally use pond ash in conformity with Clause 305.2.1.131 or the
material from the specified borrow area. In case, he desires to use different material for his
own convenience, he shall have to carry out necessary soil investigations and redesign the
high embankment at his own cost. The Contractor shall then furnish the soil test data and
design of high embankment for approval of the Engineer, who reserves the right to accept or
reject it.
If necessary, stage construction of fills and any controlled rates of filling shall be carried
out in accordance with the Contract including installation of instruments and its monitoring.
Where required, the Contractor shall surcharge embankments or other areas of fill with
approved material for the periods specified in the Contract. If settlement of surcharged fill
results in any surcharging material, which is unacceptable for use in the fill being surcharged,
lying below formation level, the Contractor shall remove the unacceptable material and
dispose it as per direction of the Engineer. He shall then bring the resultant level up to
formation level with acceptable material.
Settlement period : Where settlement period is specified in the Contract, the
embankment shall remain in place for the required settlement period before excavating for
143
abutment, wingwall, retaining wall, footings, etc., or driving foundation piles. The duration of
the required settlement period at each location shall be as provided for in the Contract or as
directed by the Engineer.
Plying of Traffic
Construction and other vehicular traffic shall not use the prepared surface of the
embankment and/or sub-grade without the prior permission of the Engineer. Any damage
arising out of such use shall, however, be made good by the Contractor at his own expense as
directed by the Engineer.
144
4.3 SUB-BASES
This work shall consist of laying and compacting well-graded material on prepared
subgrade in accordance with the requirements of these Specifications. The material shall be
laid in one or more layers as sub-base or lower sub-base and upper sub-base (termed as
subbase hereinafter) as necessary according to lines, grades and cross-sections shown on the
drawings or as directed by the Engineer.
Materials
The material to be used for the work shall be natural sand, moorum, gravel, crushed
stone, or combination thereof depending upon the grading required. Materials like crushed
slag, crushed concrete, brick metal and kankar may be allowed only with the specific
approval of the Engineer. The material shall be free from organic or other deleterious
constituents and shall conform to the quality standards as prescribed in the specifications.
Table 400-1 prescribes four gradings for Granular Sub-Base (GSB). Gradings I and II in
Table 400-1 are well graded granular sub-base materials. These can be used at locations
where drainage requirement are not predominant. Gradings III and IV are gap graded and
addresses to the concern of the drainage requirements. These can be used at location
experiencing heavy rainfall, flooding etc. Cases where GSB is to be provided in two layers, it
is recommended to adopt either grading III or grading IV for lower layer and either grading I
or grading II for upper layer. Minimum thickness of lower layer at locations where drainage
requirements are predominant shall not be less than 200 mm. The grading to be adopted for a
project shall be as specified in the Contract.
401.2.2 Physical requirements: The material shall have a 10 percent fines value of 50kN
or more (for sample in soaked condition) when tested in compliance with IS:2386 (Part IV)
1963. The water absorption value of the coarse aggregate shall be determined as per IS:2386
(Part 3); if this value is greater than 2 percent, the soundness test shall be carried out on the
material delivered to site as per IS:383. For Gradings II and IV materials, the CBR shall be
determined at the density and moisture content likely to be developed in the field.
Sub-Bases,Bases (Non-Bituminous) and Shoulders Section 400
Construction Operations
4.2 Spreading and compacting : The sub-base material of grading specified in the
Contract shall be spread on the prepared subgrade with the help of a motor grader of adequate
capacity, its blade having hydraulic controls suitable for initial adjustment and for
maintaining the required slope and grade during the operation or other means as approved by
the Engineer.
When the sub-base material consists of combination of materials mentioned in Clause
401.2.1, mixing shall be done mechanically by the mix-in-place method.
Manual mixing shall be permitted only where the width of laying is not adequate for
mechanical operations, as in small-sized jobs. The equipment used for mix-in-place
construction shall be a rotavator or similar approved equipment capable of mixing the
material to the desired degree. If so desired by the Engineer, trial runs with the equipment
shall be carried out to establish its suitability for the work.
Moisture content of the loose material shall be checked in accordance with IS:2720 (Part
2) and suitably adjusted by sprinkling additional water from a truck mounted or trailer
mounted water tank and suitable for applying water uniformly and at controlled quantities to
variable widths of surface or other means approved by the Engineer so that, at the time of
compaction, it is from 1 percent above to 2 percent below the optimum moisture content
corresponding to IS:2720 (Part 8). While adding water, due allowance shall be made for
evaporation losses. After water has been added, the material shall be processed by
mechanical or other approved means like disc harrows, rotavators until the layer is uniformly
wet.
Immediately thereafter, rolling shall start. If the thickness of the compacted layer does
not exceed 100 mm, a smooth wheeled roller of 80 to 100 kN weight may be used. For a
compacted single layer upto 200 mm the compaction shall be done with the help of a
vibratory roller of minimum 80 to 100 kN static weight with plain drum or pad foot-drum or
heavy pneumatic tyred roller of minimum 200 to 300 kN weight having a minimum tyre
pressure of 0.7 MPa or equivalent capacity roller capable of achieving the required
compaction. Rolling shall commence at the lower edge and proceed towards the upper edge
longitudinally for portions having unidirectional crossfall and super-elevation shall
commence at the edges and progress towards the centre for portions having crossfall on both
sides.
Each pass of the roller shall uniformly overlap not less than one-third of the track made
in the preceding pass. During rolling, the grade and crossfall (camber) shall be checked and
any high spots or depressions which become apparent, corrected by removing or adding fresh
material. The speed of the roller shall not exceed 5 km per hour.
Rolling shall be continued till the density achieved is at least 98 percent of the maximum
dry density for the material determined as per IS:2720 (Part 8). The surface of any layer of
146
material on completion of compaction shall be well closed, free from movement under
compaction equipment and from compaction planes, ridges, cracks or loose material. All
loose, segregated or otherwise defective areas shall be made good to the full thickness of
layer and re-compacted.
This work shall consist of clean crushed aggregates mechanically interlocked by rolling
and bonding together with screening, binding material where necessary and water laid on a
properly prepared subgrade/sub-base/base or existing pavement, as the case may be and
finished in accordance with the requirements of these Specifications and in close conformity
with the lines, grades, cross-sections and thickness as per approved plans or as directed by the
Engineer. This specification is meant for repairs and minor works of widening nature and
also at locations where not feasible to lay WMM.
Coarse aggregates : Coarse aggregates shall be either crushed or broken stone, crushed
slag, overburnt (Jhama) brick aggregates or any other naturally occurring aggregates such as
kankar and laterite of suitable quality. Materials other than crushed or broken stone and
crushed slag shall be used in sub-base courses only. If crushed gravel /shingle is used, not
less than 90 percent by weight of the gravel/shingle pieces retained on 4.75 mm sieve shall
have at least two fractured faces. The aggregates shall conform to the physical requirements
set forth in Table 400-5. The type and size range of the aggregate shall be specified in the
Contract or shall be as specified by the Engineer. If the water absorption value of the coarse
aggregate is greater than 2 percent, the soundness test shall be carried out on the material
delivered to site as per IS:2386 (Part 5).
Table 400-5 Physical Requirements of Coarse Aggregates for Water Bound
Macadam for Sub-base/Base Courses
404.2.2 Crushed or broken stone : The crushed or broken stone shall be hard, durable
and free from excess flat, elongated, soft and disintegrated particles, dirt and other deleterious
material.
147
404.2.3 Crushed slag : Crushed slag shall be made from air-cooled blast furnace slag. It
shall be of angular shape, reasonably uniform in quality and density and generally free from
thin, elongated and soft pieces, dirt or other deleterious materials. The weight of crushed slag
shall not be less than 11.2 kN per m3 and the percentage of glossy material shall not be more
than 20. It should also comply with the following requirements:
i) Chemical stability : To comply with requirements of appendix of BS:1047.
ii) Sulphur content : Maximum 2 percent
iii) Water absorption : Maximum 10 percent
to the sub-grade level except where widening specifications envisages laying of a stablised
sub-base using in-situ operations in which case the same should be removed only up to the
sub-base level.
404.3.4 Spreading coarse aggregates : The coarse aggregates shall be spread uniformly
and evenly upon the prepared sub-grade/sub-base in the required quantities from the
stockpiles to proper profile by using templates placed across the road about 6 m apart, in such
quantities that the thickness of each compacted layer is not more than 75 mm. In no case shall
these be dumped in heaps directly on the area where these are to be laid nor shall their
hauling over a partly completed base be permitted. Wherever possible, approved mechanical
devies such as aggregate spreader shall be used to spread the aggregates uniformly so as to
minimize the need for manual rectification afterwards.
No segregation of coarse or fine aggregates shall be allowed and the coarse aggregates,
as spread shall be of uniform gradation with no pockets of fine material. The surface of the
aggregates spread shall be carefully checked with templates and all high or low spots
remedied by removing or adding aggregates as may be required. The surface shall be checked
frequently with a straight edge while spreading and rolling so as to ensure a finished surface
as per approved drawings. The coarse aggregates shall not normally be spread more than 3
days in advance of the subsequent construction operations.
404.3.5 Rolling : Immediately following the spreading of the coarse aggregates, rolling
shall be started with three wheeled power rollers of 80 to 100 kN capacity or tandem or
vibratory rollers of 80 to 100 kN static weight. The type of roller to be used shall be approved
by the Engineer based on trial run.
Except on superelevated portions where the rolling shall proceed from inner edge to the
outer, rolling shall begin from the edges gradually progressing towards the center. First the
edge/edges shall be compacted with roller running forward and backward. The roller shall
then move inward parallel to the center line of the road, in successive passes uniformly
lapping preceding tracks by at least one-half width.
Rolling shall be continued until the road metal is thoroughly keyed and the creeping of
stone ahead of the roller is no longer visible. During rolling, slight sprinkling of water may be
done, if necessary. Rolling shall not be done when the sub-grade is soft or yielding or when it
causes a wave-like motion in the sub-grade or sub-base course.
The rolled surface shall be checked transversely with templates and longitudinally with 3
m straight edge. Any irregularities, exceeding 12 mm, shall be corrected by loosening the
surface, adding or removing necessary amount of aggregates and re-rolling until the entire
surface conforms to the desired camber and grade. In no case shall the use of screenings be
permitted to make up depressions.
Material, which gets crushed excessively during compaction or becomes segregated,
shall be removed and replaced with suitable aggregates.
149
404.3.6 Application of screenings : After the coarse aggregates have been rolled to
Clause 404.3.5, screenings to completely fill the interstices shall be applied gradually over
the surface. These shall not be damp or wet at the time of application. Dry rolling shall be
done while the screenings are being spread so that vibrations of the roller cause them to settle
into the voids of the coarse aggregates. The screenings shall not be dumped in piles but be
spread uniformly in successive thin layers either by the spreading motions of hand shovels or
by mechanical spreaders, or directly from tipper with suitable grit spreading arrangement.
Tipper operating for spreading the screenings shall be equipped with pneumatic tyres and
operated so as not to disturb the coarse aggregates.
The screenings shall be applied at a slow and uniform rate (in three or more applications)
so as to ensure filling of all voids. This shall be accompanied by dry rolling and brooming
with mechanical brooms, hand brooms or both. In no case shall the screenings be applied so
fast and thick as to form cakes or ridges on the surface in such a manner as would prevent
filling of voids or prevent the direct bearing of the roller on the coarse aggregates.
The spreading, rolling, and brooming of screenings shall be carried out in only such
lengths of the road which could be completed within one days operation.
404.3.7 Sprinkling of water and grouting : After application of screenings, the surface
shall be copiously sprinkled with water, swept and rolled. Hand brooms shall be used to
sweep the wet screenings into voids and to distribute them evenly. The sprinkling, sweeping
and rolling operation shall be continued, with additional screenings applied as necessary until
the coarse aggregates have been thoroughly keyed, well-bonded and firmly set in its full
depth and a grout has been formed of screenings. Care shall be taken to see that the sub-base
or sub-grade does not get damaged due to the addition of excessive quantities of water during
construction.
In case of lime treated soil sub-base, construction of water bound macadam on top of it
can cause excessive water to flow down to the lime treated sub-base before it has picked up
enough strength (is still green) and thus cause damage to the sub-base layer. The laying of
water bound macadam layer in such cases shall be done after the sub-base attains adequate
strength, as directed by the Engineer.
404.3.8 Application of binding material : After the application of screenings in
accordance with Clauses 404.3.6 and 404.3.7, the binding material where it is required to be
used (Clause 404.2.7) shall be applied successively in two or more thin layers at a slow and
uniform rate. After each application, the surface shall be copiously sprinkled with water, the
resulting slurry swept in with hand brooms, or mechanical brooms to fill the voids properly,
and rolled during which water shall be applied to the wheels of the rollers if necessary to
wash down the binding material sticking to them. These operations shall continue until the
resulting slurry after filling of voids, forms a wave ahead of the wheels of the moving roller.
In case the aggregates are of a soft variety it would be preferred to replace binder material
with an equivalent amount of additional screenings.
150
404.3.9 Setting and drying : After the final compaction of water bound macadam
course, the pavement shall be allowed to dry overnight. Next morning hungry spots shall be
filled with screenings or binding material as directed, lightly sprinkled with water if
necessary and rolled. No traffic shall be allowed on the road until the macadam has set.
The Engineer shall have the discretion to stop hauling traffic from using the completed
water bound macadam course, it in his opinion if would cause excessive damage to the
surface.
The compacted water bound macadam course shall be allowed to completely dry and set
before the next pavement course is laid over it.
404.4 Surface Finish and Quality Control of Work
404.4.1 The surface finish of construction shall conform to the requirements of Clause
902.
404.4.2 Control on the quality of materials and works shall be exercised by the Engineer
in accordance with Section 900.
404.4.3 The water bound macadam work shall not be carried out when the atmospheric
temperature is less than 10C in the shade.
404.4.4 Reconstruction of defective macadam : The finished surface of water bound
macadam shall conform to the tolerance of surface regularity as prescribed in Clause 902.
However, where the surface irregularity of the course exceeds the tolerances or where the
course is otherwise defective due to sub-grade soil mixing with the aggregates, the course to
its full thickness shall be scarified over the affected area, reshaped with added material or
removed and replaced with fresh material as applicable and recompacted. The area treated
shall not be less than 10 sq.m. In no case shall depressions be filled up with screenings or
binding material.
404.5 Arrangements for Traffic.
During the period of construction, the arrangements for traffic shall be done as per
Clause 112.
404.6 Measurements for Payment
Water bound macadam shall be measured as finished work in position in cubic metres.
404.7 Rate
The Contract unit rate for water bound macadam sub-base/base course shall be payable
in full for carrying out the required operations including full compensation for all
components listed in Clause 401.8 (i) to (v), including arrangement of water used in the work
as approved by the Engineer.
151
152
The mix may be spread by a paver finisher The paver finisher shall be self-propelled, of
repute make, proven design and adequate capcity with following features:i) Tractor unit shall have crawler tracks or pneumatic tyre.
ii) Racks provide greater traction and suitable to work on soft or loose sub-bases and
laying large width up to 10 m or moreWheeled paver is faster and normally preferred to work
on hard surfaces with width up to 8 m.
iii) Material distribution system comprising of hopper, two conveyor belts each working
independently, conveyor speed adjustable with limit switches and auger system easily
capable of raising and lower; to provide a smooth uninterrupted material flow for different
layer thicknesses from the tipper to the screed
iv) Hydraulically operated telescopic screed for paving width upto to 8.5 m and fixed
screed beyond this. The screed shall have tamping and vibrating arrangement for initial
compaction of the layer.
v) The drive shall be hydrostatic with infinite variable speed.
vi) Automatic leveling control system with electronic sensing device to maintain mat
thickness and cross slope of mat during laying procedure.
In exceptional cases where it is not possible for the paver to be utilized, mechanical
means like motor grader may be used with the prior approval of the Engineer. The motor
grader shall be capable of spreading the material uniformly all over the surface. For portions
where mechanical means cannot be used, manual means as approved by the Engineer shall be
used only in restricted areas.
The surface of the aggregate shall be carefully checked with templates and all high or
low spots remedied by removing or adding aggregate as may be required. The layer may be
tested by depth blocks during construction. No segregation of larger and fine particles should
be allowed. The aggregates as spread should be of uniform gradation with no pockets of fine
materials.
The Engineer may permit manual mixing and /or laying of wet mix macadam where
small quantity of wet mix macadam is to be executed. Manual mixing/laying in inaccessible/
remote locations and in situations where use of machinery is not feasible can also be
permitted. Where manual mixing/laying is intended to be permitted, the same shall be
indicated in the Contract.
406.3.5 Compaction : After the mix has been laid to the required thickness, grade and
crossfall/camber the same shall be uniformly compacted to the full depth with suitable roller.
If the thickness of single compacted layer does not exceed 200 mm, a smooth wheel roller of
80 to 100kN weight may be used. For a compacted single layer upto 200 mm, the compaction
shall be done with the help of vibratory roller of minimum static weight of 80 to 100 kN with
153
on amplitude not exceeding 0.7 mm or equivalent capacity roller. The speed of the roller shall
not exceed 5 km/h.
In portions having unidirectional cross fall/superelevation, rolling shall commence from
the lower edge and progress gradually towards the upper edge. Thereafter, roller should
progress parallel to the center line of the road, uniformly over-lapping each preceding track
by at least one-third width until the entire surface has been rolled. Alternate trips of the roller
shall be terminated in stops at least 1 m away from any preceding stop.
In portions in camber, rolling should begin at the edge with the roller running forward
and backward until the edges have been firmly compacted. The roller shall then progress
gradually towards the center parallel to the center line of the road uniformly overlapping each
of the preceding track by at least one-third width until the entire surface has been rolled.
Any displacement occurring as a result of reversing of the direction of a roller or from
any other cause shall be corrected at once as specified and/or removed and made good.
Along forms, kerbs, walls or other places not accessible to the roller, the mixture shall be
thoroughly compacted with mechanical tampers or a plate compactor. Skin patching of an
area without scarifying the surface to permit proper bonding of the added material shall not
be permitted.
Rolling should not be done when the sub-grade is soft or yielding or when it causes a
wave-like motion in the sub-base/base course or sub-grade. If irregularities develop during
rolling which exceed 12 mm when tested with a 3 m straight edge, the surface should be
loosened and premixed material added or removed as required before rolling again so as to
achieve a uniform surface conforming to the desired grade and crossfall. In no case shall the
use of unmixed material be permitted to make up the depressions.
Rolling shall be continued till the density achieved is at least 98 percent of the maximum
dry density for the material as determined by the method outlined in IS:2720 (Part-8).
After completion, the surface of any finished layer shall be well-closed, free from
movement under compaction equipment or any compaction planes, ridges, cracks and loose
material.
All loose, segregated or otherwise defective areas shall be made good to the full
thickness of the layer and recompacted.
154
1.4 Transporting
Bituminous materials shall be transported in clean insulated and covered vehicles. An
asphalt release agent, such as soap or lime water, which does not adversely affect the
bituminous mixes may be applied to the interior of the vehicle to prevent sticking and to
facilitate discharge of the material.
Specifications. When laying binder course or wearing course approaching an expansion joint
of a structure, machine laying shall stop 300 mm short of the joint. The remainder of the
pavement up to the joint, and the corresponding area beyond it, shall be laid by hand, and the
joint or joint cavity shall be kept clear of surfacing material.
Bituminous material, with a temperature greater than 145C, shall not be laid or
deposited on bridge deck water-proofing systems, unless precautions against heat damage
have been approved by the Engineer.
501.5.4 Cleanliness and overlaying: Bituminous material shall be kept clean and
uncontaminated. The only traffic permitted run on bituminous material to be overlaid shall be
that engaged in laying and compacting the next course or, where a binder course is to be
sealed or surface dressed, that engaged on such surface treatment. Should any bituminous
material become contaminated, the Contractor shall make it good to the satisfaction of the
Engineer, in compliance with Clause 501.8.
Binder course material shall not remain uncovered by either the wearing course or
surface treatment, whichever is specified in the Contract, for more than three consecutive
days after being laid. The Engineer may extend this period, by the minimum amount of time
necessary, because of weather conditions or for any other reason. If the surface of the base
course is subjected to traffic or not covered within three days, a tack coat shall be applied as
directed by the Engineer.
501.6 Compaction
Bituminous materials shall be laid and compacted in layers, which enable the specified
thickness, surface level, regularity requirements and compaction to be achieved.
Compaction of bituminous materials shall commence as soon as possible after laying.
Compaction shall be substantially completed before the temperature falls below the
minimum rolling temperatures stated in the relevant part of these Specifications. Rolling of
the longitudinal joints shall be done immediately behind the paving operation. After this,
rolling shall commence at the edges and progress towards the center longitudinally except
that on super elevated and unidirectional cambered portions, it shall progress from the lower
to the upper edge parallel to the center line of the pavement. Rolling shall continue until all
roller marks have been removed from the surface. All deficiencies in the surface after laying
shall be made good by the attendants behind the paver, before initial rolling is commenced.
The initial or breakdown rolling shall be done with 810 tonne dead weight smooth-wheeled
rollers. The intermediate rolling shall be done with 810 tonne dead weight or vibratory roller
or with a pneumatic tyred roller of 12 to 15 tonne weight having nine wheels, with a tyre
pressure of at least 5.6 kg/sq.cm. The finish rolling shall be done with 6 to 8 tonne smooth
wheeled tandem rollers.
Where compaction is to be determined by density of cores, the requirements to prove the
performance of rollers shall apply in order to demonstrate that the specified density can be
156
achieved. In such cases the Contractor shall nominate the plant, and the method by which he
intends to achieve the specified level of compaction and finish at temperatures above the
minimum specified rolling temperature. Laying trials shall then demonstrate the acceptability
of the plant and method used.
Bituminous materials shall be rolled in a longitudinal direction, with the driven rolls
nearest the paver. The roller shall first compact material adjacent to joints and then work
from the lower to the upper side of the layer, overlapping on successive passes by at least
onethird of the width of the rear roll or, in the case of a pneumatic-tyred roller, at least the
nominal width of 300 mm.
In portions with super-elevated and uni-directional camber, after the edge has been
rolled, the roller shall progress from the lower to the upper edge.
Rollers should move at a speed of not more than 5 km per hour. The roller shall not be
permitted to stand on pavement which has not been fully compacted, and necessary
precautions shall be taken to prevent dropping of oil, grease, petrol or other foreign matter on
the pavement either when the rollers are operating or standing. The wheels of rollers machine
shall be in good working order, to prevent the mixture from adhering to the wheels.
Only sufficient moisture to prevent adhesion between the wheels of rollers and the
mixture should be used. Surplus water shall not be allowed to stand on the partially
compacted pavement.
501.7 Joints
a) Where joints are made, the material shall be fully compacted and the joint made flush
in one of the following ways; All joints shall be cut vertical to the full thickness of the
previously laid mix. All loosened material shall be discarded and the vertical face be coated
with any viscosity grade bitumen, or cold applied emulsified bitumen. While spreading the
material along the joint the material spread shall overlap 25 mm to 50 mm on the previously
laid mix beyond the vertical face of the joint. The thickness of the loose overlap material
should be approximately a quarter more than the final compacted thickness.
The overlapped mix should be dragged back to the hot lane so that the roller can press
the small excess into the hot side of the joint to obtain a high joint density.
b) By using two or more pavers in echelon, where this is practicable and in sufficient
proximity for adjacent widths to be fully compacted by continuous rolling.
All joints shall be offset at least 300 mm from parallel joints in the layer beneath or as
directed, and in a layout approved by the Engineer. Joints in the wearing course shall
coincide with either the lane edge or the lane marking, which ever is appropriate.
Longitudinal joints shall not be situated in wheel track zones.
For transverse joints method a) above shall apply. Transverse joints in the successive and
adjoining layers shall have a minimum offset of 2 meters.
157
501.8.3.1 Preparing existing granular surface : Where the existing surface is granular,
all loose materials shall be removed, and the surface lightly watered where the profile
corrective course to be provided as a separate layer is also granular. Where the profile
corrective course of bituminous material is to be laid over the existing granular surface, the
latter shall, after removal of all loose material, be primed in accordance with Clause 502.
The surface finish of all granular layers on which bituminous works are to be placed,
shall, unless otherwise specifically instructed by the Engineer, be free from dust. All such
layers must be capable of being swept, after the removal of any non-integral loose material,
by means of a mechanical broom, without shedding significant quantities of material and dust
removed by air jet, washing, or other means approved by the Engineer.
After cleaning the surface shall be correct to line and level, within the tolerances
specified for base course.
501.8.3.2 Scarifying existing bituminous surface : Where specified or shown on the
drawings, the existing bituminous layer in the specified width shall be removed with care and
without causing undue disturbance to the underlying layer, by a suitable method approved by
the Engineer. After removal, all loose and disintegrated material, the underlying layers which
might have been disturbed should be suitable reworked and compacted to line and level.
After supplementing the base material as necessary with suitable fresh stone, the compacted
finished surface shall be primed in accordance with Clause 502. Reusable materials shall be
stacked as directed by the Engineer within 1000m of their origin.
501.8.3.3 Patching of potholes and sealing of cracks : Where the existing surface to be
overlaid is bituminous, any existing potholes and cracks shall be repaired and sealed in
accordance with Clauses 3004.2 and 3004.3, or as directed by the Engineer.
501.8.3.4 Laying the profile corrective course
501.8.3.4.1 Laying on granular base : After preparing the granular surface in
accordance with Clauses 501.8.3.1 and 501.8.3.2, the profile corrective course shall be laid
using material as described in Clauses501.8.2.3 and 501.8.2.4, or as otherwise described in
the Contract, and compacted to the requirements of the particular Specification.
501.8.3.4.2 Laying on existing bituminous surface : The existing bituminous surface
shall be prepared in accordance with Clause 501.8.3.3, and after applying a tack coat
conforming to Clause 503, the bituminous profile corrective course shall be laid and
compacted to the requirements of the particular Specification.
501.8.3.4.3 Correction of local depressions : Where local sags or depressions occur in
the existing pavement, a specific filling operation shall be instructed by the Engineer, which
should be laid in accordance with Figure 500-1. Normally, the maximum layer thickness at
158
any point should not exceed 100 mm. In placing multiple lifts, they should be arranged
according to the correct method as illustrated.
For correction of camber or super-elevation of the existing carriageway, the method
shown in Figure, 500-2 shall be adopted, depending on the profile of the existing
carriageway.
501.8.3.5 Covering the profile corrective courses : Profile corrective course
particularly shall be so planned that the layer shall be covered by the designed base/wearing
course at the earliest opportunity, before opening to regular traffic.
501.8.4 Surface finish and quality control of work : The relevant provisions of Section
900 shall apply.
501.8.5 Arrangements for traffic : During construction operations, arrangements for
traffic shall be made in accordance with the provisions of Clause 112.
501.8.6 Environmental protection : The provisions of Clause 111 and the provision of
Appendix A to Clause 501 shall apply.
159
2.2 Areas where water is regularly or repetitively used for dust suppression purposes
shall be laid to fall to specially-constructed settlement tanks to permit sedimentation of
particulate matter. After settlement, the water may be re-used for dust suppression and
rinsing.
2.3 All water and other liquid waste products arising on the Site shall be collected and
disposed of at a location on or off the Site and in a manner that shall not cause nuisance or
pollution.
2.4 The Contractor shall not discharge or deposit any matter arising from the execution
of the Works into any waters except with the permission of the Engineer and the regulatory
authorities concerned.
2.5 The Contractor shall at all times ensure that all existing stream courses and drains
within, and adjacent to, the Site are kept safe and free from any debris and any materials
arising from the Works.
2.6 The Contractor shall protect all watercourses, waterways, ditches, canals, drains,
lakes and the like from pollution as a result of the execution of the Works.
3 Air Quality
3.1 The Contractor shall devise and arrange methods of working to minimize dust,
gaseous or other air-borne emissions and carry out the Works in such a manner as to
minimize adverse impacts on air quality.
3.2 The Contractor shall utilize effective water sprays during delivery manufacture,
processing and handling of materials when dust is likely to be created, and to dampen stored
materials during dry and windy weather. Stockpiles of friable materials shall be covered with
clean tarpaulins, with application of sprayed water during dry and windy weather. Stockpiles
of material or debris shall be dampened prior to their movement, except where this is contrary
to the Specifications.
3.3 Any vehicle with an open load-carrying area used for transporting potentially dust
producing material shall have properly fitting side and tail boards. Materials having the
potential to produce dust shall not be loaded to a level higher than the side and tail boards,
and shall be covered with a clean tarpaulin in good condition. The tarpaulin shall be properly
secured and extended at least 300 mm over the edges of the side and tail boards.
3.4 In the event that the Contractor is permitted to use gravel or earth roads for haulage,
he shall provide suitable measures for dust palliation, if these are, in the opinion of the
Engineer, necessary. Such measures may include sprinkling water on the road surface at
regular intervals.
4 Noise
4.1 The Contractor shall consider noise abutment measures in his planning and execution
of the Works.
160
4.2 The Contractor shall take all necessary measures so that the operation of all
mechanical equipment and construction processes on and off the Site shall not cause any
unnecessary or excessive noise, taking into account applicable environment requirements.
The Contractor shall use all necessary measures and shall maintain all plant and silencing
equipment in good condition so as to minimize the noise emission during construction works.
5 Control of Wastes
5.1 The Contractor shall control the disposal of all forms of waste generated by the
construction operations and in all associated activities. No uncontrolled deposition or
dumping shall be permitted.
Wastes to be so controlled shall include, but shall not be limited to, all forms of fuel and
engine oils, all types of bitumen, cement, surplus aggregates, gravels, bituminous mixtures
etc. The Contractor shall make specific provision for the proper disposal of these and any
other waste products, conforming to local regulations and acceptable to the Engineer.
6 Emergency Response
6.1 The Contractor shall plan and provide for remedial measures to be implemented in
the event of occurrence of emergencies such as spillages of oil or bitumen or chemicals.
6.2 The Contractor shall provide the Engineer with a statement of the measures he
intends to implement in the event of such an emergency, which shall include a statement of
how he intends to provide personnel adequately trained to implement such measures.
7. Measurement
7.1 No separate measurement shall be made in respect of compliance by the Contractor
with these provisions. The Contractor shall be deemed to have made allowance for such
compliance with these provisions in the preparation of his prices for items of work included
in the Bills of Quantities and full compensation for such compliance will be deemed to be
covered by them.
Material
VG-40
160-170
160-175
160-170
150 Min
100 Min
VG-30
150-165
150-170
150-165
140 Min
90 Min
VG-20
145-165
145-170
145-165
135 Min
85 Min
VG-10
140-160
140-165
140-160
130 Min
80 Min
* Rolling must be completed before the mat cools to these minimum temperatures.
506.3.6 Rolling : Compaction shall be carried out in accordance with the provisions of
Clauses 501.6 and 501.7.
Rolling shall be continued until the specified density is achieved, or where no density is
specified, until there is no further movement under the roller. The required frequency of
testing is defined in Clause 903.
506.4 Surface Finish and Quality Control of Work
162
The surface finish of the completed construction shall conform to the requirements of
Clause 902. For control of the quality of materials and the works carried out, the relevant
provisions of Section 900 shall apply.
In the remix process, the scarified material should be taken from the mixing unit of the
plant where it is recycled with fresh binder, aggregate and recycling agent. Then the recycled
mixture is spread on the preheated surface and tamped and compacted to the required profile.
520.6.2 Heating and scarifying : Surfaces to be treated shall be heated by plant with
surfaces insulated and fully enclosed. The heated width of surfacing shall exceed the scarified
width by at least 75 mm on each side, except against the edge of the carriageway or kerb face.
When new surfacing material is spilled onto the road surface it shall be removed before the
existing surface is heated and scarified. Areas of unscarified material shall not exceed 50 mm
x 50 mm.
The depth of scarification shall be such that the bottom of the scarified layer is parallel to
and below the finished road surface level by the thickness of wearing course material
specified. A tolerance of 6 mm is permissible.
Where street furniture and other obstructions occur, these shall be suitably protected or
removed and the void covered. Surface dressing and large areas of road markings shall be
removed by milling, planning scarifying or by similar approved processes.
The heated surface shall be evenly scarified to comply with the requirements of this
Clause. When street furniture is left in place or raised, the adjacent area shall be scarified by
other means, with the material either left in place or removed, prior to passage of the
machine.
If furniture needs to be repositioned on completion of work, the new wearing course
material shall be used to make good the road surface for a maximum width of 200 mm
around the obstruction.
During the reheating process, the surface temperature of the road shall not exceed 200C
for more than 5 minutes.
520.6.3 Rejuvenator: For Remix, when required, rejuvenator shall be uniformly sprayed
across the fullwidth of the processed material. The machine shall incorporate a meter for
continuous verification of quantities which shall be within 5% of the specified rate. The
volume of rejuvenator shall vary in relation to the operating speed of the machine, which
shall be r4elated to the volume of material mixed or scarified.
The rejuvenator shall be a non-emulsified aromatic extract. Its properties shall be
verified using the Rolling Thin Film Oven Test.
Rejuvenation of the existing pavement may also be performed by adding new hot-mix
bituminous material containing a soft binder for restoring the binder in the existing pavement
to the required viscosity. Use of rejuvenating oil may be resorted to in case the target values
of viscosity, penetration and softening are not met.
165
520.6.4 Mixing : When required, new hot-mix material shall be mixed with the heated
and scarified road pavement material in a pugmill within the Remix machine, observing the
mixing temperatures specified in Table 500-15.
After mixing, the recycled bituminous materials shall be automatically led to a finishing
unit, which spreads and levels the mixture to the specified thickness and cross-section.
The new bituminous concrete wearing course shall comply with Clause 508.
520.6.5 Additional material (general) : The proportion of new hot-mix bituminous
material, and the proportion of existing bituminous pavement material shall be as directed by
the Engineer, together with the amount the road surface level is to be raised (if any).
The type and quantity of the new hot-mix material shall be determined by using the
Marshall Mix Design procedure specified in the Asphalt Institute Manual MS-2, before work
commences. Remix designs shall incorporate the stated proportion of material sampled from
the existing road surface.
When additional coarse or fine aggregate or filler are required to be added, they shall
comply with the requirements of Clause 508.2. The amount of additional coarse or fine
aggregate or filler to be added to the existing bituminous pavement material shall be notified
to the Engineer.
520.6.6 Additional aggregate (remix process) : The coarse aggregate, fine aggregate
and filler added to the Remixed material shall comply with the requirements of Clause 508.2.
520.6.7 New surfacing (repave and remix/repave processes) : New surfacing material
shall be bituminous concrete wearing course complying with Clause 508, or other wearing
course material approved by the Engineer.
The new surfacing material shall be laid on, and compacted with, the reprofiled
surfacing, which shall be at a temperature within the range of 100C to 150C.
166
601.5 Construction
601.5.1 General : The pace and programme of the Dry Lean Concrete (DLC) subbase
construction shall be matching suitably with the programme of construction of the PQC over
it. The DLC sub-base shall be overlaid with PQC only after 7 days after subbase construction.
The DLC sub-base shall be constructed over granular subbase / drainage layer (vide Clause
400).
601.5.2 Batching and mixing : The batching plant shall be capable of proportioning the
materials by weight, each type of material being weighed separately in accordance with
Clause 602.9.3.2. The cement from the bulk stock shall be weighed separately from the
aggregates. The capacity of batching and mixing plant shall be at least 25 percent higher than
the proposed capacity for the laying arrangements. The batching and mixing shall be carried
out preferably in a forced action central batching and mixing having necessary automatic
controls to ensure accurate proportioning and mixing. Other types of mixes shall be permitted
subject to demonstration of their satisfactory performance during the trial length. The type
and capacity of the plant shall be got approved by the Engineer before commencement of the
trial length. The weighing balances shall be calibrated by weighing with large weighing
machine or in a weigh bridge. The accuracy of weighing scales of the batching plant shall be
within 2 percent in the case of aggregates and 1 per cent in the case of cement, fly ash,
ground granulated slag and water.
The design features of Batching Plant should be such that the shifting operations of the
plant will not take very long time when they are to be shifted from place to place with the
progress of the work.
601.5.3 Transporting : Plant mix lean concrete shall be discharged immediately from
the mixer, transported directly to the point where it is to be laid and protected from the
weather by covering the tippers/dumpers with tarpaulin during transit. The concrete shall be
transported by tipping trucks, sufficient in number to ensure a continuous supply of material
to feed the laying equipment to work at a uniform speed and in an uninterrupted manner. The
lead of the batching plant to paving site shall be such that the travel time available from
mixing to paving as specified in Clause 601.5.5.2 will be adhered to. Tipping truck shall not
have old concrete sticking to it. Each tipping truck shall be washed with water jet before next
loading as and where required after inspection.
601.5.4 Placing : Lean concrete shall be placed by a paver with electronic sensor on subbase/base as per clause 400. The equipment shall be capable of laying the material in one
layer in an even manner without segregation, so that after completion the total thickness is as
167
specified. The paving machine shall have high amplitude tamping bars to give good initial
compaction to the sub-base. One day before placing of the dry lean cement concrete sub-base,
the surface of the untreated granular sub-base / drainage layer shall be given a fine spray of
water and rolled with a smooth wheeled roller.
The laying of the two-lane road sub-base may preferably be done in full width. In case of
unavoidable situation lane by lane laying may be done. Preferably the lean concrete shall be
placed and compacted across the full width of the road, by constructing it in one go or in two
lanes running forward simultaneously. No joints shall normally be constructed in Dry Lean
Concrete construction except in the following situations:
a) Transverse butt type joints shall be provided at the end of the construction in a day.
Longitudinal construction joint shall be provided only when lane by lane construction is done
or in case of multiple lane exceeding two lane where pavers of adequate width capable of
paving in one go are not available. Transverse joints in PQC shall not be co-terminal with the
construction butt type joint of DLC. It shall be staggered from the construction butt type joint
in DLC by 800-1000mm.
Longitudinal joint in DLC shall be similarly staggered by 300-400 mm from the
longitudinal joint of PQC.
The DLC shall be laid in such a way that it is atleast 500 mm wider on each side than the
proposed width including paved shoulders of PQC.
602.2.9 Storage of materials : All materials shall be stored in accordance with the
provisions of Clause 1014 of the Specifications and other relevant IS Specifications. All
efforts must be made to store the materials in proper places so as to prevent their deterioration
or contamination by foreign matter and to ensure their satisfactory quality and fitness for the
work. The platform where aggregates are stock piled shall be on a levelled platform elevated
from the ground atleast by 150 mm. This platform will be a pucca paved platform, preferably
brick paved. The area shall have slope and drain to drain off rain water. The storage space
must also permit easy inspection, removal and storage of the materials. Aggregates of
different sizes shall be stored in partitioned stackyards.
All such materials even though stored in approved godowns must be subjected to
acceptance test as per Clause 903 of these Specifications immediately prior to their use.
shall be straight, free of irregularities and burring restricting slippage in the concrete. The
sliding ends shall be sawn or cropped cleanly with no protrusions outside the normal diameter
of the bar. To remove any protrusions, the ends of the dowel bars shall be ground by filling.
The dowel bar shall be supported on cradles/dowel chairs in prefabricated joint assemblies
positioned prior to the construction of the slabs or mechanically inserted with vibration into
the plastic concrete by a method which ensures correct placement of the bars besides full recompaction of the concrete around the dowel bars. Modern slip form pavers are equipped
with automatic dowel bars inserter (DBI).
602.6.5.2 Unless shown otherwise on the drawings, dowel bars shall be positioned at mid
depth of the slab within a tolerance of 20 mm, and centered equally about intended lines of
the joint within a tolerance of 25 mm. They shall be aligned parallel to the finished surface
of the slab and to the centre line of the carriageway and to each other within tolerances given
hereunder, the compliance of which shall be checked as per Clause 602.10.7.
i) For bars supported on cradles prior to the laying of the slab:
a) All bars in a joint shall be within 3 mm per 300 mm length of bar
b) 2/3rd of the bars shall be within 2 mm per 300 mm length of bar
c) No bar shall differ in alignment from an adjoining bar by more than 3 mm per 300 mm
length of bar in either the horizontal or vertical plane
d) Cradles supporting dowel bar shall not extend across the line of joint i.e. no steel bar
of the cradle assembly shall be continuous across the joint.
ii) For all bars inserted after laying of the slab:
a) Twice the tolerance for alignment as indicated in (i) above.
602.6.5.3 Dowel bars, supported on cradles in assemblies, when subject to a load of 110
N applied at either end and in either the vertical or horizontal direction (upwards and
downwards and both directions horizontally) shall conform to be within the following limits:
i) Two-thirds of the number of bars of any assembly tested shall not deflect more than 2
mm per 300 mm length of bar
ii) The remainder of the bars in that assembly shall not deflect more than 3 mm per 300
mm length of bar.
602.6.5.4 The assembly of dowel bars and supporting cradles, including the joint filler
board in the case of expansion joints, shall have the following degree of rigidity when fixed
in position:i) For expansion joints, the deflection of the top edge of the filler board shall be not
greater than 13 mm, when a load of 1.3 kN is applied perpendicular to the vertical face of the
joint filler board and distributed over a length of 600 mm by means of a bar or timber
packing, at mid depth and midway between individual fixings, 0r 300 mm from either end of
169
any length of filler board, if a continuous fixing is used. The residual deflection after load
shall be not more than 3 mm.
ii) The joint assembly fixing to sub-base shall not fail under the 1.3 kN load applied for
testing the rigidity of the assembly but shall fail before the load reaches 2.4 kN.
iii) The fixings for contraction joint shall not fail under 1.3 kN load and shall fail before
the load reaches 2.6 kN when applied over a length of 600 mm by means of a bar or timber
packing placed as near to the level of the line of fixings as practicable.
iv) Fixings shall be deemed to fail when there is displacement of the assemblies by more
than 3 mm with any form of fixing, under the test load. The displacement shall be measured
at the nearest part of the assembly to the centre of the bar or timber packing.
602.6.5.5 Dowel bars in the contraction joints, construction joints and expansion joints
shall be covered by a thin plastic sheath. The sheath shall be not more than 125 micron thick
and shall be tightly fitted on the bar for at least two-thirds of the length from one end for
dowel bars in contraction joints or half the length plus 50 mm for expansion joints. The
sheathed bar shall comply with the following pull-out tests:
i) Four bars shall be taken at random from stock and without any special preparation
shall be covered by sheaths as required in this Clause.
The ends of the dowel bars which have been sheathed shall be cast centrally into
concrete specimens 150 x 150 x 600 mm, made of the same mix proportions to be used in the
pavement, but with a maximum nominal aggregate size of 20 mm and cured in accordance
with IS: 516. At 7 days a tensile load shall be applied to achieve a movement of the bar of at
least 0.25 mm. The average bond stress to achieve this movement shall not be greater than
0.14 MPa.
602.6.5.6 For expansion joints, a closely fitting cap 100 mm long consisting of
waterproofed cardboard or an approved synthetic material like PVC or GI pipe shall be
placed over the sheathed end of each dowel bar. An expansion space ( about 25 mm ) at least
equal in length to the thickness of the joint filler board shall be formed between the end of the
cap and the end of the dowel bar by using compressible sponge. To block the entry of cement
slurry between dowel and cap it shall be taped.
602.6.6 Tie bars
602.6.6.1 Tie bars in longitudinal joints shall be deformed steel bards of strength
500MPa complying with IS:1786 and in accordance with the requirements given below. The
bars shall be free from oil, dirt, loose rust and scale.
602.6.6.2 Tie bars projecting across the longitudinal joint shall be protected from
corrosion for 75mm on each side of the joint by a protective coating of bituminous paint with
the approval pf the Engineer. The coating shall be dry when the tie bars are used. In the case
of coastal resin, tie bars shall be epoxy coated as per IS: 13620.
170
602.6.6.3 Tie bars in longitudinal joints shall be made up into rigid assemblies with
adequate supports and fixings to remain firmly in position during the construction of the slab.
Alternatively, tie bars at longitudinal joints may be mechanically or manually inserted into
the plastic concrete from above by vibration using a method which ensures correct
placements of the bars and recompaction of the concrete around the tie bars. The modern slip
form pavers are equipped with automatic tie bars inserter (TBI).
602.6.6.4 Tie bars shall be positioned to remain within the middle third of the slab depth
as indicated in the drawings and approximately parallel to the surface and approximately
perpendicular to the line of the joint, with the centre of each bar on the intended line of the
joints within a tolerance of 50mm, and with a minimum cover of 30mm below the joint
groove.
602.7 Weather and Seasonal Limitations
602.7.1 Concreting during monsoon months: When concrete is being placed during
monsoon months and when it may be expected to rain, sufficient supply of tarpaulin or other
water proof cloth shall be provided along the line of the work. Any time when it rains, all
freshly laid concrete which had not been covered for curing purposes shall be adequately
protected. Any concrete damaged by rain shall be removed and replaced. If the damage is
limited to texture, it shall be retextured in accordance with the directions of the Engineer.
No concreting shall be done when the concrete temperature is above 30 degree
Centigrade. Besides in adverse conditions like high temperature, low relative humidity,
excessive wind velocity, imminence of rains etc., if so desired by the Engineer, tents on
mobile trusses may be provided over the freshly laid concrete for a minimum period of 3
hours as directed by the Engineer. The temperature of the concrete mix on reaching the
paving site shall not be more than 30C. To bring down the temperature, if necessary chilled
water or ice flakes should be made use of. When the ambient temperature is more than 350C,
no concreting shall be permitted.
No concreting shall be done when the concrete temperature is below 50C and the
temperature is further descending.
602.8 Side Forms, Rails and Guidewires
602.8.1 Side forms and rails : All side forms shall be of mild steel of depth equal to the
thickness of pavement or slightly less to accommodate the surface regularity of the sub-base.
The forms can be placed in series of steel packing plates or shims to take care of irregularity
of sub-base. They shall be sufficiently robust and rigid o support the weight and pressure
caused by a paving equipment. Side forms for use with wheeled paving machines shall
incorporate metal rails firmly fixed at a constant height below the top of the forms. The forms
and rails shall be firmly secured in position by not less than 3 stakes/pins per each 3 m length
so as to prevent movement in any direction. Forms and rails shall be straight within a
tolerance of 3 mm in 3 m and when in place shall not settle in excess of 1.5mm in 3 m while
171
paving is being done. Forms shall be cleaned and oiled immediately before each use. The
forms shall be bedded on a continuous bed of low moisture content lean cement mortar or
concrete and set to the line and levels shown on the drawings within tolerances 10 mm and
3 mm respectively. The bedding shall not extend under the slab and there shall be no
vertical step between adjacent forms of more than 3 mm. The forms shall be got inspected
from the Engineer for his approval before 12 hours on the day before the construction of the
slab and shall not be removed until at least 12 hours afterwards.
602.8.2 At all times sufficient forms shall be used and set to the required alignment for at
least 300 m length of pavement immediately in advance of the paving operations, or the
anticipated length of pavement to be laid within the next 24 hrs whichever is more.
602.8.3 Use of guidewires
602.8.3.1 Where slip form paving is proposed, a guidewire shall be provided along both
sides of the slab. Each guidewire shall be at a constant height above and parallel to the
required edges of the slab as described in the contract/drawing within a vertical tolerance of
3mm. Additionally, one of the wires shall be kept at a constant horizontal distance from the
required edge of the pavement as indicated in the contract/drawing within a lateral tolerance
of 10 mm.
602.8.3.2 The guidewires shall be supported on stakes not more than 6 m apart by
connectors capable of fine horizontal and vertical adjustment. The guidewire shall be
tensioned on the stakes so that a 500 gm weight shall produce a deflection of not more than
20 mm when suspended at the mid point between any pair of stakes. The ends of the
guidewires shall be anchored to fixing point or winch and not on the stakes. On the curves the
stakes shall be fixed at not more than 3 m centre to centre.
602.8.3.3 The stakes shall be positioned hammered into the ground and the
connectorswill be maintained at their correct height and alignment from 12 hours on the day
before concreting takes place until 12 hours after finishing of the concrete.
The guidewire shall be erected and tensioned on the connectors at any section for at least
2 hours before concreting that section.
602.8.3.4 The Contractor shall submit to the Engineer for his approval of line and level,
the stakes and connectors which are ready for use in the length of road to be constructed by
12 hours on the working day before the day of construction of slab. Any deficiencies noted
by the Engineer shall be rectified by the Contractor who shall then re-apply for approval of
the affected stakes. Work shall not proceed until the Engineer has given his approval. It shall
be ensured that the stakes and guidewires are not affected by the construction equipment
when concreting is in progress.
602.9 Construction
602.9.1 General : A systems approach may be adopted for construction of the pavement,
and the Method Statement for carrying out the work, detailing all the activities, indication of
172
time-cycle, equipment, personnel etc., shall be got approved from the Engineer before the
commencement of the work. The above shall include the type, capacity and make of the
batching and mixing plant besides the hauling arrangement and paving equipment. The
capacity of paving equipment, batching plant as well as all the ancillary equipment shall be
adequate for a paving rate of atleast 500 m in one day. The desirable paving speed of slipform
pavers is 1 m per minute, but it shall not be less than 0.5 m per minute average. The frequent
stop and starts need to be avoided.
602.9.2. Batching and mixing: Batching and mixing of the concrete shall be done at a
central batching and mixing plant with automatic controls, located at a suitable place which
takes into account sufficient space for stockpiling of cement, aggregates and stationary water
tanks. This shall be, however, situated at an approved distance, duly considering the
properties of the mix and the transporting arrangements available with the Contractor.
The plasticizer/super plasticizer shall be pumped in the end of input of all ingredients i.e.
when cement, aggregate, fly ash and water etc. have been thoroughly mixed. Proper dispersal
of plasticizer/super plasticizer and air entraining agent shall be ensured.
Tipping trucks shall be washed at a regular frequency as prescribed by the Engineer to
ensure that no left-over mix of previous loading remain stuck. Desirably each tipping truck
shall be washed with water jet before next loading.
602.9.4 Hauling and placing of concrete
602.9.4.1 Freshly mixed concrete from the central batching and mixing plant shall be
transported to the paver site by means of trucks/tippers of sufficient capacity and approved
design in sufficient numbers to ensure a constant supply of concrete. Covers shall be used for
protection of concrete against the weather. While loading the concrete trucks shall be moved
back and forth under the discharge chute to prevent segregation. The trucks/tippers shall be
capable of maintaining the mixed concrete in a homogeneous state and discharging the same
without segregation and loss of cement slurry. The feeding to the paver is to be regulated in
such a way that the paving is done in an uninterrupted manner with a uniform speed
throughout the days work.
602.9.4.2 Placing of concrete
Concrete mixed in central mixing plant shall be transported to the site without delay and
the concrete which, in the opinion of the Engineer has been mixed too long before laying will
be rejected and shall be removed from the site.
The total time taken from the addition of the water to the mix, until the completion of the
surface finishing and texturing shall not exceed 120 minutes when concrete temperature is
less than 25C and 90 minutes when the concrete temperature is between 25C to 30C.
Trucks/tippers delivering concrete shall not run on plastic sheeting nor shall they run on
completed slabs until after 28 days of placing the concrete. The paver shall be capable of
paving the carriageway as shown in the drawings, in a single pass and lift. Side
173
tipping/dumping of mix with storage facility should be created to ensure continuous paving
besides ensuring no damage to the sheathing/DLC due to tipping trucks.
The placing of concrete in front of the PQC paver should preferably be from the side
placer to avoid damage to DLC by the PQC concrete trucks. In case of unavoidable situation,
truck supplying PQC concrete to the paver may be allowed to ply on the DLC with the
approval of the Engineer. The paver shall be capable of paving the carriageway as shown in
the drawings, in a single pass and lift.
602.9.4.3 Where fixed form pavers are to be used, forms shall be fixed in advance as per
Clause 602.8. of the Specifications. Before any paving is done, the site shall be shown to the
Engineer, in order to verify the arrangement for paving besides placing of dowels, tie-bars
etc., as per the relevant Clauses of these Specifications. The mixing and placing of concrete
shall progress only at such a rate as to permit proper finishing, protecting and curing of the
pavement.
602.9.4.4 In all cases, the temperature of the concrete shall be measured at the point of
discharge from the delivery vehicle.
602.9.4.5 The addition of water to the surface of the concrete to facilitate the finishing
operations will not be permitted except with the approval of the Engineer when it shall be
applied as a mist by means of approved equipment.
602.9.4.6 If considered necessary by the Engineer, the paving machines shall be
provided with approved covers to protect the surface of the slab under construction from
direct sunlight and rain or hot wind.
602.9.4.7 While the concrete is still plastic, its surface shall be textured by brush or tines
as per the instructions of the engineers in compliance with Clause 602.9.8. The surface and
edges of the slab shall be cured by the application of a sprayed liquid curing membrane in
compliance with Clause 602.9.9. After the surface texturing, but before the curing compound
is applied, the concrete slab shall be marked with the chainage at every 100 m interval by
embossing.
602.9.4.8 As soon as the side forms are removed, edges of the slabs shall be corrected
wherever irregularities have occurred by using fine concrete composed of one part of cement
to 3 parts of fine chips and fine aggregate under the supervision of the Engineer.
602.9.4.9 If the requirement of Clause 902.4. for surface regularity fails to be achieved
on two consecutive working days, then normal working shall cease until the cause of the
excessive irregularity has been identified and remedied.
602.9.5 Construction by fixed form paver
602.9.5.1 The fixed form paving train shall consist of separate powered machines which
spread, compact and finish the concrete in a continuous operation.
174
602.9.5.2 The concrete shall be discharged without segregation into a hopper spreader
which is equipped with means for controlling its rate of deposition on to the subbase. The
spreader shall be operated to strike off concrete upto a level requiring a small amount of
cutting down by the distributor of the spreader. The distributor of spreader shall strike off the
concrete to the surcharge adequate to ensure that the vibratory compactor thoroughly
compacts the layer. If necessary, poker vibrators shall be used adjacent to the side forms and
edges of the previously constructed slab. The vibratory compactor shall be set to strike off the
surface slightly high so that it is cut down to the required level by the oscillating beam. The
machine shall be capable of being rapidly adjusted for changes in average and differential
surcharge necessitated by changes in slab thickness or cross fall. The final finisher shall be
able to finish the surface to the required level and smoothness as specified, care being taken
to avoid bringing up of excessive mortar to the surface by over working.
602.9.6 Construction by slip form paver
602.9.6.1 The slip form paving train shall consist of power machine which spreads,
compacts and finishes the concrete in a continuous operation. The slip form paving machine
shall compact the concrete by internal vibration and shape it between the side forms with
either a conforming plate or by vibrating and oscillating finishing beams. The concrete shall
be deposited without segregation in front of slip from paver across the whole width and to a
height which at all times is in excess of the required surcharge. The deposited concrete shall
be struck off to the necessary average and differential surcharge by means of the strike off
plate or a crew auger device extending across the whole width of the slab.
The equipment for striking-off the concrete shall be capable of being rapidly adjusted for
changes of the average and differential surcharge necessitated by change in slab thickness or
crossfall.
602.9.6.2 The level of the conforming plate and finishing beams shall be controlled
automatically from the guide wires installed as per Clause 602.8 by sensors attached at the
four corners of the slip form paving machine. The alignment of the paver shall be controlled
automatically from the guide wire by at least one set of sensors attached to the paver. The
alignment and level of ancillary machines for finishing, texturing and curing of the concrete
shall be automatically controlled relative to the guide wire or to the surface and edge of the
slab.
602.9.6.3 Slip-form paving machines shall have vibrators of variable output, with a
maximum energy output of not less than 2.5 KW per metre width of slab per 300 mm depth
of slab for a laying speed upto 1.5 m per minute or pro-rata for higher speeds. The machines
shall be of sufficient mass to provide adequate reaction during spreading and paving
operations on the traction units to maintain forward movements during the placing of
concrete in all situations.
602.9.6.4 If the edges of the slip formed slab slump to the extent that the surface of the
top edge of the slab does not comply with the requirements of Clause 602.14, then special
175
measures such as fixing of side forms held in position by screwed jacks or any other suitable
device approved by the Engineer shall be taken to support the edges to the required levels and
work shall be stopped until such time as the Contractor can demonstrate his ability to slip
form the edges to the required levels.
Pavers with adequate width to pave the entire carriageway width in one go will be
employed. Paving in part width will be avoided, except in unavoidable circumstances. In case
of part width paving, care will be taken to ensure that while paving the next lane bond
between the old concrete and newly laid concrete is properly formed to develop adequate
bond strength between tie bars and concrete as specified in IRC:58 (Appendix-4 of IRC 58).
Care shall be taken to avoid damage to the previous lane.
Work on next lane shall be permitted when the previously paved lane is cured for at least
14 days and is in a position to bear the weight of paving machines. When the wheels or
crawler tracks are to ply on the already paved surface, necessary precautions shall be taken by
placing protective pads of rubber or similar material so that texture is not damaged.
The wheel or track shall be reasonably away from the edge to avoid damage to the
previously paved slab.
Upon the instructions of the Engineer, Contractor shall scrap the concrete surface when
in plastic state with a 3 m long tube float fixed with a long and stable handle before texturing.
Tube float shall be of an alloy steel tube of 50 to 60 mm diameter with a long and stable
handle. The length of tube float shall preferably be longer than the half of the length of slab
i.e., half the distance between two transverse contraction joints. This operation shall be done
to improve surface irregularity caused due to varied causes like frequent stoppages of work,
surface deformation due to plastic flow etc. The tube float shall be placed at the centre of the
slab parallel to longitudinal joint and pulled slowly and uniformly towards the edges. After
the use of float tube, it shall be frequently cleaned before further use. The slurry removed
shall be discarded. This activity shall be advanced laterally by providing an overlap of half
the length of tube float. The removal of the cement slurry from the surface shall be sufficient
enough such that the texture is formed on a firm surface and is more durable. This operation,
however, shall be carried out after removing bleeding water. This operation shall be done in
the case of pavement construction using fixed form or slip form paving technique.
602.9.7 Semi-Mechanised and Labour-Oriented Construction Technique: Areas in which
hand-guided methods of construction become indispensable shall be got approved by the
Engineer in writing in advance. Such work may be permitted only in restricted areas in small
lengths. Work shall be carried out by skilled personnel as per methods approved by the
Engineer. The acceptance criteria regarding level, thickness, surface regularity, texture,
finish, strength, of concrete and all other quality control measures shall be the same as in the
case of machine laid work. Guidelines on the use of plants, equipment, tools, hauling of mix,
compaction floating, straight edging, texturing, edging etc. shall be as per IRC:15 (Clause
9.10).
176
Transition Slabs : At the interface of rigid and flexible pavement, at least 3 m long
reinforced buried slab should be provided to give a long lasting joint at the interface. The
details are shown in IRC: 15 (Clause 9.10.11, Fig. 3 of IRC: 15)
Anchor beam and terminal slab beam adjoining bridged structures: Cement concrete
slabs will expand during hot season and this will result in the building up of horizontal thrust
on adjoining bridge structure. To contain this thrust RCC anchor beams are to be provided in
the terminal slab. The terminal slab also needs to be provided with reinforcement to
strengthen it. A typical arrangement of anchor beam and the terminal slab are show in Fig.
given below. In case of culverts, etc. where the concrete slabs are provided above the
superstructure, there is no need to construct anchor beams and terminal slab. In case the
concrete slab abuts with culvert structure, the construction of anchor beam and terminal slab
will be necessary. The details are shown in IRC: 15 (Clause 8.5.2, Fig. 2 of IRC: 15).
The treatment of PQC on Culverts: The PQC shall be taken over the culverts. At both
ends of the abutment walls, expansion joint with 12 mm thick synthetic board shall be
provided in addition to contraction joints in between the expansion joints, if required.
602.9.8 Surface texture
602.9.8.1 After final floating and finishing of the slab and before application of the liquid
curing membrane, the surface of concrete slabs shall be textured either in the transverse
direction (i.e., at right angles to the longitudinal axis of the road) or in longitudinal direction
(i.e., parallel to the centreline of the roadway). The texturing shall be done by tinning the
finished concrete surface by using rectangular steel tines. A beam or a bridge mounted with
steel tines shall be equipped and operated with automatic sensing and control devices from
main paver or auxiliary unit. The tinning unit shall have facility for adjustment of the
download pressure on the tines as necessary to produce the desired finish. The tinning rakes
shall be cleaned often to remove snots of slurry. The tines will be inspected daily and all the
damaged and bent tines shall be replaced before commencing texturing.
Tined grooves shall be 3 mm wide and 3 to 4 mm deep. Before commencing texturing,
the bleeding water, if any, shall be removed and texturing shall be done on a firm surface.
Normally, transverse tinning will be preferred.
Transverse Tinning :
When the texturing is specified in transverse direction, a beam of at least 3 m length
mounted with tines shall be moved in transverse direction to produce the texture. The grooves
produced shall be at random spacing of grooves but uniform in width and depth. The spacing
shall conform to a pattern shown below:
Random spacing in mm
10 14 16 11 10 13 15 16 11 10 21 13 10
177
The above pattern shall be repeated. Texturing shall be done at the right time such that
the grooves after forming shall not close and they shall not get roughened. Swerving of
groove patterns will not be permitted. The completed textured surface shall be uniform in
appearance.
Longitudinal tinning :
Longitudinal tinning shall be done, if specified in the Contract. The texturing bridge shall
be wide enough to cover the entire width of the carriageway but within 75 mm from the
pavement edge. The centre to centre spacing shall be 18 to 21 mm. The width of tine texture
shall be 3 mm and depth shall be 3 to 4 mm.
602.9.8.2 Alternatively on the instructions of the Engineer, the brushed texturing shall be
applied. The brushed surface texture shall be applied evenly across the slab in one direction
by the use of a wire brush not less than 450 mm wide but wider brushes normally of 3 m
length are preferred. The brush shall be made of 32 gauge tape wires grouped together in tufts
placed at 10 mm centres. The tufts shall contain an average of 14 wires and initially be 100
mm long. The brush shall have two rows of tufts. The rows shall be 20 mm apart and the tufts
in one row shall be opposite the centre of the gap between tufts in the other row. The brush
shall be replaced when the shortest tuft wears down to 90 mm long.
602.9.8.3 The texture depth shall be determined by the Sand Patch Test as described in
the Clause 602.12. This test shall be performed at least once for each days paving and
wherever the Engineer considers it necessary at times after construction as under:
Five individual measurements of the texture depth shall be taken at least 2 m apart
anywhere along a diagonal line across a lane width between points 50 m apart along the
pavement.
No measurement shall be taken within 300 mm of the longitudinal edges of a concrete
slab constructed in one pass.
602.9.8.4 Texture depths shall not be less than the minimum required when
measurements are taken as given in table 600-3 nor greater than a maximum average of 1.25
mm.
TABLE : 600-3. Texture Depth
Time of Test Number of Required
Measurements Texture Depth (mm)
Specified Tolerance
Value
1. Between 24 hours and 7 days after An average of 1.00 0.25 the constn., of the slab or
until 5 measurements the slab is first used by vehicles.
178
2. Not later than 6 weeks before the An average of 1.00 +0.25 road is opened to the
public traffic. 5 measurements -0.35
602.9.8.5 After the application of the brushed texture, the surface of the slab shall have a
uniform appearance.
602.9.8.6 Where the texture depth requirements are found to be deficient, the Contractor
shall make good the texture across the full lane width over length directed by the Engineer,
by retexturing the hardened concrete surface in an approved manner.
602.9.9 Curing
602.9.9.1 Immediately after the surface texturing, the surface and sides of the slab shall
be cured by the application of approved resin-based aluminized reflective curing compound
which hardens into an impervious film or membrane with the help of mechanical sprayer.
Curing compounds shall contain sufficient flake aluminium in finely divided dispersion
to produce a complete coverage of the sprayed surface with a metallic finish. The compound
shall become stable and impervious to evaporation of water from the surface of the concrete
within 60 minutes of application and shall be of approved type. The curing compounds shall
have a water retention efficiency index of 90 per cent in accordance with B S Specification
No. 7542 or ASTM-C-309-81, type-2.
602.9.9.2 The curing compound shall not react chemically with the concrete and the film
or membrane shall not crack, peel or disintegrate within three weeks after application.
Immediately prior to use, the curing compound shall be thoroughly agitated in its
containers. The rate of spread shall be in accordance with the manufacturers instructions
checked during the construction of the trial length and subsequently whenever required by the
Engineer. The mechanical sprayer shall incorporate an efficient mechanical device for
continuous agitation and mixing of the compound during spraying. To give continuous
covering , the curing compound may be sprayed in two layers.
602.9.9.3 In addition to spraying of curing compound, the fresh concrete surface shall be
protected for at least 3 hours by covering the finished concrete pavement with tents as
described in Clause 602.7.2, during adverse weather conditions as directed by the Engineer.
After three hours, the pavement shall be covered by moist hessian laid in two layers and the
same shall then be kept damp for a minimum period of 14 days after which time the hessian
may be removed. The hessian shall be kept continuously moist. All damaged/torn hessian
shall be removed and replaced by new hessian on a regular basis.
602.9.9.4 The Contractor shall be liable at his expense to replace any concrete damaged
as a result of incomplete curing or cracked on a line other than that of a joint as per IRC:SP
83.
602.10.7.1 Inspection of dowel bars
179
602.10.7.1 Compliance with Clause 602.6.5. for the position and alignment of dowel
bars at construction and expansion joints shall be checked by measurements relative to the
side forms or guide wires.
602.10.7.2 When the slab has been constructed, the position and alignment of dowel bars
and any filler board shall be measured after carefully exposing them in the plastic concrete
across the whole width of the slab. When the joint is an expansion joint, the top of the filler
board shall be exposed sufficiently in the plastic concrete to permit measurement of any
lateral or vertical displacement of the board. During the course of normal working, these
measurements shall be carried out in the pavement section at the end of days work by
extending slab length by 2 m. After sawing the transverse joint groove, the extended 2 m slab
shall be removed carefully soon after concrete has set to expose dowels over half the length.
These dowels can be tested for tolerances.
602.10.7.3 If the position and alignment of the bars in a single joint in the slab is
unsatisfactory then the next two joints shall be inspected. If only one joint of the three is
defective, the rate of checking shall be increased to one joint per day until the Engineer is
satisfied that compliance is being achieved. In the event of non-compliance in two or more
successive joints, the Contractor shall revert to the construction of fresh trial lengths and
make any necessary alteration to concrete mix, paving plant or methods until the dowel bar
position and alignment are satisfactory.
602.10.7.4 After the dowel bars have been examined, the remainder of the concrete shall
be removed over a width of 500 mm on each side of the line of the joint and reinstated to the
satisfaction of the Engineer. The dowels shall be inserted on both sides of the 1 m wide slab
by drilling holes and grouting with epoxy mortar. Plastic sheath as per Clause 602.6.5.5 shall
be provided on dowels on one of the joints. The joint groove shall be widened and sealed as
per Clause 602.11.
180
Unit5
TemporaryStructuresSafety
5.1
Introduction
Unit 4 presents guidelines on formwork, scaffolds, and work at height, working platform,
ladders, ramps etc. These are referred to as temporary structures and they are required for the
construction of permanents structures. In the early part of this section, the terms pertaining to
temporary structures are defined. The guidelines for the preparation of formwork scheme
(plan) are presented. The suggested formwork arrangements for commonly used structural
elements are provided. The unit also contains the checklist to be used by the contractor for
implementing the formwork arrangement. It also contains the checklist to be used for auditing
purposes. The unit ends with the description of penalties for non compliance of various
provisions provided in this unit.
5.2
DefinitionOfTemporaryStructuresRelatedTerms
lateral bracing.(b) That part of formwork, which supports the forms usually for a long
structure, such as a bridge.
Centering (Centering)- It is a temporary supporting structure to a soffit. It is the
specialized formwork used in the construction of arches, shells space structure where the
entire falsework is struck or decentred as a unit to avoid introducing injurious stress in any
part of structure.
Mould -A frame for casting, precast concrete units.
Scaffold (Scaffolding)- A temporary structure for gaining access to higher levels of the
permanent structure during construction.
5.3GuidelinesforthepreparationofFormworkSchemes(Plans)
Designassumptions
Typesofmaterials,sizes,lengths,andconnectiondetails
Sequenceofremovalofformsandshores
Anchors,formties,shores,andbraces
Fieldadjustmentoftheformduringplacingofconcrete
Workingscaffoldsandgangways
Weepholes,vibratorholes,oraccessdoorsforinspectionandplacingofconcrete
Constructionjoints,expansionjoints
Sequenceofconcreteplacementsandminimum/maximumelapsedtimebetweenadjacent
placements
Chamferstripsorgradestripsforexposedcornersandconstructionjoints
Foundationdetailsforfalsework
Specialprovisionssuchasprotectionfromfloodwater,ice,anddebrisatstreamcrossings
Formcoatingsandreleaseagents
Meansofobtainingspecifiedconcrete
Locationofboxouts,pipes,ducts,conduitsandmiscellaneousinsertsintheconcrete,
attachedtoorpenetratingtheforms
Locationofspacingofrubberpadswhereshuttervibrationsareused.
5.3.1 Reportingofdangerousoccurrences
All cases of collapse or subsidence of any other part of any structure, formwork,
launching girder, working platform, staging, scaffolding or means of access including shall
be reported to the Inspector having jurisdiction, whether or not any disablement or death
caused to the worker. ( To be cross link with reporting section given earlier)
182
5.3.2 Frequencyofinspection
There should be a weekly Inspection of scaffold by scaffolding supervisor and the record
for the same should be maintained. The inspection of scaffold must be based on the checklist
provided for scaffold in the work zone road safety manual.
Contractors Site SHE Manager will ensure that a system of routine inspections is carried
out periodically to all temporary structures that will pose a hazard to workmen.
Specific inspections (without a predetermined date and as and when needed) shall be
performed for formwork before concreting by formwork erector. Competent supervisors shall
usually perform such inspections in accordance with the check list specified in the manual.
The check list is indicative only and depending on the method statement submitted or
developed procedures, the Indian standards, rules and regulations, and Employers
requirements, the same shall be modified. The contractor shall preserve the records for such
inspection for audit.
5.4
FormworkArrangementForTypicalStructuralElements
In the following sections some suggested formwork arrangement for commonly used
RCC elements are provided. A number of manufacturers are available in the country who
provide similar arrangements. NHAI would prepare a list of approved manufactures and
include the list in the specification on formwork.
5.4.1 Wallformwork
Wall formwork should be so designed to take the pressure exerted by the concrete on
formwork besides other anticipated loads. The formwork components should be designed
according to relevant Indian Standards and the manufacturers guidelines. Suitable provision
for working platform shall be provided (see Fig. 32). Application of travelling and climbing
formwork shall be encouraged in case wall is to be cast in more than 2-3 lifts.
183
5.4.2 ColumnFormwork
Wall formwork should be so designed to take the pressure exerted by the concrete on
formwork besides other anticipated loads. The formwork components should be designed
according to relevant Indian Standards and the manufacturers guidelines. Suitable provision
for working platform shall be provided (see Fig.33). Suitable arrangement for reaching the
working platform shall also be provided. One such arrangement is shown in Fig__.
184
5.4.3 Well/Caissonformwork
185
5.4.4 PierFormwork
5.4.5 DeckSlabFormwork
5.4.6 Edgebeamformwork
An arrangement similar to the one shown in Fig. 34 may be adopted for casting the edge
beams for flyovers and bridges.
186
5.5
Workatheight
The contractor shall so far as is reasonably practicable ensure that the surface and every
parapet, permanent rail or other such fall protection measure of every place of work at height
are checked on each occasion before the place is used.
187
Any workmen employed by the contractor shall report to the supervisor about any defect
relating to work at height which he knows is likely to endanger the safety of himself or
another person.
Every workmen shall use any work equipment or safety device provided to him for work
at height by the contractor, in accordance with (a) any training in the use of the work
equipment or device concerned which have been received by him; and (b) the instructions
respecting that use which have been provided to him by the contractor as per the
requirements of the Employer
Requirements for existing places of work and means of access or egress at height
Every existing place of work or means of access or egress at height shall (a) be stable
and of sufficient strength and rigidity for the purpose for which it is intended to be or is being
used; (b) where applicable, rest on a stable, sufficiently strong surface; (c) be of sufficient
dimensions to permit the safe passage of persons and the safe use of any plant or materials
required to be used and to provide a safe working area having regard to the work to be carried
out there; (d) possess suitable and sufficient means for preventing a fall; (e) possess a surface
which has no gap
(i) through which a person could fall;
(ii) through which any material or object could fall and injure a person; or
(iii) giving rise to other risk of injury to any person, unless measures have been taken to
protect persons against such risk;
(f) be so constructed and used, and maintained in such condition, as to prevent, so far as is
reasonably practicable (i) the risk of slipping or tripping; or
(ii) any person being caught between it and any adjacent structure;
(g) where it has moving parts, be prevented by appropriate devices from moving
inadvertently during work at height.
5.6
WorkingPlatforms
5.6.1 RequirementsforallWorkingPlatforms
189
Any supporting structure shall (a) be suitable and of sufficient strength and rigidity for the
purpose for which it is being used; (b) in the case of a wheeled structure, be prevented by
appropriate devices from moving inadvertently during work at height;
(c) in other cases, be prevented from slipping by secure attachment to the bearing surface or
to another structure, provision of an effective anti-slip device or by other means of equivalent
effectiveness;
(d) be stable while being erected, used and dismantled; and
(e) when altered or modified, be so altered or modified as to ensure that it remains stable.
(f) Have suitable base plates and properly footed thereby.
(c) be so erected and used, and maintained in such condition, as to prevent, so far as is
reasonably practicable
i) the risk of slipping or tripping; or
ii) any person being caught between the working platform and any
adjacent structure.
vi) Loading
A working platform and any supporting structure shall not be loaded so as to give rise to a
risk of collapse or to any deformation, which could affect its safe use.
5.7
Scaffolding
ii)
Where heavy wind or gale force are expected, it would be necessary to take special
precaution and install additional ties to the scaffold to prevent overturning and
collapse.
iii)
Guide rails and toe boards must be provided for all working platforms to ensure safety
for workmen.
iv)
All working platforms should be fully covered to prevent materials falling and
causing injury to the workers or passersby.
v)
Safety nets or other screens should be provided to catch any falling materials.
vi)
The use of barrels, boxes, loose earth pads or other unsuitable objects as supports for
uprights and working platform, should not be permitted.
vii)
Care should be taken to see that no uninsulated wire exists within 3 m of the working
platforms, gang ways, runs etc. of the scaffolds.
viii)
ix)
x)
Grease, mud, paint, gravel or plaster or any such material shall be removed from
scaffold platforms immediately.
191
xi)
Either sand or saw dust or other suitable material shall be spread on platforms to
prevent slipping.
xii)
xiii)
xiv)
When scaffolds are to be used to a great extent and for long period of time, they
should be inspected from time to time to ensure its soundness.
xv)
Boards and planks used for platforms, gangways should be of sound quality and
proper thickness closely laid and securely fastened and placed.
i.
ii.
A copy of the plan, including any instructions it may contain, shall be kept available
for the use of persons concerned in the assembly, use, dismantling or alteration of
scaffolding until it has been dismantled.
iii.
The dimensions, form and layout of scaffolding decks shall be appropriate to the
nature of the work to be performed and suitable for the loads to be carried and permit
work and passage in safety.
iv.
While a scaffold is not available for use, including during its assembly, dismantling or
alteration, it shall be marked with general warning signs in accordance with and be
suitably delineated by physical means preventing access to the danger zone.
192
v.
5.8
Ladders
1) Every contractor shall ensure that a ladder is used for work at height only if a risk
assessment has demonstrated that the use of more suitable work equipment is not justified
because of the low risk and
i) The short duration of use; or
ii) Existing features on site, which he cannot alter.
3) Any surface upon which a ladder rests shall be stable, firm, of sufficient strength and of
suitable composition safely to support the ladder so that its rungs or steps remain horizontal,
and any loading intended to be placed on it.
5) A suspended ladder shall be attached in a secure manner and so that, with the exception of
a flexible ladder, it cannot be displaced and swinging is prevented.
193
6) A portable ladder shall be prevented from slipping during use by i) securing the stiles at or near their upper or lower ends;
ii) an effective anti-slip or other effective stability device; or
iii) any other arrangement of equivalent effectiveness.
7) A ladder used for access shall be long enough to protrude sufficiently above the place of
landing to which it provides access, unless other measures have been taken to ensure a firm
handhold.
8) No interlocking or extension ladder shall be used unless its sections are prevented from
moving relative to each other while in use.
10) Where a ladder or run of ladders raises a vertical distance of 9 metres or more above its
base, there shall, where reasonably practicable, be provided at suitable intervals sufficient
safe landing areas or rest platforms.
(a) a secure handhold and secure support are always available to the user; and
(b) the user can maintain a safe handhold when carrying a load unless, in the case of a step
ladder, the maintenance of a handhold is not practicable when a load is carried, and a risk
assessment has demonstrated that the use of a stepladder is justified because of
(i) the low risk; and
(ii) the short duration of use.
5.9LaunchingOperation
194
As launching operation is one of the riskiest job, the contractor shall take utmost
precaution at all stages like; planning, establishing casing yard, casting segments,
transporting segments, fabrication and erection of launching girders, launching of segments,
pre-stressing, auto launching of girders and dismantling of launching girders.
The contractor shall prepare a comprehensive Method Statement for the launching
operation, adhering to the SHE conditions laid down in conditions of contract on SHE and
project SHE manual. Particular reference shall be made to the provisions on working at
height. As the entire process of launching has to be undertaken at an elevated level the safety
of workers and the girder is paramount important. The following general guidelines shall be
adhered throughout the launching operation.
ii) Provisions for mounting light fittings shall also be made available in the launching girder.
iii) The casting yard shall be established ensuring the provision given in clause 38.0
iv) The workmen engaged in fabrication of reinforcement, concreting the segment shall be
provided with necessary PPEs including compulsory hand protection gloves.
v) Casting and curing of segment shall be undertaken under the direct supervision of the
responsible engineer of the contractor.
vi) Trucks with valid registration, licence, safe worthiness certificate, Employers approval
certificate, and pollution under check certificate shall only be used for transport of segments
vii) Drivers engaged for driving these trucks, shall be trained once in 6 months at Delhi
Government and Maruti Institute of Driver Training and Research, Wazirabad Road,
Adjoining Loni Road Flyover, Delhi 110 094 on defensive driving.
viii) Drivers shall also have undergone proper medical examination as per relevant clause
mentioned under Medical Facilities.
195
ix) The segments shall rigidly secured to the truck with necessary wooden wedges and
necessary red indicators/safety tapes provided so that the vehicle is clearly seen by other road
users both in day / night time.
x) Every launching girder shall have a responsible engineer on duty all the time.
xi) All the time from erection to dismantling the area between the two piers wherein
launching is in progress shall always be barricaded.
xii) Unloading of segments from trucks, lifting of segments, shifting of segments, gluing shall
be done under the direct supervision of the approved engineer of the contractor.
xiii) Auto launching shall be done only after approval from the Employer. After every auto
launching the stability of launching girder shall be ensured.
xiv) The vertical deflection of launching girder shall be monitored at all critical stages like
with/without loads and after every auto launching.
xv) A register containing all important operational details from erection to dismantling of
launching girders shall be maintained and made available to Employer whenever called for.
xvi) Test certificate for all lifting gears including Macalloy bars shall be maintained at a
location closer to the launching girder itself so that it can be referred during all inspections.
xvii) Adequate lighting at all time shall be ensured in the entire area of operation.
xviii) Access to drinking water & toilet shall be ensured to all workmen engaged for
launching process.
xix) Proper access ladders/stairways shall be maintained for safe ascending / descending of
workmen / engineers.
196
Non-adherence to any of the clauses mentioned above shall be viewed seriously by the
Employer and penalty levied as per relevant clause.
5.10 BatchingPlant/CastingYard
i) The batching plant / casting yard shall be effectively planned for smooth flow of unloading
and stacking the aggregates reinforcements and cement, batching plant, transport of concrete,
casting the segment, stacking the segment and loading the segments to the trucks. As far as
possible the conflicts should be avoided.
ii) The batching plant / casting yard shall be barricaded and made as a compulsory PPE zone
iii) If in case of material unloading area is not maintainable as PPE zone, the same shall be
segregated properly and made as a non-PPE zone with appropriate barrications.
iv) Electrical system shall also be suitably planned so that location of diesel generator, if any,
location of DBs, routing of cables and positioning of area lighting poles/masts does not
infringe on any other utility and pose danger.
v) Drainage shall be effectively provided and waste water shall be disposed after proper
treatment
vi) Time office, canteen, drinking water, toilet and rest place shall be suitably located for the
easy access to workers. All the facilities shall be properly cleaned and maintained during the
entire period of operation.
vii) Manual handling of cement shall be avoided to a larger extent. Whenever it is absolutely
necessary the workmen shall be given full body protection, hand protection and respiratory
protection as a basic measure of ensuring better health.
viii) The PPEs provided to cement handling workmen shall conform to international
standards.
197
ix) Access roads and internal circulation roads shall be well laid and maintained properly at
all time.
x) Non-adherence to any of the above provision shall be penalised as per relevant penalty
clause.
5.11Workoverwater
1. The contractor shall ensure that all construction personnel wear minimum requirements of
PPE as mentioned under clause (PPE)
2. The contractor shall display the warning Signs of Deep water at appropriate locations.
3. The contractor shall ensure edge protection including guard rails and toe boards etc.
4. The contractor shall ensure suitable rescue equipment and provide training on how to use
them.
Rescue Equipment
1. Lifebuoys with rescue lines should be provided at intervals along the site and positioned
conveniently for use in an emergency. Floating grab lines should be attached at intervals
or floating plant.
2. Personnel must wear life jackets, or buoyancy aid equipped with a whistle and lights
(during darkness).
3. All rescue equipment must be checked by a competent person to ensure it is present and
in good condition.
4. Enough personnel should be made available who are trained in the use of rescue
equipment and emergency procedures.
Rescue Boats
1. On tidal water or fast flowing rivers, a power-driven boat should be provided and
properly equipped, including lifebuoy with buoyant rope (or) rowing boat may be
sufficient in some canals and island waterways.
198
1. Competent boatmen, Trained first aiders should be made available on this area and not to
be used for other purposes
2. Keeping platforms and ladders clean and clear of debris, slime and other tripping hazards.
3. Safety nets to arrest falls where standard working platforms or harnesses cannot be
provided.
4. Safety lines and harnesses to be used in conjunction with temporary ladder access over
water
Safety lines and harnesses to be used in conjunction with temporary ladder
CHECKLISTS
5.12PenaltiesForNonCompliance
199
Unit6
WorkerandWorkZoneSafety
6.1MaterialHandling
6.1.1a)Hazardousmaterialshandling,storage,anduse
I.
200
6.1.2b)Manualmaterialhandling
I.
General: Construction workers are at a higher risk than most workers in receiving a
manual handling injury. Manual handling involves any activity requiring the use of
force exerted by a person to lift, lower, push, pull, carry or otherwise move, hold or
restrain a person, animal or thing. Workers may suffer from musculoskeletal problems
such as aches, strains and sprains as a result of manual handling. These can also be
caused by other tasks which involve repetitive movements, force, unusual postures,
prolonged pressure on a joint, badly organised working practices or work
environment. Effects on health can include:
9 Sprains or Strains
9 Backache
9 Sciatica
9 Hernias
9 Arthritis
9 Swelling of the wrist, forearm, elbow and shoulder
II.
201
6.1.3c)Mechanicalmaterialhandling
I.
General: Construction equipment may include dumpers and dump trucks, lift
trucks and telescopic handlers, piling rigs, vibro hammers, rail welding
equipment, mobile elevating work platforms, cranes, tipper lorries, lorry loaders,
skip wagons, 360 excavators, 180 backhoe loaders, crawler tractors, scrapers,
graders, loading shovels, trenchers, side booms, pavers, planers, chippers, road
rollers, locomotives, tankers and bowsers, trailers, hydraulic and mechanical
breakers etc.
II.
III.
203
M. All wood working machines shall be fitted with suitable guards and
devices such as top guard, riving knife, push stick, guards for drive belts
and chains, and emergency stop switch easily accessible by the operator
N. Every moving and dangerous part to be securely fenced, and regularly examined
to prevent contact with the worker
O. Examination/operation of machinery to be done only by trained/certified adult
worker wearing tight fitting clothing
P. Provision of suitable devices shall be available for cutting off power in
emergencies from running machinery
Q. All parts such as lifting machines, chains, ropes and lifting tackle shall be
properly maintained and examined every 12 months
R. The lifting machines, chains, ropes and lifting tackle shall not be loaded beyond
marked safe working load
S. Crane should not approach within 6m of the working place
T. Safe working speeds of revolving machinery should not to be exceeded
U. Floors, stairs and means of access shall be of sound construction, properly
maintained, free of obstructions, and provided with handrails
V. Fencing should be provided for working at heights
W. Pits, sumps, openings in floors, etc shall be securely covered / fenced
6.1.4d)Handlingofpetroleumproducts
I.
Comply with the provisions of these rules and the conditions of any
license relating thereto;
205
6.1.5e)Spillcontrolmanagement:
There are numerous chemicals like asphalt, coal tar, gasoline, diesel which are being used for
construction purpose and spill control management is one of the prime concern for the safety
of workers.
I.
The procedure and guidelines that the Contractor shall follow for spill management
process are:
a. Identification of potential chemical spill hazard
b. Risk assessment of spill via:
i. The nature of the spilled chemical (high/low hazards)
ii. The quantity of the spill (large or small)
iii. Location of the spill
II.
The Contractor shall ensure that measures to control or eliminate the potential risk follow
the principles of:
a. Elimination: complete removal of risk of exposure
b. Replacement the substance with a less hazardous one
c. Isolation through distance or enclosure
d. Adoption of new engineering methods for redesigning the work area and proper
maintenance
e. Administrative standard operating procedure, supervision, training, rotation and
signage
f.
III.
IV.
206
j.
Adequate ventilation
g. Gather any information possible, i.e. identify the material and quantity, gather
relevant MSDS and assess any immediate risks
6.2HouseKeeping
a. General: Many injuries result from poor housekeeping, improper storage of
materials, and cluttered work areas. To maintain a clean, hazard-free workplace, all
groups of management, supervisors, and workers must cooperate.
b. General provisions that can maintain adequate housekeeping and must be ensured by
the Contractor at the construction site as well as in the campsites are:
I.
II.
III.
IV.
Weekly washing of floor. Keep aisle clear for safe passage of people and
material
V.
Nails, pieces of wood with protruding nails, and other sharp objects should
not be left on floors and walkways; store them where they cannot be
stepped on
VI.
VII.
VIII.
IX.
X.
6.3Noise
a. General: Noise may be defined as unwanted sound. Noise is perhaps the most
widespread hazard in any construction environment and it is well known that
workplace noise can cause deafness and associated conditions such as tinnitus
(ringing in the ears). Despite this, workers are exposed to noise levels which can
cause permanent noise-induced hearing loss. For example, noise from:
9 Trucks
9 Machinery
9 Tools in a workshop
9 Batching plant and HMP site
9 Stone crusher unit
9 Compressor and Generators
Hearing protection is very necessary for construction workers who are directly
exposed to a high level noise for more than the permissible limit (more than 90
decibels for 8 hours), and where the noise cannot be reduced or isolated from the
worker.
b. Control Requirement: Contractor has to ensure that construction material is operated
and transported in such a manner as not to create unnecessary noise as outlined below:
I.
Perform work within the procedures outlined herein and comply with
applicable codes, regulations, and standards established by the Central and
State Government and their agencies.
II.
IV.
V.
6.4Illumination
The Contractor shall ensure that sufficient illumination is provided at all times for
maintaining safe working conditions at a site of a building or other construction work,
where building workers are required to work or pass and for passageways, stairways,
and landings. Such illumination should not be less than that provided in the relevant
national standards.
The Contractor shall make every effort to illuminate the work site as per the
Employers requirement
The Contractor shall conduct a monthly illumination monitoring by lux meter for all
the locations and the report shall be sent to the Employer within the 7th of the next
month and the same shall be reviewed during the monthly SHE committee meeting.
210
6.5DustAndEmissionControl
Dust can be a problem in almost all construction sites. Dust at work has been one of the
largest occupational killers of all time. It has shortened life and caused misery to hundreds of
thousands of people. Whenever materials are handled and broken down, dust is liable to be
produced, i.e. dust from the stone crusher units can damage the health of the worker through
occupational asthma.
Dusts
Effects
Fibrosis Dusts
Pneumoconiosis
Toxic Dusts
Poisoning
Irritant Dusts
Allergic Dust
Carcinogenic Dusts
Cancer
General Precautions:
The Contractor shall take all necessary precautions to minimise fugitive dust emissions from
operations involving excavation, grading, and clearing of land and disposal of waste. He shall
not allow emissions of fugitive dust from any transport, handling, construction or storage
activity to remain visible in the atmosphere beyond the property line of emission source for
any prolonged period of time without notification to the Employer
If after commencement of construction activity, the Employer believes that the Contractors
equipment or methods of working are causing unacceptable dust impacts then these shall be
inspected and remedial proposals shall be drawn up by the Contractor, submitted for review to
the Employer and implemented
In developing these remedial measures, the Contractor shall inspect and review all dust
sources that may be causing health effects
The Contractor shall establish and maintain records of routine maintenance program for water
sprinkling method in the dust generated areas and shall keep records available for inspection
by the Employer
211
The Contractor shall cover loads of dust generating materials like debris and soil being
transported from construction sites. All trucks carrying loose material should be covered and
loaded with sufficient free-board to avoid spills through the tail board or side boards
The temporary dumping areas shall be maintained by the Contractor at all times until the
excavate is re-utilised for backfilling or as directed by the Employer. Dust control activities
shall continue even during any work stoppage
The Contractor shall place material in a manner that will minimise dust production. Material
storage shall be minimised each day and wetted to control dust production. During dry
weather, dust control methods must be used daily, especially on windy, dry days, to prevent
any dust from blowing across the site perimeter
The Contractor shall water down construction sites as required to suppress dust, during
handling of excavation soil or debris or during demolition. The Contractor will make water
sprinklers, water supply, and water delivering equipment available at any time that it is
required for dust control use. Dust screens will be used as feasible and when additional dust
control measures are needed, especially where the work is near sensitive receptors
The Contractor shall design and implement his blasting techniques so as to minimise dust,
noise, vibration generation, and prevention of fly rock
The Contractor shall submit to the Employer an Air Monitoring and Control Plan (AMCP)
under contract specific Site Environmental Plan to guide construction activity insofar as it
relates to monitoring, controlling, and mitigating air pollution
6.6 PersonalProtectiveEquipmentAndOtherSafetyAppliances
I.
General:
Personal Protective Equipment (PPE) is the third line of defence for protection of the
employees health and safety. The first line of defence is to eliminate accident-causing
situations at the work place by effective process changes, and the second is to reduce it
through engineering measures. PPE does not and cannot eliminate hazards at work. As a
barrier between the hazard and the worker, PPE can help to eliminate an injury or reduce
its severity, but it also hampers the work of the worker. PPE should be resorted to only if
absolute removal of the hazard or its reduction in the work environment is impossible or
212
impracticable. Even where technical/engineering control, safe systems of work, and other
techniques have been applied, it is possible that some hazards might remain. These
hazards may lead to injuries to the:
A. Respiratory system due to contaminated air
B. Head and feet, for example, from falling materials
C. Eyes, for example, from flying particles of stone works
D. Skin, for example, from contact with corrosive materials
E. Body, for example, from extremes of heat or cold
PPE includes clothing and other accessories designed to create a barrier between the user and
workplace hazards. It should be used in conjunction with engineering work practices and/or
administrative controls to provide maximum employee safety and health in the workplace.
All Contractors are responsible for providing training and ensuring the proper use of required
personal protective equipment. The principal requirements of PPEs are:
A. To safeguard the workers from identified hazards to which he/she is
exposed
B. To afford reasonable comfort while working under adverse circumstances
C. To permit essential movement of limbs required for efficient job
performance
D. To be amenable to easy cleaning and maintenance
II.
6.7WorkingAtHeight
I.
General: Working at a height is the largest single cause of serous accidents in the
construction environment. Work at height is work in any place, including a place at,
above, or below ground level, where persons can be injured if they fall from that
place. Access and egress (getting in and out) from a place of work can also be work
at height.
Examples of work activities that are classified as working at a height include:
A. working on a flat roof
B. erecting false work and formwork
C. working from a ladder
D. working at ground level adjacent to an open excavation, and
E. working near or adjacent to fragile materials
II.
Use of Scaffolds
All scaffolds should be erected and dismantled by workmen who are thoroughly experienced
in the erection and dismantling of scaffolding
All scaffolds should be inspected by a competent person at least every three days after
erection and the results of inspections recorded and the records shall be kept available for
checking by the Employers representative
214
Tags shall be fitted to all scaffolds to show whether they are safe for use or not. All Safe for
Use tags shall be signed by a senior site engineer from the Contractor
All scaffolds shall be constructed of sound materials free from patent defect
a) The scaffold shall be constructed for the correct use (Light or Heavy Duty)
b) Securely fixed to existing structures or adequately buttressed
c) The use of barrels, boxes, loose tiles or other unsuitable material shall not be used
as supports for working platforms
d) All working platforms shall be fully boarded
e) All working platforms shall have guard rails at one meter height and shall also
have an intermediate rail at half height
f) All working platforms shall be provided with toe boards
g) All working platforms shall be kept free of unnecessary obstruction or rubbish
h) Secure ladder access shall be provided
Use of Ladders
All ladders shall be of sound construction and shall be free from patent defects
Ladders should be checked weekly and defective ladders shall be promptly and properly
repaired or replaced
Ladders shall not be used as working platforms but may be used for work of short duration of
up to thirty minutes
Metal ladders shall not be used near or adjacent to overhead power lines unless they have
been certified dead under a permit to work system
Ladders shall:
(a) Be secured at the top or footed at the bottom to prevent slippage
(b) Not be used if any rung is missing
(c) Not be used for any other purpose than to provide access
(d) Be set at an angle of seventy five degrees unless designed for vertical access
(e) All vertical ladders shall be fitted with hoops to prevent falls
Fencing for work at a height
215
When any person has to work at a height from where he/she is likely to fall, provision
shall be made, so far as is reasonably practicable, by fencing or otherwise, to ensure
the safety of the person so working
216
Unit7
ElectricalandMechanicalSafety
7.1ElectricalandMechanicalSafety
7.1.1EquipmentFitnessCertificate
7.1.2DriversandOperators
7.1.3VehicleSpeed
7.1.4HandandPortablePowerTool
7.1.4.1General
1.
The contractor is wholly responsible for the safe condition of tools and equipment
used by his employees and that of his sub-contractors.
2. Use of short / damaged hand tools shall be avoided and the contractor shall ensure all
his hand tools used at his worksite are safe to work with or stored and shall also train
his employees (including his sub-contractors) for proper use thereby.
3. All hand tools and power tools shall be duly inspected before use for safe operation.
4.
All hand tools and power tools shall have sufficient grip and the design specification
on par with national/international standards on anthropometrics.
7.1.4.2Handtools
1. Hand tools shall include saws, chisels, axes and hatches, hammers, hand
planes,
217
7.1.4.3PortablePowertools
1. Power tools include drills, planes, routers, saws, jackhammers, grinders,
sprayers, chipping hammers, air nozzles and drills.
2. The contractor shall ensure that
i) Electric tools are properly grounded or / and double insulated.
ii) GFCIs/ RCCBs shall be used with all portable electric tool operated
especially outdoors or in wet condition.
iii) Before making any adjustments or changing attachments, his workers
shall disconnect the tool from the power source.
218
All power tools / hand tools shall have guards at their nip points.
xv) Low profile safety chain shall be used in case of wood working machines
and the saw shall run at high rpm when cutting and also correct chain
tension shall be ensured to avoid kickback.
xvi) Leather aprons and gloves shall be used as an additional personal
protection auxiliary to withstand kickback.
219
xvii) Push sticks shall be provided and properly used to hold the job down
on the table while the heels moves the stock forward and thus preventing
kickbacks.
xviii) Air pressure is set at a suitable level for air actuated tool or equipment
being used. Before changing or adjusting pneumatic tools, air pressure
shall be turned off.
xix) Only trained employees shall use explosive actuated tools and the tool
shall also be unloaded when not in use.
xx) Usage of such explosive actuated tools shall be avoided in case of places
where explosive/flammable vapours or gases may be present.
xxi) Explosive actuated tools and their explosives shall be stored separately
and be taken out and loaded only before the time of immediate use.
xxii) Misfired cartridges of explosive actuated tools must be placed in a
container of water and be removed safely from the project.
xxiii) No worker shall point any power operated / hand tool to any other
person especially during loading / unloading.
7.1.5SafetyinGasCuttingandWelding
1 Gas cylinders in use shall be kept upright on a custom-built stand or trolley fitted
with a bracket to accommodate the hoses and equipment or otherwise secured. The
metal cap shall be kept in place to protect the valve when the cylinder is not
connected for use.
2 Hose clamp or clip shall be used to connect hoses firmly in both sides of cylinders
and torches.
3 All gas cylinders shall be fixed with pressure regulator and dial gauges
4 Non-return valve and Flashback arrester shall be fixed at both end of cylinder and
torch.
5 Domestic LPG cylinders shall not be used for Gas welding and Cutting purpose.
220
6 DCP or CO2 type Fire Extinguisher not less than 5 kg shall be fixed at or near to
welding process zone in an easily accessible location. Fire Extinguisher should
confirm to IS 2190: 1992.
7 Use firewatchers if there is a possibility of ignition unobserved by the operator (e.g.
on the other side of bulkheads).
8 Oxygen cylinders and flammable gas cylinders shall be stored separately, at least
6.6 meters (20 feet) apart or separated by a fire proof, 1.6 meters (5 feet) high
partition. Flammable substances shall not be stored within 50 feet of cylinder storage
areas.
9 Transformer used for electrical arc welding shall be fixed with Ammeter and
Voltmeter and also fixed with separate main power switch.
10 Welding grounds and returns should be securely attached to the work by cable
lugs, by clamps in the case of stranded conductors, or by bolts for strip conductors.
The ground cable will not be attached to equipment or existing installations or
apparatus.
11 Use a low voltage open circuit relay device if welding with alternating current in
constricted or damp places.
12 Take precautions against the risk of increased fume hazards when welding with
chrome containing fluxed consumables or high current metal inert gas (MIG) or
tungsten inert gas (TIG) processes.
13 Avoid being in contact with water or wet floors when welding. Use duckboards or
rubber protection.
14 All electrical installations shall meet the IS: 5571: 1997 and NFPA 70 for gas
cylinder storage area and other hazardous areas.
15 The current for Electric arc welding shall not exceed 300 A on a hand welding
operation.
7.1.6SafetyinElectricityGeneration,Distribution,anduse
221
222
224
8.4 Where low voltage cables are to be used, reference shall be made to BS 7375. The
following standards shall also be referred to particularly for under ground cables BS
6346 and BS 6708
8.5 Cables buried directly in the ground shall be of a type incorporating armour or metal
sheath or both. Such cables shall be marked by cable covers or a suitable marking tape
and be buried at a sufficient depth to avoid their being damaged by any disturbance of
the ground. Cable routes shall be marked on the plans kept in the site electrical
register.
8.6 Cabling passing under the walk way and across way for transport and mobile
equipment shall be laid in ducts at a minimum depth of 0.6 meters.
8.7 Cables that need to cross open areas, or where span of 3m or more are involved, a
catenary wire on poles or other supports shall be provided for convenient means of
suspension. Minimum height shall be 6 m above ground.
8.8 Cables carrying a voltage to earth in excess of 65V other than supply for welding
process shall have metal armour or sheath, which has been effectively earthed and
monitored by the contractor. In case of flexible and trailing cables such earthed metal
sheath and/or armour should be in addition to the earth core in the cable and shall not
be used as the protective conductor.
8.9 Armoured cables having an over-sheath of polyvinyl chloride (PVC) or an oil resisting
and flame retardant compound shall be used whenever there is a risk of mechanical
damage occurring
9 Plugs, socket-outlets and couplers:
9.1 The contractor shall ensure plugs, socket-outlets, and couplers available in the
construction site as splash proof type. The minimum degree of Ingress
Protection should be of IP44 in accordance with BS EN 60529.
9.2 Only plugs and fittings of the weatherproof type shall be used and they should be colour
coded in accordance with the Internationally recognised standards for example as
225
detailed as follows:
(a) 110 volts : Yellow.
(b) 240 volts : Blue.
(c) 415 volts : Red.
10 Connections
10.1 Every joint and connection in a system shall be mechanically and electrically
suitable for use to prevent danger. Proper cable connectors as per
national/international standards shall only be used to connect cables.
10.2 No loose connections or tapped joints shall be allowed any where in the work
site, office area, stores and other areas. Penalty as per relevant clause shall be
put in case of observation of any tapped joints.
11 Portable and hand-held equipments:
11.1 The contractor shall ensure the use of double insulated or all-insulated portable
electrical hand equipment may be used without earthing (i.e. two core cables), but they
shall still be used only on 110V because of the risk of damage to trailing leads.
12 Other equipments:
12.1 All equipment shall have the provision for major switch/cut-off switch in the
equipment
itself.
12.2 All non-current carrying metal parts of electrical equipment shall be earthed through
insulated cable
12.3 Isolate exposed high-voltage (over 415 Volts) equipment, such as transformer banks,
open switches, and similar equipment with exposed energized parts and prevent
unauthorised access.
226
12.4 Approved perimeter markings shall be used to isolate restricted areas from designated
work areas and entryways and shall be erected before work begins and maintained for
entire duration of work. Approved perimeter marking shall be installed with either red
barrier tape printed with the words "DANGERHIGH VOLTAGE" or a barrier of yellow
or orange synthetic rope, approximately 1 to 1.5 meter above the floor or work surface.
7.1.8CompressedAir
227
7.2ConstructionPlantsSafety
7.2.1Fitnesscertificate
7.2.2Operators
7.2.3MaintenanceandWorkPermitSystem
1 The Contractor shall develop a Work Permit system, which is a formal written system
used to control certain types of work that are potentially hazardous. A work permit is a
document, which specifies the work to be done, and the precautions to be taken. Work
Permits form an essential part of safe systems of work for many construction activities. They
allow work to start only after safe procedures have been defined and they provide a clear
record that all foreseeable hazards have been considered. Permits to Work are usually
required in high-risk areas as identified by the Risk Assessments.
2 A permit is needed when construction work can only be carried out if normal
safeguards are dropped or when new hazards are introduced by the work. Examples of highrisk activities include but are not limited to:
i) Entry into confined spaces
ii) Work in close proximity to overhead power lines and telecommunication cables.
iii) Hot work.
iv) To digwhere underground services may be located.
v) Work with heavy moving machinery.
vi) Working on electrical equipment
vii) Work with radioactive isotopes.
viii) Heavy lifting operations and lifting operations closer to live power line
7.3FireSafety
1 The contractor shall ensure that construction site is provided with fire extinguishing
equipment sufficient to extinguish any probable fire at construction site. An adequate water
supply is provided at ample pressure as per national standard.
2 Recharging of fire extinguishers and their proper maintenance should be ensured and
as a minimum should meet Indian National Standards
4 The contractor shall also give consideration to the provision of adequate fire fighting
arrangements within the underground and tunneling operations including the provision of
Fire Service compatible hose connections and emergency lighting
5 As per the DBOCW Rules 2002, Rule 63(a)(vii), all lifting appliances driver cabin
should be provided with a suitable portable fire extinguisher.
6 Combustible scrap and other construction debris should be disposed off site on a
regular basis. If scrap is to be burnt on site, the burning site should be specified and located at
a distance no less than 12 meters from any construction work or any other combustible
material.
8 Emergency plans and Fire Evacuation plans shall be prepared and issued . Mock drills
should be held on a regular basis to ensure the effectiveness of the arrangements and as a part
of the programme, the Telephone Number of the local fire brigade should be prominently
displayed near each telephone on site.
230