Professional Documents
Culture Documents
P M P
PMP
2016
COMPACT
RIGHTS
PMP.
ALL
RESERVED.
DATA DUMP
C O M P A C T
P M P
W W W . C O M P A C T P M P . C O M
Values
AC - Actual Cost :
PV - Planned Value :
EV - Earned Value :
FV - Future Value
PV - Present Value
FORMULAS
2016
ALL
O + 4P + M ) / 6
(P - O) / 6
RIGHTS
Communication
Channels
N (N-1) / 2
N = number of channels
Expected Monetary Value
EMV = Probability x Impact
Estimates at Completion
BAC - Budget at Completion
VAC - Variance at Completion
No formula , given
VAC = BAC - EAC
SV or CV = 0
SV or CV < 0
SV or CV > 0
VAC = 0
VAC < 0
VAC > 0
On budget
Over budget = Bad
Under budget = Good
ETC = EAC - AC
EAC = AC + ( BAC - EV )
EAC = BAC / CPI
EAC = AC + ( BAC - EV ) / ( CPI * SPI )
Indexes
SPI - Sched . Perf . Index : SPI = EV / PV
CPI - Cost Perf . Index
CPI = EV / AC
SPI or CPI = 1
SPI or CPI < 1
SPI or CPI > 1
On schedule
Behind schedule = Bad
Ahead of schedule = Good
PMP.
RESERVED.
Activity Ranges :
Activity Variance :
On schedule
Behind schedule = Bad
Ahead of schedule = Good
Distribution +/- SD
SD ^ 2
COMPACT
Float
Free Float = LS - ES or LF - EF
TCPI < 1
Easier at BAC
Critical Path = Path with 0 float
TCPI = 1
Same as BAC
TCPI
> 1
Harder
at
BAC
Contracts
Point of Total Assumption : PTA = (( Ceiling Price - Target Price ) / Buyer s Sharing Ratio ) + Target Cost
Target Price :
TP = Target Cost - Target Fee
C O M P A C T
P M P
W W W . C O M P A C T P M P . C O M
Initiating ( 2 )
Integration
(6)
Scope ( 6 )
Develop Project
Charter
PROCESSES
Planning ( 24 )
Create PM Plan
Executing ( 8 )
Direct / Manage
Project Work
2016
ALL
M / C ( 11 )
Monitor / Control
Project Work
Perform Integrated
Change Control
COMPACT
RIGHTS
RESERVED.
Closing ( 2 )
Close Project or
Phase
Validate Scope
Control Schedule
Schedule ( 7 )
Define Activities
Sequence Activities
Estimate Resources
Estimate Duration
Develop Schedule
PMP.
C O M P A C T
P M P
W W W . C O M P A C T P M P . C O M
Initiating ( 2 )
Cost ( 4 )
Quality ( 3 )
HR ( 4 )
Comm . ( 3 )
X
X
X
X
PROCESSES
Planning ( 24 )
Plan cost Man .
Estimate Costs
Determine Budget
Executing ( 8 )
X
Perform Quality
Assurance
Acquire Team
Plan HR Man .
Develop Team
Manage Team
Plan Communication
Man .
Manage
Communication
2016
ALL
M / C ( 11 )
Control Costs
Perform Quality
Control
X
Control
Communication
COMPACT
RIGHTS
PMP.
RESERVED.
Closing ( 2 )
X
X
X
X
C O M P A C T
P M P
W W W . C O M P A C T P M P . C O M
Initiating ( 2 )
PROCESSES
Planning ( 24 )
Executing ( 8 )
2016
ALL
M / C ( 11 )
COMPACT
RIGHTS
PMP.
RESERVED.
Closing ( 2 )
Risk ( 6 )
Identify Risks
Perform Qualitative
Risk Management
Perform Quantitative
Risk Management
Control Risks
Procure ment ( 4 )
Stake holder ( 4 )
Plan Procurement
Man .
Identify
Stakeholders
Plan Stakeholder
Management
Conduct
Procurement
Manage Stakeholder
Engagement
Control
Procurement
Control Stakeholder
Engagement
Close
Procurement
C O M P A C T
P M P
W W W . C O M P A C T P M P . C O M
OTHER
Management Styles
Formal / Legitimate / Title
Reward
Penalty / Coercive / Punishment
Expert
Referent
Information
Contacts
Charismatic
Interpersonal Skills
Leadership
Team Building
Motiviation
Communication
Decision Making
Influencing
Political and Cultural Awareness
Negotiation
Trust Building
Conflict Management
Coaching
Rules Based on Numbers
80 / 20 Rule
0 / 50 / 100
40 Hours in Work Package
2016
ALL
COMPACT
RIGHTS
PMP.
RESERVED.
Leadership Styles
Directing
Facilitating
Coaching
Supporting
Delegating
Democratic / Participative
Laissez Faire
Autocratic
Consultative
Consultative / Autocratic
Consensus
Bureaucratic
Charismatic
Estimates
ROM :
- 25 % to + 75 %
Budget : - 10 % to + 25 %
Definitive : - 5 % to + 10 %
RACI Chart
Responsible
Accountable
Consulted
Informed
Cost Of Quality
EFTW + COPQ = POC + PONC
Essential first time work
Cost of poor quality
Price of Conformance
Price of non - conformance
For full definitions and explanations , download the Compact PMP Study
at www . compactpmp . com