3. Installation
2. Storage
The battery must be stored in a dry indoor
location, on open, well ventilated shelves
away from direct sunlight between 0C
and +30C (+32F and 86F).
Uptimax batteries are supplied filled with
electrolyte and charged. They can be
stored in this condition for maximum
24months from date of shipment in
accordance with the recommendations set
forth in this I&O.
Storage of a filled battery at temperatures
above +30C (+86F) can result in
permanent change and loss of product
performance, depending on the duration of
the storage above the maximum
recommended temperature.
3.1. Location
Install the battery in a dry and clean room.
Avoid direct sunlight and heat.
The battery will give the best performance
and maximum service life when the
ambient temperature is between +10C to
+30C (+50F to +86F)
3.2. Mounting
Interconnect the cells with the appropriate
polarity. Connections between the battery
and the load shall be made with nickel
plated cable lugs. Tightening torque for the
terminals must be:
M 6
4. Commissioning
Cells
stored up to 6 months:
A commissioning charge is normally not
required and the cells are ready for
immediate use. However, the product's
full performance will only be achieveable
after six months of charging in service
(see section 7.3 charge acceptance of
Technical manual).
If the published performance is required
immediately, please refer to Section 4 and
the procedure dedicated to cells stored
more than 6 months and up to 2years.
Cells
stored more than 6 months
and up to 2 years:
A commissioning charge is necessary:
C
ommissioning at ambient temperature
between + 10C to
+ 30C (+ 50F to + 86F)
-C
onstant current charge:
10 h at 0.2 C5 A recommended
(see Table A).
Notice: At the end of charge, the cell
voltage will reach about 1.80 V, thus
the charger shall be able to supply such
a voltage.
When the charger maximum voltage
setting is too low to supply constant
current charging, divide the battery into
two parts to be charged individually at
constant current.
-C
onstant potential charge:
1.55 V/cell for a minimum of 24 h
with current limit of 0.2 C5 A (see the
current in Table A).
If this voltage level is not available, then
charging may be carried out at 1.50
V/cell for 36 hours
C
ommissioning at ambient temperature
above + 30C (+ 86F)
-O
nly constant current charge:
10 h at 0.2 C5 recommended.
The electrolyte temperature is to be
monitored during charge. If the
temperature exceeds + 45C (+113F)
during charging, then it must be stopped
to reduce the temperature. The charging
can be resumed when electrolyte
temperature drops below
+ 40C (+ 104F).
Capacity
C5Ah
(Ah)
Charging
current
0.2 C5 A
(A)
Cell
connection
bolt
per pole
UP1 L 15
15
3.0
M6
UP1 L 30
30
6.0
M6
float level:
1.42 0.01 V/cell
UP1 L 47
47
9.4
UP1 L 62
62
h
igh rate (boost) level:
1.45 0.01 V/cell
UP1 L 75
75
Cell
type
UP1 L 95
Capacity
C5Ah
(Ah)
Charging
current
0.2 C5 A
(A)
Cell
connection
bolt
per pole
UP1 M 8
1.6
M6
UP1 M 16
16
3.2
M6
M6
UP1 M 24
24
4.8
M6
12.4
M6
UP1 M 32
32
6.4
M6
15.0
2xM6
UP1 M 40
40
8.0
M6
UP1 M 48
48
9.6
M6
UP1 M 65
65
13.0
2xM6
95
19.0
M8
UP1 L 110
110
22.0
2xM6
Cell
type
UP1 L 140
140
28.0
M 10
UP1 M 75
75
15.0
M8
UP1 L 185
185
27.0
M 10
UP1 M 100
100
20.0
M8
UP1 L 235
235
47.0
M 10
UP1 M 125
125
25.0
M 10
UP1 L 280
280
56.0
M 10
UP1 M 150
150
30.0
M 10
UP1 M 170
170
34.0
M 10
6. Preventive Maintenance
UP1 L 325
325
65.0
2 x M 10
UP1 M 195
195
39.0
M 10
UP1 L 375
375
75.0
2 x M 10
UP1 M 220
220
44.0
M 10
UP1 L 420
420
84.0
2 x M 10
UP1 L 470
470
94.0
2 x M 10
UP1 M 245
245
49.0
2 x M 10
UP1 L 515
515
103.0
2 x M 10
UP1 M 270
270
54.0
2 x M 10
UP1 L 560
560
112.0
2 x M 10
UP1 M 295
295
59.0
2 x M 10
UP1 M 320
320
64.0
2 x M 10
Saft
Industrial Battery Group
UP1 L 610
610
122.0
3 x M 10
UP1 M 345
345
69.0
2 x M 10
UP1 L 650
650
130.0
3 x M 10
UP1 M 370
370
74.0
2 x M 10
UP1 L 700
700
140.0
3 x M 10
UP1 M 395
395
79.0
2 x M 10
UP1 L 750
750
150.0
3 x M 10
UP1 M 420
420
84.0
2 x M 10
UP1 L 800
800
160.0
3 x M 10
UP1 M 445
445
89.0
2 x M 10
UP1 L 840
840
168.0
3 x M 10
UP1 L 890
890
178.0
4 x M 10
UP1 M 490
490
98.0
3 x M 10
UP1 L 940
940
188.0
4 x M 10
UP1 M 540
540
108.0
3 x M 10
UP1 L 980
980
196.0
4 x M 10
UP1 M 590
590
118.0
3 x M 10
UP1 L 1030
1030
206.0
4 x M 10
UP1 M 640
640
128.0
3 x M 10
UP1 L 1120
1120
224.0
4 x M 10
UP1 M 690
690
138.0
4 x M 10
UP1 M 740
740
148.0
4 x M 10
4 x M 10
UP1 L 1220
1220
244.0
5 x M 10
UP1 M 785
785
157.0
UP1 L 1300
1300
260.0
5 x M 10
UP1 M 835
835
167.0
4 x M 10
UP1 L 1400
1400
280.0
5 x M 10
UP1 M 885
885
177.0
4 x M 10
UP1 L 1500
1500
300.0
6 x M 10
UP1 M 935
935
187.0
5 x M 10
UP1 L 1600
1600
320.0
6 x M 10
UP1 M 985
985
197.0
5 x M 10
UP1 L 1700
1700
340.0
6 x M 10
206.0
5 x M 10
UP1 M 1130
1130
226.0
6 x M 10
UP1 M 1230
1230
246.0
6 x M 10
266.0
6 x M 10
www.saftbatteries.com
7. Environment
To protect the environment all used
batteries must be recycled.
Contact your local Saft representative for
further information.