FINNISHING WORKS

----------oOo---------I.

BRICK WALL

II. INTERNAL PLASTERING ON BRICK WALL


III. WATERPROOF
IV. FLOOR CREEDING
V. CEILING INSTALLATION
VI. PAINTING
VII. CERAMIC TILES FOR WALL AND FLOOR
VIII.DOOR, WOOD FURNITURE , SANITARY INSTALLATION
IX. DOORS, WINDOWS INSTALLATION
X. ROOF
XI. EXTERNAL PLASTERING ON BRICK WALL
XII. EXTERNAL WALL COATING
XIII.BASEMENT FINISHING

THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

RESPONBILITY OF SUPERVISOR ON SITE

SAFETY

HOUSE
KEEPING &
WORKING
ENVIRONMENT

SCHEDULE

SITE
SUPERVISOR

QUANTITY

QUALITY

Note:
Photos using on this guide book is the order of the parts and the
relationship between them.

THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

1. SITE PREPARATION

Cleaning the construction site before starting the


masonry works.

Setting up the gathering material area and mixing place


near hoist to provide for the mason easily.
The best way is mixing area at ground floor then
transport to masonry place.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

Sand should be berried to prevent scattering.


Sand should be sieved and free from all deleterious matter.
Water contained in the barrel.
Concrete chute should be lined by nylon canvas.
Mixing mortars place should be cleaned.

Bricks should be arranged blocks clean-limbed beside


the working place from 1.5 to 2m.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

Common mistakes On Site Floor:

Sand do not barrier and scattered on floor. Concrete chute did


not line the nylon canvas. Water barrel is leaked. Bricks, sand
is messy and clutter on sidewalk.

Scaffolds, formworks, debris are scattered and clutter


everywhere.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

2. Floor Survey :

Determine the walls position by using the snapping line


follow the approved drawing.

Dual Column
position marking

Door position
marking

Mortar layer

Determine the finished wall thickness include the mortar


layers.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

Door Position

BRICK WALL

Dual Column
Position

One diagonal show the Dual Column Position Will be poured


concrete.
Two diagonal shows Doors, Wall Opening positions

Monitor the survey task, snapping line the Wall, Door, Waiting
hole, Wall Opening before execution.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

3. Hollow Brick Masonry.

Lay the first course of stretcher bricks in the mortar.

solid-brick header

Plumb

Using the Plumb line to ensure the wall is coming up nice and
straight
Lay the solid bricks header to link walls at the corner

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

Before construct brick


wall have to install the
starter steel bars drill
or steel anchors to
connect masonry
walls with concrete
wall

Rebar must be installed


to tie masonry walls to
concrete stiffener
columns

C.
9
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

BRICK WALL

100mm thick Wall , with reinforced mesh being inserted at


every 4-5 course. This is a very strong bond when the wall is
1 brick thick.

200mm thick wall with header courses being inserted


at every 4 -5 course.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

10

BRICK WALL

In constructing put down the tarpaulin at bottom of the walls


to catch the mortar dropping down.

Technical requirements:
Parity - equality; upright- straightness; surfaces- eveness;
angles- square; unlapped mortar joints; be able to
consistent blocks.
All mortar joints of the construct blocks must be full with
mortar, equable and consistent.
Need to clean the wall surfaces immediately, if not, mortar
will be harden causing difficulty of the latter plastering and
decoration.
Brick block must be moistured (watered) at least 7 days.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

11

BRICK WALL

Typical detail between the wall corner with the


concrete stiffener column.

Concrete stiffener column after pouring.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

12

BRICK WALL

Concrete lintel must extend 20cm past the opening on each


side. After 24 hours adjoining positions of wall and beam are
built an oblique angle 450 with solid bricks, as well as holes
are pointed to avoid cracks at adjoining edges of walls and
beam bottom.

Construct stair steps follow the marked ink on the wall


exactly.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

13

BRICK WALL

Walls Inspection follow approved drawing.

All walls have to meet the quality requirements and Floor


need to clean, dry.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

14

II

PLASTERING

II. INTERNAL PLASTERING ON BRICK WALL


1.Level Marking:

Base on grid lines, wall location, rendering thickness then


worker will make the level marking at the wall bottom.

From level marking at wall bottom use Plumb line


to install others above. When combined with up to a
dozen other markers on any given wall, they provide
fairly accurate level guides during the plastering
process..
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

15

PLASTERING

Level Marking.

Level Markers are distributed in row on the wall.


Level Markers surfaces have to smooth and their size is
5cmx5cm.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

16

II

PLASTERING

2. Install M&E System

Fix the electrical outlet, switch boxes, phone socket, TV


cable, Internet socket on the wall at the designed height.
Conduits have to straight, surface of socket, switch boxes is
even surface of plastering
Water supply pipe

Drainage pipe

Water supply pipe is fixed on the wall at designed level.


The pipe have to straight run, 90 degree elbows protrude
even the plastering layer.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

17

II

PLASTERING

M&E system fixed on ceiling.

M&E system installed on toilets ceiling.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

18

II

PLASTERING

After fixing conduit, water pipe system on the wall have to


seal by mortar.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

19

II

PLASTERING

Common Mistakes When Install Sockets, Switch Boxes And Conduits:

Socket, switches installed indenting or protruding with wall


surface have to cut out and fix when installing cover.

Right technique of sockets, Switch boxes installation is


they have to be flush to the finished surface.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

20

II

PLASTERING

Repair the wrong technical installation of socket, switch


boxes by mortar.

If mortar covering is cracked, have to cut out to do it


again.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

21

II

PLASTERING

3. Iron mesh

Use iron mesh to


connect the brick into
concrete column, wall,
beam.

Plastering cracks on
the brick wall, use
iron mesh to cover it.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

22

II

PLASTERING

4. Plastering:

Covering the foot of the walls before plastering by


plastic sheet. Plastering from upside down.

Finished plastering a wall one time to avoid the bordered


between two mortar layer.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

23

II

PLASTERING

Used iron ruler to check the corner of the walls


after plastering to ensure the right angels.

Use Nivo to check the vertically of the walls.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

24

II

PLASTERING

The surface of walls, ceilings, floors must be cleaned after finish


the plastering work.
Evaluative criteria for the quality of the screeding wall:

Ensure the sizes of the walls as the design drawings


(length, width, height, thinkness). And the sizes of the
doors, windows, open technical hole.
The mortar must clinging tight on the surface of
masonries, concrete walls, without any peelings,
blisterings.
The grade of mortar must follow the design
requirements.
The surface of plastering must be flat. The permitted
deviation from 1-1,5mm.
The edges, ledges, must be sharp, plat, vertically,
horizontally. The corners is square, right angels.
The bottom of the wall must be straight, flat. And the
floor is clean without any dropping mortar. The bottom,
the edge of the wall relating to the quality of tiling,
paving works need to check carefully.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

25

III

WATERPROOF

These locations usually need waterproofing such as:


terrace, bathroom, balcony, loggia, roof, basement walls.
Waterproofing was carried out in sequence:
Applying waterproof membrane - water immersion test protection mortar screeding.

Applying waterproof membrane at loggia floor.

Water immersion test.


Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

26

III

WATERPROOF

Screeding of the protect mortar layer on the water


proofing membrane at balconies

Screeding of the protect mortar layer on the waterproofing


membrane at WC
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

27

IV SCREEDING
IV. FLOOR SCREEDING WORKS
Before the screeding work, restore the +1m level at the
plastered wall

Wall marked with +1m high level

Check the screeding level from standard level +1m

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

28

IV SCREEDING

Making screeding landmark at middle of floor from the


landmark at the wall

Screeding landmark
The surface of the screeding landmark is the surface of floor
after screeding.
The surface of the screeding landmark should not too big,
will affect the quality of screeding surface
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

29

IV SCREEDING

Before screed, use the plastic sheet to cover the wall,


watering entire the floor, after that, use wet mortar for
screeding.

When the mortar dry, restore the standard


coordinate axis in preparation for the tiling work

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

30

IV SCREEDING
Common mistakes when do screeding work:
-Floor peeling, blistering due to dry mortar, do not watering
the concrete floor before screeding.
-Pitting and cracking at the surface of floor cause by dirt sand
and improperly graded mortar.
-The surface of floor is not flat cause by false screeding
landmark.

Pitting at surface cause by dirt sand

Wall with stains cause by do not cover before screeding


Evaluative criteria for the quality of the screeding floor:
-Flat screeding surface
-Properly design level, ensure the slope as design.
-Ensure the mortar thickness, and grade mortar as
technical requirement.
-Ensure the rigidity of mortar layer, without any blistering.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

31

CEILING

V. CEILING WORK
Gypsum work will be follow after plastering work with M&E
system at the upper floor already install and check the activities
quality. Ceiling of WC will be install after tiling wall finishes.

Leveling the high of the ceiling from +1.0m standard


level, fixed the L aluminum around the wall

Mark the location of the hanging ceiling system


Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

32

CEILING

Check the flat of the frame according to the horizontal,


vertical, diagonal direction by tension string.

Ceiling frame already finish, follow with gypsum installation

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

33

CEILING

Fixed the gypsum panel with frame system by the screws


Check the flat of the ceiling according to the horizontal,
vertical, diagonal direction by tension string.

The gypsum ceiling after fixed with


frame system

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

34

CEILING

Flat the screw hole.


Apply the mesh glue at the gypsum panel
connection.

Use Nivo to check the plat of ceiling.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

35

CEILING

The ceiling after apply anti-crack mesh.


Evaluative criteria for the quality
of the gypsum ceiling:

.Properly level as design.


.Plat ceiling surface.
.Hanging ceiling must be vertically, do not oblique, with the
same tensions.
.The main and sub bars should be evenly spaced.
Constructing the frame based on the design due to avoid the
position of lamps, wild throat. etc .
.The edges, corners must align, right angles. The surface of
the gypsum board must be flat, shadowline slot must be
straightness.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

36

VI PAINTING
VI. PAINTING WORK.
1. Putty.

Inspecting the quality of plastering, the moisture of the mortar


before do the painting work.

When the mortar surface dry, do the putty work.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

37

VI PAINTING

Applying putty on the wall by the worker.

Applying the second layer of putty after


The fist layer is dry. Smooth the surface of putty
when the second layer is dry by sandpaper.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

38

VI PAINTING

Illumination by lamps, use sandpaper makes the surface of wall,


ceiling become plat, smooth.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

39

VI PAINTING
2.Painting:

Cleaning the wall surface, apply the first coasting layer.

When the coasting layer is dry, apply the finish painting layer.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

40

VI PAINTING
Common mistakes:

Carelessly painting work.

The shadow line is not straight, choppy, eneven.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

41

VI PAINTING

Painting does not even cover, with blur on the walls, ceiling.
Evaluative criteria for the quality
of the putty, painting:

The surface of putty must be smooth, clean, without any


peeling, sloughing.
The thickness layer of putty does not over 1mm, tight
clinging on the walls. permitted deviation from 1-1,5mm.
The edges, ledges, must be sharp, plat, vertically,
horizontally. The corners is square, right angels.
The surface must be the same color, without any blur on
surface.
The floor must be clean, dont have any putty and painting
on surface.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

42

VII TILING
VII. TILING WORK.
1.Tiling inside the room.

Tiling the first row according to the shopdrawing.

Correction the plat of surface, use gauge to fix the joint.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

43

VII TILING

Border tiling by the worker.

Protect the tiling surface by plastic sheet.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

44

VII TILING

Carpeted floor to protect the marble.


Common mistake:

Joint is uneven because gauge is not be


used.
The tiling surface is not flat.
The tiling is blistering.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

45

VII TILING

The edges between ceramic bricks is not align.

The edges of ceramic brick is broken, big join.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

46

VII TILING

Used broken ceramic brick for tiling.


Evaluative criteria for the quality tiling work:

Tight clinging into the floor, when knock do not hear


blistering sound.
The finish surface is plat, right at design level.
Join is straight, steadily, with width follow the
design.
The ceramics are the same color.
Border ceramic tiling are straight, with the same join
width.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

47

VII TILING
2. WC tiling.
The WC tiling will follow after M&E system, waterproofing,
plastering and screeding already finish and check. Start
tiling from inside out.

Install the fist ceramic brick according to shopdrawing by


worker.

Correcting the plat of ceramic surface at every single brick.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

48

VII TILING

Must insert the gauge at every corner of ceramic brick.

Clean ceramic surface after join filling.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

49

VII TILING
Paving the WC floor after finish the wall tiling.

Tiling the fist arrow according to the shopdrawing

Correction the surface flat, install the gauge at join corner

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

50

VII TILING

Clean ceramic surface after join filling.


Evaluative criteria for the quality
of the WC tiling:
. Tight clinging into the wall, when knock do not hear
blistering sound.
. The finish surface of wall and floor is plat.
. The slope of floor follow the design drawing.
. Join is straight, steadily, with width follow the design.
. The ceramics are the same color.
. Join at the connection between wall and floor tiling is
less than 3mm.
. The ceramic brick have to fix with water collection
hopper.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

51

VII TILING
3. Ceramic tiling at hallway, lift lobby area.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

52

VII TILING
Granite tiling guide:
Granite sheet with 6-10mm thik will use mortar tiling as
ceramic tiles.
Granite sheet => 20mm thik have to use steel plate to connect
with the wall.

Tiling 20mm thik granite to the wall used plate steel connection.

Plate steel hanging granite sheet on the wall.


Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

53

VII TILING
Wood tiling guide.

Wood tiling in done only after the surface is dry.


Cleaning the surface of floor.
Moisture-proof plastic coverings.

Soundproofing installation.
Install the wood sheet together.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

54

VII TILING

When finish the whole floor, check again the plat, after that
locate and Install the border tiling.

Cleaning the surface of woodfloor.


Cover the floor against scratches with
plastic foam protection.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

55

VII TILING
Install the wallpaper.

Clean the wall surface.


Locate the vertical line for the first set paper.
Apply adhesive to the paper, put the paper on the wall.
Before flat strokes, align the paper straight.

Flat strokes the paper from inside to the outer mat.Cut


redundants.
Install the next paper
Pasted the next paper overthrust to the previous 2-3cm so
that the shape can be fit.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

56

VIII DOORS
VIII. INSTALL DOORS, WOOD FURNITURE, WC EQUIPMENTS
.

DOOR ADJUSTMENT

Plastic tape wrapped to


protect wooden door.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

57

VIII FURNITURE

Installation of wall cabinet.

Installation of kitchen cabinets.


C.
58
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

58

VIII SANITARY

Installation of bathtub, shower.

Glass-walled
shower cabin
installation

C.
59
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

59

VIII SANITARY

Shelf-lavabo installation

Installation of sanitary wares in the bathrooms.


Must wrap the equipments after installation to avoid
scratching the surface.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

60

VIII SANITARY

Lights installation.
Use the gloves to keep the ceiling clean.

Installation of mask power outlet.


Must have gloves when operate to keep the walls clean.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

61

VIII SANITARY
Common mistakes when finishing work is not done well,
bad influence when put in use.

Mortar enters into the drainage funnel tub cause by


uncovered.

Mortar debris fell into the toilet hole.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

62

VIII SANITARY

Enameled layer of lavatory, tub, water closet will be


scratched if not cover carefully.

Showers, faucets if not cover carefully, it will be easily


to scratched the chrome layer.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

63

VIII RAILING

Installation of a balcony.

Balcony tiling.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

64

IX

DOORS & WINDOWS

IX. INSTALATION OF THE OUTER DOOR AND WINDOW.

Door frame installation.

Window frame installation.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

65

IX

DOORS & WINDOWS

Grouting sealing between the door frame and the wall.

The joints should be inserted carefully, to avoid repellent


from the rain .

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

66

X ROOF
X. ROOF FINISHING WORK.

Waterproofing for roof concrete slabs.


Water immersion test.
Screeding of the protect mortar layer on the water
proofing membrane.
.

Install the insulation sheet steel mesh linking


50mm concrete layer - China-brick tiling.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

67

XI

EXTERNAL PLASTER

XI. PLASTERING THE EXTERNAL WALL WORK.

Use a plumb to check


the vertical of the
wallmark.

Wall mark at the


external wall

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

68

XI

EXTERNAL PLASTER

Cement mortar
rendering to exterior
face of brick wall.

Power floated wall


surface.
Joint cutting on the
wall.
Water drop slot
cutting underside of
window sills and
balconies

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

69

XI

EXTERNAL PLASTER

The first mastic layer dried then applying the 2nd layer.
Scrape with sandpaper to ensure that the surface is smooth
and free from dust, dirt.

Grind and claw edges of joints on the wall and water drop
slot underside of window sills, balconies.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

70

XII

EXTERNAL PAINTING

XII. PAINTING EXTERNAL WALL FINISH

Conduct the moisture test before applying mastic.

Apply the 1st mastic trowel.


Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

71

XII

EXTERNAL PAINTING

The first mastic layer dried then applying the 2nd layer.
Scrape with sandpaper to ensure that the surface is smooth
and free from dust, dirt.

Grind and claw edges of joints on the wall and water drop
slot underside of window sills, balconies.
Prepared by : QAQC Department
THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

72

XII

EXTERNAL PAINTING

Joint, Water drop slot must be aligned and sharp.

After the 2nd mastic dried, conduct the primer then


paint the last layer.

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

73

XIII BASEMENT
XIII. FINISHING FOR BASEMENT FLOOR
1.WATERPROOF FOR BASEMENT WALLS
2.CEMENT MOTOR RENDERING FOR COLUMN, BEAM,
BASEMENT WALL
3.BASEMENT FLOOR CREED
4.PAINTING, SIGNAGE INSTALLATION FOR BASEMENT FLOOR

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh
103enc@gmail.com

74

XIII BASEMENT
XIII. FINISHING FOR BASEMENT FLOOR

Prepared by : QAQC Department


THE UNIQUE QUALITY BUILDER

QUALITY BEAUTYFUL - PRESTIGE

www.103enc.com.kh