Professional Documents
Culture Documents
PROJECT : ABC
ISSUE
NC No
Issue
Month
Date of NC
Raised
Nature
Nature of
Occurrence
Category of NC
Major/
Minor/
Critical
New /
Repetitive
Workmanship /
Material /
Process
/Supervision/
Design
Trade
Area/Location
CLOSURE
Contractor to
whom NC was
given
Description of NC
Issued by
Correction
TPQA/Site
QAQC/Co
QAQC/Site Exec
To be filled in by
Project Head
To be filled in
by Project
Head
3/6/2015
Major
New
Design
Geo technical
6/10/2015
Minor
New
Process
Drawings
Tower-3
Site Exe.
17/06/15
Minor
New
Supervision
Piling
P1-201
DPJ
Improper supervision
23/06/15
Minor
New
Supervision
Tools
Tower-3
DPJ
24/06/15
Major
New
Material
Testing
Tower-3
DPJ
Proper Steel Base fabrication done Fixed steel base in all around the fabrication
Poor Workmanship and Supervsion for Fabrication and Concrete Has yard and other places has been barricaded
been poured n the Sings zone
properly.
Mar-15
June'15
Design team
Proposed Date
of Closure
Total Re-hab
project
Departmental
Responsibility
Site QA/QC
8/11/2015
Minor
New
Supervision
Process
8/21/2015
Minor
New
Material
Stocking
Steel Yard
DPJ
Aug'15
Site QA/QC
closed
23/06/15
23/06/15
closed
Fixed 4 cubes casting team will be Team has been fixed and training will be given
used with proper training for one and the after onemonth the strength details
Site Exec.
month.the analyse the report
will be verified and procured further
7/28/2015
7/30/2015
closed
9/7/2015
9/8/2015
closed
Site Exec.
8/22/2015
8/22/2015
closed
Site Exec.
9/18/2015
9/18/2015
0 closed
After RNC
excavtion done
3/26/2016
Closed
closed
DPJ
Oct'15
10/6/2015
Minor
new
Process
Process
P3-346
DPJ
12/1/2015
Minor
New
Supervision
1/4/2016 Major
New
Process
11
Jan'16
Excavation
Tower-3
12
RNC
RNC
2/20/2016 Major
New
workmanship/
supervision
Concrete
Tower-1
13
RNC
Feb'16
14
2/26/2016 Major
New
2/27/2016 Minor
Process/
supervision
Material
Concrete
Tower-2
RNC
Tower-1
15
2/27/2016
Minor
New
Supervision
Concrete
16
3/3/2016
Minor
New
Processs
Concrete
Cover block
casting yard
17
3/5/2016
Minor
New
Supervision
Formwork
RNC
Site QA/QC
12/15/2015
1/6/2016
12/20/2015
1/11/2016
3/3/2016
closed
7/12/2016 Open
Reinforcement
Site QA/QC
Site QA/QC
PC2J Pile cap concreting from Tower-2 has been
completed without following the approved method
statement for Thermal control testing /monitoring
New
Mar'16
Site QA/QC
Improper Dewatering
Site Exec.
Curing Tank
Stocking
P1-64 Pile has been found under catsed than the cutoff
Site QA/QC
level.
closed
7/18/2015
Supervision
DPJ
3/25/2016
16/07/2015
Have to accryout the PIT and PDA After 28 days from concreteing date. PDA will
to analyse the pile
be conducted to analyse the efficiency of pile
New
closed
Minor
Piling
Remarks
9/18/2015
Dec'15
NC
Status
11/6/2015
Sep'15
10
Delay
(Days)
11/6/2015
Site QA/QC
Actual Date
of Closure
3/3/2016
7/15/2016 Open
2/27/2016 27.02.16
3/1/2016
Closed
3/1/2016
closed
RNC
3/16/2016
closed
RNC
3/19/2016
closed
Mar'16
18
3/21/2016
Minor
new
Material
Reinforcement
Steelyard
19
3/29/2016
Major
new
workmanship/
supervision
Concrete
NC - 20/ RNC
-009
Apr-16
NC - 21/ RNC
-010
RNC
Site QA/QC
Site QA/QC
28-04-16
Major
New
Material
Concrete
Tower-1 @PC3H
RNC
5/26/2016
Major
New
Supervision
Concrete
PC1B Tower-2
RNC
Site QAQC
5/27/2016
Major
New
material
Tower 2 (PC4G)
Reinforcement and Tower-1 (PC3N
& PC5)
OCPPL
Site QAQC
RNC
RNC QA/QC
RNC QA/QC
May'16
NC - 22/ RNC
-011
3/24/2016
3/28/2016
closed
3/30/2016
6/29/2016
90
closed
4/30/2016
4/30/2016
7/29/2016
Closed
closed
July'16
At Tower-3, Grid J - C16 has been noted with column
cover issue around 15 mm short from actual cover.As
per our Spec, Acceptable tolerance limit for this work is Site QAQC
+10mm and 0 mm.
NC - 23 /
RNC -012
6/6/2016 Major
New
workmanship/
supervision
Concrete
OCPPL
NC - 24 /
RNC -013
6/7/2016 Major
New
workmanship/
supervision
Concrete
OCPPL
NC - 25 /
RNC -014
6/7/2016 Major
New
workmanship/
supervision
Concrete
OCPPL
New
workmanship/
supervision
Concrete
the Extra cover (More than 25mm from clear cover) for
outside lift wall and Less cover for inside reinforcement
Site QAQC
has been noted. Which is the deviation from our actual
tolerance limit i.e. +10mm/-0mm.
OCPPL
Cube test for Tower-3 Pile cap and Semi basement slab
concrete at Grid (1-1a),(I-J),(1-5a),(H-I), 5 out of 20
Site QAQC
cubes attain less strength than characteristic
compressive strength i.e. 40 N/mm2.
Site QAQC
6/16/2016
closed
Open
6/16/2016
closed
June'16
NC - 26 /
RNC -015
6/8/2016 Major
NC - 27 /
RNC -016
6/14/2016 Minor
Repetative
workmanship/
supervision
Concrete
OCPPL
NC - 28 /
RNC -017
6/16/2016 Minor
New
Supervision
Backfilling
OCPPL
NC - 29 /
RNC -018
6/17/2016 Maor
New
Material
Reinforcement
OCPPL
Delay in progress
Minor
New
Material
Concrete
at C7@ (5-G),C9@
(5-F) (6-F) (7F),C8@(C-6) (C-8)
(C-9),C15@(4a-H)
OCPPL
NC - 31/ RNC
-020
7/8/2016 Minor
New
Material
Concrete
OCPPL
NC - 32/ RNC
-021
7/8/2016 Major
New
Supervision
Concrete
Liftwall @ Tower-3
OCPPL
Site QAQC
NC - 33/ RNC
-022
7/13/2016 Major
New
Design
Concrete
PC-5 Tower-1
OCPPL
Site QAQC
OCPPL
Poor Supervsion
NC - 30/ RNC
-019
7/5/2016
July'16
NC - 34/ RNC
-023
7/15/2016 Minor
NC - 35/ RNC
-024
New
7/21/2016 Major
Site QAQC
RNC QA/QC
Open
July''16
closed
Open
6/29/2016 closed
Open
Open
Open
Open
closed
July'16
element shown at site needs to be
cleared with all soil coverings and Backfilling and earrth filling with necessarty
proper access to be made
care to the adjacent structure.
Supervision
Backfilling
Tower-1 NE corner
Design
Concrete
PC4G-Tower-2
OCPPL
Site QAQC
Open
Design
Concrete
PC4K - Tower01
OCPPL
Site QAQC
Open
New
NC - 36/ RNC
-025
7/25/2016 Major
New