Intermediate school

2016

Apr

May

Jun

Classic Schedule Layout

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

15-Apr-16, Executive Summary

Apr

May

Jun

2017

Jul

Aug

Sep

Oct

Nov

Dec

28-Aug-17, Intermediate school

23-Apr-16 23:24
2018
Jan

Feb

Letter of Acceptance
Contract Signature

Project commencement date


right of access to site

19-Apr-16, External Works and Mobilization

Cleaning and Removing obesticals


Fixing the fence

Erection of site offices

Surveying

06-Jul-16, Sub structure Works

28-Apr-16, Excavation
Excavations

31-May-16, Footings

Shuttering plain concrete footing


Placing plain concrete footing

Curing of Plane Concrete Footings

Deshuttering plain concrete footing


Shuttering RC footing

Steel fixing RC footing


Placing RC footing

Curing of RC Footings

Deshuttering RC footing

26-May-16, Ground Beams

Shuttering Ground Beams

Steel Fixing of Ground Beams


Placing Ground Beams

Curing of Ground Beams

Deshuttering Ground Beams

13-Jun-16, Column Necks

Shuttering Columns Neck

Steel Fixing Columns Neck

Actual Work

Remaining Work

Critical Remaining ...


Milestone

Page 1 of 7

TASK filter: All Activities

Oracle Corporation

Intermediate school
2016

Apr

May

Jun

Classic Schedule Layout

Jul

Aug

Placing Columns Neck

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2017

Jul

Aug

Sep

Oct

Nov

Dec

23-Apr-16 23:24
2018
Jan

Feb

Curing Columns Neck

Deshuttering Columns Neck

20-Jun-16, Isolation and Backfilling

Isolation

Backfilling

06-Jul-16, Slab On Grade

Shuttering Slab on Grade formwork


Steel Fixing Slab on Grade

Placing Slab on grade Concrete


Curing Slab on Grade

Deshuttering Slab on grade Formwork


19-Dec-16, Ground Floor Works

28-Aug-17, Super Structure Works

30-Sep-16, Concrete Works


09-Aug-16, Columns
Shuttering columns
Steel fixing columns

Placing RC columns

Curing RC Columns

Deshuttering columns

25-Aug-16, Stairs
Shuttering Stairs Formworks

Steel Fixing Stairs Formworks


Placing Stairs Formworks

Curing Stairs Formworks

Deshuttering Stairs Formworks

30-Sep-16, Slab
Shuttering slab
Steel fixing slab

Placing RC slab

Curing Ground Floor Slab


Deshuttering slab

30-Sep-16, Floor Beams


Actual Work

Remaining Work

Critical Remaining ...


Milestone

Page 2 of 7

TASK filter: All Activities

Oracle Corporation

Intermediate school
2016

Apr

May

Jun

Jul

Classic Schedule Layout


Aug

Sep

Oct

Nov

Dec

Jan

Shuttering Ground Floor Beams

Feb

Mar

Apr

May

Jun

2017

Jul

Aug

Sep

Oct

Nov

Dec

23-Apr-16 23:24
2018
Jan

Feb

Steel Fixing of Ground Floor Beams


Placing Ground Floor Beams

Curing Ground Floor Beams

Deshuttering Ground Floor Beams


Stone Works

19-Dec-16, Finishing Works

Preliminary carpentrary work

Preliminary electrical work


Preliminary sanitary work
Floor Tiling

Plastering Splach and rough coat


Plastering Smooth Coat
Painting

Windows

Finishing Carpentary work


Finishing electrical work
Finishing sanitary work

Ground Floor Completion

18-Oct-16, Partions
Brick works
Insulations

21-Mar-17, First Floor Works

22-Dec-16, Concrete Works


20-Oct-16, Columns
Shuttering columns
Steel fixing columns

Placing RC columns

Curing Rc Columns

Deshuttering columns

01-Nov-16, Stairs
Shuttering Stairs Formworks

Steel Fixing Stairs Formworks


Placing Stairs Formworks

Actual Work

Remaining Work

Critical Remaining ...


Milestone

Page 3 of 7

TASK filter: All Activities

Oracle Corporation

Intermediate school
2016

Apr

May

Jun

Jul

Classic Schedule Layout


Aug

Sep

Oct

Nov

Dec

Jan

Curing Stairs Formworks

Feb

Mar

Apr

May

Jun

2017

Jul

Aug

Sep

Oct

Nov

Dec

23-Apr-16 23:24
2018
Jan

Feb

Deshuttering Stairs Formworks

22-Dec-16, Slab and Beams


Shuttering slab and beams
Steel fixing slab and beams

Placing RC slab and beams

Curing Slab and beams

Deshuttering slab and beams

21-Mar-17, Finishing Works

Stone Works

Preliminary carpentrary work

Preliminary electrical work


Preliminary sanitary work
Floor Tiling

Plastering Splach and rough coat


Plastering Smooth Coat
Painting

Windows

Finishing Carpentary work


Finishing electrical work
Finishing sanitary work

05-Jan-17, Partions
Bricks work

First Floor Completion

Insulations

08-Jun-17, Second Floor Works

13-Mar-17, Concrete Works


09-Jan-17, Columns
Shuttering columns
Steel fixing columns

Placing RC columns
Curing Rc Columns

Deshuttering columns
19-Jan-17, Stairs

Actual Work

Remaining Work

Critical Remaining ...


Milestone

Page 4 of 7

TASK filter: All Activities

Oracle Corporation

Intermediate school
2016

Apr

May

Jun

Jul

Classic Schedule Layout


Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

Shuttering Stairs Formworks

May

Jun

2017

Jul

Aug

Sep

Oct

Nov

Dec

23-Apr-16 23:24
2018
Jan

Feb

Steel Fixing Stairs Formworks


Placing Stairs Formworks
Curing Stairs Formworks

Deshuttering Stairs Formworks

13-Mar-17, Slab and Beams


Shuttering slab and beams
Steel fixing slab and beams

Placing RC slab and beams

Curing Slab and beams

Deshuttering slab and beams

08-Jun-17, Finishing Works

Stone Works

Preliminary carpentrary work

Preliminary electrical work


Preliminary sanitary work
Floor Tiling

Plastering Splach and rough coat


Plastering Smooth Coat
Painting

Windows

Finishing Carpentary work


Finishing electrical work
Finishing sanitary work

27-Mar-17, Partions
Bricks work
Insulations

Second Floor Completion

28-Aug-17, Third Floor Works

31-May-17, Concrete Works


29-Mar-17, Columns
Shuttering columns
Steel fixing columns

Placing RC columns

Actual Work

Remaining Work

Critical Remaining ...


Milestone

Page 5 of 7

TASK filter: All Activities

Oracle Corporation

Intermediate school
2016

Apr

May

Jun

Jul

Classic Schedule Layout


Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Curing Rc Columns

2017

Jul

Aug

Sep

Oct

Nov

Dec

23-Apr-16 23:24
2018
Jan

Feb

Deshuttering columns

10-Apr-17, Stairs
Shuttering Stairs Formworks

Steel Fixing Stairs Formworks


Placing Stairs Formworks
Curing Stairs Formworks

Deshuttering Stairs Formworks

31-May-17, Slab and Beams


Shuttering slab and beams
Steel fixing slab and beams

Placing RC slab and beams

Curing Slab and beams

Deshuttering slab and beams

28-Aug-17, Finishing Works

Stone Works

Preliminary carpentrary work

Preliminary electrical work


Preliminary sanitary work
Floor Tiling

Plastering Splach and rough coat


Plastering Smooth Coat
Painting

Windows

Finishing Carpentary work


Finishing electrical work
Finishing sanitary work

14-Jun-17, Partions
Bricks work

Third Floor Completion

Insulations

05-Jun-17, Roof Works

Screed and Roofing Works

28-Aug-17, Project Delivary

Actual Work

Remaining Work

Critical Remaining ...


Milestone

Page 6 of 7

TASK filter: All Activities

Oracle Corporation

Intermediate school
2016

Apr

May

Jun

Jul

Classic Schedule Layout


Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

2017

Jul

Aug

Sep

Oct

Nov

Dec

Handeling Over Mobilization

23-Apr-16 23:24
2018
Jan

Feb

Handeling Over 4 Floors

Handeling Over roof and external works

Project Completion Date and demobilization

Actual Work

Remaining Work

Critical Remaining ...


Milestone