Professional Documents
Culture Documents
Proceedings of ICDER-2016
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
streams. In order to recover heat from the steams using a waste heat recovery steam generator a
steam cycle was used and it was estimated that about 4.4 MW of electricity could be generated.
Camdali et al. (2004) carried out energy and energy analysis for a dry system rotary burner
with pre-calcinations in a cement plant of an important cement producer in Turkey using actual
operational data. It was founded that energy and energy efficiency values for rotary burner were
85% and 64% respectively. An energy audit analysis of a dry type rotary kiln system with a
capacity of 600 ton clinker working per day was performed by Engin and Ari (2005) in a cement
plant in Turkey. They found that about 40% of the total input energy was being lost through hot
flue gas (19.15%), cooler stack (5.61%) and kiln shell (15.11%) convection plus radiation. A
waste heat recovery steam generation system was proposed which recovered 1 MW energy for
the heat loss through hot flue gas and cooler exhaust
Rasul et al. (2005) conducted a research base data from Indonesian Portland cement plant.
They presented a simple model to evaluate the thermal performance of the cement industry.
Mass, energy as well as energy balance is used as the main aspects for building the
developed model. The results obtained were:
burning efficiency was 52.7%,
cooler efficiency was 45%,
Heat recovery efficiency was 51.2%.
Due to convection and radiation there was a high heat loss at the cooler of 19%
Heat recovery from rotary kiln for a cement plant in Turkey was examined by sogut at
el.(2009). It was determined that 5% of the waste heat could be utilized with the heat recovery
exchanger. Domestic-coal and natural gas consumption can be decreased by (51.55% and 62.62%
respectively] through installing this system.
Energy audit of kiln system in a cement plant is conducted by; using data measured from
a typical cement plant in Coimbatore, India and this is the main theme of the paper. The possible
approaches of heat recovery from some major heat loss sources are discussed by making a detailed
analysis of kiln, grate cooler, raw mill and coal mill.
PROCESS DESCRIPTION
MINES
At about a distance of 6.5kms from plant the plant is having its own mining facility. For
convenient transportation the mined limestone is crushed into small sizes with the help of primary
and secondary crusher in the mines itself. Through aerial ropeways the crushed limestone is
transported to plant and using tertiary crusher it is further crushed into small particles.
RAW MILL
The plant has one raw mill capacity of120TPH. Raw milling involves mixing the extracted
raw materials to obtain the correct chemical configuration, and grinding them to achieve the
www.iaetsd.in
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
proper particle-size to ensure optimal fuel efficiency in the kiln and strength in the final concrete
product.
Lime Stone, sweetner and latrite are the main raw materials and they are grounded
proportionately in the mill. Blending & Storage silos are used to store the mill output product as
raw meal. To remove the moisture content from meal hot gas from PH section is used. Material
moisture is 4% in Inlet whereas after mill the moisture content in raw meal is 0%.
COAL MILL
At the plant there are three coal mills of capacity varying from 3.3 TPH to 15TPH. The
coal that is to be burnt in the kiln and Precalciner section is dried and finely grounded. It is from
the storage silos that the fined coal is fed to Kiln burner and Precalciner section. While entering
the mill the moisture content in the coal is around 10% whereas it becomes 2% at the outlet.
Energy Audit of kiln system in a Cement Plant
www.iaetsd.in
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
GRATE COOLER
In order to preserve the ideal quality and for maneuver by conveyors the clinker has cooled
to 70-1000C after the clinker formation. . In cooler, clinker cooling is taking place with the help
of ambient air supplied by cooler fans to recover the heat from clinker, after taking heat from
clinker one part of hot air is supplied into kiln as secondary air for complete combustion and one
part is supplied to precalciner as tertiary air and remaining will be vent through ESP and ID fan.
Six fans are used in the cooler section for clinker cooling of varying flow rates. The clinker
is conveyed and stored in yard for the next process after cooling it at a desired temperature.
CEMENT MILL
This is the final stage in the process of cement making. There are two mills installed in
the plant for cement grinding with capacity of 35 TPH and 65 TPH for Ordinary Portland Cement
(OPC).To convert cement into a fine powder it is grinded with other materials like slag, gypsum
etc (which impart special characteristics to the finished product) in the cement mill. To separate
the materials that has not been completely grinded is sent back into the mill and after it gets
separated in separator. The output of the mill is then sent to cement storage silos where it is stored
and sent to the packing units which are consisting of manual as well as electronic packers.
OBSERVATION AND ANALYSIS
RAW MILL
Average production rate of mill is varying from 115 120 TPH. As per plant data moisture
content present in raw material IN and OUT of Raw mill is 4% and 0% respectively. The total
power consumption of the raw mill system is constant throughout the logging period and it is
1150KW. Average specific energy consumption is 26.9 kWh / Tons of material. Pressure drop
between cyclones, Separator, ESP are as follows119, 200, 68mmWC.
COAL MILL
Three mills are used for plant installation, in which two mills (CM-1&5) are of ball mill
type and other one is vertical roller mill (CM-3). The design capacity of the mill is 3TPH, 5 TPH
and 15 TPH (with higher fineness) respectively. The typical coal mill circuit diagram with
temperature, pressure, oxygen percentage and flow of fans at various locations is given below.
www.iaetsd.in
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
Average production rate of CM-1 is 1.4 TPH, CM-5 is 3.05 TPH and CM-3 is 4.7 TPH.
Moisture content present in raw material IN and OUT of Coal mill is 7-12% and 2.2-3.5%
respectively as per plant data.
In CM-1 and CM-5 the power consumption of coal is almost constant and it consumes 69 kW
and 116 kW respectively. Power consumption of CM-3 (VRM) is varying between 78 90 kW.
60.1 kWh is consumed in average for per Ton of material. From PH fan to coal mill booster fan
air ingress across duct is 20%.
Air ingress across Coal mill booster fan and VRM cyclone is 26.5%.
Air ingress across VRM cyclone and bag house outlet is 6%.
Air ingress at different locations as mentioned above is on the higher side, reducing
the air ingression would reduce power of mill fans and Bag house fan.
PYROPROCESSING SECTION
There are 4 stages for Preheater and Precalciner, the preheater section consists of dual
streams (preheater and precalciner).The raw meal after gets grind in raw mill stored in storage silo
is fed into the preheater section through the first cyclone which gets heated up by the upcoming
hot gas in both streams.
Fuel (coal) is conveyed through compressed air for firing in kiln and precalciner. The
pyroprocessing section of the cement plant is shown in figure 2
Energy Audit of Kiln System in a Cement Plant
www.iaetsd.in
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
GCT Outlet
10
ESP Outlet
11.7
Pressure drop across cyclone 2 & 3 are found high. Possible material clogging that needs
to be cleaned was checked. The resulting reduction is observed in power consumption of Preheater
fan through the reduction of pressure drop. It was found that there is ambient air infiltration into
the Preheater and Precalciner from the flue gas analysis which is the ducting system that increases
the work load of PH fan and Kiln ESP fan. Oxygen percentage in kiln discharge is satisfactory.
At present air infiltration percentage is 15.5%, so the specific air flow in preheater section is 2.47
NM3/kg of clinker which is on the higher side compare to the standard 1.6 NM3/kg of clinker.
The air infiltration must be reduced to 8 % to reduce specific air flow to 2.31 NM3/kg of clinker.
Since only one string is in operation this is on higher side.
GRATE COOLER
Grate cooler is installed in the plant to cool the hot clinker which comes out from the kiln
after calcinations process. The design parameters of cooler is the Capacity- 1250 TPD of clinker
and Grate area 52.92 m2. The plant is running on partial load with one string operation in
preheater section during the study. The clinker coming in to the cooler is reduced by half in one
string operation, but during this time also grate speed is at its design 3.5 Strokes/min. The specific
air flow of cooler is calculated from our measurements and it is found to be 5.22 NM 3/kg of
clinker which is on higher side compared to its standard of 1.8 NM3/kg of clinker. The main
reasons for this is the Kiln is running with 50% load so clinker coming in to the cooler is less than
the rated and cooler fans are running at full speed. The bed thickness would be thin and uneven
since Grate speed is also at its rated/full load speed.
HEAT BALANCE
Following assumption are made in order to analyze the heat balance of the Rotary kiln and Grate
cooler.
Steady state working condition
www.iaetsd.in
10
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
ROTARY KILN
One Rotary Kiln with production capacity of 1250 TPD is installed by the plant. The
present Kiln speed is 1.2 rpm. To control the flame shape the kiln is installed with one centrifugal
fan for swirl air and one root bowler for axial air and the same air is acting as primary air for
combustion.
Coal is conveyed through compressed air into the kiln. During study various operating
parameters have been observed and measured and the important data collected is given below:
1. The average coal consumption of main kiln burner is 3 TPH coal.
2. The average kiln feed is 74.5 TPH and clinker production is 52 TPH.
To reduce kiln surface heat losses in its interior surface is covered with refractoriness of
alumina bricks with 200mm thickness. The measured average surface temperature of kiln is
1810C.
During the audit the kiln drive power consumption was taken and the average power
consumption is 40 kW.
The heat balance is done based on coal firing quantity, measured air flow rates and
temperature. The following parameters are considered as the basis for the analysis:
1. Ambient air temperature is 34oC.
2. Clinker production at kiln discharge is 52 TPH.
3. Assumed clinker temperature at kiln discharge side is 1270 0C.
Proximate analysis of coal (Fixed carbon-39%, Ash-29%, Volatile matter-27.7%,
Moisture-2.44%) and ultimate analysis of coal (Carbon-54.62%, Hydrogen-3.54%,
Nitrogen-1.54%)
The Gross Calorific value of coal (GCV) can be calculated by using Dulongs formulae as
GCV = ([35.5C+114.8H+9.5S-14.5O] = 23422.212 kJ/kg.
Composition of clinker is SiO2-20.90%, Al2O3-5.25%, Fe2O3-2.93%, CaO-62.11%, MgO-5.82%.
Heat of reaction of clinker (HR) = (4.11Al2O3) + (6.48MgO) + (7.646CaO) (5.11SiO2)-(0.59Fe2O3)
= 1779.50 kJ/kg of clinker
www.iaetsd.in
11
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
INPUT ENERGY
Equation
Coal combustion
in
kiln
(Q1), m*GCV
GCV= 23422.212
KJ/Kg
Coal combustion
in
precalciner m*GCV
(O2),
GCV=
23422.212 KJ/Kg
of Temp C
Result
Cp
(KJ/Kg
(KJ/Kg) of
clinker)
0.094
2201.68
41.14
0.1345
3150.28
58.86
5351.96
100
1779.50
33.24
1.1670
T1= 420
T2= 75.1
1.01574 408.83
7.63
Quantity of coal
used in coal mill m*Cp(T1-T2)
(Q5)
0.2891
T1=420
T2= 73.1
1.01573 101.86
1.9
1.9699
T1=75
T2=34
1.0241
82.70
1.54
1.58
T1=73
T2=34
1.0241
63.401
1.184
T1=110
T2=34
0.7774
59.08
1.103
5.88
T1=180
T2=34
1.01574 871.95
www.iaetsd.in
Mass, m
(Kg/Kg
clinker)
12
16.29
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
12 Convection heat
loss from kiln
surface (Q14)
13 Heat losses by
surface convection
and radiation from
cooler (Q15)
m*Cp(T1-T2)
4.162
T1=139
T2=34
T1=420
T2=34
m*Cp(T1-T2)
2.55
(L+(Cps+(T1T2)*M)
Mkiln=0.0943 T1=840
Mpc=0.1049
T2=34
0.9990
436.56
8.15
1.0241
1008.02
18.83
1.881
26.25
0.49
MNA (Ts4TO4),Akiln=1272.3
4m2
Ts=181
T_=34
89.53
1.67
2.32Akiln(TsTO)1.250.86,
Akiln=1272.34m2
{[0.548(T1/55.55
)4-(T2/55..55)4+
1.957 (T1-T2)1.25]
0.86} Acooler,
Acooler=310.2m2
Ts=181
T_=34
89.82
1.68
8.51
0.16
T1=328K
T2=307K
5026.011 94.26
325.98
6.9
www.iaetsd.in
13
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
This formula can be used to calculate the total heat that could potentially be recovered:
Q = VCpT
Flow rate (V) of gas inlet to gas conditioning tower in m3/hr
Density of gas() corresponding to the gas temperature in kg\m3
Specific heat (Cp ) of gas corresponding to the temperature in kcal/kgC.
Combined() of waste heat recovery boiler and turbine
Change in temperature(T) in C
Q = 2, 32,9620.55760.24 (360-185)0.18=982041/860.4/1000
=1.14MW
Investment- Rs 1500Lakhs
14
IAETSD 2016
ISBN-13: 978-1537033419
Proceedings of ICDER-2016
energy recovery from these waste gases of (16.48%). A waste heat recovery steam generation
system was selected showing the energy saving potential of 1.14 MW from the waste heat streams
with simple pay back of 48 months.
Thermal energy conservation study is carried out in a cement industry as the energy cost
plays a major role in production cost of the cement. The total investment required to implement
all proposals will be Rs 1534 Lakhs, which gives an overall payback period of 37 months.
REFERENCES
1. Schuer, A., Leian, A., and Ellerbock H .G. 1992. Possible Ways of Saving Energy in
Cement Production, Cement Gips, pp-175-182
2. ShaleenKhurana, Rangan Banerjee, UdayGaitonde 2002.Energy balance
cogeneration of cement plant Applied Thermal Engineering Vol.22, pp.485-494
and
3. Candali, U., Erisen, A. and Celen F. 2004. Energy and Exergy Analyses in a Rotary burner
with Pre-calcinations in Cement production, Energy conservation management pp-18-19
(2004) 3017-3031
4. TahsinEngin,Vedat Ari 2004 Energy auditing and recovery for dry type cement rotary kiln
systemsA case study, Energy conservation and management2005(551-562)
5. Rasul M G, Widianto W, Mohanthy B.(2005): Assessment of the thermal performance
and energy conservation opportunities of a cement Industry in Indonesia: Applied thermal
Engineering, Vol.25, pp2950-2965.
6. Sogut M.Z., Oktay Z, Hepbasli A. (2009): Energetic and exergetic assessment of a trass
mill process in a cement plant Energy, Conversion and Management Vol.50, pp.2316
2323.
7. Peray,K.E., Cement Manufactures Handbook, New York, NY: Chemical Publishing
Co.,Inc.1979.
www.iaetsd.in
15
IAETSD 2016