You are on page 1of 16

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


1 of 16
B02

Material Requisition
For
Power Transformers

B02

03-Jun-2014

Issued For Design

T.Rostami

R.Hajinajaf

A.Bodaghi

B01

15-Jan-2014

Issued For Comment

S.Garjani

S.Garjani

A.Bodaghi

Rev.

Date

Description

Prepared

Checked

Approved
SAZ. POI :

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

IFD1

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


2 of 16
B02

TABULATION OF REVISED PAGES


SHEET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

REVISIONS
01 02 03 04 05 06 07
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X

SHEET

REVISIONS
01 02 03 04 05 06 07

51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


3 of 16
B02

Table of Contents
I.

INTRODUCTION ...................................................................................................... 4

II. Definitions ................................................................................................................. 4


III. APPLICABLE DOCUMENTS .................................................................................... 4
1. Purpose .................................................................................................................... 5
2. General ..................................................................................................................... 5
3. Order of Precedence................................................................................................. 5
4. Inspection and Test................................................................................................... 5
5. Vendors Proposal..................................................................................................... 6
6. Deviation from Purchasers Requirements ................................................................ 6
7. Spare Parts ............................................................................................................... 6
7.1 Erection, Pre-commissioning, Commissioning and Start-up Spare Parts ...................... 6
7.2 Two Years Operation Spare Parts ................................................................................. 7
7.3 Capital Spare Parts ........................................................................................................ 7
8. Attachments .............................................................................................................. 8
8.1
8.2
8.3
8.4

Attachment #1: List of Documents Supplied and Presented by Purchaser ................... 9


Attachment #2: List of Documents Required from Vendor ........................................... 10
Attachment #3: Scope of Supply and Work ................................................................. 13
Attachment #4: Inspection Procedure Manual for Power Transformers ...................... 15

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

I.

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


4 of 16
B02

INTRODUCTION
South Yaran oil field is located in Kuzestan province 120KM west of Ahwaz with 20Km
length and 2.5Km width at south part of Yaran oil field.
24 No wells considered at this area consisting of 14 No Sarvak wells, 8 No Fahlian &
Gadvan wells and 2 No appraisal wells for sarvak and fahlian & Gadvan layers with total
estimated output between 50,000 to 60,000 STB/Day.
Flow of wells is transferred to the 2 phase separation unit (Cluster) for separation of gas
from liquids and dehydrating of gas.
The dehydrated gas is transferred to NGL 3200 and the liquids are transferred to Karoon
production plant for further processing.

II.

Definitions
OWNER
Client
CONSULTING ENGINEER
PROJECT
LOCATION
APPROVED
FW

SW

: Witness inspection/test at the initial stage or other time


of fabrication on one or specified percentage of similar
items or material.
: Verify by reviewing the manufacturer's inspection/test
record
: Manufacturer's official records/certificates required for
Contractor inspector's review and vendor's inspection
report
: Contractor
: Manufacturer's
: Welding procedure specification
: Procedure qualification record

R
OR

C
MFR'S
WPS
PQR

III.

: NIOC
: Petroleum Engineering and development Co. (PEDEC)
: Sazeh Consultants
: South Yaran Petroleum Filed Development (Basic
Engineering)
: Khuzestan Province-120Km west of AHWAZ
: Approved by Client
: Full witness inspection /test
The supplier cannot carry out the specified controls and
tests without Purchaser/Owner attendance and
witnessing. The supplier must notify Purchaser/Owner
by fax of the dedicated inspection activity at least fifteen
(15) days in advance. The supplier cannot deviate from
this rule unless written approval has been given by
Purchaser/Owner.

APPLICABLE DOCUMENTS
Codes and Standards
Design, materials and workmanship shall be in accordance with this job specification and
the following IEC standard:

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


5 of 16
B02

International Electrical Committee (IEC)

IEC 60076

Power Transformer.

Iranian Petroleum Standards (IPS)

IPS-M-EL-150(1)

Material and equipment standard for power transformers

IPS-M-EL-151(1)

Material and
transformers s

IPS-M-EL-152(1)

Material and equipment standard for oil immersed power


transformers

equipment

standard

for

dry

type

power

PROJECT Specifications

SYME-ELBASC-ENEL-SPEL-0001

Specification for Power Transformer

1. Purpose
The purpose of this requisition is to define Purchasers required equipment (Table 1), their
supply requirements, documentation requirements together with list of documents supplied
and presented by Purchaser.

2. General
Engineering specifications and documents, listed in Attachment #1 of this Requisition,
entitled LIST OF DOCUMENTS SUPPLIED & PRESENTED BY PURCHASER, are
applicable for supply of the items mentioned in table 1 above.
The Vendor is the sole responsible party for the correct application of the contractual
documents and adherence to all specifications and codes as mentioned above Definitions.

3. Order of Precedence
In case of conflict between requisition, purchase order and documents listed in Attachment
#1 of the requisition, entitled LIST OF DOCUMENTS SUPPLIED & PRESENTED BY
PURCHASER, or codes and standards listed in the relevant engineering specifications,
the order of precedence shall be considered as follow:
a) Purchase Order (In case of P.O. placement)
b) Material Requisition
c) Data sheet
d) Project specifications
e) Code and standards
Any conflict between the above documents must be brought to Purchasers attention and
written Purchasers approval shall be obtained before proceeding with manufacturing
and/or any other work. Generally, the most stringent requirement applies.

4. Inspection and Test


Inspection and test items in accordance with data sheet and Inspection & test plan shall be,
as a minimum, carried out at vendors shop.

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


6 of 16
B02

5. Vendors Proposal
1) Vendors proposal shall comprise information mentioned in this paragraph in addition to
the required information mentioned in Attachment 2 of the Material Requisition, entitled
List of Documents Required from Vendor.
2) Further to terms mentioned in Attachment 2 of the Material Requisition, List of
Documents Required from Vendor, Vendors proposal shall contain at least the following
information:
Quality Assurance system certificates, ISO9001 or equivalent
Vendors Reference List
Deviations or Alternatives, if any.

6. Deviation from Purchasers Requirements


Vendors proposal shall be in strict conformity with purchasers requirements. Unless
exceptions, deviations or alternatives are clearly identified in Vendor Deviation Form,
attached to the invitation to tender letter, the requirements and conditions in this
attachment and all documents attached to the requisition is deemed to be accepted by
vendor.

7. Spare Parts
Vendor shall provide the list of recommended spare parts for commissioning, two years of
operation, capital spares and required special tools at the bidding stage. Following items
shall be considered as a minimum for the recommended spare parts.
7.1

Erection, Pre-commissioning, Commissioning and Start-up Spare Parts


Pumps:
Gland packing
Mechanical seals
Carbon Teflon rings
Gasket sets and o-rings
Electrical Motors:
Grease nipples where applicable
Lighting fixtures
Flag relay
Time relay
Terminal block
Auxiliary relays
Moving contacts
Fixed contacts
Coils for contactors
Boucholz relay
Thermometer
Local control station
Sockets
Plugs

200% per mat's /size


100% per model/type
500% per model/ type
100%
10%
1%
2%
2%
2%
1%
15%
10%
10%
one of each type & size
10%
5%
5%
5%

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

7.2

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


7 of 16
B02

Two Years Operation Spare Parts


SPARE PARTS FOR CENTRIFUGAL PUMPS
Number of pumps using

more

Shaft, impeller, throat bushing

Shaft sleeve, bearing set,

30% of no. of
Pumps
50% of no. of
Pumps

Impellers and case wearing rings


Gasket sets, packings, mechanical
Seal, Non-metallic faces, o-rings,
Gaskets, springs

Mechanical seal, metallic faces

Mechanical seal assembly

100% of no.
of pumps
100% of no.
of pumps
50%

NOTES:
(i) The parts listed above are the principal parts only. Other parts, such as impeller
special bolts etc. shall be considered for recommendation in quantities consistent with
the above table.
(ii) Spare impellers shall be ordered in the maximum diameters.
(iii) Quantities listed above are based on one part per pump. If the pump has more than
one, the number of parts shall be modified accordingly.
(iv) For rotary pumps, provide a matching set of rotors with shaft.
SPARE PARTS FOR ELECTRICAL EQUIPMENT
Items
Qtys
1) Motors
No. of machines
1
2
3
4
5
more
Set of bearing
1
1
1
2
2
40%
NOTE:
These are the spare parts required for two years operation. Vendor shall recommend the
spares based on their experience.
(*)The Quantities indicated are only preliminary estimation, so the firm quantities will be
specified later in conjunction with recommendations of equipment vendors. The
quantities shall be approved by Owner.
7.3

Capital Spare Parts

Centrifugal Pumps, Multistage:

Rotor assembly (1 per type)


Oil pumps (1 per type), where applicable
Oil pump couplings (1 per type), where applicable

Centrifugal Pumps, One/Two stage

Impeller set (1 per type)

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


8 of 16
B02

8. Attachments
Attachment #1: List of Documents Supplied and Presented by Purchaser
Attachment #2: List of Documents Required from Vendor
Attachment #3: Scope of Supply and Work
Attachment #4: Inspection Procedure Manual

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

8.1

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

Attachment #1: List of Documents Supplied and Presented by Purchaser

NO.

DESCRIPTION

A-

General Documents :

Painting Specification

Process Design Basis

B-

Technical Documents:

B.1

Specification and data sheet

Specification For Power Transformer

Data Sheet for Power Transformer

Electrical Design Criteria

B.2

Electrical equipment Layout in Cluster


Substation

Electrical Key Single Line Diagram

4
5

DOCUMENT NO.

REV.

REMARKS

SYME-PIBASC-ENPISPPA-0001
SYME-PRBASCENPS-BSDE-9005

SYME-ELBASCENEL-SPEL-0001
SYME-ELBASCENEL-DSEL-0001
SYME-ELBASCENEL-CIDE-0001

Drawings:

SHEET NO. : REV.:


9 of 16
B02

Overal Electrical Single Line Diagram


For Cluster
MV&LV Metering and Protection Single
Line Diagram
Typical Single Line Diagram For Well
Head Distribution Panel

SYME-ELBASCENEL-DWLO-0001
SYME-ELBASCENEL-DISL-0003
SYME-ELBASCENEL-DISL-0004
SYME-ELBASCENEL-DISL-0005
SYME-ELBASCENEL-DISL-0002

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

8.2

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

:
:

SHEET NO. : REV.:


10 of 16
B02

Attachment #2: List of Documents Required from Vendor


AFTER ORDERING

ITEM
NO.

DESCRIPTION

AT THE
TIME
OF BID
Q/TYPE

DRAWINGS AND DOCUMENTS


Q/TYPE
(Note 1)

DEL. TIME
(Note 2)

PURPOSE
(Note 3)

FINAL
ISSUE
(Note 1)

AT THE
FINAL
INSP.
(Note 4)

Manufacturing Schedule /
Inspection Schedule /
Status Report

2W

Organization Chart

2W

Vendor Print Index and Schedule

2W

Sub-supplier List

2W

General Arrangement Drawings

6w

10

6W

10

10W

10

10W

10

10W

10

8W

10

12W

10

12W

10

12W

10

6
7
8
9
10
11
12
13

Auxiliary Equipment Outline


Drawing
Motor General Arrangement
Drawing
LO console General
Arrangement Drawing
Packing and Seal system
Drawing
Customer Piping Connections
Component and/or Cross
Sectional Drawings
Packing Cross Sectional
Drawings
Coupling Drawing showing Bill of
Material

14

Pump Cross Sectional Drawings

12W

10

15

Motor Shaft/End Detail Drawings

8W

10

8W

10

8W

10

16
17

Foundation/Skid Drawings
(Including Driver)
Loading and Bolt Setting
Diagram

18

Calculations

10W

10

19

Torsional Analysis

12W

10

4W

6W

10

20
21

Shop Detail
Drawings/Catalogues
Surface Preparation and Painting
Procedures

22

Welding Procedures / PQRs

6W

10

23

Test Procedures

16W
(Purchasers

10

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

:
:

SHEET NO. : REV.:


11 of 16
B02

AFTER ORDERING
ITEM
NO.

DESCRIPTION

AT THE
TIME
OF BID
Q/TYPE

DRAWINGS AND DOCUMENTS


Q/TYPE
(Note 1)

DEL. TIME
(Note 2)

Approval
shall be
obtained
one Month
before test)

PURPOSE
(Note 3)

FINAL
ISSUE
(Note 1)

10

10

AT THE
FINAL
INSP.
(Note 4)

24

Mechanical Run Test Procedure

25

Functional Test Procedure

26

P&IDs / PFDs

4W

10

27

Allowable Forces and Moments

6W

10

8W

10

6W

10

8W

10

8W

10

14W

10

12W

10

12W

10

10W

10

28
29
30
31
32
33

34

35

Piping Schematics & Piping


Layout Drawings (Plan &
Isometric)
Filled in Purchasers equipment
Data Sheets
Completed Noise Data Sheet
Completed Motor Data Sheets,
Electrical load / motor schedule
and control list (signal list)
Completed Instrument (ISA) Data
Sheets
Electrical & Instrument Wiring
Motor drawings such as outline,
performance curves, electric
wiring for Motor, Cubicle, Space
Heater, PT100, Leakage
Detector, etc.
Control and Instrument
Schematics

36

Control Panel / PLC / DCS Data

10W

10

37

Instrument Loop and Logic


Diagrams

10W

10

38

I/O list

12W

10

39

Instrument / Electrical Installation


Drawings

20W

10

40

Performance Curves / Data

4W

10

41

Bills of Materials / Parts List

14W

10

20W

10

20W

10

20W

10

X
X

42
43
44

Recommended Spare Parts for


Commissioning
Recommended Spare Parts for 2
years of Operation
Recommended Capital Spare
Parts

45

Special Tools List

8W

10

46

Utility Requirements

6W

10

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

:
:

SHEET NO. : REV.:


12 of 16
B02

AFTER ORDERING
ITEM
NO.

47
48
49
50

DESCRIPTION

Erection Drawings
Max Piece Weight and
Dimensional Data
Packing & Transportation
Procedure
Installation Operation &
Maintenance Manuals

AT THE
TIME
OF BID
Q/TYPE

DRAWINGS AND DOCUMENTS

AT THE
FINAL
INSP.
(Note 4)

Q/TYPE
(Note 1)

DEL. TIME
(Note 2)

PURPOSE
(Note 3)

FINAL
ISSUE
(Note 1)

20W

10

14W

10

40W

10

1M Before
Shipping

10

51

Material Test / NDE Certificates

20W

10

52

Hydrostatic / Mechanical Run/


Performance Test Certificates

1M Before
Shipping

10

53

Certified Test & Calibration


Reports

1M Before
Shipping

10

54

Motor Inspection & Test Report

1M Before
Shipping

10

55

Motor Certified for ExplosionProof, Increased Safety and


Intrinsically Safe Circuits

1M Before
Shipping

10

56

Mechanical Test Report

10

57

Manufacturers Data Books

10

58

List of Manufacturers Data Book

10

4W

10

4W

59
60

Quality Control Plan/Inspection


and Test Plan
Nonconformance Control and
Corrective action Procedure

1M Before
Shipping
1M Before
Shipping
1M Before
Shipping

61

Lubrication List

4W

62

Progress Report

Monthly

10

Notes:
(1) Qty=Quantity of documents paper copies, moreover one CD containing e-files of
submitted documents shall be included in each transmittal.
(2) W=Weeks after Order, WPD=Weeks Prior to Delivery
(3) R=for Review / Information, A=for Approval
(4) X=Documents to Be Submitted at the Final Inspection

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

8.3

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

:
:

SHEET NO. : REV.:


13 of 16
B02

Attachment #3: Scope of Supply and Work


Vendor's proposal shall include, but not be limited to, equipment, materials and works
Listed in below tables as Scope of Supply and Work.
Items marked with (X) shall be within Vendor's scope of supply. Those marked with (R)
shall be within Vendor's scope of supply if Vendor requires them. Meanwhile, those
marked with (S) shall be quoted separately by Vendor and shall be of Purchaser's
option. Price for items marked with * shall be broken down in Vendor's proposal.
A) Scope of Supply for Power Transformers

No.

Items

01-TR-1201,
01-TR-1202

01-TR-1401,
01-TR-1402,
01-TR-1403,
01-TR-1404

XX-TR-1401
~XX-TR-1409

XX-TR-1410
~XX-TR-1424

Quantity
Required by
Purchaser

Proposed
by Vendor
(Note 1)

2
(X)

( )

4
(X)

( )

9
(X)

( )

15
(X)

( )

Description
Power Transformer (33/40MVA)
ONAN/ONAF, oil immersed ,33/11.5kV, , %
impedance: 8, Dyn11, Temperature insulation
Class A,
25kA for 3 Sec.(Secondary), 1 CT for 64 and
1 CT for 51G, For the detail please refer to
the enclosed data sheet.
Power Transformer (2.5MVA) ONAN, oil
immersed , 6/0.42kV, % impedance: 7,
Dyn11, Temperature insulation Class A,
63kA for 1 Sec.(Secondary), 1 CT for 64 and
1 CT for 51G, For the detail please refer to
the enclosed SP12-2Y2-EL-DS-999- X-109.
Power Transformer (315kVA) AN, dry type,
33/0.42kV, % impedance: 4, Dyn11,
Temperature insulation Class B,
16kA for 1 Sec.(Secondary), For the detail
please refer to the enclosed data sheet
Power Transformer (100kVA) AN, dry type,
33/0.42kV, % impedance: 4, Dyn11,
Temperature insulation Class B,
16kA for 1 Sec.(Secondary), For the detail
please refer to the enclosed data sheet

Note 1: Vendor shall mark (X) for each item when accepting Purchasers requirements.

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


14 of 16
B02

B) Scope of Work

Items

Required
by
Purchaser

Proposed
by Vendor
(Note 1)

Engineering responsibility for all equipment


covered by this requisition

(X)

( )

Engineering and Documentation

(X)

( )

Manufacturing and assembling

(X)

( )

Mechanical Guarantee

(X)

( )

Performance Guarantee

(X)

( )

Sub-Vendors Coordination

(X)

( )

Inspection and testing at shop

(X)*

( )

Wiring and Tubing to Junction Box within


package

(X)

( )

Insulation and Personnel Protection

(X)

( )

10

Piping within the Package

(X)

( )

11

Painting
Prime Coats at Shop
Finish Coats at Shop

(X)
(X)

( )
( )

12

Packing and Marking


Export Packing
Rust Prevention
For Long Term (12 month)

(X)
(X)
(X)

( )
( )
( )

13

Shipping and Transportation to point of


delivery (according to delivery condition)

(X)

( )

14

Supervision for installation

(X)*

( )

15

Supervision for erection, commissioning


and start up

(X)*

( )

16

Shop and field training

(S)*

( )

17

Installation at site

( )

( )

18

Running test at site

(S)*

( )

No.

Remarks

Note 1: Vendor shall mark (X) for each item when accepting Purchasers requirements.

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

SHEET NO. : REV.:


15 of 16
B02

8.4

Attachment #4: Inspection Procedure Manual for Power Transformers

No

Inspection
Requirement/Check
Items

Acceptance Criteria

Witnessed/
Reviewed By

MFR's
Record
Certificate

1.

PRE-INSPECTION
MEETING

Applicable
specification and
data sheets

2.

VISUAL INSPECTION

Approved procedure
and drawings

SW

3.

DIMENSIONAL
INSPECTION

Approved procedure
and drawings

SW

Approved procedure

SW

Approved procedure

SW

OR

SW

OR

SW

SW

OR

OR

SW

SW

OR

SW

SW

OR

Approved procedure

OR

4.
5.
6.

INSULATION
RESISTANCE TEST
MEASUREMENT OF
WINDING RESISTANCE
MEASUREMENT OF
VOLTAGE RATIO

OR

Approved procedure

Approved procedure

Approved Procedure

OR

15. CONTROL PANEL TEST

Approved Procedure

OR

INDUCED
16. OVERVOLTAGE
WITHSTAND TEST

Approved procedure

OR

8.

9.
10.

11.
12.
13.

14.

OR

MEASUREMENT OF
NO-LOAD LOSS AND
CURRENT
MEASUREMENT OF
SHORT-CIRCUIT
IMPEDANCE AND LOAD
LOSS
DIELECTRIC
RESISTANCE TEST
TEST ON-LOAD TAP
CHANGERS, WHERE
APPROPRIATE
SEPARATE SOURCE
VOLTAGE WITHSTAND
TEST
MEASUREMENT OF
NOISE LEVEL
TEMPERATURE RISE
TEST
TYPE TEST RECORDS:
-IMPULSE TEST
-MEASUREMENT OF
ZERO SEQUENCE
IMPEDANCE
-THERMAL ABILITY TO
WITHSTAND SHORT
CIRCUIT
- SHORT CIRCUIT TEST

7.

Remarks

Approved procedure

Approved procedure
Approved procedure

Approved procedure

Approved procedure

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.

PROJECT:

SOUTH YARAN OIL FIELD


DEVELOPMENT PROJECT
DOCUMENT TITLE
DOCUMENT NO

No
17.
18.
19.
20.
21.

:
:

Material Requisition For Power Transformers


SYME-ELBASC-ENEL-RQMA-0001-B02

Inspection
Requirement/Check
Items
ASSEMBLING/DISASSE
MBLING
INSTRUMENT
CALIBRATION
CURRENT
TRANSFORMER TEST
PROTECTION DEVICES
LOOP TEST
PAINTING/PRESERVATI
ON INSPECTION

Acceptance Criteria

SHEET NO. : REV.:


16 of 16
B02

Witnessed/
Reviewed By

MFR's
Record
Certificate

OR

OR

Approved Procedure

OR

Approved procedure
and drawings

OR

No defect shall be
observed
Approved procedure
and drawings
Approved Procedure
and Drawings

Remarks

1-VENDOR SHALL SUBMIT MANUFACTURERS DATA RECORD AS REQUIRED.


2. NO WITNESSED INSPECTION IS REQUIRED FOR TRANSFORMER LESS THAN 1000V, ONLY
REVIEW OF INSPECTION AND TEST RECORDS.
3. RECORDS FOR ON-LOAD TAP CHANGER TO BE SUBMITTED.
4. ALL TRANSFORMERS ABOVE 1000KVA SHALL BE TESTED INDEPENDENT OF VOLTAGE
RANGE.
5. TEMPERATURE RISE TEST SHALL BE MADE ON THE UNIT OF EACH TRANSFORMER SIZE.
6. THE EQUIPMENT SHALL BE COMPLETELY SHOP-ASSEMBLED IN ORDER TO VERIFY THE
SPECIFIED FUNCTION AT SHOP ACCORDING TO DESIGN DATA, AND TO CHECK THE
ELECTRICAL SYSTEM. DISASSEMBLED PARTS MUST BE CLEARLY MATCH-MARKED FOR FIELD
RE-ASSEMBLING.
7. PER CASE OMISSION OF PIM CAN BE REQUESTED BY CONTRACTOR AND WAIVED BY CLIENT

This document is the property of OWNER. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.