You are on page 1of 3

XEROX

Kit Installation Instructions

Global Knowledge and Language Services

Xerox 4112/4127

Product(s):

Date:

COLOR SCANNER KIT OPTION

Title:
Instruction #:

604E40940

Tag/MOD #:

IOT 13

8/17/2007

Page:

1 of 3

Kit part # 498K16720


Classification code:

Purpose
To enable color scanning on the 4112 / 4127, for Color
Scan back capabilities.

a)

Kit Contents
Check the components contained in the kit.
Description
Quantity
LYRA3 PWB.

Memory DIMM (128mb)

Stand-off hardware

Installation Instructions

b)

a)

Prerequisites
System SW v1.0 or higher

Procedure
Read the entire procedure before you start the
removal activity.
WARNING
After turning OFF the copier, turn OFF the circuit
breaker and unplug the power cord and apply
Lockout Tag Kit
WARNING

Figure 1
__ 3.

If there is a DFE Enablement kit installed (tag


3) proceed to Step 4, otherwise continue with
step 6

__ 4.

Remove the BP PWB (Figure 2)


a) Remove the (4) screws
b) Carefully separate the BP PWB from the
DFE Interface and ESS PWBs by
moving it in the direction of the arrows

Use the ESD kit to handle the PWBs.

__ 1.

Remove the ESS Chassis/Green Controller


from the Printer per Step 2 (PL 2.5 and Item
1.)

__ 2.

Unplug all of the cables and connections


located on the side of the ESS Chassis on
the IOT (Figure 1)
a) Remove the (5) screws.
b) Pull the top handle to remove the ESS
Chassis and place on a flat work
surface.

NOTE: If this system has an OHCF attached, it will


be necessary to disconnect; un-dock and move the
feeder away from the IOT in order to pull the Green
Controller out.

BP PWB
Figure 2

XEROX
Kit part #:

498K16720

Instruction #:

604E40940

Date:

8/17/2007

__ 7.
__ 5.

Remove the (2) screws from the DFE


Interface bracket/PWB. (Figure 3)

Page:

2 of 3

Install the Memory DIMM (128M) supplied


with this kit in slot (Figure 5 DFE PWB shown
removed)
__ a.

Insert supplied DIMM

__ b.

Using finger, gently press downward


to secure the DIMM

Figure 3
__ 6.

Remove (1) screw and lift bracket and PWB


upward (Fig 4)

NOTE: Backplane PWB shown installed in photo,


but was removed in prior steps

DFE Interface PWB

Lift PWB upward

Figure 5

__ 8.

Perform steps 4 through 6 to reinstall the


DFE interface and BP PWBs if removed in
previous steps.

__ 9.

Install the LYRA3 PWB provided (Figure 6)

Note: Ensure the LYRA3 PWB is mated properly


prior to securing it to the ESS PWB in the following
steps.
__ a.

Remove / save the (1) screw. (Figure


6)

Remove (1) screw


Figure 4

Figure 6

XEROX
Kit part #:

498K16720
__ b.

Instruction #:

604E40940

Install the standoff included with the


kit in place of the screw. (Figure 7)

Date:

8/17/2007

Page:

3 of 3

Verifying operation
__ 1.

Reattach cabling removed in Step 2

__ 2.

Reinstall covers.

__ 3.

Remove the Lockout Tag device.

__ 4.

Connect the Power Cord.

__ 5.

Power ON the system.

__ 6.

Verify DADF / Scanner and System operation

__ 7.

Perform dC945 CCD calibration and White


Reference Adjustments.

__ 8.

Familiarize yourself with the added settings


in the Machine for the new Color Scan
Options:
SELECT: ALL SERVICES ICON

Figure 7

SELECT: SCAN TO PC
__ c.
__ d.

Mate the LYRA3 PWB to the ESS


PWB
Secure the LYRA3 PWB to the
Green Controller (1 screw removed
previously). (Figure 7)

Observe Color Scan selections.


__ 9.

If the Analyst Trainer or Customer IT person


or User with System Administrator Guide has
set up the Scan to Mailbox or Scan to FTP
function, verify Color scanning is working
correctly. If these features have not been set
up, proceed to Call CLOSE.

__ 10. Mark off IOT Tag # 13

Figure 7
__ 10. Reinstall the ESS Chassis in the card cage.
Ensure chassis engages 3 tabs at the top
when inserting.