Precedence of the Contract Documents
By Arthur F. O'Leary, FAIA, MRIAI

ClickHeretoSubscribeTodayforYourFREEDCDMagazine
Subscription
Errors in Construction Documents
Considering the extraordinary volume of data contained in the typical set of construction
documents, literally hundreds of thousands of information bits, it is surprising that we do not
see more errors, ambiguities, inconsistencies, and anomalies. Fortunately, most errors
encountered after the documents are released are trivial and cause no more than momentary
pause and possibly some degree of professional embarrassment to the architect, with little or
no economic or practical consequence to the owner or contractor.
Document Review Procedures
Properly managed architectural and engineering practices employ rigorous review procedures
and the work product is routinely checked at various stages of progress. Voluminous
comprehensive check lists are available, some produced by individual offices to reflect past
problems and hopefully to eliminate them in the future.
Document review should always be under the responsible supervision of competent qualified
senior personnel. Checking of drawings and specifications is not high on the list of favorite
tasks in an architects office, so it is easy to assign it to junior people. This could be one of
the costliest errors an office could make, as only a fully qualified architect or engineer is
likely to recognize sophisticated or complex errors, particularly those of omission.
The completed documents should be checked for compliance with the owners program and
instructions, applicable building codes, industry standards, and customary construction
procedures. Checking should also evaluate whether the documents, when executed in the
field, will effectively carry out the design intent. The checker should always make sure that
the documents reflect the proper use of materials and that the structural and other systems
are practical, economical, and constructable. One of the most important aspects of document

review is checking for physical coordination among the various engineering and design
disciplines. It is also necessary to confirm that all engineering recommendations are carried
out on the drawings and in the specifications.
The final review before release of the documents for contract bidding should be
comprehensive and thorough. Regardless of the scope, depth, and quality of document review,
however, it is inevitable that some level of error or inconsistency will remain undetected.
Errors in General
Documentation errors that consist of erroneous entries or notations, such as wrong materials,
faulty methods, or inaccurate dimensions, cannot be automatically resolved by the adoption of
some agreed formula or course of action. The same is true of errors of omission. These types
of errors, when found, must be resolved by an architects considered decision clarifying what
should be done, and who will pay for it.
Errors that are discovered by or brought to the attention of the architect during the bidding
period can be easily dealt with by prompt consideration of the technical problem and issuance
of an appropriate addendum to the affected document. Most of the remaining errors will
usually be discovered during the construction period. However, some will remain undetected
to surface years later or possibly never.
Errors of Inconsistency
Other errors will be in the form of inconsistencies between the various elements of the
contract documents. For example, the specifications might not agree with the drawings or the
agreements in some respect. However, some inconsistencies and conflicts will occur within a
single document. For example, one segment of the specifications does not agree with another,
or the floor plan is not in accord with a cross section.
This discussion will be limited to those anomalies that are manifested by conflicting
requirements in two or more of the contract documents or within a single document. These
inconsistencies could sometimes be easily resolved if the documents could be ranked in a
hierarchical order of authority. This would be simple and effective for some types of
inconsistency.
For example, if the specifications stated that a certain large group of light bulbs is to be 300
watts and the lighting fixture schedule on the electrical drawings required 500 watts, then the
higher ranked document would govern. However, this settles only the contractual obligation of
the contractor allowing other problems to remain unresolved. For example, if the drawings

were designated as governing, then the 500 watt bulbs would have to be supplied by the
contractor. However, if the 500 watt designation is incorrect then the contractor must be
redirected to supply 300 watt bulbs and issue a credit for the difference in cost between 500
watt and 300 watt bulbs. But if the error is not discovered until after the 500 watt bulbs have
already been installed, then the contractor must be reimbursed for the extra costs of
relamping, restocking (if allowed by the supplier), supervision, overhead, and profit. The
credit for changing to smaller bulbs will be consumed or exceeded by the associated costs.
Some will point out that this problem could have been prevented altogether if the same
information had not been given in two places, that the bulb size should be shown in the
lighting fixture schedule on the drawings and eliminated from the specifications, or vice versa.
This is undoubtedly true for this example and is good advice generally. However, other
situations often arise where the inconsistency is more difficult to perceive. For example,
where an industry standard, code, or regulation is cited in the specifications and the size,
gauge, thickness, or some other quality shown on the drawings is inconsistent with the cited
standard, code, or regulation.
Priority of Documents
There is no universally accepted general principle that dictates the priority of one document
over another. The only way that one document will take precedence over another is if that is
spelled out in the contract. If a contract is silent on the subject, then no document governs.
The concept of establishing a hierarchy of documents has never been embraced by the
committees of architects that are responsible for authoring the AIA General Conditions down
through the years. On the contrary, the AIA recommends that a precedence of documents not
be established, but rather it should be provided that all documents are complementary. What
is required by one document is as binding as if required by all. (Note 1)
This does not directly resolve the problem of inconsistent or conflicting requirements but
instead requires the architect to make a determination taking into account all relevant factors
gleaned from anywhere in the documents or reasonably inferable from them. The architects
decision must determine what the contractor is obligated to do and what adjustment, if any,
is to be made in the contract price or time. This is the acid test of an architects ability to be
fair to both owner and contractor.
The AIA, recognizing that occasionally some situations require a precedence of documents to
be established, in its Guide for Supplementary Conditions, recommends a priority ranking of
the documents followed by a requirement that in case of inconsistencies in or between

drawings and specifications, the higher cost condition should govern. (Note 2)
The recommended order of precedence considers the drawings and specifications to be of
equal authority, and they are last after all other documents. The final paragraph which relates
only to inconsistencies between the drawings and specifications settles only the matter of
controlling the contractors obligation for price and time but does not settle the issue of which
requirement is correct or proper to be carried out. When the error is not discovered until after
the questioned work is completed, the contractor must be paid all extra costs of changing
from the more stringent or costly condition to the correct one. The paragraph apparently does
not apply to inconsistencies between or among these two documents and the others listed. It
also fails to answer the question of inconsistencies among the other documents.
Most architects who feel that it is preferable to have a precedence of documents provision in
their contract documents tend to favor drawings over specifications, while construction
attorneys seem partial to the agreement over all other documents. Apparently each is more
trusting of the documents with which they are most familiar or have the most control over.
Some architects specify that largescale drawings will take precedence over smallscale
drawings and that figured dimensions take priority over scaled dimensions. The architect still
must decide which document is correct when the one of highest precedence is clearly wrong.
The architects decision becomes difficult when the contractor has already carried out
incorrect work while following the governing document of highest precedence, all the while
unaware that the correct information is elsewhere in the documents.
Rules made in a contract to provide which of two inconsistent contract requirements should
govern do not always neatly settle the issue. For example, a rule that the most costly
condition or most stringent condition will govern would be impossible to apply to an erroneous
location dimension, an incorrect door swing, or a wrong color.
Interpretation Must Be Credible
Obviously incorrect typographic or clerical errors must be interpreted reasonably. No
contractor can be considered credible when claiming to be misled by a 40inch thick concrete
floor slab requirement that is obviously intended to be 4 inches thick, or by a number 30 steel
reinforcing bar that is obviously meant to be a number 3 steel bar. Neither is the owner to be
taken seriously when demanding that the contractor furnish the 40inch thick concrete slab or
the number 30 steel bars or requests a monetary credit in lieu thereof.
Architects Interpretations

Architects who are required to render interpretations and make decisions resolving
inconsistencies or conflicts between or among the documents must stay meticulously within
the contractual guidelines of A2012007, Paragraph 1.2, Correlation and Intent of the Contract
Documents.
Regardless of what the architect had in mind, or intended to include in the documents, the
decision and all inferences must be based on what can be actually found in the contract
documents. The architectdecisionmaker, being also the author responsible for the
inconsistent or erroneous documents, must at all costs guard against selfserving rulings.
Sometimes a fair ruling must be in favor of the contractor and against the owner. If this
precipitates some problem between the architect and client, then this is a matter that they
will have to resolve between themselves. It is of no concern to the contractor and should not
enter into the architects decision regarding the contractual relationship between the owner
and contractor. The contractor should not under any circumstances be required to pay for the
architects errors. In determining what is reasonably inferable from ambiguous, inconsistent,
erroneous, or incomplete documents, the architect must exercise impartial judgment based on
a credible and plausible analysis justified by the actual state of the documents. This decision
will be final and binding upon the parties if not appealed to mediation or arbitration within
the time limits in A2012007, Article 15, Claims and Disputes.
If the architects determination is not sustainable from evidence that can be found in the
contract documents, fair, knowledgeable, and reasonable arbitrators will find no difficulty in
overturning or amending the architects decision in their award. (Note 3)

Notes
1. General Conditions of the Contract for Construction, A2012007, Paragraph 1.2 Correlation and Intent of
the Contract Documents: The intent of the Contract Documents is to include all items necessary for the
proper execution and completion of the Work by the Contractor. The Contract Documents are
complementary, and what is required by one shall be as binding as if required by all; performance by the
Contractor shall be required only to the extent consistent with the Contract Documents and reasonably
inferable from them as being necessary to produce the intended results.
2. Guide for Supplementary Conditions, AIA Document A511, Fourth Edition, 1987, where an order of
precedence is required, suggests the following: In the event of conflicts or discrepancies among the
Contract Documents, interpretations will be based on the following priorities:
1) The Agreement,
2) Addenda, with those of later date having preference over those of earlier date,
3) The Supplementary Conditions,
4) The General Conditions of the Contract for Construction,

5) Drawings and Specifications. In the case of an inconsistency between Drawings and Specifications or
within either Document not
clarified by addendum, the better quality or greater quantity
of Work shall be provided in accordance with the Architects
interpretation.
3. This article is based on a similar article in the March/April 1997 issue of Design Cost Data.