cable to make it possible for a new node to be installed to serve 350 HHP and relieve congestion.
1480 1380
Service provisioning was required through a coax
New Node
temporary cable.
The temporary needed to cross a two-lane avenue
and an apartment complex parking lot.
548
The .700 cable was installed under an 8-lane
boulevard Florida State Road 820.
Complication:
Four inches of rain fell during the 3.5 hour core
ejection and fiber jetting project. 234
How the Work Proceeded:
The object of installing a new node was to transfer 350
Aerial to Underground Fiber
598 398
HHP from a node at Pines Boulevard and SW 145th
Ave. which was serving several apartment complexes
350
and several commercial customers totaling ~1200 HHP.
Deep Fiber Solutions first installed temporary service using an RG11 cable which passed over 134th Avenue and a parking lot trees provided a safe clearance height to the site of the new node location. Then the Deep Fiber Solutions team established the vault located on the north side of Pines Boulevard as the injection point for two spans of cable totaling 782 ft. before fiber slack. In a torrential downpour the team ejected a 234 ft. span at the riser on the South side of Pines Blvd. and ejected a 548 ft. span at the new node location, the 350 HHP apartment complex. Deep Fiber Solutions then blew a new 12-count micro-core fiber cable from the riser to the new node location for a total of 1050 feet including splicing fiber slack. Using a polyethylene sleeve, the Deep Fiber Solutions team had earlier joined the two spans together to avoid a splice or figure-eighting at the vault. Once fiber blowing was completed the new node was spliced in and the temporary was removed the same day.
Results:
All node split work core ejection, fiber jetting and
splicing was completed in less than a single day.
Two brief service interruptions, to install and remove
temporary service, were unnoticed by customers, taking less than 60 seconds each.
A lengthy permitting process to bore
under Pines Blvd. was avoided.
Core ejection saved the cable operator
58% contrasted with typical construction techniques.
Risks associated with boring a major
highway, including the potential for damaging utilities or the roadway itself and traffic issues, were avoided.