You are on page 1of 19

Design of A.P.M.

Name of work :Name of outlet :-

pkn
gip
TECHNICAL DATA
Sn.
1
2
3
4
5
6
7
8

Design summary :Opning of gate


Water head

Item
DISCHARGE
F.S.D
F. B. in canal
SIDE SLOPE
N.S.L.
CBL
FSL
TBL

bt x y =
Hs
=

0.58
fsd=
d

fb= 0.20
fsd= 0.38

CANAL
0.1179
0.38
0.20
1
271.72
260.63
261.01
261.21

OUTLET
0.0254
----:1
271.72
260.630
-----

0.22

0.10
0.11

meter
meter
meter
meter

mtr

C.C. coping
R.C.C.slab
A.P.M. cast iron gate
1.60
4.80
4.00
0.11

Apm sill level


Bed level 260.63
0.05

Cumec
Cumec
meter

R.R. stone masonry super


1 IN 15

0.22

R.R.Stone masonry foundation

0.50

C.C1:3:6

0.30

center line x-section

A.P.M. cast iron gate


8.38
0.40

0.40
0.40
0.60

0.58

0.40
4.00

1.00

0.60

0.40
0.10

0.30

0.30
0.40

0.30
Plan

0.80

U/S x- section of canal

pk_nandwanayahoo.co.in

DESIGN of A.P.M.

Name of work :Name of outlet :Sn.


1
2
3
4
5
6
7
8
9
10

pkn
gip
TECHNICAL DATA
Item
CANAL
DISCHARGE
0.1179
F.S.D
0.38
F. B. in canal
0.20
SIDE SLOPE
1
N.S.L.
271.72
CBL
260.63
FSL
261.01
TBL
261.21
W/C length
Foundation Depth (below CB

for proportionality
Hs/D
or
Hs =0.30xD

=
=

Now q= 4.04*Bt*Y*(Hs)1/2
from discharge equation Bt*Y=
Keeping

then

Bt=
Y=
Bt=
Y2 =
Y=(
Bt=

Say

Bt=

Keep
or

Minimum Modular Head =0.82Hs-Bt/2 =

Hs

0.30
0.30

OUTLET
0.0254
----:1
271.72
260.630
----15
0.50

or Bt*Y =
0.0254 /
0.045
0.01896
Y
2.5
0.047
0.220

0.82

Check for passing descharge

meter
meter
meter
meter
meter
meter

=
=
=
=

0.11

q/4.04/Hs^1/2
4.04 /( 0.11 )^0.5 =

/
0.045 =
/
2.50
x 0.01896 =
)2= 0.22
/
2.5
=

0.10

Hm

0.38

Cumec
Cumec
meter

0.110

0.110 0.0698 <

0.42

>

0.09

to

/2

0.040

pk_nandwana@yahoo.co.in

=
=
=
=

0.088

0.10

0.040
0.15 hence ok

4.04 x
0.10
0.02948 Cumec

260.680
0.11
0.10
0.22

0.14

0.047

Passing discharge is grater than required discharge


0.02948 >
0.0254
Hence OK.
Design Sill level of out let
Hs
Bt
Y

0.01896

0.22

x(

0.11

NAME OF WORK :-APM FOR CHAK

0
RCC 1:1.5:3

TBL

0.58
fb= 0.20
fsd= 0.38

0.58

1.60
0.11

1 :1

0.22

APM sill level

TBL W/C
FSL W/C
0.050
3 :1

4.80
1 IN 15

0.05

0.50

CBL 260.63
0.50
Foundation level
0.30

0.30

CROSS SECTION

0.15
0.30

X-X

4.00

1.00

###

###

0.58

###

8.38
A
0.60 0.60

###

0.60
0.40
0.30

###

0.40
0.10
0.40

###

###

0.60

1:5

###

0.60

B.W.

Data
1
1 :1

:1

bt
1.00

1.5
U/S X section of canal

pk_nandwana@yahoo.co.in

###

0.60

f.s.d.+ f.b.

15 m

0.58
1.00

0.50
*.*.*.*.*.*.*.*.*.*.*.*..* 0.30
2.00 + bt
X- section at AA

0.08

1
2
3
4
5

NSL
BL
FSL
TBL
Foundation lev

APM
#REF!
260.63
260.85
261.21
#REF!

DETAIL
NAME OF WORK :-APM FOR CHAK

Sno.
Item
1 Excavation
including
loading
unloading
disposal and dressing of excavated earth
within initial lead of 50m and lift upto 1.5m in
dry or moist including drsssing of excaveted
area, dewatering wherever required and all
applicable taxes and levies etc. complete in all
respect.
canal Sides slope
Bank top
Berral
expantion
D/s wing wall
connecting to water course

Detail

1
1
1
1
1
1

x
x
x
x
x
x

0.58
1.60
4.00
1.00
0.40
15.00

x
x
x
x
x
x

2.00
2.00
2.00
2.00
1.90
2.00

x
x
x
x
x
x

For

qty

1.43
1.43
1.43
1.43
1.43
1.43
1.00

A.Hard soil mixed with kanker/ boulders ,


morrum .

/
/

2
2
total
No

=
=
=
=
=
=
=

0.83
4.58
11.44
2.86
1.09
42.90
63.69
63.70
cum
16.00

25

% qty taken

25
25
25

% qty taken
% qty taken
% qty taken

16.00
16.00
16.00
cum

=
=
=
=
=
=

0.35
0.96
2.40
0.60
0.23
9.00
13.54
13.60
cum

2 Earth work in excavation including loading


unloading, disposal and dressing of excavated
rock within initial lead of 50 m and lift upto 1.50
m indry or moist including dressing of
excavated area wirh cost of dewatering
wherever required and all applicable taxes
and . levies etc. complete in all respect.
(B)Soft disintegreted rock.
(C)Hard rock not rquirding blasting
(D) Phylites & other hard rockrequiring nominal
blasting

2 Cement Concrete in (1:3:6) M10 well mixed


and laid in position complete including all leads
of all construction materiasl Including Curing
and finishing having well graded broken stone
aggregate of maximum size upto 20mm
canal Sides slope
Bank top
Barrel
expansion
D/s wing wall
connecting to water course

1
1
1
1
1
1

x
x
x
x
x
x

0.58
1.60
4.00
1.00
0.40
15.00

x
x
x
x
x
x

2.00
2.00
2.00
2.00
1.90
2.00
For

x
x
x
x
x
x

0.30
0.30
0.30
0.30
0.30
0.30
1.00

total
No

3 R.R. Stone masonry (using R.R stones where


75% stone to be not less than 15 cm in size in
any direction and weighing not less than 23
kg.) for Foundation including curing all leads
of construction materials & all taxes and with
initial lift /delift of 5 m from G.L.etc complete .In
cement sand mortar 1:5
canal Sides slope
Bank top
Barrel
D/s wing wall
connecting to water course

1
1
1
1
1

x
x
x
x
x

0.58
1.60
4.00
1.40
15.00

x
x
x
x
x

2.00
2.00
2.00
2.00
2.00

x
x
x
x
x

For

0.50
0.50
0.50
0.50
0.50
1.00

=
=
=
=
=
total
No

0.58
1.60
4.00
1.40
15.00
22.58
22.60

4 R.R. Stone masonry (using R.R stones where


75% stone to be not less than 15 cm in size in
any direction and weighing not less than 23
kg.) for Superstructure including curing all
leads of construction materials & all taxes and
with initial lift /delift of 5 m from G.L.etc
complete .In cement sand mortar 1:5
canal Sides slope

2 x 0.58 x( 1.00

Bank top

1 x 1.60 x( 1.00

Barrel

1 x 4.00 x( 1.00

D/s wing wall

1 x 1.40 x( 1.00

connecting to water course

1 x 15.00 x( 1.00
For

+
2
+
2
+
2
+
2
+
2

0.40 )x 0.66 =
2
0.40 )x 0.66 =

0.27

0.40 )x 0.45 =

1.26

0.40 )x 0.45 =

0.44

0.40 )x 0.45 =
total
1.00
No
=

4.73
7.43
7.50
cum

0.73

5 Cement Concrete in (1:2:4) M15 well mixed


and laid in position complete including all leads
of all construction materials Including Curing
and finishing having well graded broken stone
aggregate of maximum size upto 20mm
APM length + Berral
connecting to water course

1 x 7.58 x
1 x 15.00 x

0.66
0.66
For

6 Plaster in cement sand mortar (1:4) including


raking of joint ,smooth finishing with & curing
etc. including all leads of all construction
matarials complete of thickness, 20mm

x 0.050
x 0.050

=
=

1.00

total
No
=

0.25
0.49
0.74
0.80
cum

u/s inside
Barrel inside
Expansion inside
D/s wing wall inside
connecting to water course inside

2
2
2
2
2
2

x
x
x
x
x
x

0.58
1.60
4.00
1.40
0.80
15.00

x
x
x
x
x
x

0.66
0.66
0.45
0.45
0.45
0.45

For

=
=
=
=
=
=

1.00

total
No
=

1.00

=
total
No
=

9.0
9.00
9.00
sqm

=
=
=

0.66
0.96
6.54
8.16
8.20
sqm

7 Flush and ruled pointing on stone masonry


including raking of joint and curing etc.
complete including of all leads of all
construction materials in cement mortar 1:3
connecting to water course out side

2 x 15.00 x

0.30
For

0.38
2.10
3.60
1.26
0.72
13.50
21.56
21.60
sqm

8 Providing and laying cement concrete copping


in (1:2:4) with maximum size of crusher broken
aggregate upto 20mm including shuttering etc
with all leads of material complete in all
respect.in thickness of 50 mm
u/s
U/p& d/s wing wall
side wall

2 x 0.82
4 x 0.60
2 x 8.18

x
x
x

For

Centering and shuttering for slabs, beams,


9 lintels,columns,trough with or with out caps
and base including proping and remove.
(Rates as per BSR 2006 page 44 item 2)
for slab

0.40
0.40
0.40

2 x
2 x
1 x

4.80 x
0.90 x
4.80 x

1.00

total
No
=

1.00

Total
No

=
=
=
=
=

1.44
0.27
1.44
3.15
3.20
sqm

total
No

=
=
=

0.65
0.65
0.70
cum

0.15
0.15
0.30
For

10 Cement concrete (1:1 :3 ) M-20 well mixed


1/2
and laid in position complete including of all
leads of all construction materials including
curing and finishing having well graded broken
stone aggrigate of maximum size upto
for slab

4.80 x

0.90 x
For

11

Supplying of M.S. reinforcement including


labour charges for bending binding and placing
in position all reinforcement as per drawing
including cost of binding wire and all leads and
lifts using .

0.15
1.00

Supplying of M.S. reinforcement including


labour charges for bending binding and placing
in position all reinforcement as per drawing
including cost of binding wire and all leads and
lifts using .
(II) Tor or ribed bars (IS:1139 &IS: 1786)
for slab main 12mm @300c/c
distribution
8mm @300c/c

Nos length
wt/m
17 x
0.90 x 0.888
4 x
4.80 x 0.395
total
10 %cutting & over lapping
For

12 Extra labour charges for obstruction in laying


and placing the reinforced cement concrete
due to reinforecement.for slab

1.00

as per item no 10

13 Supplying and fixing in Position of APM block


made of C.I. as per standard specification with
adjustable arrangment and required fixture
including transportation to site second stage
concreting in C.C.(1:2:4) centreing shuttering
painting with red oxide finishing etc. complete
in all respect cost of A.P.M. block (all size) per
block.

total
No

=
=
=
=
=
=

13.59
7.58
21.17
2.12
23.29
24.00
Kg

0.70
cum

1
Nos

32.00
cum

for out let


14 Re-handling of excavated material including
loading unloading and dressing within initial
leads of 50 m and lift 1.5 m with cost of dewatering wherever required and all applicable
taxes and levies etc complete in all respect.

50 % of item no 1

ABSTRACT OF COST
NAME OF WORK :-APM FOR CHAK
Sno.
Item
1 Excavtion including loading unloading , disposal and dressing
of excavated earth with in initial leads of 50 m and lift upto
1.50 m in dry or moist including dressing of excavated area,
de-watering wherever required and all applicable taxes and
levies etc. complete in all respect.

Qty

Rate

Unit

Amount

63.70

47.00

Cum

2994.00

16.00
16.00

78.00
121.00

Cum
Cum

1248.00
1936.00

16.00

166.00

Cum

2656.00

13.60

2105.00

Cum

28628.00

22.60

1618.00

Cum

36567.00

7.50

1660.00

Cum

12450.00

(Rates as per BSR 2008 page 13 item No1)


A.Hard soil mixed with kanker/ boulders,morrum .
2

Earth work in excavation


including loading unloading,
disposal and dressing of excavated rock within initial lead of
50 m and lift upto 1.50 m indry or moist including dressing of
excavated area wirh cost of dewatering wherever required
and all applicable taxes and . levies etc. complete in all
respect.
(Rates as per BSR 2008 page 13 item No1)
(B)Soft disintegreted rock.
(C)Hard rock not rquirding blasting
(D) Phylites & other hard rock requiring nominal blasting

3 Cement concrete (1:3:6 ) M-10 well mixed and laid in position


complete including of all leads of all construction materials
including curing and finishing having well graded broken
stone aggrigate of maximum size upto 20mm
(Rates as per BSR 2008 page 22 item no 6d)
4 Random rubble stone masonry kharanja (Using R.R. stones
where 75% stones to be not less than 15 cm in siz in any
direction and weighing not less 23 kg) for foundation
including curing all leads of all construction materials & all
taxes and with initial lift / de lift of 5 m from ground level etc.
complete .in 1:5 cement mortar.
(Rate as per BSR 2008 page 29 item 4)
5 Random rubble stone masonry kharanja (Using R.R. stones
where 75% stones to be not less than 15 cm in siz in any
direction and weighing not less 23 kg) for superstructure
including curing all leads of all construction materials & all
taxes and with initial lift / de lift of 5 m from ground level etc.
complete .in 1:6 cement mortar.
(Rate as per BSR 2008 page 29+31 item 4+13a)
6 Cement concrete (1:2:4 ) M-15 well mixed and laid in position
complete including of all leads of all construction materials
including curing and finishing having well graded broken
stone aggrigate of maximum size upto

Cement concrete (1:2:4 ) M-15 well mixed and laid in position


complete including of all leads of all construction materials
including curing and finishing having well graded broken
stone aggrigate of maximum size upto
(Rates as per BSR 2008 page 22 ch 7 item no 5d)
0.80

2509.00

Cum

2007.00

7 Plaster in cement sand mortar ( 1:4 ) including raking of


joints, smooth finishing with sandla & curing etc.complete
including of all leads of all construction materials : thickness :
20mm
(Rate as per BSR 2008 page no 34 item 4c)
21.60

94.00

Sqm

2030.00

8 Flush and ruled pointing on stone masonry including raking


of joints and curing etc.complete including all leads of all
construction materials in mortar ratio.
(Rate as per BSR 2008 page no 35 item 15c)
9.00

52.00

Sqm

468.00

8.20

185.00

p sqm

1517.00

10 Centering
and
shuttering
for
slabs,
beams,
lintels,columns,trough with or with out caps and base
including proping and remove.
(Rates as per BSR 2008 page 36 item 2)
3.20

131.00

Sqm

419.00

11 Cement concrete (1:1 :3 ) M-20 well mixed and laid in


1/2
position complete including of all leads of all construction
materials including curing and finishing having well graded
broken stone aggrigate of maximum size upto
(Rates as per BSR 2008 page 22 ch 7 item no 4d)
0.70

2951.00

Cum

2066.00

55.00

Kg.

1320.00

111.00

Sqm

78.00

5966.00

per block

5966.00

9 Providing and laying cement concrete copping in (1:2:4) with


maximum size of crusher broken aggregate upto 20mm
including shuttring etc. with all leads of material complete in
all respect in thickness of:75mm
(Rate as per BSR 2008 page 43 ch 12 item 17a)

12 Supplying of M.S. reinforcement including labour charges for


bending binding and placing in position all reinforcement as
per drawing including cost of binding wire and all leads and
lifts using
(II) Tor or ribed bars (IS:1139 &IS: 1786)
24.00
.(Rates as per BSR 2008 page 37 item 10(b)
13 Extra labour charges for obstruction in laying and placing the
reinforced cement concrete due to reinforecement.
Columns, slabs, cantilevers, projections, stairscase, lintels,
beams, chajjas, retaining walls, piers, abutments, galleries,
arch covers bed plates sluice capastan bases etc.
0.70
(Rates as per BSR 2008 page 37 item 11b)
14 Supplying and fixing in Position of APM block made of C.I.
as per standard specification with adjustable arrangment and
required fixture including transportation to site second stage
concreting in C.C.(1:2:4) centreing shuttering painting with
red oxide finishing etc. complete in all respect cost of A.P.M.
block (all size) per block.

(Rate as BSR 2008 page 44 ch 12 item 22)


15 Re-handling of excavated material including loading
unloading and dressing within initial leads of 50 m and lift 1.5
m with cost of de-watering wherever required and all
applicable taxes and levies etc complete in all respect.
(Rates as per BSR 2008 page14 ch 5 item 8)
Mixed Strata muck
32.00
Add

52.00

Cum
Total
% contengency
G Total
Say Rs.
1.08

1664.00
104014.00
3120.00
107134.00
lacs

29

350

44

64

64

64

ABSTRACT OF COST
NAME OF WORK :-APM FOR CHAK
1
2
3

NIT No.
NIT Amount
Earnest money

4
5
6
7
8
9

Tender cost
Date of Selling Tender
Date of Receiving Tender
Date of Opening Tender
Time of completion
B.S.R.

Sno.
Item
1 Excavtion including loading unloading , disposal and
dressing of excavated earth with in initial leads of 50 m
and lift upto 1.50 m in dry or moist including dressing of
excavated area, de-watering wherever required and all
applicable taxes and levies etc. complete in all respect.

7/2008-09 S.No.32
Rs.
1.05
1.Regd. Contractor @1/2%Rs.
2.Other Contractor @ 2%Rs.
Rs. 200
15.09.08 to22.09.08
24.09.08 upto 3.00 PM
24.09.08 At 4.00 PM
4 Month
Irrigation BSR 2008

530.00
2100.00

Qty

Rate

Unit

Amount

63.70

47.00

Cum

2994.00

16.00
16.00
16.00

78.00
121.00
166.00

Cum
Cum
Cum

1248.00
1936.00
2656.00

13.60

2105.00

Cum

28628.00

22.60

1618.00

Cum

36567.00

(Rates as per BSR 2008 page 13 item No1)


A.Hard soil mixed with kanker/ boulders,morrum .
2

Earth work in excavation including loading unloading,


disposal and dressing of excavated rock within initial
lead of 50 m and lift upto 1.50 m indry or moist including
dressing of excavated area wirh cost of dewatering
wherever required and all applicable taxes and . levies
etc. complete in all respect.
(Rates as per BSR 2008 page 13 item No1)
(B)Soft disintegreted rock.
(C)Hard rock not rquirding blasting
(D) Phylites & other hard rock requiring nominal blasting

3 Cement concrete (1:3:6 ) M-10 well mixed and laid in


position complete including of all leads of all
construction materials including curing and finishing
having well graded broken stone aggrigate of maximum
size upto 20mm
(Rates as per BSR 2008 page 22 item no 6d)
4 Random rubble stone masonry kharanja (Using R.R.
stones where 75% stones to be not less than 15 cm in
siz in any direction and weighing not less 23 kg) for
foundation including curing all leads of all construction
materials & all taxes and with initial lift / de lift of 5 m
from ground level etc. complete .in 1:5 cement mortar.
(Rate as per BSR 2008 page 29 item 4)
5 Random rubble stone masonry kharanja (Using R.R.
stones where 75% stones to be not less than 15 cm in
siz in any direction and weighing not less 23 kg) for
superstructure
including curing all leads of all
construction materials & all taxes and with initial lift / de
lift of 5 m from ground level etc. complete .in 1:6 cement
mortar.

Random rubble stone masonry kharanja (Using R.R.


stones where 75% stones to be not less than 15 cm in
siz in any direction and weighing not less 23 kg) for
superstructure
including curing all leads of all
construction materials & all taxes and with initial lift / de
lift of 5 m from ground level etc. complete .in 1:6 cement
mortar.

7.50

1660.00

Cum

12450.00

Cement concrete (1:2:4 ) M-15 well mixed and laid in


6 position complete including of all leads of all
construction materials including curing and finishing
having well graded broken stone aggrigate of maximum
size upto
(Rates as per BSR 2008 page 22 ch 7 item no 5d)

0.80

2509.00

Cum

2007.00

7 Plaster in cement sand mortar ( 1:4 ) including raking of


joints, smooth finishing with sandla & curing
etc.complete including of all leads of all construction
materials : thickness : 20mm
(Rate as per BSR 2008 page no 34 item 4c)

21.60

94.00

Sqm

2030.00

8 Flush and ruled pointing on stone masonry including


raking of joints and curing etc.complete including all
leads of all construction materials in mortar ratio.
(Rate as per BSR 2008 page no 35 item 15c)

9.00

52.00

Sqm

468.00

8.20

185.00

p sqm

1517.00

10 Centering
and
shuttering
for
slabs,
beams,
lintels,columns,trough with or with out caps and base
including proping and remove.
(Rates as per BSR 2008 page 36 item 2)

3.20

131.00

Sqm

419.00

Cement concrete (1:11/2:3 ) M-20 well mixed and laid in


11 position complete including of all leads of all
construction materials including curing and finishing
having well graded broken stone aggrigate of maximum
size upto
(Rates as per BSR 2008 page 22 ch 7 item no 4d)

0.70

2951.00

Cum

2066.00

24.00

55.00

Kg.

1320.00

(Rate as per BSR 2008 page 29+31 item 4+13a)

9 Providing and laying cement concrete copping in (1:2:4)


with maximum size of crusher broken aggregate upto
20mm including shuttring etc. with all leads of material
complete in all respect in thickness of:75mm
(Rate as per BSR 2008 page 43 ch 12 item 17a)

12 Supplying of M.S. reinforcement including labour


charges for bending binding and placing in position all
reinforcement as per drawing including cost of binding
wire and all leads and lifts using
(II) Tor or ribed bars (IS:1139 &IS: 1786)
.(Rates as per BSR 2008 page 37 item 10(b)
13 Extra labour charges for obstruction in laying and
placing the reinforced cement concrete due to
reinforecement.

Columns, slabs, cantilevers, projections, stairscase,


lintels, beams, chajjas, retaining walls, piers, abutments,
galleries, arch covers bed plates sluice capastan bases
etc.
(Rates as per BSR 2008 page 37 item 11b)
14 Supplying and fixing in Position of APM block made of
C.I. as per standard specification with adjustable
arrangment and required fixture including transportation
to site second stage concreting in C.C.(1:2:4) centreing
shuttering painting with red oxide finishing etc. complete
in all respect cost of A.P.M. block (all size) per block.

0.70

111.00

Sqm

78.00

5966.00

per block

5966.00

32.00

52.00

(Rate as BSR 2008 page 44 ch 12 item 22)


15 Re-handling of excavated material including loading
unloading and dressing within initial leads of 50 m and
lift 1.5 m with cost of de-watering wherever required and
all applicable taxes and levies etc complete in all
respect.
(Rates as per BSR 2008 page14 ch 5 item 8)
Mixed Strata muck

Say Rs.

Cum
Total
1.05

1664.00
104014.00
lacs

DESIGN OF OUTLET
Name of work:-Construction of L.M.C. from 25 km to 38.715 km.

S.No. R.D.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

26295
27480
28255
28845
30245
31035
32055
32825
33330
33810
34495
34785
36245
36995
38020
38700

Name of
out let
7L
8L
9L
10L
11L
12L
13L
14L
15L
16L
17L
18L
19L
20L
21L
22L

G.C.A. in C.C.A. in
hact.
hact.
85.95
70.909
95.525
90.255
98.48
103.65
74.44
74.96
67.59
72.49
80.197
86.434
79.109
68.888
97.506
73.776

82.446
60.675
88.126
82.433
78.25
88.26
61.85
73.5
67.29
71.46
76.125
80.03
69.18
55.065
90.087
72.009

CANAL DATA

Design of outlet

Discharge of
out let in
cusec

C.B.L.

F.S.L.

N.S.L.

Bt

Ya

0.0288
0.0212
0.0308
0.0288
0.0273
0.0308
0.0216
0.0257
0.0235
0.0249
0.0266
0.0279
0.0241
0.0192
0.0314
0.0251

270.78
270.55
270.46
270.34
269.9
269.67
269.33
269.07
268.9
268.83
268.6
268.58
267.09
266.84
264
263.77

271.64
271.41
271.25
271.13
270.68
270.45
270.11
269.85
269.68
269.52
269.28
269.19
267.7
267.45
264.61
264.38

271.72
272.27
271.5
271.4
269.81
270.22
270.94
269.6
269.4
270.07
269.38
269.09
267.25
267.15
264.16
264.7

0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

Head (Hs)=
q2/(4.04*bt*y)2
=q2/0.0036

0.23
0.12
0.26
0.23
0.20
0.26
0.13
0.18
0.15
0.17
0.19
0.21
0.16
0.10
0.27
0.17

Fixing
R.L.(outlet
bed level)

271.26
271.14
270.84
270.75
270.33
270.04
269.83
269.52
269.38
269.20
268.94
268.83
267.39
267.20
264.19
264.06

DESIGN OF OUTLET (APM)


Name of work:-Construction of Ram nagar minor of L.M.C. .

S.No. R.D.
1
2
3
4

1845
2625
3060
3787

Name of
out let

G.C.A. in C.C.A. in
hact.
hact.

1RNM(L)
2RNM(L)
3RNMR)
4RNM(L)

122.037
85.486
84.059
89.566

88.656
74.511
88.126
77.501

CANAL DATA

Design of outlet

Discharge of
out let in
cusec

C.B.L.

F.S.L.

N.S.L.

Hs

Bt

Ya

0.0309
0.0260
0.0308
0.0270

260.63
259.38
258.95
257.32

260.97
259.67
259.24
257.52

271.72
272.27
271.5
271.4

0.11
0.00
0.00
0.00

0.10
0.00
0.00
0.00

0.22
0.00
0.00
0.00

Proposed
Fixing
R.L.(outlet foundation level
bed level)
for APM
260.64
259.83
259.67
258.58
259.24
258.15
257.52
256.52

DESIGN OF OUTLET
Name of work:-Construction of Ram nagar minor of L.M.C. .

S.No. R.D.
1
2
3
4

1845
2625
3060
3787

Name of
out let

G.C.A. in C.C.A. in
hact.
hact.

1RNM(L)
2RNM(L)
3RNMR)
4RNM(L)

122.037
85.486
84.059
89.566

88.656
74.511
88.126
77.501

CANAL DATA

Design of outlet

Head (Hs)=

Discharge of
out let in
cusec

C.B.L.

F.S.L.

N.S.L.

Bt

Ya

q2/(4.04*bt*y)
hs=q2/0.0036

0.0309
0.0260
0.0308
0.0270

260.63
259.38
258.95
257.32

260.97
259.67
259.24
257.52

271.72
272.27
271.5
271.4

0.10
0.10
0.15
0.30

0.22
0.20
0.25
0.20

0.12
0.10
0.04
0.01

Proposed
Fixing
foundation
level
R.L.(outlet
for APM
bed level)
260.63
259.83
259.37
258.58
258.95
258.15
257.31
256.52

FSD

REQUIRED
DEPTH

0.34
0.29
0.29
0.20

0.34
0.30
0.29
0.21

You might also like