SITE INSTRUCTION

NAME OF PROJECT: HO FUME ROAD PROJECT (KM 0 7) & (KM 28.7 40.1)
VARIATION ORDER N.O.4 (LIKPE-TODOME CAVE ROAD).
SECTION: KM 0+00-3+KM 3+895

CONTRACTOR: ROLIDER

Ref No. S.I. 49

DATE: 21/07/2016

SUBJECT: Re: Construct the road according to the working drawing provided by the
Engineer.

You are instructed to Construct the road using the vertical and horizontal alignments in the
drawing. For any future minor changes, the ER must be informed with the center line set out
for the ER to inspect and approve or disapprove.

ISSUED BY THE RE

RECEIVED BY THE CONTRACTOR

Name: C. K. Baah

Name:

Signature: CKBaah

Signature:

Date: 21/07/2016

Date: