CUSTOMER NAME: M/S AGROLMOS S.A.

PROJECT CODE: UI5338


LOCATION: AGROLMOS PERU
SR ACT.
ERECTION ACTIVITY
PLANNED/ MATERIAL DESPATCH SCHEDULE (MDS as
NO. SEQ.
ACTUAL
receive from Project)
Foundation Checking
PLANNED
Reached site on 4th April ,16
1
1
ACTUAL
Support Structure Erection and
PLANNED
Reached site on 4th April ,2016
2
2
Alignment
ACTUAL
Ground Assembly of Casing
PLANNED
Reached site on 4th April ,2016
3
2.1 Panels with
ACTUAL
Columns
PLANNED
Ground Assembly of Inlet Nozzle
Nozzle Reached Site & GD Screen is Expected
4
2.2 with GD
to Reach CIF Callao
ACTUAL
Screen
Port on 21st May, 16
ESP Bearing installation &
alignemnt

3.1

3.2

ESP casing erection with Girder,


alignment and welding

Erection and alignment of


collecting plate surface support
channel arrangement

10

5.1

Erection, Alignment and welding


of staircase and platform with
Handrail & Grating

Ground Assembly of Outlet


Nozzle with gas Distribution(GD)
screen
Ground Assembly of Hopper

PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED

5.2

12

PLANNED
ACTUAL

NA

Fixing of Rigitrodes on top High


Voltage
(H.V) frame
Hot roof (inner roof) erection, Fit10
up & welding
Erection of penthouse with side
11
wall, fitup & welding
Erection of cold roof (top roof)
12
Fit-up & welding
Erection of rigitrode bottom
12.1
guide frame
Erection of monorail with Its
13
support structure
Erection of hoppers, Fit-up &
13.1
welding
Erection of support Insulators &
13.2 its allied
Parts
Erection of all rappers Shaft & its
14
components
Fixing of electrical items
14.1

PLANNED
ACTUAL

Expected to Reach CIF Callao Port by last week


of June ,2016

PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL

NA

7.1

15

19
20
21
22
23
24
25
26
27
28
29

Erection of TR sets with its base


14.2
frame
Erection of all platform at
15
hopper level
Fixing of the cable trays On ESP,
15.1
for all cables
15.2 Alignment of regitrodes w.r.t.

PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED

Foundation Elevation & Pocket


FOUNDATION Diagonal Checking
Support Structure Column Alignment
Support Structure Cap Plate

PROJECT ISO PROT


PROTOCOL FORMAT

CBI/APC/ESP/FEP/ 0901 /R
CBI/APC/ESP/FDC/ 0902 /R
CBI/APC/ESP/SSCAE/ 0903
CBI/APC/ESP/SSCP/ 0904 /
CBI/APC/ESP/CCAC/ 0906/

Casing Column Assembly Checking

Inlet & Outlet Nozzle Diagonal

Base Plate Alignment

Hopper Diagonal checking

CBI/APC/ESP/I/OND/ 0910/

CBI/APC/ESP/BPA/ 0905 /R

CBI/APC/ESP/I/OND/ 0910/

CBI/APC/ESP/HD/ 0915 /Re

Casing Structure Column Alignment

CBI/APC/ESP/CSCA/ 0907/

Casing Column Top Plate

CBI/APC/ESP/CCTP/ 0908/R

Top Girder Alignment

CBI/APC/ESP/TGA/ 0909 /R

Floating Channel Alignment

CBI/APC/ESP/FCA/ 0911/Re

NA

Collecting Plate is Expected to Reach CIF Ground Assembly of Collecting Plate


Callao Port on 21st May,
16 & Tadpole is Expected Date to Reach CIF
Callao Port on 21st May, 16
NA
NA

PLANNED
ACTUAL
PLANNED
ACTUAL

14

18

Staircase & Plateform reached site. Handrail &


Grating is expected to Reach CIF Callao Port on
21st May, 16

PLANNED
ACTUAL
PLANNED
ACTUAL

17

ACTUAL

Reached site

Erection of collecting plate


panels (by crane / winch)
Erection, Alignment and Welding
of Inlet
& Outlet Nozzle
Alignment of collecting plate
panels
Positioning of top HV frame ( by
crane / winch)

13

16

Ground assembly of collecting


plates

Expected to Reach CIF Callao Port on 21st


May, 16

ACTUAL
PLANNED
ACTUAL

ERECTION STAGE

Reached Site & GD Screen is Expected to


Reach CIF Callao Port on
Inlet & Outlet Nozzle Diagonal
21st May, 16

Reached site

PLANNED
11

Reached site

INSPECTION

NA

CBI/APC/ESP/GACP/ 0912/

NA

NA
NA

NA

Reached site
NA
Expected to Reach CIF Callao Port on 21st
May, 16
Expected to Reach CIF Callao Port bylast week
of June ,2016
NA

Collecting Plate Plum


Collecting Plate Field Alignment
High Voltage Frame Alignment

NA

CBI/APC/ESP/CPP/ 0913/Re
CBI/APC/ESP/CPFA/ 0916 /
CBI/APC/ESP/HVFA/ 0914/R

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

CBI/APC/ESP/SIA/ 0917/Re
Support Insulator Alignment

Reached site
Expected to Reach CIF Callao Port on 21st
May, 16
Expected to Reach CIF Callao Port bylast week
of June ,2016
NA
NA
NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

30
31
32
33

16
16.1
16.2
17

collecting plates
Cable laying
Cable termination
Cable dressing
Air leak test

37

Fixing of mechanical interlock


18 system,
Sign & brackets
Thermal Insulation (After Air
18.1
Leak Test)
Pre-commissioning activities
18.2
started
Commissioning of ESP Start
19

38

19.1

39

20

34
35
36

ESP Interlock
Handing over the unit to the
plant person

ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL
PLANNED
ACTUAL

Expected to Reach CIF Callao Port bylast week


of June ,2016
NA
NA
NA
Expected to Reach CIF Callao Port on 21st
May, 16
Expected to Reach CIF Callao Port bylast week
of June ,2016
NA
NA
NA
NA

NA

NA

NA

NA

NA
Air Leak Test (Soap Solution Test)
NA
NA
Pre-commissioning Report
Mechanical Completion Checklist
Electrical Completion Checklist
NA
Commissioning Report
Acceptance Report

NA

CBI/APC/ESP/ALT/ 0918 /R

NA
NA

CBI/APC/ESP/PCR/ 092

CBI/APC/ESP/MCC/ 0919 /R
CBI/APC/ESP/ECC/ 0920 /R
NA

CBI/APC/ESP/CR/ 0923 /Re


CBI/APC/ESP/AR/ 0924 /Re