Professional Documents
Culture Documents
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
PROJECT
LOCATION
OWNER
CONTRACT NO
15/C00000/2011-S2
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 2 / 12
Dec 7, 2012
NHK
YGK
IF/SDL
Rev.
Description
Date
Prepared
By
Checked
By
Approved
By
Page/ Paragraf
Item
Description of Change
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 3 / 12
INDEX
1. INTRODUCTION(4/12)
2. METHOD OF WORK.(5/12)
3. QA / QC ..(10/12)
4. SAFETY ......(12/12)
5. ATTACHMENT
- JOB SAFETY ANALYSIS
1. INTRODUCTION
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 4 / 12
This method statement describes the method, sequence of work at construction site for
cutting pile work :
Project Name
Contractor
Owner
: PT. Pertamina
2. METHOD OF WORK
2.1 Cutting pile will be conducted by 2 (two) methods :
2.1.1 First method : pile is cut after the soil excavation is finished until elevation
below foundation or elevation match the planning design.
CONSORTIUM ADHI GS E&C
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 5 / 12
2.1.2 Second method : Pile is cut first as high as the existing ground level and
then excavation work is conducted until the design level. Afterward, the
pile is cutting.
2.2 The first method (2.1.1) is done because the height of the existing ground level is not
more than 3 meter.
2.3 The second (2.1.2) method is done because the height of the cutting pile is more
than 3 meter. This condition is not safe if the first method is applied.
2.4 There are 2 (two) stages for cutting pile:
- The first stage : pile is cut directly, concrete and iron, it means that the pile is all
cut. The equipments used are portable grinder machine for (iron and concrete)
- The second stage: pile will be sliced with 3-4 cm depth or not touch the iron part of
the pile. Then, the piles will be perforated carefully so that the iron pile for the
starter bar is not damaged or broken.
- The distance between the first stage and the second stage is 30 cm.
2.5 The equipments / tools used for cutting pile :
- String wire + clip + accessories
- Crane or excavator
If the height of the cutting pile is not more than 3.5 meter, string wire will be
installed in 4 (four) sides (north, south, east and west) to maintain the stability of
the cutting piles falling down and if the height of the cutting pile is more than 3.5
meter, crane will be used to maintain the balance of the cutting pile so that its
dropdown may be properly controlled.
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 6 / 12
2.6 The last stage is the finishing and cleaning pile cut waste in the work area:
- Cleaning cutting pile surface will use grinder so that surface of cutting pile will be
flat and rebar installation can be done properly.
CONSORTIUM ADHI GS E&C
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 7 / 12
- The concrete waste stuck in the pile /starter bar should be cleaned so that the
formwork foundation will completely bind the old re-bar and the new foundation
structure.
- The cutting pile waste will be removed to the temporary stock pile, that have been
provide by clients using dump truck or other vehicle .
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 8 / 12
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 9 / 12
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 10 / 12
3. QA / QC
Site QA/QC Manager under the direction of Site Manager and Construction
Manager is responsible for supervision of Site Quality Assurance and Quality
Control activities and coordinates project quality control efforts to ensure the
desired results.
QC Engineer and Inspectors will be working under direction of QA/QC
Manager.
Site QA/QC Engineer & Inspector shall be responsible for the followings:
1)
2)
3)
4)
Holds
Inspection
Meeting
between
PERTAMINA,
other
parties
and
Attends
kick-off
meeting
with
Subcontractors,
PERTAMINA
and
7)
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 11 / 12
8)
9)
Monitors and controls quality control activities to confirm that they comply
with the specified procedure.
10) Supports Site and Construction Managers activities for quality control
matters by:
Obtaining PERTAMINA ideas, by evaluating the specified procedures.
Demarcate inspection activities between QC group and Construction
group.
Advising or being consulted by QC Engineer or QC Inspector on quality
control procedures, methods and application.
Interpreting
codes,
standards,
specifications
and
government
regulations.
11) Holds Inspection Meeting between CONTRACTOR and Subcontractor to
emphasize procedures, progress or other inspection and test matters.
12) Reviews and submits Daily Inspection Schedule and Weekly Inspection
Schedule for specified items to PERTAMINA.
Doc.No. : RFCC-G-CS-PR-006
Rev. No. : 0
Page No : 12 / 12
4. SAFETY
4.1 Before commencing the activity, the complete works force will receive a toolbox
meeting, which covers the importance of PPE precountionary measure to the
forecasted risk.
4.2 The field engineer in charge shall ensure that all necessary to work have been
obtained in advance and are available at site all the time for verification , and any
special condition imposed in the permit to work shall be implemented.
4.3 The use or restriction of the machine or hand tools will be monitored all the time by
the foreman concerned personally.
4.4 Prior to commence cutting pile work and if applicable and required, hard barricades,
signs and warning lights shall be arranged and assembled at the area of
excavation. Likewise suitable steps for safe access for workers and for inspection
purpose shall be provided.
4.5 Banksman or signal man must standy by for 1 (one) equipment in the site when
cutting pile work begin.
4.6 Toilet facility, shelter and drinkable water will be provided at site all time.