S.No.

Description of Item
Expenses incurred (
in lakhs) Remarks
As per the PPR, the labour rates were considered without any lift charges, where
as per the site conditions and
for high rise buildings works (2 B +G+19 Floors) without lift charges no labour
will work.
1
As per the construction industry practices lift charges for upper floors have to
pay to the labour for the
Shuttering and reinforcement works.
154.56
2
Even rate was not considered for Openings / Cutouts /sleeves/ PVC rungs, but whe
reas labour charges paid
as per the site conditions on needy basis.
6.22
3
As per our signed contract documents and specifications the back propping for tw
o levels are included in
BOQ rate, whereas that was not considered in the PPR,
17.71
4
Due to shortfall in mobilization of shuttering materials in podium are, addition
al labour engaged for internal
shifting of materials to the required area, this was not considered in PPR.
4.50
5
Internal shifting of steel in required at site level as per the logistic plan i.
e. steel yard beyond 300 mtrs to the
tower location), this shifting charges was not considered in PPR.
17.72
6
Blocks shifting and lifting charges paid, due to mobilization delay of builder h
oists which was not considered
in PPR.
5.08
7
Manually concrete charges paid at the period of Tower Crane failure and break do
wn and height increase
process.
4.86
88
Additional labour expenses incurred due to construction of extra Labour shed (Co
ntractual agreed 700 Nos
whereas manpower deployed 1000 Nos for senior management commitments)
3 50 3.50
9
Additional labour expenses incurred due to construction of barricading wall, Cli
ent & Consultants Offices on
Free of Cost as per senior management commitments.
42.49
10
Quantity survey agency engaged including BBS & Master quantification works at si
te instead of deployment
of QS Engineers, this was booked in the Concrete, Rebar & Shuttering works.
18.00
11
Due to non provision of Dewatering pumps in the scheduled time more labour has b
een enguaged for the

removal of slush cleaning in foundations, which is also a reason for the delay o
f foundation works. 3.00
12 Debrie Removal from site to dumping yard and dumping yard to out of the site.
10.50
13 Safety equipments and man power engaged for the same not considered for Proje
ct costing 12.00
14
Tie rod Hole, Removing of PVC pipe and filling with grouting material Was not co
nsidered, which is also
costing the project . Tie rod cutting , chipping around the same and packing wit
h water proofing material. 15.00
Over all
estimated of 45
lakhs
15
Movement of vehicles during rains, No cost considered for approach way preperati
on during rains and the
same has been done due to the site requirements (With debris and GSB materials).
6.00
16 No Construction water purchase is been considered for the project 15.50
17
Entrance portal works has been handeled with additional men and material due to
the odd shape of the
structure has costed more than the qty. basis items.
3.45
18
All mass excavation works are been carried by client provided agencies, But isol
ated footing , retaining wall
excavation and backfilling works are been carried with hire Excavator and tracto
rs (Work is still in progress).
9.60
12000 cum of
back filling work
is still to be
done
19 House keeping (Work is still in progress). 10.73
Total 360.42