44
Figure 5-2 Installing an equipotential cable (using the power cabinet and battery cabinet as an
example)
----End
Issue 01 (2014-07-09)
45
6 Installing Components
Installing Components
Rectifiers are found intact after unpacking and check. In case of any discrepancy, contact
your local Huawei office.
The filler panels on the slot for installing the rectifiers have been removed from the
cabinet.
Do not put your hands into rectifier slots, avoiding electric shocks.
When a rectifier is running, a high temperature is generated around the air exhaust vent at
the rear. Do not touch the vent or cover the vent with cables or other objects.
Procedure
Step 1 Push the locking latch towards the left.
Step 2 Draw the handle downwards.
Step 3 Gently push a rectifier into its slot along the guide rail.
Step 4 Push the handle upwards.
Step 5 Push the locking latch towards the right to secure the handle.
Issue 01 (2014-07-09)
46
6 Installing Components
----End
Issue 01 (2014-07-09)
47
6 Installing Components
----End
Step 3 Secure the smoke sensor to the base, as shown in Figure 6-3.
Issue 01 (2014-07-09)
48
6 Installing Components
Step 4 Connect one end of the signal cable to the smoke sensor and the other end to the SMOKE port
on the UIM panel, as shown in Figure 6-4.
Figure 6-4 Installing a signal cable for the smoke sensor
----End
Issue 01 (2014-07-09)
49
6 Installing Components
When stacking cabinets, the water sensor must be installed in the battery cabinet.
When you install a water sensor, ensure that the sensor is 5 mm to 10 mm away from the cabinet
bottom.
----End
Issue 01 (2014-07-09)
50
6 Installing Components
Issue 01 (2014-07-09)
51
6 Installing Components
Step 6 Connect the other end of the signal cable for the temperature and humidity sensor to the
TEM-HUM port on the UIM panel, as shown in Figure 6-8.
Issue 01 (2014-07-09)
52
6 Installing Components
Figure 6-8 Installing a signal cable for the temperature and humidity sensor
----End
Issue 01 (2014-07-09)
53
7 Installing Cables
Installing Cables
Ensure that the upstream AC input circuit breaker is OFF, and attach labels such as "No
operations allowed."
----End
Issue 01 (2014-07-09)
54
7 Installing Cables
(1) FE port
----End
(1) FE port
----End
Issue 01 (2014-07-09)
55
7 Installing Cables
Step 2 Connect the other end to the MON1 port on the BBU, as shown in Figure 7-4.
Figure 7-4 Connecting a communications cable (over the RS485 port)
----End
(1) FE port
----End
Issue 01 (2014-07-09)
56
7 Installing Cables
----End
Issue 01 (2014-07-09)
57
7 Installing Cables
Figure 7-7 Installing DC output power cables (using the TP48200A-HX09A5 as an example)
(1) DC load
----End
Issue 01 (2014-07-09)
58
7 Installing Cables
Step 2 Connect the negative terminal on the other end of the power cable to the 10 A load circuit
breaker.
Step 3 Connect the positive terminal on the other end of the power cable to the RTN+ busbar.
Figure 7-8 Installing a TCUC power cable (using the TP48200A-HX09A5 and TBC300A-DCA7
as an example)
----End
Issue 01 (2014-07-09)
59
7 Installing Cables
Issue 01 (2014-07-09)
60
7 Installing Cables
----End
Procedure
Step 1 Lay out the heater power cable, and route it into the power cabinet through the package entry
module.
One end is secured to the power port on the heater in the battery cabinet, and the other end is reserved on
the battery cabinet.
Issue 01 (2014-07-09)
61
7 Installing Cables
Step 2 Connect the other end to the AC output circuit breaker and terminal on the power cabinet.
Figure 7-11 Installing a heater power cable (TP48200A-HX09A5 and TP48200A-DX09A2)
Issue 01 (2014-07-09)
62
7 Installing Cables
Issue 01 (2014-07-09)
63
7 Installing Cables
(1) ACDB
----End
Issue 01 (2014-07-09)
64
7 Installing Cables
Step 3 Lay out an AC input power cable, and route it into the cabinet through the cable hole in the
left part of the cabinet bottom.
Step 4 Secure the AC input power cable to the AC input circuit breaker and terminal, as shown in
Figure 7-15.
Issue 01 (2014-07-09)
65
7 Installing Cables
(1) ACDB
----End
Issue 01 (2014-07-09)
66
7 Installing Cables
(1) ACDB
----End
Issue 01 (2014-07-09)
67