Professional Documents
Culture Documents
Conbextra EP65
A range of epoxy grouts for dynamic / repetitive load applications with good
chemical resistence
important to keep cool those surfaces of the equipment that come into direct contact with the material itself.
III. Try to avoid application during the hottest times of the day, arrange temporary shading as necessary.
IV. At lower temperatures, Conbextra EP65 grout should be applied only when the substrate temperature and the ambient
temperature is above 5C and rising. When temperatures are less than 10oC, consideration must be given particularly
when early loading is anticipated, to heated storage, tenting and possibly heating the work piece. Those requirements
V. Make sufficient material, plant and labour available to ensure that application is a continuous process.
EQUIPMENT
It is suggested that the following list of equipment is adopted as a minimum requirement for the correct application of this
material (N.B. Product users must adhere to current OH&S requirements applicable to their site and all statutory
legislation):
Protective clothing :
Mixing equipment :
- Pouring equipment
PARCHEM
CONCRETE REPAIR
METHOD STATEMENT
DECEMBER 12
www.parchem.com.au
FLOORING
JOINTING SYSTEMS
WATERPROOFING
Conbextra EP65
APPLICATION POINTS OF NOTE
Parchem operates a policy to encourage the use, where possible, of recommended applicators, since the long-term
performance of the materials is dependant upon proper application. For contractors who wish to apply the materials
themselves, Parchem is also able to offer technical assistance.
shall be left clean and free from oil, grease, rust, scale, or other loosely adherent material. It is recommended the
exposed steel is protected by the application of Primer No. 13. Grouting is to take place within 72 hours of primer
application.
2.2 It may be necessary to provide air-pressure relief holes to allow venting of any isolated high spots.
2.3 The base plate shall be located to line and level and braced to minimise movement of the baseplate during the cure
period of the grout. As levelling shims are to be removed once the grout has hardened, then they should be pre-treated
pouring hopper and not have any easier routes around the sides.
3.3 The formwork itself must be constructed to be leak-proof, to prevent any possible grout loss and designed to give the
correct head of grout for the flow distance and gap width.This can be achieved by using a foam rubber strip or Parchem
Construction Silicone beneath the formwork, and at any joints of the formwork. It must not deform, deflect or leak when
3.4 Grouting of holding-down bolts at the same time as under-plate grouting shall not be allowed. All bolt pockets and
sleeves shall be grouted / anchored with a proprietary anchoring material prior to the grouting application.
3.5 Under plate grouting may commence immediately after the completion of the bolt pocket grouting.
3.6 The formwork shall be constructed in such a way as to keep the final, unrestrained surface area of the grout to a
minimum, to avoid problems with cracking at a later stage. Wherever possible unrestrained shoulders are to be
avoided. These have a tendency to crack and / or de-bond, due to their unrestrained nature.
3.7 For free flow grout conditions; it is essential to provide a hydrostatic head of grout. A feeding hopper system is
recommended for such situations. It should be done in such a way as to allow easy stripping, without causing damage
3.8 All dirt and debris are to be removed from the grout area before the last piece of formwork is fixed.
Conbextra EP65
4.0 FORMWORK - GEOMETRY
4.1 POURING SIDE
- set up so that grout will be poured the shortest distance across the base plate
- erected a minimum of 150 mm higher than the underside of the base plate
5.0 MIXING
5.1 Mix the base and hardener contents separately in their containers.
5.2 Place the mixed base and hardener into a forced action mixer. Ensure that the entire volume is poured in. Mix for 2-3
minutes until a uniform colour is achieved.
6.0 PLACING
6.1 It is essential that the machine mixing capacity, material supply and labour availability is adequate to enable the
6.2 Immediately prior to placement, the mixed grout should be briefly agitated to release any surface tension. Place the
6.3 The grout shall be placed in accordance with good grouting practise and within the time restraints of the selected
product.
6.4 Conbextra EP65 grout can be placed in thicknesses from 35 mm minimum up to 65 mm in a single pour when used as
an under-plate grout.
6.5 Any bolt pockets must be grouted / anchored, prior to grouting between the substrate and the base plate.
6.6 Continuous grout flow during the grouting operation is essential. Sufficient grout must be available prior to starting,
and time taken to pour a batch must be regulated to the time taken to prepare the next one.
6.7 The mixed grout should be poured only from one side of the void to eliminate the entrapment of air. The grout head
6.8 When the grout reaches the open side of the formwork, and rises above the underside of the base plate, pouring should
continue slowly down the length of the base plate until completed.
6.9 If any leaks occur from the formwork shuttering these shall be immediately plugged with an appropriate quick setting
6.10 Conbextra EP65 has a pot life of 30 minutes @20 0C. After mixing, Conbextra EP65 should be used within the pot life
period or else the material will harden and therefore will have to be discarded.
Conbextra EP65
7.0 FINISHING
7.1 Wherever possible unrestrained shoulders are to be avoided. These have a tendency to crack and / or de-bond, due to
7.2 On completion of the grouting operation the exposed edges shall be protected during the curing period of the grout.
8.0 PROTECTION
8.1 On completion of the grouting operation, all exposed areas of grout should be protected from solar heat gain by
This method statement is offered by Parchem as a standard proposal for the application of Conbextra EP65. It remains the
responsibility of the Customer to determine the correct method for any given application.
Parchem does not accept any liability either directly or indirectly for any losses suffered in connection with the use or
application of the product whether or not in accordance with any advice, specification, recommendation or information
given by it.
PARCHEM
CONCRETE REPAIR
METHOD STATEMENT
DECEMBER 12
www.parchem.com.au
FLOORING
JOINTING SYSTEMS
WATERPROOFING