You are on page 1of 27

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Contents

Background
Modular Vs Float-over Comparison
Jacket and Geometry
Sequence
Active Vs Passive Systems
Weather Conditions
Components
Motion Analysis
Loads
Structural Design

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Background of the floatover concept


Oil companies are looking to exploit new and larger
reservoirs in their increasing quest to bridge the demand
supply gap
Thi
This h
has resulted
lt d in
i the
th increased
i
d sizes
i
off the
th decks
d k
required to process the reservoir fluids offshore

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Background of the floatover concept

Topside weight
The recent ONGC projects indicate large weight due to
combination of facilities and to maximise the production due
to increased price of oil

ICPR Process =11,000 Tonnes


MNP Process = 28,000 Tonnes
B193 Well Cum Process = 16,000 Tonnes

Availability of offshore lift vessels in the region

Upto 3000 MT, with some new vessels coming in the market
capacities 4000 / 7000 MT
3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Background of the floatover concept


Large topside decks

+
Limited availability of offshore heavy lift
capacity

Multiple modular lifts offshore

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Modular Installation

Large Topsides The topsides weight for the process


platforms are ranging from 10000T to 30000T depending on
the platform requirements

Small crane capacity Many lifting cranes available in the


region has a lifting capacity is in the order of 2000T to 3500T

Thus the topsides will be split into smaller logical units


(module) and installed on the jacket one by one. This is to be
carefully worked out depending on the weight of the module
and its location.

The disadvantage of the modular installation is long offshore


t e for
time
o installation,
sta at o , hookup
oo up and
a d commissioning.
co
ss o
g

Several occasions the design of sub-assemblies and the


integration becomes a major task during engineering.

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

3/22/2013

Module
3

Module
4

Base
Module 1

Module
5

Module
6

Module
7

Base
Module 2

Float-over Installation

Total topsides transported to the site in Single Piece on a


deep draft or semi-sub barge

Jacket legs (inner) spaced such that the barge enter


b t
between
the
th legs.
l

The barge with topsides position in such a way that the


jacket legs and deck legs comes on vertical alignment using
precision alignment devices.

Barge brought to the location in slightly de-ballasted


position with a clear gap between the jacket leg top and
bottom of deck leg.

Ballasting down the barge makes the deck leg to make


contact with the jacket leg

This operation is called Float-Over

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

3/22/2013

LQ
Module

Top
structure

Base
structure

Barge

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

10

LQ
Module

Top
sides

Base
structure

Barge

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

11

SOME APPLICATION FLOATOVER


Deck Float Over
TLP Float
l
on Float
l
Off

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

12

Weather Conditions
Non-swell conditions are preferred and float over
operation has been done in the past with passive
systems in asia and other regions where the
significant wav height is less than 1.5m
1 5m
Swell conditions are not preferred but can use the
active systems
Typical weather window for floatover operations
around 36 to 48 hours

MOORING LINES
36000

TUG

TUG

Maximum WL during undocking (HAT + 0.15m Inst tolerance)


Minimum freeboard during undocking = 0.75m
El 1.2m Min WL for start docking
El 0.0m LAT

BARGE
JACKET
FLOATOVER ON JACKET STRUCTURE

TOPSIDE
FLOATOVER ON SPAR

3/22/2013

FLOATOVER ON SEMISUBMERSIBLE

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

13

SEQUENCE

LOADOUT
TRANSPORTATION
DOCKING
MATING

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

14

Loadout on to vessel

3/22/2013

15

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Float over principle


Fixed substructure

East Area GN
Deck on HTV
Black Marlin
Operator:
ExxonMobil
Weight: ~18000 mT

Location: Offshore
Nigeria
I
3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

16

Float-over Sequence
load-out

Critical Factors in a Loadout Operation:


Vessel pumping capacity;
Vessel strength/skid beam design;
Pulling jack capacity and reliability;
Integrated deck weight and
skidding friction;
Tidal range;
Quayside dimensions.

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

3/22/2013

17

Float-over Sequence
sea transportation

Critical factors during sea transportation:


Vessel stability vs. deck weight/CG
height;
g ;
Global strength of vessel;
Local strength of vessel;
Sea fastening arrangement vs. motion
induced forces.

60.000 tons
@
37 00 m
37.00
12.000 tons
@
18.00 m

63.00 m

3/22/2013

42.00 m

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

18

Float-over Sequence docking


Critical factors during docking operation:

Heading control of the vessel;


Transverse control of the vessel w/
away
a
ay fenders
d
and
a d cross
o lines;;
Longitudinal control of the vessel with
mooring lines and cross lines;
Control impact loads on jacket w/sway
fenders;
Maintain vertical clearances during
entry and withdrawal operations.

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

19

Float-over Sequence
mating: non-swell environments

Critical factors during mating operation

Limit horizontal excursion circle prior to lowering operation through


fenders & cross lines:
Minimize vertical impact loads between jacket & deck legs through
installed LMUs;
Minimize vertical impact loads between deck legs and vessel deck through
DSUs;
Achieve load transfer from vessel to jacket legs through vessel ballasting;
Continue vessel ballasting until sufficient vertical clearances for withdrawal
operation.

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

20

10

Float-over Sequence
mating: swell environments

Critical factors during mating operation


Limit stabbing cone horizontal excursion within designed circle by an anti-surge
y
;
system;
Minimize vertical impact loads between jacket & deck legs through hydraulic
cylinders and LMUs;
Minimize vertical impact loads between deck legs and vessel deck through quick
separation system (hydraulic cylinders) and DSUs;
Achieve load transfer from vessel to jacket legs through vessel ballasting and
cylinder extension/retraction;
Combined vessel ballasting and cylinder retraction for vertical clearances prior to
exit operation.

21

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

3/22/2013

History
40000
35000

Deck weight [st]

30000
25000
20000
15000
10000
5000
0
1990

1992

1994

1996

1998

2000

2002

2004

2006

2008

Year

Source : Dockwise
3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

22

11

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

23

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

24

12

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

25

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

26

13

Load out

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

27

Transportation

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

28

14

Positioning / Docking

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

29

Positioning / Docking

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

30

15

Positioning / Docking

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

31

Positioning / Docking

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

32

16

Ready for weight transfer

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

33

Ready for weight transfer

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

34

17

LEG MATING UNITS


LEG MATING UNIT

RECEPTOR
CONE

ELASTOMERIC
BEARING

SAND JACK

JACKET
LEG

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

35

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

36

Weight transfer

3/22/2013

18

Weight transfer complete

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

37

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

38

Undocking

3/22/2013

19

Undocking complete

39

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

3/22/2013

Passive float-over methods

Load transfer only by vessel ballasting;


Moderate to mild wave climate w/o swells;
Sufficient draft fluctuation of the vessel to suit
requirement;
q
;
Utilization of LMUs and DSUs to reduce impact
loads;
Capacity >21000 tons.

Full load on
DSUs

Ballast

0% Load

3/22/2013

Partial load on
DSUs

0% Load

Ballast

Ballast

Partial load on
LMUs
Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

Full load w/ Steelto-Steel contacts


40

20

Active float-over methods

Active lowering system w/ cylinders integrated with deck supports;


Applications in swell environments during installation seasons (5
of 12 months in West Africa environments);
R
Require
i an anti-surge
ti
system
t
to
t reduce
d
excursion
i
circle;
i l
Draft fluctuation insufficient to create gaps for entrance/exit
clearances;
Quick separation system is required to obtain vertical exit
clearances;
Capacity 18.000 tons or less so far.

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

41

Pontoon barge method

No slot required for fixed jackets;


Suitable for SPAR buoys;
Require a transfer operation prior
to installation;
i
ll i
Not suitable for long distance sea
voyage under pontoon barge
configuration;
One successful installation for
fixed jacket by ODL for Corocoro
WHP project;
One successful installation for
Kikeh Spar project
j
by Technip.

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

42

21

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

43

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

44

22

Friction fender concept

3/22/2013

Utilize friction to reduce vessel heave motions;


Eliminate hydraulic cylinders to improve system
reliability;
Suitable for floating and fixed platform topsides
installations;

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

45

Improve pontoon barge method


Loadout directly onto two pontoon barges at
fabrication yard;
Purposely built pontoon barges;
Suitable for transportation
p
under harsh environments;;
Suitable for both fixed and floating platforms;

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

46

23

Outrigger concept

For high CG heavy decks, stability, not displacement, is the big


challenge;
Increase stability by adding removable sponsons far away from vessel
CL;
Whole system, sponsons plus truss, is independently maneuvered and
transported;
Increase transport speed by adding self-propulsion systems to the
sponsons;
Suitable for transverse loadout;
Internal development is underway.

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

47

Components

Loadout Support Frame (LSF)


Fenders
Leg Mating Unit (LMU)
(
)
Jacks.

24

Motion Analysis
Motion analysis and the reaction forces on sway and surge
fenders needs to evaluated
These
ese forces
o ces will be used to
o a
analyse
a yse the
e jac
jacket
e a
and
d dec
deck
structure prior to mating.

Loading Stages

0% Load Transfer Stage


50% Load Transfer Stage
100% Load
d Transfer
f Stage
Post Mating Loads

25

DOCKING LOADS

Typical Loads (Payload 6,000 T)


LOAD DESCRIPTION

0% Load transfer maximum


LMU -X-dir load
0% Load transfer maximum
LMU -Y-dir load
0% Load transfer maximum
LMU -Z-dir load
50% Load transfer
maximum LMU -X-dir load
50% Load transfer
maximum LMU -Y-dir
Y dir load
50% Load transfer
maximum LMU -Z-dir load
100% Load transfer
maximum LSF -Z-dir load

SWAY
SURGE
(Tonnes)
(Tonnes)
PRE-MATING
514
81

HEAVE
(Tonnes)
450

170

788

194

242

179

971

502

82

2498

146

70

1973

203

2861

1191

POST-MATING
5

26

Conclusions
Float-over is a mature installation method;
Float-over is a competitive alternative for:
Integrated decks beyond crane vessel capacity;
Integrated decks to be installed in remote areas;
Less environmentally sensitive than lifting option.
Improvements to be expected in the fields of:
Workability and system reliability under swell
environments;
Installation capacity for heavy and high CG topsides;
Alternative float-over system such as pontoon barge
method.

3/22/2013

Dr. S. Nallayarasu
Department of Ocean Engineering
Indian Institute of Technology Madras,
Chennai - 36

53

27

You might also like