Professional Documents
Culture Documents
TRIBHUVAN UNIVERSITY
CENTRAL CAMPUS OF TECHNOLOGY, HATTISAR, DHARAN
item 2
SOURCE
labour
tools &plant
Earthwork excavation in any type of (Hard clay, Gravel/ Boulder mixed ) soil
( In Foundation ,Trench Excavation with 30m lead and 2m lift. )
LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
unskilled
1.00 nos
400.00
400.00
13.41
473.80
ACTUAL RATE
15% OVERHEAD
TOTAL
200.00
ACTUAL RATE
Rate per cft =
Rate per Cu.m =
item 4
SOURCE
Labour
Material
item 5
SOURCE
Labour
Material
6.71
236.90
15% OVERHEAD
TOTAL
Rate / cft =
Rate / cu.m =
84.94
3000.06
Actual Rate
15%overhead
Total
item 6.a LOCAL CHIMNEY MADE 'A' CLASS BRICKWORK IN 1:5 CEMENT MORTAR.
( 250 mm thick wall ) Analysis for 1 cu m
SOURCE
LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
Labour
skilled
1.50 Nos.
575.00
862.50
unskilled
2.20 Nos.
400.00
880.00
Material
Cement
1.70 bag
661.00
1123.70
Brick
500.00 Nos.
14.30
7150.00
Sand
0.30 Cu.m
1100.00
330.00
Scaffolding
3% of unskilled
52.28
Actual Rate
Page 1
item 6.b
item 7
item 8
for 1 cu m
RATE
COST
575.00
575.00
400.00
2800.00
661.00
5288.00
1925.00
1617.00
1100.00
462.00
Actual Rate
15%overhead
Total
RATE
COST
575.00
400.00
989.00
1028.00
627.36
127.00
166004.00
6900.96
317.50
8300.20
Actual Rate
15%overhead
Total
61.38
660.46
item 10
349.75
12353.30
item 9
UNIT
Nos.
Nos.
bag
Cu.m
Cu.m
UNIT
Nos.
Nos.
kg
K.G.
RATE
UNIT
Nos.
Nos.
bag
RATE
COST
575.00
400.00
80.30
93.95
109.26
QUANTITY
0.05
0.05
0.03
Page 2
5750.00
4000.00
84315.00
939.50
Actual Rate
15%overhead
Total
COST
575.00
400.00
661.00
28.75
20.00
22.47
Sand
item 11
0.03 Cu.m
10079.87
285.39
1100.00
RATE
575.00
400.00
661.00
1925.00
1100.00
33.00
Actual Rate
15%overhead
Total
COST
575.00
1600.00
4362.60
1732.50
495.00
Actual Rate
15%overhead
Total
Page 3
138.00
Material
item 13
unskilled
Cement
Sand
0.32 Nos.
0.20 bag
0.03 Cu.m
400.00
661.00
1100.00
128.00
132.20
33.00
Actual Rate
15%overhead
Total
item 14
38mm Thick Sal wood frame glazed shutter with 5mm thick glass
For 1.83 x 1.22 = 2.23 sq m
SOURCE
LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
Labour
skilled
5.00 Nos.
575.00
2875.00
unskilled
0.90 Nos.
400.00
360.00
Material
SAL WOOD
0.05 Cu.m
166004.00
8134.20
5 mm th glass
1.09 sq. m
686.55
744.91
10 CM HINGE
8.00 Nos.
25.00
200.00
15 CM TOWER BOLT
4.00 Nos.
45.00
180.00
15 CM HANDLE
2.00 Nos.
70.00
140.00
M/S HOOK
2.00 Nos.
15.00
30.00
SCREWS
LS
150.00
150.00
Miscellaneous
LS
150.00
Actual Rate
621.27
15%overhead
Rate Per sq m =
6685.52
Total
item 15
38mm x 75mm Sal wood frame panalled door shutter with 25mm thick planks
For 1.07 x 1.982 = 2.114 sq m
SOURCE
LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
Labour
skilled
8.00 Nos.
575.00
4600.00
unskilled
1.00 Nos.
400.00
400.00
Material
SAL WOOD
0.08 Cu.m
166004.00
13944.34
300mm T/ bolt
1.00 Nos.
93.50
93.50
12 CM HINGE
6.00 Nos.
34.10
204.60
15 CM T/ BOLT
1.00 Nos.
49.50
49.50
15 CM HANDLE
2.00 Nos.
70.00
140.00
300mm aldrop
1.00 Nos.
190.00
190.00
SCREWS
LS
150.00
150.00
Miscellaneous
LS
150.00
Actual Rate
Rate Per sft =
1007.10
15%overhead
Rate Per sqm =
10837.38
Total
Page 4
item 16
item 17
Flush door shutter with 4mm thick plywood on 38x75mm size salwood frame,
with 30 gauge aluminum sheet both sides
For 1.092 x 2.058 = 2.245 sq m
SOURCE
LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
Labour
skilled
5.00 Nos.
575.00
2875.00
unskilled
0.70 Nos.
400.00
280.00
Material
SAL WOOD
0.03 Cu.m
166004.00
5743.74
4mm com/ ply
4.65 sq m
224.90
1045.79
10 CM HINGE
3.00 Nos.
25.00
75.00
15 CM T/ BOLT
1.00 Nos.
45.00
45.00
15 CM HANDLE
2.00 Nos.
70.00
140.00
200mm aldrop
1.00 Nos.
105.00
105.00
30# Al sheet
4.65 sq m
450.00
2092.50
Miscellaneous
LS
300.00
Actual Rate
Rate Per sft m =
604.65
15%overhead
Rate Per sq m =
6506.60
Total
item 18
item 19
item 20
RATE
COST
575.00
400.00
439.00
470.00
Actual Rate
15%overhead
Total
22.95
247.01
RATE
COST
575.00
400.00
84.52
Page 5
6900.00
3200.00
3555.90
7520.00
2875.00
2000.00
4099.22
146.25
Actual Rate
15%overhead
Total
SOURCE
Labour
LEVEL/TYPE
skilled
Material
unskilled
Providing and fixing grill
of 5x20 mm m/s flat b
item 21
QUANTITY
UNIT
RATE
20.17 kg
COST
135.00
155.25
2722.95
Actual Rate
15%overhead
Total
Providing and fixing medium class GI pipe Hand rail on stair and balcony
For 5 rm, Al paint on pipe work
item 22
SOURCE
Labour
Material
item 23
SOURCE
Labour
Material
LEVEL/TYPE
QUANTITY
Masson
1.00
welder
2.00
Labour
0.50
Painter
0.25
Coolie
2.00
38mm dia(1.5 ") GI pi
5.00
25mm dia (1") GI pipe
22.00
Metal primer
0.30
Aluminum paint
0.50
Miscellaneous - 3% of labor cost
970.18
Rate Per rm.= Rs. 3183.14
UNIT
Nos.
Nos.
Nos.
Nos.
1722.71
Page 6
COST
500.00
500.00
350.00
500.00
350.00
559.60
372.83
215.00
400.00
rm
m
Lit.
Lit.
RATE
RATE
500.00
1000.00
175.00
125.00
700.00
2798.00
8202.26
64.50
200.00
75.00
Actual Rate
15%overhead
Total
COST
575.00
400.00
22.00
686.55
40.00
368.00
256.00
89.10
744.91
40.00
Actual Rate
15%overhead
Total
item 24
SOURCE
Labour
Material
item 25
SOURCE
Labour
Material
item 26
SOURCE
Labour
Material
item 27
Flush door shutter with 3mm thick plywood on 38x75mm size salwood frame,
SOURCE
Labour
Material
Page 7
UNIT
Nos.
Nos.
Cu.m
sq m
Nos.
Nos.
Nos.
Nos.
RATE
500.00
350.00
141276.00
172.00
25.00
45.00
70.00
105.00
COST
2500.00
245.00
4888.15
799.80
75.00
45.00
140.00
105.00
300.00
Actual Rate
15%overhead
Total
item 28
SOURCE
Labour
Material
item 29
8410.70
238.13
UNIT
Nos.
Nos.
bag
Cu.m
Cu.m
For 1 cu.m
RATE
COST
575.00
575.00
400.00
1600.00
661.00
2908.40
1925.00
1713.25
1100.00
517.00
Actual Rate
15%overhead
Total
item 30
SOURCE
Labour
Material
Roof treatment : avg 50mm thick concrete (1:1.5:3) with water proof
compound including punning (For 10 sqm)
LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
skilled
1.20 Nos.
575.00
690.00
unskilled
2.00 Nos.
400.00
800.00
cement
4.00 bag
661.00
2644.00
Sand
0.30 cum
1100.00
330.00
12mm Agg
0.57 cum
1925.00
1097.25
WP compound
with punning
2.88 Kg
289.00
832.32
40.07
431.20
Actual Rate
15%overhead
Total
Page 8
white cement
Miscellaneous
Rate Per sft=
Rate Per sqm =
item 32
SOURCE
Labour
Material
item 33
3.23 kg
26.00
199.88
2150.91
83.93
50.00
Actual Rate
15%overhead
Total
item 34
SOURCE
Labour
Material
item 35
SOURCE
Labour
Material
558.33
170.17
UNIT
Nos.
Nos.
rm
Nos.
RATE
COST
575.00
400.00
342.50
20.00
LS
287.50
200.00
3767.50
400.00
200.00
Actual Rate
15%overhead
Total
Page 9
Rate Per kg =
item 36
SOURCE
Labour
Material
item 37
SOURCE
Labour
Material
SOURCE
Labour
Material
SOURCE
Labour
Material
COST
575.00
400.00
734.61
15.00
25.00
1.00
2.00
RATE
165.71
1783.26
Page 10
632.50
500.00
0.00
8815.32
450.00
625.00
55.00
135.00
Actual Rate
15%overhead
Total
COST
575.00
400.00
661.00
1100.00
5750.00
5600.00
4045.32
693.00
Total
15%overhead
Total
185.02
17.19
RATE
119.83
1289.47
item 39
256.06
item 38
Actual Rate
15%overhead
Total
RATE
COST
575.00
400.00
35.00
686.55
50.00
368.00
256.00
141.75
744.91
40.00
Actual Rate
15%overhead
Total
item 40
SOURCE
Labour
Material
item 41
SOURCE
Labour
Material
item 42
item 43
RATE
COST
109.26
313.28
61.38
22.56
9.75
Actual Rate
15%overhead
Total
293.31
962.35
Page 11
666.49
830.19
460.35
439.45
154.05
RATE
COST
575.00
400.00
632.50
500.00
Material
24 gauge coloured C
sheet
8mm nut bolt
J-hook
Bitumin washer
Metal washer
Rate Per sqft =
Rate Per sq m =
item 45
SOURCE
Labour
Material
item 46
SOURCE
Labour
Material
item 45
SOURCE
Labour
Material
884.55
15.00
25.00
1.00
2.00
139.06
1496.39
SOURCE
labour
tools &plant
sq. m
Nos.
Nos.
Nos.
Nos.
0.00
10614.60
450.00
625.00
55.00
135.00
Actual Rate
15%overhead
Total
item 46
0.00
12.00
30.00
25.00
55.00
25.00
Roof cleaning
For 1000 sft
LEVEL/TYPE
unskilled
5% of labor
cost
62.40
Actual Rate
15%overhead
Total
1506.96
42.67
QUANTITY
UNIT
1.00 nos
RATE
COST
400.00
400.00
ACTUAL RATE
Page 12
item 48
SOURCE
labour
tools &plant
item 49
0.47
5.10
15% OVERHEAD
TOTAL
item 50
SOURCE
Labour
Material
item 51
SOURCE
Labour
Material
Page 13
17.33 rft
0.20 kg
item 53
SOURCE
Labour
Material
33.00
120.00
200.00
571.89
24.00
200.00
Actual Rate
15%overhead
Total
172.31
1854.09
item 10
LEVEL/TYPE
Labour
skilled
1.07 Nos.
575.00
615.25
unskilled
5.38 Nos.
400.00
2152.00
transportation
2.00 kg
400.00
800.00
Material
miscellaneous
QUANTITY
3% of labor
9.69
31.80
Page 14
UNIT
cost
RATE
COST
83.02
Actual Rate
15%overhead
2.42
Total
item 8
LEVEL/TYPE
work
Earth work
QUANTITY
2.40 cft
UNIT
RATE
13.41
COST
32.18
Form work
5.00 sft
50.00
250.00
1:2:4 concrete
1.04 cft
106.14
110.60
Pole fixing
1.00 Nos.
LS
34.50
Plastic sheet
1.60 sft
LS
11.50
pole transportation
1.00 Nos.
LS
11.50
Miscellaneous
5.00
Actual Rate
5% overhead
682.92
Page 15
Total
mixed ) soil
TOTAL
400.00
12.00
412.00
61.80
473.80
TOTAL
200.00
6.00
206.00
30.90
236.90
TOTAL
0.00
2600.00
10285.00
78.00
12963.00
1944.45
14907.45
TOTAL
328.75
2280.00
2608.75
391.31
3000.06
TOTAL
1742.50
8655.98
10398.48
Page 16
1559.77
11958.25
TOTAL
2022.50
9069.48
11091.98
1663.80
12755.77
TOTAL
3375.00
7367.00
10742.00
1611.30
12353.30
TOTAL
2017.00
1725.24
317.50
1383.37
300.00
5743.11
861.47
6604.57
TOTAL
9750.00
85254.50
95004.50
14250.68
109255.18
TOTAL
48.75
Page 17
55.47
104.22
15.63
119.86
TOTAL
2175.00
6590.10
8765.10
1314.77
10079.87
TOTAL
15650.00
11706.80
469.50
27826.30
4173.95
32000.25
TOTAL
13300.00
7808.20
21108.20
3166.23
24274.43
TOTAL
13300.00
8744.80
399.00
22443.80
3366.57
25810.37
TOTAL
Page 18
266.00
165.20
431.20
64.68
495.88
TOTAL
12700.00
185456.40
198156.40
29723.46
227879.86
4500*35.319
158935.50
227879.86
TOTAL
3235.00
9729.10
12964.10
1944.62
14908.72
TOTAL
5000.00
14921.94
19921.94
2988.29
22910.23
Page 19
TOTAL
360.00
10.80
370.80
55.62
426.42
TOTAL
3155.00
9547.02
12702.02
1905.30
14607.33
TOTAL
10100.00
11075.90
303.00
21478.90
3221.84
24700.74
TOTAL
4875.00
4099.22
146.25
9120.47
1368.07
10488.54
Page 20
TOTAL
2722.95
2722.95
408.44
3131.39
TOTAL
975.00
755.66
1730.66
259.60
1990.26
TOTAL
2500.00
11339.76
13839.76
2075.96
15915.72
TOTAL
624.00
874.01
1498.01
224.70
1722.71
Page 21
ajjain 1:5 CM
TOTAL
2550.00
85.40
76.50
2711.90
406.79
3118.69
TOTAL
687.50
6862.75
7550.25
1132.54
8682.79
TOTAL
3260.00
6361.65
9621.65
1443.25
11064.90
TOTAL
2745.00
6352.95
9097.95
1364.69
10462.64
Page 22
TOTAL
2175.00
5138.65
7313.65
1097.05
8410.70
TOTAL
2175.00
6590.10
6064.06
14829.16
2224.37
17053.53
TOTAL
1490.00
2259.57
3749.57
562.44
4312.01
TOTAL
5825.00
Page 23
12878.55
18703.55
2805.53
21509.08
TOTAL
915.00
20940.90
21855.90
3278.39
25134.29
TOTAL
2175.00
6590.10
6523.70
15288.80
2293.32
17582.12
TOTAL
487.50
4367.50
4855.00
728.25
5583.25
TOTAL
3325.00
9887.60
Page 24
13212.60
1981.89
15194.49
TOTAL
722.50
3151.60
3874.10
581.12
4455.22
TOTAL
1132.50
10080.32
11212.82
1681.92
12894.74
TOTAL
0.00
11350.00
4738.32
16088.32
2413.25
18501.57
TOTAL
624.00
926.66
1550.66
232.60
1783.26
Page 25
TOTAL
6800.00
6800.00
1020.00
7820.00
TOTAL
1432.50
1432.50
214.88
1647.38
TOTAL
2062.50
3695.77
5758.27
863.74
6622.01
TOTAL
2550.53
2550.53
382.58
2933.11
TOTAL
1132.50
Page 26
11879.60
13012.10
1951.82
14963.92
TOTAL
487.50
4367.50
4855.00
728.25
5583.25
TOTAL
4300.00
7684.40
11984.40
1797.66
13782.06
TOTAL
1248.00
62.40
1310.40
196.56
1506.96
TOTAL
400.00
12.00
412.00
Page 27
61.80
473.80
TOTAL
400.00
20.00
420.00
63.00
483.00
TOTAL
1600.00
48.00
1648.00
247.20
1895.20
TOTAL
16625.00
9670.50
498.75
26794.25
4019.14
30813.39
TOTAL
15650.00
13989.20
29639.20
4445.88
34085.08
TOTAL
1862.50
Page 28
1104.29
2966.79
445.02
3411.81
4352.39
6989.89
1048.48
8038.38
TOTAL
4300.00
1397.00
5697.00
854.55
6551.55
TOTAL
2767.25
3650.27
3650.27
547.54
Page 29
4197.81
TOTAL
455.28
227.64
682.92
Page 30
SANITARY WORKS
ANALYSIS OF RATE
( Fiscal year 2071)
item 14 providing and fixing low level fiber glass flushing cistern
with flushing pipe, flexible pipe and all necessary accessories
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
Labour
skilled
0.50 Nos.
575.00
287.50
unskilled
0.50 Nos.
400.00
200.00
487.50
Material Low level cistern
1.00
3481.50
3481.50
Bracket
2.00 Nos.
LS
200.00
Conection pipe
1.00 Nos.
250.00
250.00
flexible pipe
Nos.
concrete & etc
LS Nos.
LS
300.00
miscellaneous
LS Nos.
LS
300.00
4531.50
Actual Rate
5019.00
15%overhead
752.85
Rate Pe no =
5771.85
Total
5771.85
item 16
Supplying and fitting 5mm thick bevelled edge plastic frame looking mirror
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
MATERIALlooking
mirror
1.00
no
440.00
440.00
440.00
LABOR
10% of
material cost
44.00
44.00
Actual Rate
484.00
15%overhead
72.60
Rate pe number =
556.60
Total
556.60
item 24
Supplying and fitting 20mm dia gunmetal gate valve
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
MATERIAL25mm dia GM
gate valve
1.00
no
1406.90
1406.90
1406.90
LABOR
10% of
material cost
140.69
140.69
Actual Rate
1547.59
15%overhead
232.14
Rate / number =
1779.73
Total
1779.73
item
Supplying and fitting 15mm dia gunmetal gate valve
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
MATERIAL15mm dia GM
gate valve
1.00
no
LABOR
10% of
material cost
COST
TOTAL
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Actual Rate
15%overhead
Total
item 21
SUPPLYING AND FIXING 15 MM DIA FLEXIBLE CONNECTION PIPE
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
MATERIAL15 mm dia flexible
connection pipe
1.00
no
154.00
154.00
154.00
LABOR
10% of
material cost
15.40
15.40
Actual Rate
169.40
15%overhead
25.41
Rate / number =
194.81
Total
194.81
item 31
Supplying and fitting 15mm dia angle valve
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
MATERIAL155 dia angle
valve
1.00
no
660.00
660.00
660.00
LABOR
10% of
material cost
66.00
66.00
Actual Rate
726.00
15%overhead
108.90
Rate / number =
834.90
Total
834.90
item 30
Rate / number =
218.47
15%overhead
Total
28.50
218.47
COST
TOTAL
0.00
0.00
Actual Rate
15%overhead
Total
0.00
0.00
0.00
0.00
Rate pe number =
76.53
Total
76.53
item 18
item 17 providing and fixing 750 liter plastic water tank with
all necessary accessories
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
Labour
skilled
1.00 Nos.
unskilled
1.00 Nos.
Material 500 lit water tank
750.00 liter
Tank nipple
1.00 Nos.
Check nut
2.00 Nos.
Brick work ,
concrete & etc
LS
miscellaneous
LS Nos.
LS
Rate Per tank = Rs. 14167.43
COST
TOTAL
0.00
0.00
0.00
Actual Rate
15%overhead
Total
0.00
0.00
0.00
0.00
COST
TOTAL
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Actual Rate
15%overhead
Total
item 23
Supplying and fitting 15mm dia plastic ball cock
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
MATERIAL15mm dia plastic
ball cock
1.00
no
170.00
LABOR
10% of
material cost
0.00
Actual Rate
15%overhead
Rate pe number = Rs. 215.05
Total
item 13 providing and fixing 500 mm orissa pan with P or S trap and
all necessary accessories
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
Labour
skilled
1.00 Nos.
575.00
unskilled
1.00 Nos.
400.00
Material 500mm pan
1.00
990.00
S trap
1.00 Nos.
200.00
flexible pipe
1.00 Nos.
100.00
concrete & etc
LS Nos.
LS
0.00
0.00
0.00
0.00
0.00
TOTAL
575.00
400.00
990.00
200.00
100.00
500.00
975.00
miscellaneous
LS Nos.
LS
2386.25
300.00
Actual Rate
15%overhead
Total
1100.00
2075.00
311.25
2386.25
COST
TOTAL
0.00
0.00
0.00
0.00
0.00
Sand
white cement
Miscellaneous
0.15 cum
3.23 kg
0.00
0.00
0.00
0.00
0.00
0.00
Actual Rate
15%overhead
Total
COST
TOTAL
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Actual Rate
15%overhead
Total
item 8
For 1 cu.m
COST
0.00
0.00
0.00
0.00
TOTAL
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Actual Rate
15%overhead
Total Rate
COST
0.00
TOTAL
Labour
Material
skilled
unskilled
Steel
Binding wire
12.00
12.00
1050.00
10.00
Nos.
Nos.
kg
K.G.
0.00
0.00
0.00
0.00
0.00
0.00
Actual Rate
0.00
Rate Per kg = Rs.110.94
15%overhead
0.00
Total
0.00
item 3
12.5 mm. PLASTER ON WALL IN 1:5 CEMENT/SAND MORTAR
FOR 100 SQUARE METER
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
Labour
skilled
12.00 Nos.
550.00
6600.00
unskilled
16.00 Nos.
350.00
5600.00
12200.00
Material Cement
8.10 bag
640.00
5184.00
Sand
1.40 M3
1000.00
1400.00
6584.00
Actual Rate
18784.00
15%overhead
2817.60
Rate Per Sq. M. =Rs.216.06
Total
21601.60
25mm THICK CEMENT SCREED IN 1:4 CEMENT MORTAR on floor ( for 1 sq m )
Including 1~1.5mm thick 1:1 cement mortar/thick cement punning on top
SOURCE LEVEL/TYPE
QUANTITY
UNIT
RATE
COST
TOTAL
Labour
skilled
0.24 Nos.
550.00
132.00
unskilled
0.32 Nos.
385.00
123.20
255.20
Material Cement
0.20 bag
640.00
128.00
Sand
0.03 Cu.m
1000.00
30.00
158.00
Actual Rate
413.20
44.16
15%overhead
61.98
Rate per Sq.m = Rs.475.18
Total
475.18
item 11
item 31.e
SOURCE LEVEL/TYPE
MATERIAL15mm dia
elbow
LABOR
10% of
material cost
no
Rate pe number =
0.00
0.00
0.00
Actual Rate
15%overhead
Total
0.00
0.00
0.00
0.00
129.41
no
102.30
102.30
10.23
Actual Rate
15%overhead
Total
10.23
112.53
16.88
129.41