Professional Documents
Culture Documents
Time Estimates
Activity
to
tm
tp
1-2
9
12
21
1-3
6
12
18
2-4
1
1.5
5
3-4
4
8.5
10
2-5
10
14
24
4-5
1
2
3
1.Determine the critical path
2.Calculate the slack for each event.
3.Obtain critical and slack paths.
4.Compute the activity float.
Average
13
12
2
8
15
2
1
2
3
4
5
Earliest
operating
time
0
13
12
20
28
Latest
operating
time
0
13
18
26
28
Slack=LOTEOT
0
0
6
6
0
LOT
(j)
13
18
26
26
28
28
EOT(
j)
13
12
20
20
28
28
LOT(
i)
0
0
13
18
13
26
EOT(
i)
0
0
13
12
13
20
Time(i
,j)
13
12
2
8
15
2
TF FF
0
6
11
6
0
6
duration
1-2
13
1-3
12
2-4
2
3-4
8
2-5
15
4-5
2
total
Budgeted Release
Year 1- 69.00
Year 2- 68.00
0
0
5
0
0
6
IF
0
0
5
-6
0
0
Year 3- 19.00
Problems in scheduling Real life projects
- Number of activities are more
o Use linear program whenever there are multiple
constraints
o Heuristic programs
Rule of thumb
Computer programs
Schedule critical activities first
Schedule activity with largest
independent float in the end.
Resource leveling programs
Resource allocation programs
PERT Analysis
- Measures of variability
o = [to- tp]/6,
o Variance = 2 = [ to-tp]2/ 36
o Mean of the critical path duration
o Standard deviation of critical path duration
= [Sum of variances of individual activity]
- Assuming that the critical path duration is normally
distributed
o A number of inferences can be made.
- Eg: In the following example compute the
stad.deviation of critical path duration and determine
the probability that the activity will be completed
within 26 weeks?
to
9
6
1
4
10
1
Time Estimates
tm
tp
12
21
2
12
18
2
1.5
5
0.66
8.5
10
1
14
24
2.33
2
3
0.33
4
4
0.44
1
5.44
0.11
Illustration
Activit
y
1-2
1-3
2-4
3-4
2-5
4-5
total
Normal
Crash Normal Crash Crashin
duration duratio
costcostg
n
Direct Direc Cost/we
t
ek
13
10 15000 1900
1333
0
12
8 13000 1700
1000
0
2
1
6000 8000
2000
8
5
9000 1350
1500
0
15
12 21000 2400
1000
0
2
1
6000 3000
3000
70000 8450
0
Activity
1-2
1-3
Normal
Crash
duration duration
13
10
12
8
cost
15000
13000
Crash
cost
19000
17000
2-4
3-4
2-5
4-5
total
2
8
12
2
1
5
1
6000
9000
24000
6000
73000
8000
13500
3000
84500
Activity
1-2
1-3
2-4
3-4
2-5
4-5
total
Normal
Crash
duration duration
10
12
8
2
1
8
5
12
2
1
cost
19000
13000
6000
9000
24000
6000
77000
Crash
cost
17000
8000
13500
3000
84500
Critical path
Both 1-2-5 and 1-3-4-8
No further crashing is possible on the critical path.
Completion time =22 weeks
Total cost = 77000+22000 = 99000
Result : optimum week for completion = 25 weeks ,
cost =Rs.98000
Activity
1-2
1-3
1-4
1-7
2-4
2-6
2-7
3-4
4-5
5-6
3-7
6-7
to
4
3
5
2
6
3
5
3
2
1
2
1
Time in weeks
tm
tp
6
10
7
12
6
9
4
6
10
20
4
7
9
15
7
12
4
5
3
6
5
8
2
6
Required:
a.Draw the network diagram
b.Determine the critical path
c. Calculate event slacks and activity floats
d.Find the standard deviation of the critical
path duration
Time in
normal
5
6
4
7
9
12
10
7
6
12
weeks
crash
2
3
2
4
5
3
6
4
4
7
Cost in Rs.
Normal
Crash
6000
9000
7000 10000
1000
4000
6000
16000
15000
4000
3000
4000
2000
8000
9200
19600
18000
4900
4200
8500