KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT

DIREKTORAT JENDERAL SUMBER DAYA AIR


BALAI BESAR WILAYAH SUNGAI CIMANUK CISANGGARUNG
SNVT PEMBANGUNAN BENDUNGAN

MAY 24, 2016

LOCATION MAP OF JATIGEDE DAM PROJECT

Bend. Jatigede

CIMANUK CISANGGARUNG RIVER BASIN

Rentang Weir

Jatigede Dam

3
3

BENEFID OF THE PROJECT

Irrigation : 90,000 Ha
SI Cipelang
(Kiri)= 38,612ha

SI Sindupraja
(Kanan)= 51,388 ha

Water Supply: 3,500 l/sec


COVERING AREA

Cirebon, Indramayu
Majalengka, Sumedang
Regency

Rentang
Weir

Irrigation
Scheme Rentang
= 90,000 ha

Jatigede Reservoir

HYDRO POWER
Inst. Capacity 110 MW

Flood Control
14.000 Ha

JATIGEDE DAM
RESERVOIR AREA

4,402 HA

ORGANIZATION (1)

1.
2.
3.
4.

Employer : Minister of Public Works


Engineer : Cimanuk Cisanggarung River Basin Agency
Engineers Representative : SNVT Dam Construction
Supervision Consultant : PT. Indra Karya in association
with PT. Mettana, PT. Tata Guna Patria, and PT.
Wiratman & Ass.
5. DED Consultant : SWHI (Sichuan Water Resources and
Hydroelectric Investigation & Design Institute)
6. Contractor : Sinohydro-JO-CIC (Consortium of
Indonesian Contractor), comprise of: PT. Wijaya Karya,
PT. Waskita Karya, PT. Pembangunan Perumahan and
PT. Hutama Karya

ORGANIZATION

Head of CimanukCisanggarung River Basin


Agency
Trisasongko Widianto
Head of SNVT Dam
Construction
Harya Muldianto

PPSPM
Dicky Mutakin

Staf
Commitment
Officer for Dam
Planning
Harya
Muldianto

Staf

Commitment
Officer for Dam I
Dony
Faturochman

Staf

Commitment
Officer for
Dam II

Lukman
Hakim

Staf

Commitment
Commitment
Officer for
Officer for Dam
Embung, Lake
III
and Situ
A. H. Subarda
M. Alkham

Staf

Staf

Commitment
Officer for
Land
Acquisition
Endang
Suratman

Staf

Treasury
Dede
Ruslan
Effendi

Staf

PREVIOUS STUDY

Reconnaisance Study,
Master Plan Study,
Pre Feasibility Study,

1963 - PT. Indah Karya


1967 - Coyne et Bellier (France)
1973 - Nedeco (Dutch) &
SMEC (Australia)
Detailed Design,
1977 - SMEC (Australia)
Review Feasibility Study,
1983 - SMEC (Australia)
Detailed Design,
1986 SMEC (Australia) &
PT. Indra Karya (Persero)
Consolidation Study,
1991 - SMEC (Australia) &
PT. Indra Karya (Persero)
Project Implementation Preparation Review Study, 2000 by
Colenco Binni Black PT. Indra Karya (Persero) PT. Indec

Optimization Study of Jatigede Dam, 2003 by PT.Indra Karya


(Persero), PT.Tata Guna Patria dan PT.Barunadri

Review Detail Design, 2004 - PT.Indra Karya (Persero) and


PT.Wiratman & Associates.

Chronology of Jatigede Dam Project


1. INITIATION

OF IDEA FOR JATIGEDE DAM PROJECT , YEAR 1963

2. DETAIL DESIGN OF JATIGEDE DAM PREPARED SINCE 1986 BY

SMEC-CONSULTANT, AUSTRALIA

3. LAND ACQUISITION

PERMENDAGRI NO 15/1975 == LAND ACQUISITION 1982-1986 (4.065 KK)


KEPPRES NO 55/1993
== LAND ACQUISITION 1994-1997 (1.226 KK)
PERPRES NO 36/2005 dan
== LAND ACQUISITION 2005-SKRG (1.918 KK)
PERATURAN KEPALA BPN NO 3/2007
4. SIGNING OF CONTRACT, DATED APRIL 30, 2007, BETWEEN SINOHYDRO CORPORATION LIMITED JOIN

OPERATION WITH CONSORSIUM OF INDONESIAN CONTRACTORS (CIC) AND COMMITMENT OFFICER JATIGEDE
DAM PROJECT
5. IMPLEMENTATION PERIOD NOVEMBER 15, 2007 U/T SEPTEMBER 09, 2016
SATUAN KERJA NON VERTIKAL TERTENTU (SNVT) JATIGEDE DAM PROJECT ASSISTED BY NATIONAL CONSULTANT AND
FOREIGN CONSULTANT FROM PEOPLE REPUBLIC OF CHINA
6. OCTOBER 23, 2008 : FIRST BLASTING TO START CONSTRUCTION OF DIVERSION TUNNEL SET AS THE

COMMENCEMENT OF PHYSICAL ACTIVITIES OF JATIGEDE DAM PROJECT


7. AUGUST 03, 2011 : DIVERSION OF CIMANUK STREAM TO DIVERSION TUNNEL SET AS THE COMMENCEMENT
OF PHYSICAL ACTIVITIES JATIGEDE MAIN DAM
8. COMPLETION PLAN OF SOCIAL IMPACT AND ENVIRONMENTAL MATTER FOR IMPOUNDING : JUNE 2013
INITIAL IMPOUNDING, AUGUST 31, 2015

OPENING CEREMONY OF JATIGEDE DAM


9
??????

JATIGEDE DAM PROJECT PROFILE (1/2)


HIDROLOGY
Catchment area
: 1,462 km2
Annual discharge
: 2.5 x 109 m3
RESERVOIR
Water Elevation(WE) of max. flood : El. +262
WE Max. Operation (FSL)
: El. +260
WE Min. Operation (MOL)
: El. +230
Area (El. 262)
: 41.22 km2
Total volume (gross) (El. +260)
: 980 x 106 m3
Effective volume(between El.+221 Dan El +260)
: 877 x 106 m3
DAM
Type
: Rock fill, vertical core
Dam crest elevation
: El. +265
Length
: 1,715 m
Width of dam crest
: 12 m
Max. Dam height
: 114 m
Volume of embankment
: 6.7 x 106 m3
SPILLWAY
Location
: at the dam body
Type
: Chute type with 4 radial gates
Width of top Weir
: 52 m (4 x 13.0 m), El.+247
Dimension of radial gates
: 4 bh (W=13.0 m ; H=14.5 m)
Q
: 11,000 m3/s

JATIGEDE DAM PROJECT PROFILE (2/2)


IRRIGATION OUTLET
Location
Elevation of apron
Type of structure
Dimention of conduit
DIVERSION TUNNEL
Location
Elevation of Inlet
Type
Design discharge (Q100)
Dimention of tunnel
POWER WATER WAY FOR PLTA
Location
Inlet bottom
Dimension of power water way
Drop height
Type of turbin
Capacity
Average production

: at the spillway body


: El. +221
: Reinforced Concrete Conduit with
Steel Liner
: b = 3.9 m; h = 4.1 m, L = 166 m
: below the spillway
: El. +164
: Circular, reinforced concrete
: 3,200 m3/dt
: D = 10 m ; L = 546 m

: at right side of main dam


: El. +221
: D = 4.5 m ; L = 3,095 m
: 170 m
: Francis
: 2 x 55 MW = 110 MW
: 690 GWH/year

LOAN PROFILE (1/2)


JATIGEDE DAM PROJECT
I. ORIGINAL
1.1. Name of Loan
1.2. No. of Loan
1.3. No. of Register
1.4 Loan Agreement Date
1.5 Loan Effectiveness Date
1.6 Loan Value
1.7 Loan Period
- Grace Period
- Repayment period

:
:
:
:
:
:
:
:
:

Preferential Buyer Credit


China Exim Bank PBC No. (14) Total No. (35)
21595701
25 September 2007
20 November 2007
USD. 215,615,732.40
15 years
6 years
(20 November 2007 u/t 20 November 2013)
9 years

LOAN PROFILE (2/2)


JATIGEDE DAM PROJECT

II. ADDITION
1.1. Name of Loan
1.2.
1.3.
1.4.
1.5.
1.6.
1.7.

:
No. of Loan
:
No. of Register
:
Loan Agreement Date :
Loan Effectiveness Date :
Loan Value
:
Loan Period
:
- Grace Period
:
- Repayment period

Preferential Buyer Credit


China Exim Bank PBC No. (31) Total No. (275)
21674001
3 September 2013
19 September 2007
USD. 117,000,000.00
156 months (13 years)
36 months (3 years)
(19 September 2013 u/t 19 September 2016)
: 120 months (10 years)

IMPLEMENTATION STATUS
JATIGEDE DAM PROJECT
1. Contract Price
Original Contract Price

: Rp.

Additional Contract Price

: Rp. 1,300,397,982,822 + USD. 84,974,114.67

Total Contract Price + GOI

: Rp. 2,169,497,067,264 + USD. 229,041,756.67

Self Funding (FY 2012)

: USD

869,099,084,442 + USD. 144,067,642

467,448,O27.80

2. Implementation Period
Original Contract : 1,950 days (15 Nov.2007 u/t 17 Mar.2013)
Time Extension I : 1,950 + 248 = 2,198 days (15 Nov. 2007 u/t 20 Nov. 2013)
Time Extension II : 2,198 + 313 = 2,513 days (15 Nov. 2007 u/t 1 Okt. 2014)
Time Extension III : 2.513 + 304 = 2,817 days (15 Nov. 2007 u/t 1 August 2015
Time Extension IV : 2,817 + 405 = 3,222 days (15 Nov. 2007 u/t 9 Sept. 2016)

15

LAYOUT OF JATIGEDE DAM PROJECT

JATIGEDE DAM
GENERAL PLAN

DAM

SPILLWAY
IRRIGATION
OUTLET

DIVERSION
TUNNEL

POWER
WATERWAY
17

TIPIKAL POTONGAN MELINTANG BENDUNGAN

LEFT BANK

RIGHT BANK

Spillway, Chute and Plunge Pool

Plunge Pool

PROCESS OF DIVERSION OF RIVER FLOW (3)

DIVERSION TUNNEL

32

33

LAY-OUT OF POWER WATERWAY

SWITCH
YARD

SURGE
SHAFT

INTAKE
POWER

HEADRACE
TUNNEL

OUTLET
WORKS

POWER
STATION

GATE CONTROL
SHAFT
TAILRACE
TUNNEL

CIMANUK RIVER

REGULATING
DAM

LONGITUDINAL SECTION OF THE TUNNEL AND GATE SHAFT

38

SCENARIO FOR INITIAL IMPOUNDING OF RESERVOIR


31 AGUSTUS 2015
Axis of Main Dam
Axis of Gate
Chamber

EL. +260,00 m
EL. +247,00 m
EL. +230,00 m
EL. +221,00 m

DESA
DESA
DESA
DESA
CIPAKU
CIPAKU
CIPAKU
CIPAKU

Day 518 (29 Jan 2017)

Day 227 (13 Apr 2016)


Day 133 (10 Jan 2016)

EL. +204,00 mDay 102 (10 Des 2015) U/S Diversion


Tunnel

Day 68 (6 Nov 2015)

DESA
DESA
DESA
PAKUALAM
PAKUALAM
PAKUALAM

DESA
KARANGPAKUA
N

DESA JEMAH
DESA
DESA
DESA
DESA
JEMAH
JEMAH
JEMAH
JEMAH

DESA
DESA
DESA
DESA
SUKAREKSA DESA
DESA
CIRANGGEM
DESASUKAREKS
SUKAREKS
CIBOGO
CIRANGGE
CIRANGGE
AA

MM

DESA
SUKARATU
DESA

DESA
LEUWIHIDEU
LEUWIHIDEUNG
DESA
NG
DESA
DESA
DESA
DESA
CISURAT
PADAJAYA
JATIBUNGUR
PADAJAYA
PADAJAYA
DESA
DESA
DESA
DESA
DESA
MEKARASI
MEKARASI
SUKAMENAK
DESA
JATIBUNG
SIRNASARI
HH
UR
DESA
DESA
DESA
WADO PAWENANG
DESA
CISURAT
SUKAMENA

DESA
MEKARASIH

Explanation :
1. Irrigasion Gate Fully Close and Open 12 hours : May 1 until May 31, 2016 (1
month).
2. Irrigasion Gate will be Closed : Sept. 1, 2016
3. Spillway Gate will be Closed : June 1, 2016
4. Elv. +260 will be reached : Jan. 29, 2017

200,00
180,00

Elev +260 will be reached


in January 2017,

Q-intake Jatigede 2016


Q-POLA
Q-demand (Rentang weir)

160,00

May Agust 2016


reservoir will release the
discharge from 51 m3/sec
60.27 m3/sec.

DISCHARGE (m3/sec)

140,00
120,00

Fulfillment of discharge
requirement

100,00
80,00
60,00

60,3

60,3

59,9

59,0

59,0

59,0

57,8

57,0

55,9

54,3

52,9

51,1

40,00
20,00

0,00
MEI-1 MEI-2 MEI-3 JUN-1 JUN-2 JUN-3 JULI-1 JULI-2 JULI-3 AGT-1 AGT-2 AGT-3
PERIOD DECADE

Liability: 46 % - 100 %

SCENARIO

OPENE CLOSE
IRRIGATION
GATE &
SPILLWAY

IRRIGATION
LIABILITY

MEAN
DISCHARGE
MT II
(m3/s)

TARGET

46 100 %

57,20 m3/sec

JAN. 29, 2017

REMARKS

Operation
Irrigation Intake
April August
12 hour

Notes:
Operation Close and Open of Irrigation Intake Gate - 12 hour for 5
months

45

SCHEME OF LAND ACQUISITION


ACQUIRED
PUBLIC AREA

3,256.44 Ha

3.259 Ha
UN-ACQUIRED

2,56 Ha

TO BE EVALUATED

RESERVOIR

4,402.15 Ha

SUBSTITUTED

521.18 Ha
FORESTRY AREA

1,143.15 Ha
IMPOUNDING AREA+
DAM STRUCTURE
AND FACILITIES

UN-SUBSTITUTED

PROGRAM FY 2013
92.81 Ha

621.97 Ha

4,980.30 Ha

ACQUIRED
308.47 Ha
PUBLIC AREA
332 Ha

UN-ACQUIRED
23.53 Ha

TO BE PROGRAMMED
529.16 Ha

ROAD RELOCATION
23.53 Ha

DAM STRUCTURE
AND AUXILIARY
FACILITIES

578.15 Ha
FORESTRY AREA
246.15 Ha

Note: There are claim of un-acquired land


toward land acquisition process from
1982-1986, and illegal housing matter

SUBSTITUTED
246.15 Ha

DAM STRUCTURE
AND WORKING AREA

PENYUSUNAN TATA KAWASAN WADUK JATIGEDE

LANDSCAPE ZONING OF JATIGEDE DAM PROJECT AREA

49

Summary of Sensitivity Analysis


(Cost: Dam+App+Hydro Power+Land Acq., Benefit: Irrigation+Hydropower+Watsup)
Construction cost (IDR)

NO

CONDITION

8,873,953,210,980.00

B/C

NPV B-C

EIRR

Normal

1.436

275,328.72 16.76%

Benefit (is reduced by 10%)

1.292

184,640.47 15.29%

Cost (is increased by 10%)

1.305

212,173.34 15.43%

Benefit (reduced, 10%) and Cost (increased, 10%)

1.175

121,485.09 14.02%
50