Professional Documents
Culture Documents
REVISION STATUS
Issue
No.
Date
Reason of revision
Issued by
Approved by
IS
This copy
Ab o v e G ro u n d P i p i n g
Installations
Page 2
Initial Review
Section
REVISIONS
Number
General
of 11
Ab o v e G ro u n d P i p i n g
Installations
CONTENTS
1.0
INTRODUCTION
2.0
SCOPE
3.0
SAFETY
4.0
RESPONSIBILITIES
5.0
CONSTRUCTION PROCEDURE
5.1
Preparatory Works
5.2
5.3
Welding
5.4
Radiographic Examination
6.0
PRESSURE TESTING
7.0
IDENTIFICATION RECORDS
8.0
EQUIPMENT
APPENDICES
1. Daily Tally Sheet (for A/G Piping Installation)
Page 3
of 11
Ab o v e G ro u n d P i p i n g
Installations
1.0
Page 4
of 11
INTRODUCTION
The purpose of this procedure is to define the methods of erection and welding
for the above ground piping at Zawiya Terminal Facilities. The procedure target is
to help the site personnel to execute the job in a planned, controlled manner and
in accordance with the relevant codes and contract requirements.
2.0
SCOPE
The Scope of Work covered by this procedure includes all aboveground carbon
steel pipes and tanks interconnecting pipework at Zawiya Terminal Facilities.
In support of the Works, reference shall be made to the following:
CODES AND STANDARDS
ANSI B 31.3 Chemical Plant and Petroleum Refinery Piping
ANSI B 31.4 Liquid Transmission and Distribution Piping Systems
ASME
System
Section IX, Welding Qualification
Section V, Non Destructive Examination
AWS A5.18 Specification for Carbon Steel Filler Materials for Shielding Arc
Welding
ANSI B 16.5 Pipe Flanges and Flanged Fittings
ANSI B 16.25
Ab o v e G ro u n d P i p i n g
Installations
Page 5
of 11
9601004/DO/M/103-ZW
9601004/DO/M/107-ZW
9601004/DO/M/113-ZW
9601004/DO/H/122-ZW
9601004/DO/M/104-ZW
3.0
SAFETY
This procedure
Safety Clothing
Safety Shoes
Hard Helmets
Safety Belts
Welders Gloves and Helmets
Safety Goggles
Dust Masks
Tidy Work Area
Warning Signs (for radiographic activities)
4.0
RESPONSIBILITIES
SITE MANAGER
Responsible to the Project Manager for:
Ab o v e G ro u n d P i p i n g
Installations
Page 6
of 11
Ensuring the smooth and on time execution of the fabrication works, according to
schedule.
Determining the plant and equipment to be used during the above operations.
Preparing all the necessary shop construction sketches related to pipes, spools
etc. according to the approved drawings and handing over the same for
execution on site.
PIPING FOREMAN
Responsible to the Mechanical Engineer for:
Supervision of the pipe work activities on site and control of all stages of the
work, i.e. fitting, welding and installation throughout the Project.
Ensuring that all related works are carried out in good workmanship and
according to the approved drawings and procedures.
Ab o v e G ro u n d P i p i n g
Installations
Page 7
of 11
Ensuring that each individual operation is carried out safely under the proper
conditions.
Preparing all the necessary plant, equipment, tools, consumables etc, required
for the execution of the job.
Monitoring all A/G pipe work installation activities and tests (e.g. welding, hydro
testing etc) being performed and notifying / informing the Mechanical Engineer
accordingly on a daily basis.
MATERIALS CONTROLLER
Responsible to the Construction Manager and Mechanical Engineer for :
Receiving, handling and storing at site of all the pipe work materials.
Releasing all the necessary pipes and appurtenances needed for erection.
Liasing with the Operators Materials Controller for a close monitoring of the
materials.
Keeping close records with respect to the incoming and outgoing materials.
Conducting regular safety inspections during pipe work operations and ensuring
that all necessary safety precautions are being taken.
Preparatory Works
Before starting any erection / installation activity, all piping shall be closely
observed for any defects during prefabrication in the Workshop.
Ab o v e G ro u n d P i p i n g
Installations
Page 8
of 11
All flanged joints shall be correctly aligned with the gasket faces in contact
across their full width.
Valves and pipe work mating flanges shall be parallel and concentric. The gaps
between flange faces shall be just sufficient to insert the gasket before tightening
the flange bolts.
All welded joints in a pipe work section shall be completed before flanged joints
connections to equipment are done.
Piping shall be erected level on its supports and in a stress free condition.
Piping shall not be strained into position by the use of levers, chain blocks or
other means. If the piping does not fit, it shall be removed and readjusted to suit.
The ends of all piping shall be securely closed at the end of each days
work and shall not be re-opened until piping works are resumed.
Ab o v e G ro u n d P i p i n g
Installations
5.3
Page 9
of 11
Welding
Welding electrodes shall be of the approved type, i.e. ESAB - OK 6010
pipe weld and ESAB - OK 48.00 E 7018.
Only qualified welders shall be employed in the job and they will have
their identification badges with them at all times. The welders will follow
the applicable welding procedures, as specified in the relevant Welding
Procedure Specifications.
More than one welder may be used for all pipe sizes.
Each welder shall mark with an identifying marker each of his welds. Die
stamping is not permitted.
No electrodes shall be left lying around at site. Electrodes so left shall be
scrapped and removed.
The maximum time delay between completion of the root and the start of
the second pass shall be 5 minutes.
External clamps shall be used and shall not be removed until at least 50%
of the root pass is completed.
The pipe shall not be lifted until the welding is 100% completed.
Downhill mode shall not be used, nor will any kind of internal welding.
Only Shielded Metal Arc Welding (S.M.A.W) process shall be used.
Permanent backing rings and copper backing rings are prohibited.
Penning of the weld is prohibited.
Flame gouging, air-arc gouging and chipping shall not be used.
The pipes shall not be hammered or heated to remove the slag.
The root pass shall be ground clean.
No rectification, repair or modification shall be made without the approval
of the Operators Engineer.
Repairs shall be completed after the initial radiography.
A minimum preheat of the pipes at 40C shall be used when the ambient
temperature is below 0C or when the weld surfaces are humid.
Ab o v e G ro u n d P i p i n g
Installations
Page 10
of 11
Radiographic Examination
The erected and field welded piping joints shall by radiographically
examined as per the relevant QA/QC procedure and records shall be kept
accordingly.
In case of a repair, this shall be carried out according to WPSs
6.0
PRESSURE TESTING
IDENTIFICATION RECORDS
One set of the AFC drawings pertaining to the aboveground piping shall be
maintained as production welding and fabrication records.
Every spool piece shall be cross-referenced with the associated drawing.
On this drawing, the prefabricated joints will be identified by W symbols (see also
Construction Procedure for Piping Prefabrication) and the field joints by FW
symbols. Only the FW symbols shall be filled in during the aboveground piping
installation stage.
Appendix 1 herein depicts the information required to cover this procedure.
The above-mentioned production records will be updated on a daily basis and be
made available to the Operators Engineer upon request. A set of drawings with
these records will be maintained and submitted as part of the As-built
documentation.
Ab o v e G ro u n d P i p i n g
Installations
8.0
Page 11 of
11
EQUIPMENT
The following major equipment shall be used for the aboveground piping
installation activities :
-
Welding Sets
Air Compressors
Cranes
Trailers Flat Bed with Prime Mover
Generators
Power Tools
NDT Equipment
Hydro testing Pumps (Filling and Pressurizing)