Instruction: Compliance to be mentioned with

Sr.
Check List Description
No.
1
Check flow arrow as per P&ID, North direction, key
plan as per Plot plan.
2
Check the Grid & column numbers are in line with
Eqpt layout & Civil drawings. Check the Coordinates
are as per Eqpt layout/Plot plan
3
Make sure proper notes, Legends & holds are added.
Mention Eqpt layout, match line piping GA drgs as
minimum in reference drg.
4
Make sure the 3D draft is made at correct Elevations.
Designer to double check this.
5
Make sure all equipments are properly located with
coordinate
6
Show secondary (major) pipe support with tag as
minimum. Follow Client Go by or requirement on
extends of detailing.
7
The cryogenic pipelines require very large insulation
thickness & hence it is very important to space
these lines as per actual thickness
8
All pipe supports requiring ROCK foundations are
detailed on the drawing.
9
For major pipe supports & pipe racks suspended
from beams and columns, details are indicated on the
drawing. MPS no identified
10
Alignment bellows are added for large size (10"NB
&above) piping connected to machines, in
consultation with piping ''Lead Engineer".
11
Underground /Above ground piping interfaces are
clearly identified in the piping GA along with
Insulating joint with proper SPO item number
12
Piping interfaces with others is properly identified with
coordinates & B/L flanges ( or Valves). Make sure it is
properly conveyed to relevant parties.
13
For Underground piping GA, make sure the valve pits
are added with all detailed & Pit numbers. Make sure
the same properly conveyed to Civil.
14
Monorails are clearly marked with center line. Make
sure no piping is passing under the monorail. Space
below monorails is kept clear for easy removal of
equipment.
15
Identify access way , tube removal, drop out zone,
parking area , turning radius, eqpt un-loading zone,
maintenance space, etc. properly & make sure no
piping is routed in this area.
16
Make sure the all master print comments, Client
comments are taken care while revising the piping
GA drg.
17
Check the Line numbers, Equipment nos, Nozzle
numbers & sizes are shown are as per P&ID.
18

Check the Instrument tags, SP item tags are as per


P&ID

19

Check the Tie in numbers, Vessel Trims

Page 1of2

Compliance
Originator Checker

Remarks

Sr.
No.
20

Check List Description

Compliance
Originator Checker

21

Check whether the existing piping and Future piping


identified correctly.

22

Check for Match line information (i.e.drawing no., Co


ordinates ,line type, description)

23

Check the Title Block(i.e. Title drawing no., Revision


description & no., scale ,Project no.,signatures, date)

24

Check for Reference drawings and documents.

25

Check for Notes and hold points(if any).

26

Check for Revision clouds and Rev.triangles.

27

Check for drawing continuation cross reference.

28

Check the Pipe support numbers, locations &


symbols

29

Check whether the Floor cutouts are properly marked


with size.

Check the Manual Valve accessibility, operability and


orientation

Page 2of2