1.1.
Organization
The Contractor proposes to execute the engineering, design, procurement and
construction of the Project by assigning a dedicated task force to the project. The task
force approach dedicates all required resources to the project, improves
communication and develops a cohesive team.
The following briefly describes the responsibilities of the key team members.
Task Force
Under the direction of Project Manager this team will be operated comprehensively to
ensure :
Project Manager
The Project Manager has full responsibility for the execution of the engineering,
procurement and construction work.
His responsibilities include :
Planning
Organizing
Technical Execution
Monitoring, including schedule and quality control
He will direct and coordinate all phases of the work associated with the design,
procurement assistance and scheduling of the project. He will be responsible for
providing the necessary administrative and technical leadership to bring the project to a
successful conclusion.
Project Engineer
Work with the Project Manager and discipline engineers to establish basis of design
and scope of work from contract documents.
Work with Cost and Schedule Controllers to establish budgets and schedules.
Schedule Controller
The Schedule Controller has the responsibility for the development and updating of
project schedule using computer software and detailed worksheets, while the task
force has the responsibility for adherence to the updated schedule. He will closely
keep in contact with not only all discipline lead engineers but also procurement,
fabrication and construction management to develop and monitor the project schedule.
Document Controller
The Document Controller is administratively and functionally responsible to the Project
Manager and he will :
Monitor all documentation required for project files to identify possible delays in
schedules.
Coordinate with other disciplines to assemble required data and job progress.
Procurement Coordinator
The Procurement Coordinator is responsible for coordinating, monitoring and
expediting the performance of all key activities related to the procurement. He will
establish and maintain records, files and schedules of major equipment items. He will
also coordinate and expedite the technical review of received quotations and mediate
the resolution of any technical questions or vendor exceptions.
Lead Engineer
Each lead Engineer is responsible for providing technical design review and
assistance with analysis for his respective discipline of the project. He will review the
engineering and design data for the project and will make calculations, write
specifications, prepare equipment requisitions, and check and approve drawings.
1.2.
Project Schedule
Compliance with the schedule is subject to the on time completion of all procurement
and construction activities. Failure to comply with this schedule will impact the
deliverables schedule and commercial consideration of this project.
1.3.
Following the kickoff meetings with the Client, the Project Manager will hold an
internal Project meeting during which he will complete the staffing of the project
team and assign tasks as required by the execution procedures and project
schedule.
2) Engineering Phase
An initial activity of the design phase will be the compilation of a Design Brief based
upon the proposed design. This document will be comprehensively reviewed by
the Project Manager, Lead Discipline Engineers and used to compile the Work
Breakdown Structure and Work Scopes for each Discipline.
This design review period will also be used to validate the design package and
ensure that the designs produced are suitable for further development. This will
include a review of the process simulation and a check on the data sheets of
equipment and facilities. During this period a Safety Review will also be performed,
ensuring that all safety requirements for the protection of personnel, plant and
property are incorporated into the design.
Regular meetings among the Client and project management team for the
project to discuss technical and administrative matters and to review progress.
4) Procurement Phase
a) Planning and Procedure Development
Subsequent to initiation of project execution, the Procurement Coordinator will
work with other project contractor members to identify equipment with critical
delivery schedules, establish procedures and requirements for processing
requests for quotation (RFQs) and engineering technical review of vendor
proposals.
b) Preparation and Issuance of RFQs
The Procurement Coordinator will issue RFQs to the approved vendors. The
length of time allowed for vendors to submit their quotations will be based on
such factors as the type and complexity of the equipment included in the
inquiry, the critical nature of the equipment with respect to the project schedule
and the geographical location of the vendors with respect to travel time for both
the inquiry package and resultant quotation.
c) Technical Evaluation of Bids
Vendor Quotations forwarded to Procurement Coordinator will be submitted to
the appropriate engineers for technical evaluation. This evaluation will result in
relative rankings along with appropriate explanations among the bidders of a
specific equipment item ; a list of any required clarifications or modifications
and a list of recommended vendor. Each engineer involved in reviewing the
bids for a specific item will clearly initial each of his comments in case of further
questions and also for record purposes.
Direct communication between engineers and vendors, except for a general
informational nature, will be prohibited without the presence of the Procurement
Coordinator or an appropriate designer, so that potential confusion of
misunderstanding is avoided. This will also aid in maintaining control of
approved change orders.
When the technical evaluations are completed, the Procurement Coordinator
will forward a recommendation to Project Manager for review.
d) Request for Purchase Order
As soon as a decision has been reached on the successful vendor and the bid
tabulation has been approved by all parties, The Contractor will update the
inquiry specifications to purchase specifications by incorporating any technical
changes approved during the bid tabulation. The Procurement Coordinator will
prepare a request for purchase order including the updated purchase
specifications and forward the request to the Project Manager for review. The
Procurement Coordinator will also notify the appropriate task force members of
the preliminary schedule for the drawing approval cycle so that work can be
scheduled accordingly.
Upon receipt of a copy of the vendor's
acknowledgement of purchase order receipt, the Procurement Coordinator will
advise the task force of the final schedule for the drawing approval cycle and
other document information.
5) Approval and Certified Drawings and Data
The Procurement Coordinator will be responsible for maintaining current status
report of the receipt and return to the vendor of all approval drawings and design
documents. He will retain an unmarked copy for the purchasing file and submit
additional copies to the Project Manager for routing to appropriate engineers for
review and approval by using an established standard check list and procedure.
6)
Construction phase
A.
Construction Policy
The successful implementation of the construction work will depend upon two
fundamentals:
Experienced site organization and the requisite labor resources, all motivated to
execute the strategy.
B.
Mobilization plan
The supervisory and craft personnel will be mobilized from the following sources:
- The Country
In order to achieve the maximum participation of Local manpower and in conformance
with the Contractor's local recruitment plan, some of the staff and all the clerical
assistance will be obtained in The Country. All the Local labor will be mobilized by
subcontractors.
For the purpose of efficient mobilization, the construction management team, will arrive
at site prior to actual start of construction activities. Their first task will be the layout and
construction of temporary facilities.
1)
Supervisory Personnel
The Contractor will mobilize key construction personnel in accordance with the
construction schedule.
The first stage in the supervisory staff mobilization program will be the assignment
of key personnel to engineering / procurement offices to input construct ability into
the design and for a period of familiarization with the project prior to being assigned
to the site. Concurrent with their familiarization program, all necessary visas,
inculcation, etc. required for entry in the Country will be completed.
2)
Labor
Required labor will be forecasted 30 days in advance and will be recruited
accordingly by the subcontractors. Skilled labor will be tested according to
qualification standards detailed in the quality assurance procedure.
All the labor will be provided with the following information before being admitted to
work at site.
- Description of the project
- Safety and sanitary regulations
- Quality control standards
C.
D.
Construction Equipment
Most of the construction equipment, tools and consumable will be supplied by
subcontractors according to the construction equipment schedule which will be set up
before construction work starts and will be updated monthly by the Contractor.
The Contractor will check and inspect the construction equipment provided by
subcontractors to ensure the first class condition of these construction equipment.
The Contractor will mobilize their own construction equipment or rent from the agent
outside The Country when those heavy equipment handling construction equipment
needed are not available in The Country
The Contractor's head quarters, overseas branch offices and the site office will
cooperate closely to achieve this goal timely and successfully.
E.
General
Material management at site is under the responsibility of the material control
manager.
The material control manager monitors the status of all materials from receiving to
field erection at the site.
Any damage or shortage of materials or equipment will be checked during receiving
inspection and material control manager will report directly to the project manager
the monitoring status.
His responsibility will also include field procurement and coordination for smooth
and timely customs clearance.
2)
Material Control
a) Receiving
All shipment will have been properly cleared and , if originating from outside The
Country, released by customs before any receiving action can be taken. An
initial check will then be considered before being off-loaded.
The initial check comprises;
Quantity check
Damage check
The material control manager maintains a file for each shipment or purchase
order item which contains the completed history of the order.
These files contain:
Requisitions
Purchase orders
Material certificates
OS & D reports
Insurance claims
3)
Issuance of Materials
Materials shall not be issued from the warehouse or its enclosures without a
warehouse withdrawal slip.
This issue slip specifies where the material is to be used, the quantity, size and
description and will be signed by an authorized personnel.
The issue slip is presented to the warehouse for withdrawal of the material, checked
by the warehouseman and initiated to record the issuance.
The issue slip is utilized for the information of respective stock record or purchase
order card.
At the close of each day, the warehouseman will pass all warehouse withdrawals
slips to the chief warehouse engineer for the posting up of the stock record or
purchase order cards. When all issues have been posted up, the withdrawal slips
will be filed numerically.
Materials that are stored in the warehouse or its enclosures will be checked
periodically. The actual number and date of inventory will be entered on the face of
the stock recorded.
F.
G.
Start-up
General
The commissioning team will be composed of the following engineering, technical and
operating personnel. They will operate under the direction of the commissioning manager.
The commissioning manager will coordinate with Client's O & M members for the activities of
the initial operation teams. Each team will consist of engineering, technical and operating
personnel in the fields of process, instrumentation, electrical, mechanical and safety to support
the Client.
Each team will have at its disposal a maintenance crew consist of millwrights, electrical and
instrumentation technicians, welders, fitters and general labor.
It will be the responsibility of the commissioning will be the responsibility of the Contractor that,
Contractor will utilize the Contractor's operating personnel to assist in "hands-on" operations to
supplement their training activities.
Operation of the facilities during commissioning will be the responsibility of the Contractor that,
Contractor will utilize the Contractor's operating personnel to assist in "hands-on" operations to
supplement their training activities.
Pre-commissioning
Pre-commissioning will include all activities associated with preparing and conditioning all
prefabricated and field erected facilities in accordance with recommended engineering
practices so as to permit start-up and initial operation of the facilities.
Prior to the date scheduled for pe-commissioning, the pre-commissioning plan and manual will
be submitted which shall detail the sequence of events and describe specific activities to be
performed and results to be achieved for all designed systems and equipment.
The manual will stipulate, describe and list all equipment and consumable items required for
each system and equipment and provide applicable check-out forms. tags and certification
documents for subsequent issuance of the certificate of pro-visional acceptance of work.
These pre-commissioning activities will be performed in accordance
precommissioning plan and manual and witnessed by the Contractor.
with
the