3) Dispatch of single Bought out materials from Production Plant Create a semi
finished/finished material having same description of bought out material.
Create the BOM for semi finished/finished material with assigning bought out material
to the BOM.
Assign the BOM material to WBS element.
Select the item category L (Stock Item)
Select the procurement type Reservation for WBS element.
MRP run (Scheduled in background).
Purchase requisition, Purchase order & Good receipt for BOM Components
Produce semi finished/finished material by creating a production order.
Good receipt against production order to take bought out in to stock.
Delivery& PGI the material through sales order. (Delivery Based sale order)
Raise invoice against respective delivery document in SAP.
4) Procurement of single bought out material from vendor to customer (no liability of
FPE) and billing to single line item
Assign material to WBS element under plant.
Select the item category N (Non Stock)
Select the procurement type Third party order for network.
Purchase Requisition, Purchase Order.
Generate Proforma invoice in SAP through sale order. (Non delivery based sale
Order)
Logical GR (once stores receive complete despatch documents and vendor
invoice)
Generate Billing Invoice in SAP.
5) Procurement of Multiple bought out material from vendor to customer (no liability of
FPE) and billing to single line item (
Assign all materials WBS element under plant.
Select the item category N (Non Stock)
Select the procurement type Third party order for network.
Purchase requisition, Purchase order.
Create a material for billing purpose use same material in the sales order line
item.
Sum of the procurement quantity should be equal to the order quantity in the
sales order line item.
Generate Proforma Invoice in SAP through sale order (Non delivery based sale
Order)
Logical GR (once stores receive complete despatch documents and vendor
invoice).
Generate Billing Invoice in SAP
Check the schedule line of the item and feed proposed date for creating the delivery
document now (VL01N)
Save the document, Delivery document no. is generated. (Note Picking, PGI not done at
this stage)