You are on page 1of 2

I

El
Fl
I-
1i
The 2007 Version protection will likely see prices increase.
Of The AlA A 101 The third change concerns responses to RFIs and relates closely
And A 201 to the intent design features of 2007 documents. Since the archi
tect is no longer obligated to respond to these inquiries from con
by Carol Sigtnond tractors, the contractors do not have a right to design information
Dunningron, Bartho low ctMiIler LLP from the owner’s architect. This will leave the contractor to guess,
and only after shop drawings or installation will the contractor
Many condos and co-ops use standard construc learn if the guess was right or wrong. The cost implication of this
don documents offered by the American Insti risk on the contractor will be passed back to the owner in the
tute of Architects (AlA) for Local Law 11, other roof and façade form of increased costs.
repairs, and interior decorating. Customarily, the forms for con
struction used for these jobs are the AlOl Standard Agreement and There is a fourth change to the AlA 2007 construction documents
the A 201 General Conditions. These documents were revised and that deserves mention: the introduction of the ‘Independent Deci
new versions termed the Al01-2007 and A201-2007 were released. sion Maker’ (1DM) to resolve disputes between the owner and the
Many commentators consider these documents to be ‘pro’ owner, contractor, The role of the 1DM is to make decisions respecting the
and that was certainly the intent of the drafters. From my per design and construction of the project so as to promote timely com
spective, these documents are not necessarily good for owners. The pletion of the project. The 1DM concept then allows the parties
changes in the documents signal an increase in contentious in the to arbitrate disputes. In theory, the 1DM is intended to promote
relationship between contractors on the one hand and owners and cooperation. However, there are many questions about the 1DM.
architects on the other hand. More practically, the documents are For example, who will pay the 1DM? If the owner pays the 1DM, is
so one-sided, contentiousness cannot be the primary concern: own the 1DM really independent? If the contractor pays half the cost of
ers should beware of contractor pricing under these documents. the 1DM, what are the cost implications for the project?

Construction pricing is governed by four factors: labor costs and Unless the parties name an 1DM, the architect fills this role. Since
availability, commodity and fuel availability and prices, competi the architect is not ‘independent’ of the owner, for most projects,
tion, and risk, Of these, the least quantifiable is risk. Risk is also this 1DM is merely window dressing to allow the architect, act
the factor that will cause prices to seem high relative to the quan ing at the owner’s behest, to force the contractor to complete the
tity of work. Under the 2007 AlA documents, risk is assigned to project. A cynic would question whether the 1DM is intended to
the contractor to such an extent that pricing will be increased. allow the architect to act as the owner’s agent, making decisions
for the owner’s benefit to completion and then testifying on the
To illustrate the point that the contractor is assuming significant owner’s behalf at arbitration. Owners may find contractors view
risk under the AlA A 101-2007 and A 201-2007, three provisions the architect-as-IDM with suspicion, and contractors are likely to
f the new agreement to illustrate my point: changes to the haz
0 insist on changes to the basic agreements to prevent the architect
ardous material risk allocation; the recognition that the design from having a free hand as 1DM.
will be ‘intent’ only; and responses to ‘Requests for Information’
(RFI). The first change, the hazardous material risk is perhaps the Overall, construction under the AlA A10l-2007 and A201-2007
change that most illustrates my point of the attempted pro-owner is likely to be more expensive and contentious than under the
bias in the new documents, In the AL A 101-1997 and AlA A AlA 1997 agreements. Condo and co-op boatds should carefully
201-1997, the owner assumed all risk associated with hazardous evaluate the risk components of their respective projects and tailor
materials specified for the project. Risks 0f contamination and architectural and construction agreements to realistically allocate
clean up 0 f specified hazardous materials have been transferted risk and manage the project sensibly. Also, have direct and frank
to the contractor under the AlA Al0l-2007 and A201-2007. Ob communications with prospective contractors so that you are able
viously, if a design includes such materials, the contractor will to understand the needs and concerns of the contractor. Probing
increase the price accordingly. existing conditions so that the contractor knows what to expect
maybe critical to controlling prices. If you manage the contractor’s
The second change to the AlA A101-2007 and A201-2007 is the concerns and expectations and ask your design professionals to pro
shift of responsibility for the design detail to the contractor. Pre vide a complete design, you should be able to achieve a fair cOntract
viously, the AlA documents called for the architect to provide a at a fair price.
complete design and for the contractor to provide shop drawings
to show execution of the design. Under the AlA 2007 documents, Carol Sigmond
the architect provides only an ‘intent’ design. As a result, the role Dunnington, Bartliolow óMillcr LLP
of the shop drawing has been elevated to part of the primary design 477 Madison Avenue
process. This will impact plumbers, electricians, HVAC, and fire New York, NY 10022
protection subcontractors more than most other subcontractors. As Thl: 212-682-8811
a result, projects that include plumbing, electrical, HVAC, or fire csigmond@dunnington.com

MRIB 67

You might also like